Ice ball making mold
By designing ice hockey molds including ply plates and multiple pairs of molds, the problems of low production efficiency and poor regularity of existing ice hockey molds are solved, and efficient and regular ice hockey preparation and convenient storage are achieved, meeting the experimental needs.
Patent Information
- Application Number
- CN202420653975.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-01
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-04-01
AI Technical Summary
The existing ice hockey molds have low preparation efficiency, poor ice hockey regularity, and poor tightening effect of many ice hockey molds, which can easily lead to ice hockey melting and deformation and cannot meet the test needs.
The ice hockey mold design includes plywood and multiple pairs of molds. The fastening bolts are evenly distributed. The mold components are made of stainless steel. The step structure and groove bosses are combined to slow down the expansion and deformation of the ice hockey, ensure the regularity of the ice hockey, and provide convenient installation. Disassembly and storage methods.
It improves the efficiency of ice hockey preparation, ensures the regularity of ice hockey, reduces the risks of ice hockey melting and deformation, realizes batch preparation and convenient storage, and meets the test needs.
Smart Images

Figure CN222104005U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of molds, and specifically relates to an ice ball making mold. Background Art
[0002] At present, some types of glass need to undergo a variety of ice ball tests to test their performance, such as hail impact tests, etc. The tests have certain requirements for the regularity of ice balls, and the molds currently used to prepare regular ice balls for tests are mostly independent single ice ball molds. Although the prepared ice balls have high regularity, the ice ball making efficiency is low, and it is time-consuming to remove the ice balls. Although there are a small number of multi-ice ball molds on the market, multiple mold openings to remove ice balls can easily cause the remaining ice balls to melt, and the remaining ice balls are inconvenient to store. Therefore, the number of single-mold ice balls is not large, usually around 6, which is also difficult to meet the test requirements. In addition, the fastening effect of the multi-ice ball mold is poor, and long-term use will cause deformation due to the solidification and expansion of water ice. Existing conventional ice ball molds are mostly made of plastic, rubber and other materials, and the ice balls made have poor regularity and cannot meet the test requirements.
[0003] The utility model patent with the announcement number CN 202911040U was published on May 1, 2013. The name of the improved ice ball production mold is that the ice ball production mold includes a combined mold that can form a spherical mold cavity with a water injection port by closing the mold, and the mold cavity surface of each component of the combined mold is evenly coated with an oil film with a higher freezing point than water and insoluble in water. The ice ball production mold has a poor fastening effect and cannot ensure that the ice ball produced has good regularity. Utility Model Content
[0004] The utility model aims to provide an ice ball making mold which is convenient to use, not easy to deform and has good regularity of the ice ball made, in view of the deficiencies of the prior art.
[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0006] The ice ball making mold comprises a clamping plate, wherein the clamping plate comprises an upper clamping plate and a lower clamping plate, the mold is arranged between the upper clamping plate and the lower clamping plate, the mold comprises an upper mold and a lower mold, the upper mold is arranged at the upper end of the lower mold, and a fastening bolt is connected between the upper clamping plate and the lower clamping plate.
[0007] The exteriors of the upper mold and the lower mold are both stepped structures, the upper end of the upper mold is provided with a first step, the bottom end of the lower mold is provided with a second step, the upper clamping plate is provided with a first mounting hole, the lower clamping plate is provided with a second mounting hole, the first step is located in the first mounting hole, and the second step is located in the second mounting hole.
[0008] The bottom end of the upper mold is provided with a groove, and the top end of the lower mold is provided with a boss, and the groove cooperates with the boss.
[0009] The first mounting holes are evenly distributed on the upper clamping plate, and the second mounting holes are evenly distributed on the lower clamping plate. The first mounting holes and the second mounting holes are both distributed in a matrix.
[0010] A water injection hole is provided in the middle of the top end of the upper mold, and a chamfer is provided at the end of the water injection hole.
[0011] The first step diameter is smaller than the first mounting hole diameter, and the second step diameter is smaller than the second mounting hole diameter.
[0012] The fastening bolts are evenly distributed, and the fastening bolts press the upper clamping plate and are connected with the lower clamping plate.
[0013] A gasket is sleeved on the fastening bolt, and the fastening bolt presses the gasket.
[0014] The upper clamping plate, the lower clamping plate, the upper mold, the lower mold, the fastening bolts and the gasket are all made of stainless steel.
[0015] The technical effects of the utility model are as follows: by adopting the ice ball making mold of the utility model, through the use of a splint and a plurality of pairs of molds, under the tightening action of the fastening bolts, the mold is evenly stressed between the splints, and the deformation caused by the solidification and expansion of water after long-term use is slowed down, thereby ensuring the regularity of the ice ball, and achieving high efficiency in making ice balls, and batch production of ice balls can be achieved at a single time; the upper mold and the lower mold fit tightly, and are easy to assemble and disassemble, and a surplus space is provided between the mold and the splint, and the ice balls are easy to remove; each pair of modules independently prepares ice balls, and the process of opening the mold and taking out the ice balls is convenient, and it is also convenient to store the remaining ice balls; the mold assembly is made of stainless steel, and the risk of deformation is low, further ensuring that the regularity of the produced ice balls is good. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] This specification includes the following drawings, which show the following contents:
[0017] Figure 1 It is a three-dimensional schematic diagram of the installation of the ice ball mold of the utility model;
[0018] Figure 2 It is a schematic side view of the installation of the ice ball making mold of the utility model;
[0019] Figure 3 It is a cross-sectional schematic diagram of the upper mold of the utility model;
[0020] Figure 4 It is a cross-sectional schematic diagram of the lower mold of the utility model;
[0021] Figure 5 It is a top view schematic diagram of the upper clamping plate of the utility model;
[0022] Figure 6It is a top view schematic diagram of the lower clamping plate of the utility model;
[0023] Figure 7 It is a schematic top view of the installation of the ice ball making mold of the utility model.
[0024] The markings in the figure are: 1. upper clamping plate; 2. lower clamping plate; 3. upper mold; 4. lower mold; 5. fastening bolts; 6. gasket; 7. first mounting hole; 8. second mounting hole; 9. first step; 10. second step; 11. groove; 12. boss; 13. water injection hole; 14. chamfer. DETAILED DESCRIPTION
[0025] The specific implementation methods of the utility model are further explained in detail below with reference to the accompanying drawings through the description of embodiments, with the aim of helping those skilled in the art to have a more complete, accurate and in-depth understanding of the inventive concept and technical solution of the present invention and to facilitate their implementation.
[0026] like Figure 1 and Figure 2 As shown, the ice ball mold includes a clamp plate, the clamp plate includes an upper clamp plate 1 and a lower clamp plate 2, the mold is arranged between the upper clamp plate 1 and the lower clamp plate 2, the mold includes an upper mold 3 and a lower mold 4, the upper mold 3 is arranged at the upper end of the lower mold 4, and a fastening bolt 5 is connected between the upper clamp plate 1 and the lower clamp plate 2.
[0027] The ice ball mold includes two parallel clamps, multiple pairs of molds, fastening bolts 5 and gaskets 6. Each pair of molds can be nested together to prepare an ice ball. Multiple sets of molds can be clamped between the upper and lower clamps. The fastening bolts 5 are used to fasten the upper and lower molds 4 to prevent the ice ball from expanding and deforming. The upper end of the upper mold 3 is embedded in the upper clamp 1, and the bottom end of the lower mold 4 is embedded in the lower clamp 2. The mold is stably squeezed by the two clamps, which can reduce the expansion of the ice ball and stabilize the size of the ice ball molding cavity, thereby ensuring the regularity of the ice ball. Each pair of molds prepares an ice ball separately. After the ice ball is prepared, the upper and lower molds 4 can be stored separately with the ice ball. When the mold is opened to take out the ice ball, it will not affect other ice balls, so it will not cause the remaining ice balls to melt. At the same time, the remaining ice balls can also be conveniently stored.
[0028] like Figures 3 to 6As shown, the exterior of the upper mold 3 and the lower mold 4 are both stepped structures, the upper end of the upper mold 3 is provided with a first step 9, the bottom end of the lower mold 4 is provided with a second step 10, the upper clamping plate 1 is provided with a first mounting hole 7, the lower clamping plate 2 is provided with a second mounting hole 8, the first step 9 is located in the first mounting hole 7, and the second step 10 is located in the second mounting hole 8. The upper mold 3 and the lower mold 4 are both columnar structures. When the ice ball expands, the use of the columnar structure can make all parts of the mold cavity subject to the same expansion pressure, greatly reduce the deformation of the cavity structure, ensure the durability of the mold and ensure the regularity of the ice ball. The upper mold 3 and the lower mold 4 are both composed of two concentric cylinders with different diameters, where the end with a smaller diameter is a step end, which is used to correspond to the mounting holes of the upper and lower clamping plates. The step ends of the upper and lower molds 4 and the mounting holes of the upper and lower clamping plates can be changed to square, which is more convenient for removing the mold and can reduce the processing cost.
[0029] like Figure 3 and Figure 4 As shown, the bottom of the upper mold 3 is provided with a groove 11, and the top of the lower mold 4 is provided with a boss 12, and the groove 11 cooperates with the boss 12. The upper mold 3 and the lower mold 4 both include a cavity, and the cavity is a hemispherical structure. The two cavities are combined to form a sphere, which serves as the molding space for the ice ball. The upper mold 3 and the lower mold 4 use the groove 11 to cooperate with the boss 12. The combination method is tightly matched and convenient for installation and disassembly. When the ice ball is formed, the water in the cavity will not overflow, and the ice ball will have better regularity after forming.
[0030] like Figure 5 and Figure 6 As shown, the first mounting holes 7 are evenly distributed on the upper clamping plate 1, and the second mounting holes 8 are evenly distributed on the lower clamping plate 2. The first mounting holes 7 and the second mounting holes 8 are both distributed in a matrix. The diameter, hole spacing and size of the mold mounting holes are adjusted according to the size of the ice balls to be made. In the above structure, the first mounting holes 7 and the second mounting holes 8 make full use of the space of the clamping plate to achieve the effect of batch production of ice balls. The upper clamping plate 1 and the lower clamping plate 2 have the same size specifications, which is not only convenient to use, but also conducive to controlling processing costs.
[0031] like Figure 3 As shown, a water injection hole 13 is provided in the middle of the top of the upper mold 3, and a chamfer 14 is provided at the end of the water injection hole 13. The water injection hole 13 connects the cavity of the upper mold 3 with the outside. The water injection hole 13 is φ2mm and is used to inject pure water into the cavity. The chamfer 14 structure expands the space at the top of the water injection hole 13 to discharge the excess volume when the ice ball expands, further improves the regularity of the formed ice ball, and can also reduce the pressure of the water freezing expansion on the mold and the clamping plate.
[0032] like Figure 7As shown, the diameter of the first step 9 is smaller than the diameter of the first mounting hole 7, and the diameter of the second step 10 is smaller than the diameter of the second mounting hole 8. In the above structure, the diameter difference between the first step 9 and the first mounting hole 7 and the diameter difference between the second step 10 and the second mounting hole 8 are both 2 mm, leaving a margin of movement for the disassembly of each mold, making it convenient for the staff to take the mold from the splint.
[0033] like Figure 1 As shown, the fastening bolts 5 are evenly distributed, and the fastening bolts 5 press the upper clamping plate 1 and connect with the lower clamping plate 2. The fastening bolts 5 pass through the upper clamping plate 1 and are connected with the lower clamping plate 2 at the bottom. The fastening bolts 5 are arranged in a matrix, which improves the fastening effect of the two clamping plates on the mold, so that each pair of molds is subjected to the same pressure from the two clamping plates, ensuring the same regularity of the formed ice balls; the fastening bolts 5 are arranged around each pair of molds, which reduces the number of fastening bolts 5 used compared to using multiple single ice ball molds, and facilitates the assembly and disassembly operations of the staff.
[0034] like Figure 1 As shown, a gasket 6 is sleeved on the fastening bolt 5, and the fastening bolt 5 presses the gasket 6. The gasket 6 is used to disperse the pressure at the extrusion surface of the fastening bolt 5 to prevent the upper clamping plate 1 from being deformed and damaged, thereby further improving the uniformity of the fastening effect of the fastening bolt 5.
[0035] The upper clamping plate 1, the lower clamping plate 2, the upper mold 3, the lower mold 4, the fastening bolts 5 and the gasket 6 are all made of stainless steel. The use of stainless steel can prevent the above components from being corroded and damaged. The stainless steel has a certain structural strength and can resist the deformation caused by the expansion of the ice ball.
[0036] Take a single mold with 12 ice balls with a diameter of 35mm as an example: the upper clamping plate 1 has 12 φ37mm first mounting holes 7 evenly distributed, and 25 φ8.5mm through holes for the fastening bolts 5 to pass through, with a hole spacing of 47mm; the number, hole position and size of the lower clamping plate 2 are consistent with those of the upper clamping plate 1, and the connection hole connected to the fastening bolts 5 is an M8 threaded hole. The upper mold 3 has a size of φ45mm and a height of 22.5mm. The bottom of the upper mold 3 is a φ40mm, 2mm deep groove 11, the middle of the upper mold 3 and the lower mold 4 is a φ35mm concave hemispherical cavity, the φ35mm, 10mm high first step 9 is set in the first mounting hole 7, and the top of the upper mold 3 is provided with a φ2mm water injection hole 13 connected to the top of the hemispherical cavity, and the top of the water injection hole 13 is chamfered 14 with 1mm. The lower mold 4 has a size of φ45mm and a height of 20.5mm. A boss 12 with a φ40mm and a height of 2mm protrudes from the top of the lower mold 4. A second step 10 with a φ35mm and a height of 10mm is arranged in the second mounting hole 8. Each pair of step ends of the molds and the mounting holes of the splint have a 2mm movable space for easy separation.
[0037] The ice ball mold uses a clamping plate and multiple pairs of molds. Under the tightening action of the fastening bolts 5, the mold is uniformly stressed between the clamping plates, and the deformation caused by the solidification and expansion of water after long-term use is reduced, thereby ensuring the regularity of the ice ball, and the ice ball making efficiency is high, and batch ice balls can be made in a single time; the upper mold 3 and the lower mold 4 fit tightly, and are easy to assemble and disassemble, and a surplus space is provided between the mold and the clamping plate, so that the ice balls are easy to remove; each pair of modules independently prepares ice balls, and the process of opening the mold to take out the ice balls is convenient, and it is also convenient to store the remaining ice balls; the mold assembly is made of stainless steel, and the deformation risk is low, which further ensures that the ice balls produced have good regularity.
[0038] The above is an exemplary description of the utility model in conjunction with the accompanying drawings. Obviously, the specific implementation of the utility model is not limited to the above-mentioned method. As long as various non-substantial improvements are made using the method concept and technical solution of the utility model; or the above concept and technical solution of the utility model are directly applied to other occasions without improvement, they are all within the protection scope of the utility model.
Claims
1. An ice ball mold, characterized in that: The invention comprises a clamping plate, wherein the clamping plate comprises an upper clamping plate (1) and a lower clamping plate (2), the mold is arranged between the upper clamping plate (1) and the lower clamping plate (2), the mold comprises an upper mold (3) and a lower mold (4), the upper mold (3) is arranged at the upper end of the lower mold (4), and a fastening bolt (5) is connected between the upper clamping plate (1) and the lower clamping plate (2).
2. The ice ball mold according to claim 1, characterized in that: The exteriors of the upper mold (3) and the lower mold (4) are both stepped structures, the upper end of the upper mold (3) is provided with a first step (9), the bottom end of the lower mold (4) is provided with a second step (10), the upper clamping plate (1) is provided with a first mounting hole (7), the lower clamping plate (2) is provided with a second mounting hole (8), the first step (9) is located in the first mounting hole (7), and the second step (10) is located in the second mounting hole (8).
3. The ice ball mold according to claim 2, characterized in that: The bottom end of the upper mold (3) is provided with a groove (11), and the top end of the lower mold (4) is provided with a boss (12), and the groove (11) cooperates with the boss (12).
4. The ice ball mold according to claim 2, characterized in that: The first mounting holes (7) are evenly distributed on the upper clamping plate (1), and the second mounting holes (8) are evenly distributed on the lower clamping plate (2); the first mounting holes (7) and the second mounting holes (8) are both distributed in a matrix.
5. The ice ball mold according to any one of claims 1 to 4, characterized in that: A water injection hole (13) is provided in the middle of the top end of the upper mold (3), and a chamfer (14) is provided at the end of the water injection hole (13).
6. The ice ball mold according to claim 2, characterized in that: The diameter of the first step (9) is smaller than the diameter of the first mounting hole (7), and the diameter of the second step (10) is smaller than the diameter of the second mounting hole (8).
7. The ice ball mold according to claim 5, characterized in that: The fastening bolts (5) are evenly distributed, and the fastening bolts (5) press the upper clamping plate (1) and are connected to the lower clamping plate (2).
8. The ice ball mold according to claim 7, characterized in that: A gasket (6) is sleeved on the fastening bolt (5), and the fastening bolt (5) presses the gasket (6).
9. The ice ball mold according to claim 8, characterized in that: The upper clamping plate (1), the lower clamping plate (2), the upper mold (3), the lower mold (4), the fastening bolts (5) and the gasket (6) are all made of stainless steel.
Citation Information
Cited By
Simple and efficient ice hockey mold
CN224956985U