Flue gas slitting air leakage treatment device for boiler air pre-heater

By setting up an air induced mechanism in the boiler air preloader to form a high-pressure flue gas sealing wall, the problem of high air leakage rate of the air preloader is solved, the combustion efficiency and excess air coefficient are improved, and the power consumption and environmental pollution are reduced.

CN222104510UActive Publication Date: 2024-12-03NANJING CHONON ENERGY SAVING TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323521812.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-22
Publication Date
2024-12-03
Estimated Expiration
2033-12-22

AI Technical Summary

Technical Problem

The mushroom-like deformation and wear of the sealing sheet caused by the thermal operation of the boiler air preload leads to an increase in air leakage rate, affecting combustion stability and power consumption, and cannot guarantee sufficient excess air coefficient at high loads.

Method used

A boiler air pre-driving flue gas slitting air leakage control device is designed. By setting up an air induced mechanism in the heat exchange and partition chamber to form a high-pressure flue gas sealing wall to prevent leakage from the primary and secondary wind direction flue gas side, and heat storage is carried out. The component replaces the air in the air into smoke to reduce air leakage when the rotor rotates.

Benefits of technology

The air leakage rate of the air preloader is effectively reduced, so that the radial air leakage rate on the primary and secondary air sides is close to zero, improving combustion efficiency and excess air coefficient, and reducing power consumption and environmental pollution.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222104510U_ABST
    Figure CN222104510U_ABST
Patent Text Reader

Abstract

The utility model discloses a boiler air pre-heater flue gas slitting air leakage treatment device which comprises a heat exchange mechanism and an air inducing mechanism, the heat exchange mechanism comprises an outer shell, a heat exchange sub-bin is formed in the outer shell, a rotor is rotationally connected to the center of the interior of the heat exchange sub-bin, a rotary drum is fixedly installed on the outer surface of the rotor, and an air outlet is formed in the outer shell. A primary air pipe is arranged at the front end of the left side of the outer shell, a secondary air pipe is arranged at the rear end of the left side of the outer shell, a flue gas pipeline is arranged on the right side of the outer shell, a strand of high-pressure flue gas can be introduced into the heat exchange branch bins through an air inducing mechanism, a high-pressure flue gas sealing wall is formed, and leakage of the primary air and the secondary air towards the flue gas side can be effectively prevented; the radial air leakage rate of the primary air side and the secondary air side is close to zero, meanwhile, primary air in the area B is effectively replaced by high-speed flue gas, carried air in the heat storage element is replaced by flue gas, and the carried air leakage rate of the primary air side of the rotor rotating to the flue gas side is zero.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of boiler auxiliary equipment, in particular to a boiler air preheater flue gas cutting and air leakage treatment device. Background Art

[0002] When the air preheater is running in hot state, due to the heat exchange inside the rotor, the average temperature of the upper part is high and the average temperature of the lower part is low, so a "mushroom-shaped" deformation will occur, making the triangular air leakage gap at the bottom of the rotor and the axial air leakage gap of the rotor circumference smaller than that in the cold state, while the air leakage gap at the top of the rotor becomes larger than that in the cold state. The air leakage volume also increases significantly, becoming the main air leakage of the air preheater. Moreover, with the increase of boiler load and the increase of heat exchange of the air preheater rotor, the above-mentioned "mushroom-shaped" deformation becomes more obvious, and the changes in the air leakage gaps at various locations become greater.

[0003] In addition, the rotor will also produce axial expansion and bending deformation of the lower beam, there is a gap between the moving and static parts of the air preheater, there is a pressure difference between the primary air, secondary air and flue gas flowing through the three compartments of the air preheater, and because the air preheater components are large, deviations are continuously accumulated from manufacturing to installation, resulting in air leakage. Moreover, with the increase of operating time, the mushroom-shaped deformation of the rotor during operation, the wear of the sealing plate, the debugging and positioning of the fan plate and other factors will cause the air preheater leakage rate to increase.

[0004] The increase in the air preheater leakage rate will lead to an increase in the power consumption of the three major fans, or even insufficient output. It cannot ensure a sufficient excess air coefficient at high load, affecting the combustion stability of the boiler, causing the exhaust gas temperature to rise, fly ash combustibles to exceed the standard, boiler coking, air preheater blockage, and low-temperature corrosion. In severe cases, the boiler is forced to operate at limited output and the unit is reduced in load, which directly affects the safety of the unit. Utility Model Content

[0005] The purpose of this section is to summarize some aspects of the embodiments of the utility model and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the abstract of the specification and the name of the utility model of this application to avoid blurring the purpose of this section, the abstract of the specification and the name of the utility model, and such simplifications or omissions cannot be used to limit the scope of the utility model.

[0006] In view of the above problems and / or the problems existing in the prior art, the present utility model is proposed.

[0007] Therefore, the technical problem to be solved by the utility model is that the existing boiler air preheater has a high air leakage rate, which will lead to increased power consumption of the three major fans, and cannot ensure sufficient excess air coefficient under high load, affecting the combustion stability of the boiler.

[0008] In order to solve the above technical problems, the utility model provides the following technical solutions: a boiler air preheater flue gas splitting and air leakage control device, including a heat exchange mechanism and an induced draft mechanism, wherein:

[0009] The heat exchange mechanism comprises an outer shell, a heat exchange compartment is provided inside the outer shell, a rotor is rotatably connected at the center of the heat exchange compartment, a rotating drum is fixedly installed on the outer surface of the rotor, a primary air duct is provided at the front end of the left side of the outer shell, and a secondary air duct is provided at the rear end, and a flue gas duct is provided on the right side of the outer shell;

[0010] The air induction mechanism includes a booster fan arranged at the bottom of the outer shell, the input port of the booster fan is connected to an air inlet pipe, the output end of the booster fan is connected to a first exhaust pipe, and the top end of the first exhaust pipe is connected to a second exhaust pipe.

[0011] As a preferred solution of the boiler air preheater flue gas splitting and air leakage treatment device of the utility model, wherein: the interior of the rotating drum is provided with a partition, and a total of a plurality of partitions are provided, and heat storage elements are installed in the plurality of partitions.

[0012] As a preferred solution of the boiler air preheater flue gas splitting and air leakage control device described in the utility model, the left end of the heat exchange compartment is the wind side, the right end is the flue gas side, the primary air duct and the secondary air duct are connected to the wind side, and the flue gas duct is connected to the flue gas side.

[0013] As a preferred solution of the boiler air preheater flue gas splitting and air leakage control device described in the utility model, wherein: a first air guide frame is fixedly installed at the rear end of the bottom of the heat exchange compartment, and a second air guide frame is fixedly installed at the front end, the input end of the first exhaust duct is connected to the first air guide frame, and the input end of the second exhaust duct is connected to the second air guide frame.

[0014] As a preferred solution of the boiler air preheater flue gas splitting and air leakage treatment device of the utility model, valves are installed inside the air inlet pipe, the first exhaust pipe and the second exhaust pipe.

[0015] As a preferred solution of the boiler air preheater flue gas splitting and leakage control device of the utility model, wherein: the first exhaust duct discharges into the flue gas forming area A in the heat exchange sub-chamber, and the second exhaust duct discharges into the flue gas forming area B in the heat exchange sub-chamber.

[0016] The beneficial effects of the utility model are as follows: a stream of high-pressure flue gas can be introduced into the heat exchange compartment through the arranged induced draft mechanism to form a high-pressure flue gas sealing wall, and the high-pressure airtight wind wall is formed at the junction of the flue gas side and the wind side, which can effectively prevent the leakage of the primary and secondary air to the flue gas side, so that the radial air leakage rate of the primary and secondary air sides is close to zero, and at the same time, the high-speed flue gas effectively replaces the primary air in area B, and the carried air in the heat storage element is replaced by flue gas, so that the primary air side of the rotor rotates to the smoke side and the carried air leakage is zero. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present utility model, the following briefly introduces the drawings required for the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them:

[0018] Figure 1 It is a three-dimensional structural diagram of the utility model;

[0019] Figure 2 It is a side sectional view of the utility model;

[0020] Figure 3 It is a three-dimensional diagram of the drum and the rotor of the utility model;

[0021] Figure 4 It is a top sectional view of the utility model;

[0022] Figure 5 It is a schematic diagram of the structure of the utility model in which flue gas is discharged into the heat exchange compartment. DETAILED DESCRIPTION

[0023] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.

[0024] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0025] Secondly, the present invention is described in detail with reference to the schematic diagram. When describing the embodiments of the present invention, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general proportion, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0026] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0027] Example

[0028] Reference Figures 1 to 5 The present embodiment provides a boiler air preheater flue gas splitting and air leakage control device, including a heat exchange mechanism 100 and an induced draft mechanism 200, wherein the heat exchange mechanism 100 is the air preheater body, which can realize heat exchange between flue gas and air, and transfer the heat in the flue gas to the air entering the boiler combustion chamber. The preheated air can provide a higher temperature and oxygen content, thereby promoting complete and efficient combustion. The setting of the induced draft mechanism 200 can form a high-pressure flue gas sealing wall in the heat exchange compartment 102, preventing air from directly flowing into the flue gas, resulting in increased wind pressure on one side, causing air leakage.

[0029] Specifically, the heat exchange mechanism 100 includes an outer shell 101, a heat exchange compartment 102 is provided inside the outer shell 101, a rotor 103 is rotatably connected to the center of the heat exchange compartment 102, a drum 104 is fixedly installed on the outer surface of the rotor 103, a primary air duct 105 is provided at the front end of the left side of the outer shell 101, and a secondary air duct 106 is provided at the rear end, and a flue gas duct 107 is provided on the right side of the outer shell 101, wherein a compartment 104a is provided inside the drum 104, and a plurality of compartments 104a are provided, and each of the plurality of compartments 104a is installed There is a heat storage element. When the hot flue gas discharged from the boiler enters the heat exchange compartment 102 through the flue gas duct 107, the heat inside the flue gas can be transferred to the heat storage element. At this time, after the air enters the heat exchange compartment 102 through the primary air duct 105 and the secondary air duct 106, the heat transferred by the heat storage element can heat the air, thereby increasing the temperature and oxygen content of the air. After the air is discharged and enters the boiler, the fuel can be burned more fully, thereby improving the combustion efficiency. At the same time, the flue gas temperature and the emission of harmful substances in the flue gas can be reduced, thereby helping to reduce environmental pollution.

[0030] The description of the above structure explains the main components and brief working principle of the air preheater in the prior art, but the air preheater in the prior art still has some shortcomings: there is a pressure difference between the primary air, secondary air and flue gas, and because the air preheater components are large, deviations are continuously accumulated from manufacturing to installation, resulting in air leakage. Moreover, as the operating time increases, the mushroom-shaped deformation of the rotor during operation, the wear of the sealing plate, the debugging and positioning of the fan plate and other factors will cause the power consumption of the three major fans to increase, and a sufficient excess air coefficient cannot be guaranteed at high load, affecting the combustion stability of the boiler.

[0031] In view of the shortcomings of the air preheater in the prior art, the device adds an air induction mechanism 200 to effectively solve the problem of serious air leakage in the air preheater.

[0032] Specifically, the induced draft mechanism 200 includes a booster fan 201 arranged at the bottom of the outer shell 101, the input port of the booster fan 201 is connected to the air inlet pipe 202, and the input end of the air inlet pipe 202 is connected to the induced draft fan, the smoke outlet end of the induced draft fan is connected to the inlet end of the air inlet pipe 202, and the induced draft fan can be used to enable the air inlet pipe 202 to introduce clean smoke that has passed through the electrostatic precipitator, the output end of the booster fan 201 is connected to the first exhaust pipe 203, the top of the first exhaust pipe 203 is connected to the second exhaust pipe 204, and the output ports of the first exhaust pipe 203 and the second exhaust pipe 204 are both connected to the interior of the heat exchange compartment 102, so that when the booster fan 201 is running, clean dust-free smoke can be introduced through the air inlet pipe 202, and a high-pressure smoke is formed and discharged into the heat exchange compartment 102 through the first exhaust pipe 203 and the second exhaust pipe 204.

[0033] Furthermore, the left end of the heat exchange compartment 102 is the wind side, and the right end is the smoke side, the primary air duct 105 and the secondary air duct 106 are connected to the wind side, the smoke duct 107 is connected to the smoke side, and the first air guide frame 205 is fixedly installed at the rear end of the bottom of the heat exchange compartment 102, and the second air guide frame 206 is fixedly installed at the front end, the input end of the first exhaust duct 203 is connected to the first air guide frame 205, and the input end of the second exhaust duct 204 is connected to the second air guide frame 206. When the high-pressure smoke enters the heat exchange compartment 102 through the first exhaust duct 203 and the second exhaust duct 204, it can form wind walls in the shape of area A and area B under the guidance of the first air guide frame 205 and the second air guide frame 206, and as shown in FIG. Figure 5 As shown, the wind wall formed by area A and area B is at the junction of the smoke side and the wind side, which can effectively prevent the leakage of the primary and secondary air to the smoke side, making the radial leakage rate of the primary and secondary air sides close to zero. At the same time, the high-speed smoke effectively replaces the primary air in area B, and the carried wind in the heat storage element is replaced by smoke, so that the primary air side of the rotor rotates to the smoke side and the carried air leakage is zero.

[0034] Preferably, valves 207 are installed inside the air inlet pipe 202, the first exhaust pipe 203 and the second exhaust pipe 204. The valves 207 can facilitate the staff to control the entry of smoke. At the same time, when not in use, the gas in the heat exchange compartment 102 can be prevented from leaking through the air inlet pipe 202, the first exhaust pipe 203 and the second exhaust pipe 204.

[0035] Importantly, it should be noted that the construction and arrangement of the present application shown in a plurality of different exemplary embodiments are only exemplary. Although only a few embodiments are described in detail in this disclosure, it should be readily understood by those who refer to this disclosure that many modifications are possible (e.g., the size, scale, structure, shape and ratio of various elements, and parameter values ​​(e.g., temperature, pressure, etc.), installation arrangements, use of materials, color, directional changes, etc.) without substantially departing from the novel teachings and advantages of the subject matter described in the application. For example, the element shown as integrally formed can be composed of multiple parts or elements, the position of the element can be inverted or otherwise changed, and the nature or number or position of the discrete element can be changed or changed. Therefore, all such modifications are intended to be included in the scope of the present utility model. The order or sequence of any process or method steps can be changed or reordered according to alternative embodiments. In the claims, any "device plus function" clause is intended to cover the structure of performing the function described herein, and is not only structurally equivalent but also equivalent structure. Without departing from the scope of the present invention, other substitutions, modifications, changes and omissions may be made in the design, operating conditions and arrangement of the exemplary embodiments. Therefore, the present invention is not limited to a specific embodiment, but extends to various modifications that still fall within the scope of the appended claims.

[0036] Additionally, in order to provide a concise description of example embodiments, all features of an actual embodiment (ie, those features that are not relevant to the best mode presently contemplated for carrying out the invention or those features that are not relevant to implementing the invention) may not be described.

[0037] It will be appreciated that in the development of any actual implementation, as in any engineering or design project, numerous implementation-specific decisions may be made. Such a development effort may be complex and time-consuming, but will be a routine task of design, fabrication, and production for those of ordinary skill having the benefit of this disclosure without undue experimentation.

[0038] It should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.

Claims

1. A boiler air preheater flue gas splitting and air leakage control device, characterized in that: include, A heat exchange mechanism (100) comprises an outer shell (101), a heat exchange compartment (102) is provided inside the outer shell (101), a rotor (103) is rotatably connected at the center of the heat exchange compartment (102), a rotating drum (104) is fixedly mounted on the outer surface of the rotor (103), a primary air duct (105) is provided at the front end of the left side of the outer shell (101), and a secondary air duct (106) is provided at the rear end, and a flue gas duct (107) is provided on the right side of the outer shell (101); and, The air induction mechanism (200) comprises a booster fan (201) arranged at the bottom of the outer shell (101), the input port of the booster fan (201) is connected to an air inlet pipe (202), the output end of the booster fan (201) is connected to a first exhaust pipe (203), and the top end of the first exhaust pipe (203) is connected to a second exhaust pipe (204).

2. The boiler air preheater flue gas splitting and air leakage treatment device according to claim 1 is characterized in that: The interior of the rotating drum (104) is provided with a partition (104a), and a plurality of partitions (104a) are provided, and a heat storage element is installed in each of the plurality of partitions (104a).

3. The boiler air preheater flue gas splitting and air leakage treatment device according to claim 2 is characterized in that: The left end of the heat exchange compartment (102) is the wind side, and the right end is the smoke side. The primary air duct (105) and the secondary air duct (106) are connected to the wind side, and the smoke duct (107) is connected to the smoke side.

4. The boiler air preheater flue gas splitting and air leakage treatment device according to claim 3 is characterized in that: A first air guide frame (205) is fixedly installed at the rear end of the bottom of the heat exchange compartment (102), and a second air guide frame (206) is fixedly installed at the front end; an input end of the first exhaust duct (203) is connected to the first air guide frame (205), and an input end of the second exhaust duct (204) is connected to the second air guide frame (206).

5. The boiler air preheater flue gas splitting and air leakage treatment device according to claim 4 is characterized in that: Valves (207) are installed inside the air inlet pipe (202), the first air outlet pipe (203) and the second air outlet pipe (204).

6. The boiler air preheater flue gas splitting and air leakage treatment device according to claim 5 is characterized in that: The first exhaust duct (203) discharges into a smoke forming area A in the heat exchange sub-chamber (102), and the second exhaust duct (204) discharges into a smoke forming area B in the heat exchange sub-chamber (102).