The invention belongs to the technical field of quick disassembly of air pre-heater pipes, and particularly relates to a quick disassembly and
assembly method for boiler air pre-heater pipes, the number of the boiler air pre-heater pipes is multiple, the multiple boiler air pre-heater pipes are combined into one or more boiler air pre-heater
pipe modules, and the quick disassembly and
assembly method for the boiler air pre-heater pipes comprises the following steps that S1, chemical
softening is conducted; s2, dismantling an old module; s3, cleaning the mounting position; s4, cleaning old modules; s5, a new boiler air pre-heater
pipe module is installed, the defects in the prior art are overcome, aiming at the technical problem that long time is needed for disassembly,
assembly and replacement of an existing boiler air pre-heater
pipe, the boiler air pre-heater pipe is prefabricated into the module, then during disassembly and assembly, chemical
softening is adopted firstly to reduce the mechanical
cutting difficulty, and then the prefabricated module is adopted to reduce the field
operation time; the time of field operation is shortened to the maximum extent, a large amount of time needed for field operation originally is converted to other positions for operation, and it is guaranteed that the boiler can rapidly recover to work.