Silane fluidized bed tail gas adsorption device

By using a series control and gas phase detection system of multiple adsorption towers in the silane fluidized bed exhaust gas adsorption device, the valve opening and closing is automatically adjusted, which solves the problem of poor processing efficiency and flexibility in the prior art, and achieves more efficient exhaust gas treatment and productivity.

CN222111369UActive Publication Date: 2024-12-06JIANGSU ZHONGNENG POLYSILICON TECH DEV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420658914.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-02
Publication Date
2024-12-06
Estimated Expiration
2034-04-02

AI Technical Summary

Technical Problem

The existing silane fluidized bed exhaust gas adsorption device has poor processing efficiency and flexibility, complex operation, involving multiple valves that require manual operation, which is easy to operate incorrectly, affecting production efficiency.

Method used

At least two adsorption towers are connected in series, controlled through series pipelines and control valves, combined with the gas phase detection system to obtain qualitative and quantitative analysis results, automatically adjust valve opening and closing, realize the analysis and regeneration process of adsorption tower, reduce manual participation, and improve efficiency.

Benefits of technology

It improves the analytical efficiency and processing flexibility of the adsorption tower, reduces manual misoperation, and enhances the production efficiency and protection of the silane fluidized bed exhaust adsorption device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222111369U_ABST
    Figure CN222111369U_ABST
Patent Text Reader

Abstract

The utility model discloses a silane fluidized bed tail gas adsorption device in the technical field of silane production, and aims to solve the problems of poor desorption efficiency and flexibility and complex operation of an adsorption tower in the prior art. The method comprises the following steps: connecting adsorption towers in series end to end, detecting qualitative and quantitative information of each adsorption tower through a gas phase detection system, selecting a to-be-analyzed adsorption tower, isolating the to-be-analyzed adsorption tower through opening and closing of a control valve, connecting the adsorption towers into a series loop after the adsorption towers complete the analysis, the adsorption towers with different working efficiencies are in an optimal tail gas treatment sequence by adjusting the opening and closing of the control valves, so that the desorption efficiency of the adsorption towers is improved, and the treatment is more flexible; each control valve is controlled through the valve control system, so that the problems of misoperation of personnel and the like during regeneration of the adsorption tower are solved, and the heating and cooling treatment efficiency of the adsorption tower is further improved; the monitoring of the gas phase detection system on the adsorption tower is matched with the control of a plurality of valves, so that the whole silane fluidized bed tail gas adsorption device can be conveniently protected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a silane fluidized bed tail gas adsorption device, belonging to the technical field of silane production. Background Art

[0002] Granular silicon is one of the mainstream processes for producing polysilicon, and the silane gas synthesis section is an important part of the granular silicon production process. The silane tail gas device in the granular silicon production section needs to regenerate and analyze the adsorption tower during the tail gas treatment process. This process requires the adsorption tower to be isolated, depressurized, heated, cooled, pressurized, and systemized. The process is cumbersome, involving many valves, and requires 1 to 2 people to cooperate in the operation. At the same time, the operator is prone to opening and closing the valve by mistake, which affects production efficiency, and the processing efficiency and flexibility are poor. Utility Model Content

[0003] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a silane fluidized bed tail gas adsorption device with good processing efficiency and flexibility and simple operation.

[0004] To achieve the above objectives, the present disclosure is implemented by adopting the following technical solutions:

[0005] In a first aspect, the present disclosure provides a silane fluidized bed tail gas adsorption device, comprising:

[0006] At least two adsorption towers, the outlets and inlets of adjacent adsorption towers are connected in series in sequence through series pipelines, the inlet of the first adsorption tower is also connected to the outlet of the last adsorption tower through series pipelines, and each series pipeline is controlled by a series control valve;

[0007] The inlets of the adsorption towers are all connected to the tail gas inlet pipeline, and the inlet of each adsorption tower is independently controlled by a tail gas inlet control valve;

[0008] The outlets of the adsorption towers are all connected to the tail gas outlet pipeline, and the outlet of each adsorption tower is independently controlled by a tail gas outlet control valve;

[0009] The outlets of the adsorption towers are all connected to the temperature-controlled gas inlet pipeline, and the outlet of each adsorption tower is independently controlled by a temperature-controlled gas inlet control valve;

[0010] The tops of the adsorption towers are connected to the temperature-controlled gas outlet pipeline, and the tops of the adsorption towers are independently controlled by temperature-controlled gas outlet control valves.

[0011] It also includes a valve control system, all control valves are solenoid valves, and the valve control module is connected to all control valves by electrical signals; it also includes a gas phase detection system connected to the valve control module by electrical signals, and the gas phase detection system is connected to the adsorption tower for obtaining qualitative and quantitative analysis results of each adsorption tower.

[0012] Optionally, in some embodiments of the first aspect of the present disclosure, the adsorption tower includes at least a first adsorption tower and a second adsorption tower, the outlet of the first adsorption tower and the inlet of the second adsorption tower are connected through a first series pipeline, the series control valve includes a seventh valve arranged in the first series pipeline, and the outlet of the second adsorption tower is connected to the inlet of the first adsorption tower directly or with the adsorption tower separated.

[0013] Optionally, in some embodiments of the first aspect of the present disclosure, the adsorption tower further includes at least a third adsorption tower, the outlet of the second adsorption tower is connected to the inlet of the third adsorption tower through a second series pipeline, the outlet of the third adsorption tower is connected to the inlet of the first adsorption tower through a third series pipeline, and the series control valve also includes an eighth valve provided in the second series pipeline and a ninth valve provided in the third series pipeline.

[0014] Optionally, in some embodiments of the first aspect of the present disclosure,

[0015] The inlet of the first adsorption tower is connected to the tail gas inlet pipeline through a first valve;

[0016] The inlet of the second adsorption tower is connected to the tail gas inlet pipeline through a second valve;

[0017] The inlet of the third adsorption tower is connected to the tail gas inlet pipeline through a third valve.

[0018] Optionally, in some embodiments of the first aspect of the present disclosure,

[0019] The outlet of the first adsorption tower is connected to the tail gas outlet pipeline through a thirteenth valve;

[0020] The outlet of the second adsorption tower is connected to the tail gas outlet pipeline through a fourteenth valve;

[0021] The outlet of the third adsorption tower is connected to the tail gas outlet pipeline through the fifteenth valve.

[0022] Optionally, in some embodiments of the first aspect of the present disclosure,

[0023] The top of the first adsorption tower is connected to the temperature-controlled gas outlet pipeline through a fourth valve;

[0024] The top inlet of the second adsorption tower is connected to the temperature-controlled gas outlet pipeline through a fifth valve;

[0025] The top inlet of the third adsorption tower is connected to the temperature-controlled gas outlet pipeline through a sixth valve.

[0026] Optionally, in some embodiments of the first aspect of the present disclosure,

[0027] The outlet of the first adsorption tower is connected to the temperature-controlled gas inlet pipeline through a twelfth valve;

[0028] The outlet of the second adsorption tower is connected to the temperature-controlled gas inlet pipeline through an eleventh valve;

[0029] The outlet of the third adsorption tower is connected to the temperature-controlled gas inlet pipeline through a tenth valve.

[0030] Optionally, in some embodiments of the first aspect of the present disclosure,

[0031] The inlet of the first adsorption tower is connected to the tail gas inlet pipeline through a first valve;

[0032] The inlet of the second adsorption tower is connected to the tail gas inlet pipeline through a second valve;

[0033] The inlet of the third adsorption tower is connected to the tail gas inlet pipeline through a third valve;

[0034] The outlet of the first adsorption tower is connected to the tail gas outlet pipeline through a thirteenth valve;

[0035] The outlet of the second adsorption tower is connected to the tail gas outlet pipeline through a fourteenth valve;

[0036] The outlet of the third adsorption tower is connected to the tail gas outlet pipeline through a fifteenth valve;

[0037] The top of the first adsorption tower is connected to the temperature-controlled gas outlet pipeline through a fourth valve;

[0038] The top of the second adsorption tower is connected to the temperature-controlled gas outlet pipeline through a fifth valve;

[0039] The top of the third adsorption tower is connected to the temperature-controlled gas outlet pipeline through a sixth valve.

[0040] Compared with the prior art, the present invention has the following beneficial effects:

[0041] The silane fluidized bed tail gas adsorption device provided by the present invention connects adsorption towers in series end to end, detects qualitative and quantitative information of each adsorption tower through a gas phase detection system, selects the adsorption tower to be analyzed, isolates the adsorption tower to be analyzed by opening and closing a control valve, and integrates the adsorption tower into a series loop after the analysis is completed. By adjusting the opening and closing of the control valve, the adsorption towers with different working efficiencies are placed in the best tail gas treatment sequence, thereby improving the analysis efficiency of the adsorption tower and making the treatment more flexible; the valve control system controls each control valve to solve the problem of human misoperation during the regeneration of the adsorption tower, thereby improving the heating and cooling treatment efficiency of the adsorption tower; the gas phase detection system monitors the adsorption tower in coordination with the control of multiple valves, so as to protect the entire silane fluidized bed tail gas adsorption device. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] In order to more clearly illustrate the technical solutions in the present disclosure or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0043] Figure 1 is a schematic diagram of the connection structure of the silane fluidized bed tail gas adsorption device provided in this embodiment;

[0044] Figure 2 is a flow chart of the steps of the desorption method of the adsorption tower of the silane fluidized bed tail gas adsorption device provided in this embodiment;

[0045] In the figure: 1-first valve; 2-second valve; 3-third valve; 4-fourth valve; 5-fifth valve; 6-sixth valve; 7-seventh valve; 8-eighth valve; 9-ninth valve; 10-tenth valve; 11-eleventh valve; 12-twelfth valve; 13-thirteenth valve; 14-fourteenth valve; 15-fifteenth valve; 16-sixteenth valve;

[0046] 21-exhaust gas inlet pipeline; 22-exhaust gas outlet pipeline; 23-temperature control gas inlet pipeline; 24-temperature control gas outlet pipeline;

[0047] 90-adsorption tower; 91-first adsorption tower; 92-second adsorption tower; 93-third adsorption tower;

[0048] 911 - first series pipeline; 912 - second series pipeline; 913 - third series pipeline. DETAILED DESCRIPTION

[0049] The following will be combined with the drawings in the embodiments of the present disclosure / the present application to clearly and completely describe the technical solutions in the embodiments of the present disclosure / the present application. Obviously, the described embodiments are only part of the embodiments of the present disclosure / the present application, rather than all the embodiments. The following description of at least one exemplary embodiment is actually only illustrative and is by no means intended to limit the present disclosure / the present application and its application or use. Embodiment 1

[0050] This embodiment provides a silane fluidized bed tail gas adsorption device to solve the problems of poor processing efficiency and flexibility and complex operation of the silane fluidized bed tail gas adsorption device in the prior art.

[0051] Optionally, in a further preferred but non-limiting embodiment of the present application, reference is made to Figure 1 The temperature-controlled gas uses regeneration gas, and the source of the regeneration gas can be the tail gas treated by the adsorption tower 90.

[0052] refer to Figure 1 The silane fluidized bed tail gas adsorption device provided in this embodiment includes at least two adsorption towers 90, and the outlets and inlets of adjacent adsorption towers 90 are connected in series in sequence through series pipes. The inlet of the first adsorption tower 90 and the outlet of the last adsorption tower 90 are also connected through series pipes, so that the adsorption towers 90 are connected to each other to form a loop. Each series pipe is controlled by a series control valve. By closing a specific series control valve, a path for the tail gas to flow in and out is formed on the loop, and the adsorption tower 90 that needs to be analyzed is isolated; the adjacent adsorption towers 90 and the last adsorption tower 90 and the first adsorption tower 90 are controlled by series control valves, thereby achieving protection.

[0053] The inlets of the adsorption towers 90 are connected to the exhaust gas inlet pipeline 21, and the inlet of each adsorption tower 90 is independently controlled by an exhaust gas inlet control valve; the outlets of the adsorption towers 90 are connected to the exhaust gas outlet pipeline 22, and the outlet of each adsorption tower 90 is independently controlled by an exhaust gas outlet control valve; the outlets of the adsorption towers 90 are connected to the temperature-controlled gas inlet pipeline 23, and the outlet of each adsorption tower 90 is independently controlled by a temperature-controlled gas inlet control valve; the tops of the adsorption towers 90 are connected to the temperature-controlled gas outlet pipeline 24, and the tops of each adsorption tower 90 are independently controlled by a temperature-controlled gas outlet control valve; the above-mentioned control valves independently control the entry and exit of the temperature-controlled gas or exhaust gas for each adsorption tower 90, which is convenient for isolating or merging a single adsorption tower 90.

[0054] It also includes a valve control module, all control valves are solenoid valves, and the valve control module is connected to all control valves by electrical signals; it also includes a valve control system connected to the valve control module by electrical signals, all control valves are solenoid valves, and the valve control module is connected to all control valves by electrical signals; it also includes a gas phase detection system, which is connected to the adsorption tower 90 and is used to obtain qualitative and quantitative analysis results of each adsorption tower 90.

[0055] The valve control module can adopt an automatic control module, which switches different valves according to the set switching rules or the qualitative and quantitative analysis results of different adsorption towers 90. The valve control module can also be an operation panel. Workers switch different valves through the operation panel according to the work flow and the qualitative and quantitative analysis results of each adsorption tower 90, thereby improving the efficiency of valve switching. At the same time, different control valves are switched according to the results of the gas phase detection system to protect the entire silane fluidized bed exhaust gas adsorption device.

[0056] Optionally, a non-exclusive method of analyzing the adsorption tower 9 in the order of tail gas treatment is:

[0057] Isolation stage: After completing a certain amount of exhaust gas adsorption work, the adsorption tower to be analyzed is selected from all adsorption towers 90 according to the qualitative and quantitative analysis results of the temperature-controlled gas and exhaust gas by the gas phase detection system. In this stage, the exhaust gas inlet control valve and the exhaust gas outlet control valve of the adsorption tower to be analyzed are kept closed, the temperature-controlled gas inlet control valve and the temperature-controlled gas outlet control valve of the adsorption tower to be analyzed are closed, and the series control valve between the adsorption tower to be analyzed and other adsorption towers 90 is also closed to isolate the adsorption tower to be analyzed from the loop.

[0058] Pressure relief stage: open the temperature-controlled gas outlet control valve of the adsorption tower to be analyzed, discharge the gas in the adsorption tower to be analyzed, and reduce the pressure in the adsorption tower to be analyzed.

[0059] Heating stage: open the temperature-controlled gas inlet control valve of the adsorption tower to be analyzed, add temperature-controlled gas to the adsorption tower to be analyzed, and heat the adsorption tower to be analyzed to the set analysis high temperature. The pollutants are analyzed out of the adsorption tower to be analyzed. The adsorption tower 90 generally absorbs the pollutants in the exhaust gas through activated carbon.

[0060] Cooling stage: The temperature of the adsorption tower to be analyzed is lowered to the set low temperature, forming a low temperature environment suitable for the adsorption of tail gas in the adsorption tower to be analyzed. This stage can be achieved by changing the source of the temperature control gas, for example, the source of the temperature control gas can be composed of part of the tail gas outlet gas or fresh gas.

[0061] Pressure increasing stage: close the temperature-controlled gas outlet control valve to create a high-pressure environment suitable for adsorption of tail gas in the adsorption tower to be analyzed.

[0062] Incorporation into the system: Only the tail gas outlet control valve of the adsorption tower to be analyzed is left open, and the tail gas outlet control valves of the other adsorption towers 90 are closed, all temperature-controlled gas inlet control valves are closed, and all series control valves are opened. At this time, the tail gas inlet control valve of the adsorption tower to be analyzed is closed, and the tail gas inlet control valve of another adsorption tower 90 adjacent to the adsorption tower to be analyzed is opened, so that the adsorption tower to be analyzed that has just been analyzed is at the end of the tail gas treatment sequence, that is, the tail gas treatment sequence relationship of different adsorption towers 90 is readjusted, so the adsorption efficiency of the adsorption tower 90 is high, and the number of analyses of the adsorption tower 90 is also reduced. Before the isolation stage, the tail gas inlet control valve of the adsorption tower to be analyzed is the only one opened.

[0063] The inlet and outlet of the adsorption tower 90 described in this embodiment are defined by the flow direction of the tail gas. Embodiment 2

[0064] This embodiment provides a silane fluidized bed tail gas adsorption device, which is improved on the basis of the first embodiment, and the technical scheme is detailed. For details not provided, please refer to the first embodiment. For the purpose of illustration only, optionally, the material for adsorbing harmful substances and dirt in the tail gas in the adsorption tower 90 in this embodiment is activated carbon.

[0065] Embodiment 1 mentions that a plurality of adsorption towers 90 in a silane fluidized bed tail gas adsorption device are connected in series end to end to form a loop. Optionally, in a further preferred but non-restrictive embodiment of the present application, a single silane fluidized bed tail gas adsorption device should include at least two adsorption towers 90, namely a first adsorption tower 91 and a second adsorption tower 92. The outlet of the first adsorption tower 91 and the inlet of the second adsorption tower 92 are connected through a first series pipeline 911. The series control valve includes a seventh valve 7 provided on the first series pipeline 911. The outlet of the second adsorption tower 92 is connected to the inlet of the first adsorption tower 91.

[0066] refer to Figure 1 Preferably, the adsorption tower 90 further includes at least a third adsorption tower 93, the outlet of the second adsorption tower 92 is connected to the inlet of the third adsorption tower 93 via a second series pipeline 912, the outlet of the third adsorption tower 93 is connected to the inlet of the first adsorption tower 91 via a third series pipeline 913, and the series control valve further includes an eighth valve 8 provided in the second series pipeline 912 and a ninth valve 9 provided in the third series pipeline 913.

[0067] The series loop formed by two adsorption towers 90 has a short path and is prone to complete paralysis in the event of an emergency. Therefore, the series loop formed by three adsorption towers 90 takes into account both economy and robustness.

[0068] Optionally, the inlet of the first adsorption tower 91 is connected to the exhaust gas inlet pipeline 21 through the first valve 1; the inlet of the second adsorption tower 92 is connected to the exhaust gas inlet pipeline 21 through the second valve 2; the inlet of the third adsorption tower 93 is connected to the exhaust gas inlet pipeline 21 through the third valve 3; the top of the first adsorption tower 91 is connected to the temperature-controlled gas outlet pipeline 24 through the fourth valve 4; the top of the second adsorption tower 92 is connected to the temperature-controlled gas outlet pipeline 24 through the fifth valve 5; the top of the third adsorption tower 93 is connected to the temperature-controlled gas outlet pipeline 24 through the sixth valve 6; The outlet of the auxiliary tower 93 is connected to the temperature-controlled gas inlet pipeline 23 through the tenth valve 10; the outlet of the second adsorption tower 92 is connected to the temperature-controlled gas inlet pipeline 23 through the eleventh valve 11; the outlet of the first adsorption tower 91 is connected to the temperature-controlled gas inlet pipeline 23 through the twelfth valve 12; the outlet of the first adsorption tower 91 is connected to the exhaust gas outlet pipeline 22 through the thirteenth valve 13; the outlet of the second adsorption tower 92 is connected to the exhaust gas outlet pipeline 22 through the fourteenth valve 14; the outlet of the third adsorption tower 93 is connected to the exhaust gas outlet pipeline 22 through the fifteenth valve 15. Optionally, in a further preferred but non-limiting embodiment of the present application, the temperature-controlled gas inlet pipeline 23 is also provided with a sixteenth valve 16 that is closer to the upstream than the tenth valve 10, the eleventh valve 11 and the twelfth valve 12, and the sixteenth valve 16 is used to generally control the entry of the temperature-controlled gas. The exhaust gas inlet control valve includes: a first valve 1, a second valve 2 and a third valve 3, the exhaust gas outlet control valve includes: a thirteenth valve 13, a fourteenth valve 14 and a fifteenth valve 15, the temperature-controlled gas inlet control valve includes: a tenth valve 10, an eleventh valve 11 and a twelfth valve 12, and the temperature-controlled gas outlet control valve includes: a fourth valve 4, a fifth valve 5 and a sixth valve 6.

[0069] Therefore, this embodiment takes a silane fluidized bed tail gas adsorption device in a series loop consisting of three adsorption towers 90 as an example to refine the non-exclusive method of use mentioned in the first embodiment.

[0070] refer to Figure 1, n is the serial number of the working cycle. Each time the adsorption tower 90 analyzes the activated carbon once, it enters a new working cycle. The adsorption tower that has completed the analysis is incorporated into the system and starts to adsorb pollutants. When the silane fluidized bed tail gas adsorption device reaches the end of the nth working cycle, the tail gas treatment sequence is: tail gas inlet pipeline 21→first valve 1→first adsorption tower 91→seventh valve 7→second adsorption tower 92→eighth valve 8→third adsorption tower 93→fifteenth valve 15→tail gas outlet pipeline 22. At this time, the gas phase detection system detects that the ability of the activated carbon in the first adsorption tower 91 to treat the tail gas decreases, and it is necessary to analyze the activated carbon in the first adsorption tower 91 at the end of the nth working cycle; at the end of the n-1th working cycle, the third adsorption tower 93 analyzes the activated carbon, at the end of the n-2th working cycle, the second adsorption tower 92 analyzes the activated carbon, and at the end of the n-3th working cycle, the first adsorption tower 91 analyzes the activated carbon. The control valve in the silane fluidized bed tail gas adsorption device is opened and closed by referring to the valve opening and closing status of the "Valve Switching Table of Each Stage". After the first adsorption tower 91 is incorporated into the system, the analysis of the activated carbon in the first adsorption tower 91 is completed, and the n+1 working cycle is entered; in the n+1 working cycle, the order of exhaust gas treatment is: exhaust gas inlet pipeline 21→second valve 2→second adsorption tower 2→eighth valve 8→third adsorption tower 3→ninth valve 9→first adsorption tower 1→thirteenth valve 13→exhaust gas outlet pipeline 22.

[0071]

[0072] It is not difficult for a person skilled in the art to see that, in the nth working cycle, the comparison of the time from the last analysis of the activated carbon in different adsorption towers 90 is the first adsorption tower 91> the second adsorption tower 92> the third adsorption tower 93, and the comparison of the working efficiency of the different adsorption towers 90 is the third adsorption tower 93> the second adsorption tower 92> the first adsorption tower 91. In the n+1th working cycle, the comparison of the time from the last analysis of the activated carbon in different adsorption towers 90 is the second adsorption tower 92> the third adsorption tower 93> the first adsorption tower 91, and the comparison of the working efficiency of the different adsorption towers 90 is the first adsorption tower 91> the third adsorption tower 93> the second adsorption tower 92. Therefore, at the end of the n+1th working cycle, referring to the activated carbon analysis step of the first adsorption tower 91, the second adsorption tower 92 is subjected to activated carbon analysis, so that the adsorption tower 90 with the highest working efficiency is at the end of the exhaust gas treatment path, and the series loop is cut off into a single path by switching different control valves, thereby achieving the effect of isolating the adsorption tower 90 and redefining the exhaust gas treatment order of different adsorption towers 90 according to different working efficiencies, so that the adsorption towers 90 with different working efficiencies are in the best exhaust gas treatment order.

[0073] According to the activated carbon analysis steps of the first adsorption tower 91 provided in this embodiment, it is not difficult for those skilled in the art to know the activated carbon analysis steps of the other adsorption towers 90, which will not be repeated here in view of the same principles.

[0074] According to the silane fluidized bed tail gas adsorption device composed of three adsorption towers 90 provided in this embodiment, it is not difficult for those skilled in the art to know that the structure of the silane fluidized bed tail gas adsorption device composed of two or more adsorption towers 90 and the activated carbon analysis step of the adsorption tower 90 will not be repeated here in view of the same principles. Embodiment 3

[0075] This embodiment provides an adsorption tower analysis method applicable to any one of the silane fluidized bed tail gas adsorption devices of embodiment 1 or 2, which can be controlled by a valve control system. The specific process can be referred to Figure 2 .

[0076] Adsorption tower analysis methods include:

[0077] The qualitative and quantitative analysis results of all adsorption towers 90 and the tail gas treatment sequence of all adsorption towers 90 are obtained in advance, the qualitative and quantitative analysis results include the tail gas concentration, temperature and pressure of each adsorption tower 90, and the tail gas treatment sequence includes at least the first adsorption tower, the second adsorption tower and the last adsorption tower; the tail gas inlet control valve of the first adsorption tower, all the series control valves between the first and last adsorption towers in sequence, and the tail gas outlet control valve of the last adsorption tower are opened in advance, and the other valves are closed;

[0078] In response to the tail gas concentration of the first adsorption tower reaching the concentration threshold, the tail gas inlet control valve of the second adsorption tower is opened, and the series control valve between the first and second adsorption towers and the tail gas inlet control valve of the first adsorption tower are closed in sequence to isolate the first adsorption tower;

[0079] In response to the pressure of the first adsorption tower reaching a first pressure threshold, opening the temperature-controlled gas outlet control valve of the first adsorption tower to achieve pressure relief for the first adsorption tower;

[0080] In response to the temperature of the first adsorption tower being at a first temperature threshold, opening the temperature-controlled gas inlet control valve of the first adsorption tower, and heating the first adsorption tower to achieve temperature increase of the first adsorption tower;

[0081] In response to the temperature of the first adsorption tower reaching a second temperature threshold, cooling the first adsorption tower; the second temperature is greater than the first temperature;

[0082] In response to the pressure of the first adsorption tower being below the second pressure threshold, closing the temperature-controlled gas outlet control valve of the first adsorption tower to increase the pressure of the first adsorption tower;

[0083] In response to the pressure of the first adsorption tower reaching the third pressure threshold, the series control valves between the first to the last adsorption towers in reverse order and the tail gas outlet control valve of the first adsorption tower are opened, and the tail gas outlet control valve of the last adsorption tower and the temperature-controlled gas inlet control valve of the first adsorption tower are closed to reintegrate the first adsorption tower into the series loop.

[0084] It is not difficult for those skilled in the art to see that the first adsorption tower, the second adsorption tower and the last adsorption tower do not specifically refer to a certain adsorption tower 90. After each adsorption tower analysis and update, the tail gas treatment order will change. Generally, the first adsorption tower that is analyzed and updated becomes the last adsorption tower of the next analysis and update, and the original second adsorption tower becomes the first adsorption tower of the next analysis and update, and so on. In addition, when the silane fluidized bed tail gas adsorption device has more than three adsorption towers 90, the first adsorption tower, the second adsorption tower and the last adsorption tower in the description of this embodiment only refer to three of the adsorption towers 90. When the silane fluidized bed tail gas adsorption device has only two adsorption towers 90, the second adsorption tower and the last adsorption tower refer to the same adsorption tower.

[0085] Therefore, after reintegrating the first adsorption tower into the series loop, the qualitative and quantitative analysis results of all adsorption towers 90 are obtained again, and the exhaust gas treatment order is updated from high to low according to the exhaust gas concentration, that is, a new exhaust gas treatment order is determined for the next execution of the adsorption tower analysis method.

[0086] For example, in the nth working cycle in the second embodiment, the tail gas concentration of the first adsorption tower 91> the second adsorption tower 92> the third adsorption tower 93, the first adsorption tower is the first adsorption tower 91, the second adsorption tower is the second adsorption tower 92, and the last adsorption tower is the third adsorption tower 93. It can be foreseen that in the n+1th working cycle, the tail gas concentration of the second adsorption tower 92> the third adsorption tower 93> the first adsorption tower 91, the first adsorption tower is the second adsorption tower 92, the second adsorption tower is the third adsorption tower 93, and the last adsorption tower is the first adsorption tower 91. The adsorption tower analysis method corresponding to the number of other adsorption towers 90 will not be repeated here.

[0087] Optionally, in a further but non-limiting embodiment of the present application, the various thresholds mentioned in this embodiment can be determined through technical manuals or empirical values.

[0088] The “sequential” and “reverse” mentioned in this embodiment can refer to the exhaust gas flow sequence of the adsorption tower 90 or the exhaust gas treatment sequence. For example, in the second embodiment, in the nth working cycle, the sequential order is first adsorption tower 91 → second adsorption tower 92 → third adsorption tower 93, and the reverse order is first adsorption tower 91 directly → third adsorption tower 93; in the n+1th working cycle, the sequential order is second adsorption tower 92 → third adsorption tower 93 → first adsorption tower 91.

[0089] Granular silicon is one of the mainstream processes for producing polysilicon. The silane gas synthesis section is an important part of the granular silicon production process. The silane tail gas device in the silane gas synthesis section needs to regenerate the adsorption tower during the tail gas treatment process. This process requires the adsorption tower to be isolated, depressurized, heated, cooled, pressurized, and connected to the system. The process is cumbersome, involving many valves, and requires 1 to 2 people to cooperate in the operation. At the same time, operators are prone to opening and closing valves by mistake, which affects production efficiency.

[0090] The adsorption tower analysis method provided in this embodiment solves the problems of cumbersome manual work and involving many valves, reduces the personnel participation rate, and improves production efficiency.

[0091] In the description of the present utility model, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In addition, the terms "first", "second", etc. are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, features defined as "first", "second", etc. may explicitly or implicitly include one or more of the features. In the description of the present utility model, unless otherwise specified, "multiple" means two or more.

[0092] In the description of the present utility model, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "connected", "provided in", "provided with", "located in", "installed", "set" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; the connection can be direct connection or indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances. "Hinged" includes "rotational connection".

[0093] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the protection scope of the present invention.

Claims

1. A silane fluidized bed tail gas adsorption device, characterized in that: include, At least two adsorption towers (90), the outlets and inlets of adjacent adsorption towers (90) are sequentially connected in series via series pipelines, the inlet of the first adsorption tower (90) is also connected to the outlet of the last adsorption tower (90) via series pipelines, and each of the series pipelines is controlled by a series control valve; The inlets of the adsorption towers (90) are all in communication with the tail gas inlet pipeline (21), and the inlet of each of the adsorption towers (90) is independently controlled by a tail gas inlet control valve; The outlets of the adsorption towers (90) are all in communication with the tail gas outlet pipeline (22), and the outlet of each adsorption tower (90) is independently controlled by a tail gas outlet control valve; The outlets of the adsorption towers (90) are all connected to the temperature-controlled gas inlet pipeline (23), and the outlet of each adsorption tower (90) is independently controlled by a temperature-controlled gas inlet control valve; The tops of the adsorption towers (90) are all connected to the temperature-controlled gas outlet pipeline (24), and the tops of the adsorption towers (90) are independently controlled by temperature-controlled gas outlet control valves; It also includes a valve control system, all control valves are solenoid valves, and a valve control module is electrically connected to all control valves; it also includes a gas phase detection system electrically connected to the valve control module, the gas phase detection system is connected to the adsorption tower (90) and is used to obtain qualitative and quantitative analysis results of each adsorption tower (90).

2. The silane fluidized bed tail gas adsorption device according to claim 1, characterized in that: The adsorption tower (90) comprises at least a first adsorption tower (91) and a second adsorption tower (92); the outlet of the first adsorption tower (91) and the inlet of the second adsorption tower (92) are connected via a first series pipeline (911); the series control valve comprises a seventh valve (7) arranged on the first series pipeline (911); the outlet of the second adsorption tower (92) and the inlet of the first adsorption tower (91) are connected directly or via the adsorption tower (90).

3. The silane fluidized bed tail gas adsorption device according to claim 2, characterized in that: The adsorption tower (90) further comprises at least a third adsorption tower (93), the outlet of the second adsorption tower (92) is connected to the inlet of the third adsorption tower (93) via a second series pipeline (912), the outlet of the third adsorption tower (93) is connected to the inlet of the first adsorption tower (91) via a third series pipeline (913), and the series control valve further comprises an eighth valve (8) provided on the second series pipeline (912) and a ninth valve (9) provided on the third series pipeline (913).

4. The silane fluidized bed tail gas adsorption device according to claim 3, characterized in that: The inlet of the first adsorption tower (91) is connected to the tail gas inlet pipeline (21) via a first valve (1); The inlet of the second adsorption tower (92) is connected to the tail gas inlet pipeline (21) via a second valve (2); The inlet of the third adsorption tower (93) is connected to the tail gas inlet pipeline (21) via a third valve (3).

5. The silane fluidized bed tail gas adsorption device according to claim 3, characterized in that: The outlet of the first adsorption tower (91) is connected to the tail gas outlet pipeline (22) via a thirteenth valve (13); The outlet of the second adsorption tower (92) is connected to the tail gas outlet pipeline (22) via a fourteenth valve (14); The outlet of the third adsorption tower (93) is connected to the tail gas outlet pipeline (22) via a fifteenth valve (15).

6. The silane fluidized bed tail gas adsorption device according to claim 3, characterized in that: The top of the first adsorption tower (91) is connected to the temperature-controlled gas outlet pipeline (24) via a fourth valve (4); The top of the second adsorption tower (92) is connected to the temperature-controlled gas outlet pipeline (24) via a fifth valve (5); The top of the third adsorption tower (93) is connected to the temperature-controlled gas outlet pipeline (24) via a sixth valve (6).

7. The silane fluidized bed tail gas adsorption device according to claim 3, characterized in that: The outlet of the first adsorption tower (91) is connected to the temperature-controlled gas inlet pipeline (23) via a twelfth valve (12); The outlet of the second adsorption tower (92) is connected to the temperature-controlled gas inlet pipeline (23) via an eleventh valve (11); The outlet of the third adsorption tower (93) is connected to the temperature-controlled gas inlet pipeline (23) via a tenth valve (10).

8. The silane fluidized bed tail gas adsorption device according to claim 7, characterized in that: The inlet of the first adsorption tower (91) is connected to the tail gas inlet pipeline (21) via a first valve (1); The inlet of the second adsorption tower (92) is connected to the tail gas inlet pipeline (21) via a second valve (2); The inlet of the third adsorption tower (93) is connected to the tail gas inlet pipeline (21) via a third valve (3); The outlet of the first adsorption tower (91) is connected to the tail gas outlet pipeline (22) via a thirteenth valve (13); The outlet of the second adsorption tower (92) is connected to the tail gas outlet pipeline (22) via a fourteenth valve (14); The outlet of the third adsorption tower (93) is connected to the tail gas outlet pipeline (22) via a fifteenth valve (15); The top of the first adsorption tower (91) is connected to the temperature-controlled gas outlet pipeline (24) via a fourth valve (4); The top of the second adsorption tower (92) is connected to the temperature-controlled gas outlet pipeline (24) via a fifth valve (5); The top of the third adsorption tower (93) is connected to the temperature-controlled gas outlet pipeline (24) via a sixth valve (6).