Position adjusting device of vibration measuring probe

The position adjustment device for vibration probes on gas turbines enables external and accurate alignment of probes with a simulation shaft and preamplifier system, addressing installation challenges and improving efficiency and accuracy.

CN222122799UActive Publication Date: 2024-12-06AVIC PST NANFANG GAS TURBINE COMPLETE MFG & INSTALLATION
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420430641.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-06
Publication Date
2024-12-06
Estimated Expiration
2034-03-06

AI Technical Summary

Technical Problem

The installation of vibration probes on gas turbines is difficult and inaccurate due to the need for precise adjustment in confined spaces, leading to mechanical damage risks and time-consuming operations.

Method used

A position adjustment device with a simulation shaft and preamplifier system that allows external adjustment of the vibration probe's position relative to a simulated shaft, using a pressure measuring device to ensure accurate gap alignment.

Benefits of technology

Facilitates precise and efficient installation of vibration probes outside the gas turbine, reducing mechanical damage risks and saving time while ensuring high measurement accuracy and sensitivity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222122799U_ABST
    Figure CN222122799U_ABST
Patent Text Reader

Abstract

The utility model discloses a position adjusting device of a vibration measuring probe, which comprises a base and a simulation shaft, the outer diameter of the simulation shaft is the same as the outer diameter of a shaft to be measured, the base is provided with an annular groove used for installing a bearing bush baffle along the radial direction, and the vibration measuring probe is movably installed on the bearing bush baffle through a probe fixing seat. The diameter of the outer wall of the annular groove is the same as the outer diameter of the bearing bush baffle, a center disc of the base forms a positioning disc used for being coaxially arranged with the simulation shaft and being connected with the simulation shaft in a matched mode, the vibration measuring probe is electrically connected with a front-end device used for measuring an installation gap and outputting a voltage signal, and the front-end device is electrically connected with a pressure measuring device. According to the device, the bearing bush baffle is positioned through the annular groove, so that the simulation shaft simulates the size of the shaft to be measured and is positioned through the positioning disc, the distance between the vibration measuring probe and the shaft to be measured can be adjusted by moving the vibration measuring probe, and meanwhile, whether the mounting gap meets the requirement or not is detected through the cooperation of the front-end device and the pressure measuring equipment. The device is convenient to operate, and the installation efficiency and accuracy can be greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of gas turbine vibration detection and mechanical installation, in particular to a position adjustment device for a vibration measuring probe. Background Art

[0002] Gas turbines are high-speed rotating machines that have extremely high requirements for the stability of the device. Vibration is data that needs to be monitored in real time during the operation of the gas turbine. Therefore, two vibration probes are installed near each bearing of the gas turbine to measure the vibration of the rotor. The vibration probes are pointed to the surface of the rotor journal, and the relative displacement of the rotor journal is measured by the vibration probes to reflect the vibration of the gas turbine rotor. In order to ensure the accuracy of the measurement data, the installation requirements for the vibration probes are usually quite strict, and a certain detection distance needs to be set between the vibration probe and the shaft to be measured. This detection distance is usually determined by measuring the gap voltage between the vibration probe and the shaft to be measured to determine whether it is within the qualified range.

[0003] For the vibration probes of gas turbines, some are installed before leaving the factory, while others need to be installed on the project site. In the prior art, when installing the vibration probe on site, the vibration probe needs to be installed on the bearing baffle on the bearing seat first, and then the gas turbine rotor is placed on the bearing, and then the gap voltage between the vibration probe and the rotor journal is tested to see if it is within the qualified range. If it is out of tolerance, the rotor needs to be lifted, the installation position of the vibration probe needs to be adjusted, and then the rotor needs to be lowered until the measured voltage signal is qualified. On the one hand, since the operation of adjusting the position of the vibration probe is carried out in a closed space, it will lead to operational difficulties. The adjustment of the vibration probe is difficult, and it is difficult to accurately control the detection distance between the vibration probe and the measured shaft, resulting in inaccurate measurement data. On the other hand, since the operation requires continuous adjustment of the position of the vibration probe according to the measurement of the gap voltage, the rotor needs to be repeatedly lifted and lowered. However, the operation of lifting and lowering the rotor needs to be strictly controlled. If shaking or displacement occurs, the moving blades and the stationary blades are likely to collide and cause mechanical damage. In addition, the operation takes a long time to adjust the position of the probe, which is time-consuming and labor-intensive. Utility Model Content

[0004] The utility model provides a position adjustment device for a vibration measuring probe, so as to solve the technical problem that the installation position adjustment of the vibration measuring probe in the prior art is difficult.

[0005] According to one aspect of the utility model, a position adjustment device for a vibration measuring probe is provided, which is used to adjust the distance between the vibration measuring probe and a shaft to be measured, and includes: a simulation shaft, which is coaxially arranged with a positioning plate and cooperatively connected with the positioning plate, the outer diameter of the simulation shaft is the same as the outer diameter of the shaft to be measured, and is used to simulate the shaft to be measured for measurement; a base, the base is radially provided with an annular groove for installing a bearing baffle, the vibration measuring probe is movably installed on the bearing baffle through a probe fixing seat, the outer wall diameter of the annular groove is the same as the outer diameter of the bearing baffle, and the central axis of the base forms a positioning plate for axially positioning the simulation shaft; a preamplifier, which is electrically connected to the vibration measuring probe, and is used to measure the installation gap between the vibration measuring probe and the simulation shaft and output a voltage signal, and the preamplifier is electrically connected to a pressure measuring device for receiving the voltage signal.

[0006] Furthermore, the outer diameter of the positioning plate gradually decreases from an end close to the base toward an end away from the base to form a first inclined surface, and the end of the simulation shaft is provided with a second inclined surface matched with the first inclined surface.

[0007] Furthermore, a weight-reducing hole is provided in the positioning disk and / or the dummy shaft to reduce weight.

[0008] Furthermore, a first bolt hole is arranged in the annular groove toward the direction close to the positioning plate. The first bolt hole passes through the base along the axial direction of the annular groove and is arranged toward the simulation axis. A plurality of first bolt holes are arranged radially along the annular groove.

[0009] Furthermore, a first mounting hole corresponding to the first bolt hole is opened on the simulation shaft, and the simulation shaft is detachably fixedly connected to the base by bolts passing through the first bolt hole and the first mounting hole.

[0010] Furthermore, a second bolt hole is provided in the annular groove in a direction away from the positioning plate. The second bolt hole is penetrated in the base along the axial direction of the annular groove and is arranged in the direction of the bearing baffle. A plurality of second bolt holes are arranged radially along the annular groove.

[0011] Furthermore, a second mounting hole corresponding to the second bolt hole is formed on the bearing baffle, and the bearing baffle is detachably fixedly connected to the base by bolts passing through the second bolt hole and the second mounting hole.

[0012] Furthermore, the vibration measuring probe is movably inserted into the probe fixing seat and is arranged in the direction of the simulation axis.

[0013] Furthermore, a fastener is provided on the vibration measuring probe for fixing the vibration measuring probe after position adjustment is completed.

[0014] Furthermore, a wear-resistant gasket is attached in the annular groove.

[0015] The utility model has the following beneficial effects:

[0016] The utility model discloses a position adjustment device for a vibration measuring probe, which makes the size of a simulated shaft the same as the outer diameter of a shaft to be measured to simulate the shaft to be measured, positions the bearing baffle plate through an annular groove, and positions the simulated shaft through a positioning plate to simulate the relative position relationship between the bearing baffle plate and the shaft to be measured, and the vibration measuring probe is movably mounted on the bearing baffle plate through a probe fixing seat and is electrically connected to a preamplifier, so that the relative position between the vibration measuring probe and the simulated shaft can be adjusted by manually controlling the position of the vibration measuring probe in the probe fixing seat, and at the same time, the installation gap and gap voltage between the vibration measuring probe and the simulated shaft are detected through the cooperation of the preamplifier and the pressure measuring device, and whether the installation gap of the vibration measuring probe meets the requirements is judged through the gap voltage, thereby realizing the adjustment of the installation position of the vibration measuring probe. Before the bearing baffle is installed on the gas turbine, the device first installs the bearing baffle on the device so that the position of the vibration probe can be adjusted outside the gas turbine, avoiding operation in a confined space. The installation position of the vibration probe and the relative distance between the vibration probe and the shaft to be measured can be visually observed, effectively improving the accuracy of the installation of the vibration probe, increasing the sensitivity of the vibration probe, and improving the accuracy of the vibration probe test; and avoiding mechanical damage and installation difficulties caused by installation in a confined space, simplifying the installation process of the vibration probe, reducing the difficulty of operation, saving installation time, and greatly improving the installation efficiency of the vibration probe; by simulating the size of the shaft to be measured by the simulated shaft, there is no need to install the shaft to be measured on the device, the operation is simple, and time and labor are saved; there are multiple specifications of the simulated shaft, which can be replaced according to the specifications of the shaft to be measured, so that the device can be applied to shafts to be measured of different specifications and has a wide range of applications.

[0017] In addition to the above-described purposes, features and advantages, the present invention has other purposes, features and advantages. The present invention will be further described in detail below with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The drawings constituting a part of this application are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the drawings:

[0019] Figure 1 It is a top view of the position adjustment device of the vibration measuring probe of the preferred embodiment of the utility model;

[0020] Figure 2 It is a cross-sectional view of a position adjustment device of a vibration measuring probe in a preferred embodiment of the utility model;

[0021] Figure 3 It is a cross-sectional view of the base of the position adjustment device of the vibration measuring probe of the preferred embodiment of the utility model.

[0022] Legend:

[0023] 100, vibration measuring probe; 101, fastener; 200, probe fixing seat; 300, bearing baffle; 301, second mounting hole; 400, base; 401, annular groove; 4011, first bolt hole; 4012, second bolt hole; 402, positioning plate; 403, weight reduction hole; 500, simulation shaft; 501, first mounting hole. DETAILED DESCRIPTION

[0024] The embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. However, the present invention can be implemented in a variety of different ways as defined and covered below.

[0025] like Figure 1 and Figure 2 As shown, a position adjustment device for a vibration measuring probe of the present embodiment includes a base 400 and a simulation shaft 500. The base 400 is radially provided with an annular groove 401 for installing a bearing baffle 300. The bearing baffle 300 is provided with a probe fixing seat 200. The vibration measuring probe 100 is movably mounted on the bearing baffle 300 through the probe fixing seat 200 so that the vibration measuring probe 100 can be moved in the probe fixing seat 200. The diameter of the outer wall of the annular groove 401 is the same as the outer diameter of the bearing baffle 300, so that the outer ring of the bearing baffle 300 can be closely fitted with the outer wall of the annular groove 401 for positioning. The inner wall surface of the annular groove 401 and the central axis of the base 400 form a positioning plate 402. The simulation shaft 500 and the positioning plate 402 are coaxially arranged. The simulated shaft 500 is arranged and connected with the positioning plate 402, the outer diameter of the simulated shaft 500 is the same as the outer diameter of the shaft to be measured to simulate the specifications of the shaft to be measured, so that the bearing baffle 300 is positioned by the annular groove 401 and the positioning plate 402 to position the simulated shaft 500 to simulate the relative position relationship between the bearing baffle 300 and the shaft to be measured; preferably, a plurality of simulated shafts 500 are provided, and the ends of the plurality of simulated shafts 500 are all adapted to the inner wall surface of the positioning plate 402 to achieve accurate positioning, and the outer diameters of the plurality of simulated shafts 500 are set with different sizes and are the same as the outer diameter size of the shaft to be measured to simulate different specifications of shafts to be measured for measurement, and the installation clearance of the vibration measuring probe 100 can be adjusted without installing the shaft to be measured on the gas turbine on the device. The vibration measuring probe 100 is electrically connected to a preamplifier for measuring the installation gap between the vibration measuring probe 100 and the simulated shaft 500 and outputting a voltage signal. The preamplifier is electrically connected to a pressure measuring device to receive the voltage signal. Therefore, the relative position between the vibration measuring probe 100 and the simulated shaft 500 can be adjusted by manually controlling the position of the vibration measuring probe 100 in the probe fixing seat 200. At the same time, the gap voltage between the vibration measuring probe 100 and the simulated shaft 500 is measured through the cooperation of the preamplifier and the pressure measuring device to determine whether the installation gap between the vibration measuring probe 100 and the simulated shaft 500 meets the requirements, thereby realizing the adjustment of the installation position of the vibration measuring probe 100.

[0026] When in use, firstly, the bearing baffle 300 and the simulated shaft 500 need to be positioned respectively through the annular groove 401 and the positioning plate 402 to simulate the relative position of the bearing baffle 300 and the shaft to be measured. Specifically, the base 400 of the device is placed on a flat platform, and the bearing baffle 300 is placed in the annular groove 401 so that the outer circle of the bearing baffle 300 fits tightly with the outer wall of the annular groove 401 to position the bearing baffle 300 and fix it in the annular groove 401, and then select the simulated shaft 500 with the same outer diameter as the shaft to be measured and fix it on the positioning plate 402. At this point, the relative position of the bearing baffle 300 and the shaft to be measured is determined; then, the probe fixing seat 200 on the bearing baffle 300 is controlled. The vibration probe 100 in the vibration measuring device moves toward or away from the simulated shaft 500, the preamplifier is electrically connected to the vibration measuring probe 100 through the line, the preamplifier is turned on to detect the installation gap between the vibration measuring probe 100 and the simulated shaft 500, and a voltage signal is output. The output voltage signal changes according to the installation gap. The pressure measuring device is electrically connected to the preamplifier to receive and detect the voltage output by the preamplifier. When the vibration measuring probe 100 is installed, the distance of the measuring probe toward the simulated shaft 500 is adjusted until the value read from the pressure measuring device reaches the target value, indicating that the measuring probe is installed in place; finally, the vibration measuring probe 100 after the position is determined is fixed on the probe fixing seat 200, and all operations of adjusting the position of the vibration measuring probe 100 are completed. After the position adjustment of the vibration measuring probe 100 is completed, the bearing baffle 300 is removed and installed on the gas turbine to proceed to the next installation process, without the need to adjust the position of the vibration measuring probe 100 on the gas turbine again. Preferably, during the entire installation and adjustment process, the output voltage signal can be observed to determine whether it is continuous, to preliminarily determine whether the working state of the vibration probe 100 is normal. Optionally, the vibration probe 100 is an eddy current sensor; and optionally, the pressure measuring device is a multimeter.

[0027] The device places the bearing baffle 300 on the outside of the gas turbine so that the position of the vibration probe 100 installed on the bearing baffle 300 can be adjusted externally, avoiding operation in a confined space, and being able to visually see the installation position of the vibration probe 100 and the relative distance between the vibration probe 100 and the shaft to be measured, thereby effectively improving the accuracy of the installation of the vibration probe 100, increasing the sensitivity of the vibration probe 100, and improving the accuracy of the vibration probe test; and avoiding mechanical damage and installation difficulties caused by installation in a confined space, simplifying the installation process of the vibration probe 100, reducing the difficulty of operation, saving installation time, and greatly improving the installation efficiency of the vibration probe 100; by simulating the size of the shaft to be measured by the simulated shaft 500, there is no need to install the shaft to be measured on the device, the operation is simple, and time and labor are saved; there are multiple specifications of the simulated shaft 500, which can be replaced according to the specifications of the shaft to be measured, so that the device can be applied to the measurement of shafts to be measured of different specifications, and has a wide range of applications.

[0028] like Figure 2 and Figure 3 As shown, the outer diameter of the positioning disk 402 gradually decreases from one end close to the base 400 toward the end away from the base 400 to form a first inclined surface, and the end of the simulated shaft 500 is correspondingly provided with a second inclined surface in the radial direction, and the second inclined surface is adapted to the first inclined surface, so that the positioning disk 402 can accurately position the simulated shaft 500 through the cooperation of the first inclined surface and the second inclined surface. The cooperation of the first inclined surface and the second inclined surface can ensure the coaxiality of the simulated shaft 500 and the positioning disk 402 and ensure the centering, and avoid the eccentricity of the simulated shaft 500 causing inaccurate position. Optionally, the simulated shaft 500 and the positioning disk 402 can also be positioned and centered by a snap-on connection.

[0029] like Figure 2 and Figure 3 As shown, the center disk of the base 400 forms a positioning disk 402 for positioning the simulated shaft, and a weight-reducing hole 403 is axially opened inside the positioning disk 402 to reduce the weight of the base 400, and the base 400 with the weight-reducing hole 403 is annular, which is convenient for taking; or, the simulated shaft 500 is axially opened with a weight-reducing hole 403 to reduce the weight of the simulated shaft 500, and the simulated shaft 500 with the weight-reducing hole 403 is annular or cylindrical, which is convenient for taking; or, the positioning disk 402 and the simulated shaft 500 are both axially opened with weight-reducing holes 403 to reduce weight. Optionally, the diameters of the weight-reducing holes 403 opened on the positioning disk 402 and the simulated shaft 500 are the same to facilitate the centering of the simulated shaft 500 when it is installed on the positioning disk 402.

[0030] like Figure 2As shown, a first bolt hole 4011 is provided in the annular groove 401 toward the direction close to the positioning plate 402. The first bolt hole 4011 is penetrated in the base 400 along the axial direction of the annular groove 401 and is arranged toward the direction of the simulation shaft 500. A plurality of first bolt holes 4011 are arranged along the radial direction of the annular groove 401. A first mounting hole 501 is provided at the end of the simulation shaft 500. The first mounting hole 501 is a threaded hole corresponding to the first bolt hole 4011. The simulation shaft 500 is detachably fixedly connected to the base 400 by screws penetrated through the first bolt hole 4011 and the first mounting hole 501. Optionally, the first mounting hole 501 is a blind hole. Preferably, a recessed groove is provided at one end of the first bolt hole 4011 away from the positioning plate 402, and the size of the recessed groove is adapted to the screw, so as to leave a space for the nut of the screw and an operating space for screwing in and out of the screw, so that the bottom of the base 400 remains flat after the screw is screwed into the first bolt hole 4011, thereby ensuring the levelness of the base 400. Specifically, after the simulated shaft 500 and the positioning plate 402 are positioned and centered by the cooperation of the first inclined surface and the second inclined surface, the screw is screwed in from the bottom of the base 400 through the first bolt hole 4011, so that the screw passes through the first bolt hole 4011 and the first mounting hole 501 in sequence and is screwed into the simulated shaft 500, thereby fixing the simulated shaft 500. When it is necessary to replace the simulated shaft 500 of other specifications, the screw is rotated in the opposite direction to screw out of the first mounting hole 501, so that the simulated shaft 500 loses the fastening force of the threaded connection and is easy to disassemble.

[0031] like Figure 1 and Figure 2As shown, the annular groove 401 is provided with a second bolt hole 4012 in a direction away from the positioning plate 402. The second bolt hole 4012 is penetrated in the base 400 along the axial direction of the annular groove 401 and is arranged in a direction toward the bearing bush baffle 300. A plurality of second bolt holes 4012 are arranged along the radial direction of the annular groove 401. The bearing bush baffle 300 is provided with a second mounting hole 301, which is a threaded hole corresponding to the second bolt hole 4012. The bearing bush baffle 300 is detachably fixedly connected to the base 400 by screws penetrated through the second bolt hole 4012 and the second mounting hole 301. Specifically, the bearing baffle 300 is placed in the annular groove 401, and the outer wall of the bearing baffle 300 is closely fitted with the outer wall of the annular groove 401 to position the bearing baffle 300, and then the screw is screwed in from the bottom of the base 400 through the second bolt hole 4012, so that the screw passes through the second bolt hole 4012 and the second mounting hole 301 in sequence and is screwed into the bearing baffle 300 and passes through the upper surface of the bearing baffle 300, and then the nut is screwed into the screw to achieve the fixing of the bearing baffle 300, ensuring the stability of the installation of the bearing baffle 300 and the accuracy of the positioning. Alternatively, the screw is screwed in from the second mounting hole 301 on the bearing baffle 300, and then screwed into the base 400 through the second bolt hole 4012, and then the bearing baffle 300 is fixed to the base 400 by screwing the nut into the screw. Preferably, a recessed groove is provided at one end of the second bolt hole 4012 away from the bearing baffle 300, and the size of the recessed groove is adapted to the screw, so as to leave a space for accommodating the nut or cap of the screw, and at the same time leave an operating space for screwing in and out of the screw or nut, so that the bottom of the base 400 remains flat after the screw is screwed into the second bolt hole 4012, thereby ensuring the levelness of the base 400. After the bearing baffle 300 is fixed and positioned, the position of the vibration measuring probe 100 in the probe fixing seat 200 on the bearing baffle 300 can be adjusted. When the bearing baffle 300 needs to be removed after the adjustment is completed, it is only necessary to remove the bolts and nuts, and finally the removed bearing baffle 300 is installed on the gas turbine.

[0032] like Figure 1As shown, the probe fixing seat 200 is arranged to protrude from the surface of the bearing baffle 300 and is fixedly connected to the bearing baffle 300. Optionally, the probe fixing seat 200 is connected to the bearing baffle 300 by welding or by threading. A plurality of probe fixing seats 200 are arranged at intervals along the radial direction of the bearing baffle 300, and the plurality of probe fixing seats 200 are all arranged toward the central axis direction of the base 400, and the intersection of the center lines of the plurality of probe fixing seats 200 coincides with the central axis of the base 400. A threaded through hole is opened in the probe fixing seat 200 in the direction of the central axis of the base 400, and the vibration measuring probe 100 is movably inserted into the threaded through hole, and the measuring end of the vibration measuring probe 100 is set in the direction of the analog shaft 500. The end of the vibration measuring probe 100 away from the analog shaft 500 is connected to a circuit, and is electrically connected to the preamplifier through the circuit, so that the preamplifier measures the installation gap between the vibration measuring probe 100 and the analog shaft 500 during the position adjustment process and outputs a corresponding voltage signal. The preamplifier is electrically connected to the pressure measuring equipment so that it receives the voltage signal. When in use, after the bearing baffle 300 and the simulated shaft 500 are positioned and fixed on the device, the vibration measuring probe 100 in the probe fixing seat 200 is rotated to move toward or away from the simulated shaft 500, the preamplifier is turned on to detect the installation gap between the vibration measuring probe 100 and the simulated shaft 500, and a voltage signal is output. The output voltage signal changes according to the change of the installation gap. The pressure measuring device is electrically connected to the preamplifier to receive and detect the voltage output by the preamplifier. When the vibration measuring probe 100 is installed, the distance of the measuring probe toward the simulated shaft 500 is adjusted until the value read from the pressure measuring device reaches the target value, indicating that the measuring probe is installed in place.

[0033] like Figure 1 As shown, a fastener 101 is provided on the vibration measuring probe 100, and the fastener 101 is provided at one end of the vibration measuring probe 100 away from the simulation axis 500, and is used to fix the vibration measuring probe 100 after the position adjustment is completed on the probe fixing seat 200. Preferably, the fastener 101 is a locking nut. Specifically, the vibration measuring head includes a threaded rod, and the movement of the vibration measuring probe 100 is achieved by the cooperation of the threaded rod and the threaded through hole in the probe fixing seat 200. By providing a locking nut at one end of the vibration measuring probe 100 away from the simulation axis 500, after the position adjustment of the vibration measuring probe 100 is completed, the vibration measuring probe 100 can be fixed on the probe fixing seat 200 by the cooperation of the locking nut and the threaded rod on the vibration measuring probe 100, so as to prevent the vibration measuring probe 100 from moving again to change the distance between it and the simulation axis 500.

[0034] Preferably, a wear-resistant gasket is attached in the annular groove 401 to avoid mechanical damage caused by the bearing baffle 300 being installed in the annular groove 401, thereby increasing the service life of the equipment.

[0035] The above description is only the preferred embodiment of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A position adjustment device for a vibration measuring probe, used for adjusting the gap between the vibration measuring probe (100) and a shaft to be measured, characterized in that: include: A simulation shaft (500), the outer diameter of the simulation shaft (500) being the same as the outer diameter of the shaft to be measured, and being used to simulate the shaft to be measured for measurement; A base (400), wherein the base (400) is provided with an annular groove (401) for mounting a bearing baffle (300) in a radial direction, the vibration measuring probe (100) is movably mounted on the bearing baffle (300) via a probe fixing seat (200), the outer wall diameter of the annular groove (401) is the same as the outer diameter of the bearing baffle (300), and the center disk of the base (400) forms a positioning disk (402) for axially positioning the simulated shaft (500); The preamplifier is electrically connected to the vibration measuring probe (100) and is used to measure the installation gap between the vibration measuring probe (100) and the simulation shaft (500) and output a voltage signal. The preamplifier is electrically connected to a pressure measuring device for receiving the voltage signal.

2. The position adjustment device of the vibration probe according to claim 1, characterized in that: The outer diameter of the positioning plate (402) gradually decreases from an end close to the base (400) toward an end away from the base (400) to form a first inclined surface, and the end of the simulation shaft (500) is provided with a second inclined surface adapted to the first inclined surface.

3. The position adjustment device of the vibration measuring probe according to claim 1, characterized in that: A weight-reducing hole (403) is provided in the positioning plate (402) and / or the simulated shaft (500).

4. The position adjustment device of the vibration measuring probe according to claim 1, characterized in that: A first bolt hole (4011) is arranged in the annular groove (401) in a direction close to the positioning plate (402); the first bolt hole (4011) is penetrated in the base (400) along the axial direction of the annular groove (401) and is arranged in a direction toward the simulation axis (500); and a plurality of first bolt holes (4011) are arranged radially along the annular groove (401).

5. The position adjustment device of the vibration probe according to claim 4, characterized in that: The simulation shaft (500) is provided with a first mounting hole (501) corresponding to the first bolt hole (4011), and the simulation shaft (500) is detachably fixedly connected to the base (400) by means of bolts passing through the first bolt hole (4011) and the first mounting hole (501).

6. The position adjustment device of the vibration probe according to claim 1, characterized in that: The annular groove (401) is provided with a second bolt hole (4012) in a direction away from the positioning plate (402); the second bolt hole (4012) is penetrated in the base (400) along the axial direction of the annular groove (401) and is arranged in a direction toward the bearing baffle (300); and a plurality of the second bolt holes (4012) are arranged radially along the annular groove (401).

7. The position adjustment device of the vibration probe according to claim 6, characterized in that: The bearing baffle (300) is provided with a second mounting hole (301) corresponding to the second bolt hole (4012); the bearing baffle (300) is detachably fixedly connected to the base (400) by bolts passing through the second bolt hole (4012) and the second mounting hole (301).

8. The position adjustment device of the vibration probe according to claim 1, characterized in that: The vibration measuring probe (100) is movably inserted into the probe fixing seat (200) and is arranged in the direction of the central axis of the simulation shaft (500).

9. The position adjustment device of the vibration measuring probe according to claim 1, characterized in that: The vibration measuring probe (100) is provided with a fastener (101) for fixing the vibration measuring probe (100) after position adjustment.

10. The position adjustment device of the vibration probe according to claim 1, characterized in that: A wear-resistant gasket is attached in the annular groove (401).