External climbing type building construction operation platform
By designing adjustable ceiling height components and material pick-up and placement systems on the external climbing building construction operation platform, the problems of ceiling height fixation and low construction efficiency are solved, height adjustment and ventilation and heat dissipation are achieved, and construction efficiency is improved. Worker safety.
Patent Information
- Application Number
- CN202420473224.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-12
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2034-03-12
AI Technical Summary
The ceiling height of the existing external climbing building construction operation platform is fixed, which limits the operating range of workers' construction and cannot be easily adjusted as needed, affecting construction efficiency.
A roof height adjustment component including a top cover, an extension tube, a support tube and a cylinder is designed. The side drive wheels and the front servo motor drive gear are driven by a side servo motor to match the cylinder and the extension tube. The height adjustment of the shed cover is realized, and the materials are conveniently picked up and placed through the winch frame and nylon belt, and the convex frame and fan are used to achieve ventilation and heat dissipation.
It achieves easy adjustment of the ceiling height, expands the construction operation range, improves construction efficiency, and provides ventilation and heat dissipation functions in high-temperature environments, improving workers' safety and comfort.
Smart Images

Figure CN222140654U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction operation platforms, in particular to an external climbing type building construction operation platform. Background Art
[0002] The external climbing construction operation platform is a common construction equipment, usually erected on the outer wall of the building, connected to the outer wall of the building through connectors, and driven by a motor to move the construction platform up and down along the standard section, making it convenient for workers to carry out construction at different heights.
[0003] At present, the common external climbing construction operation platforms on the market are mostly similar in structure, with multiple sets of steel standard sections as the main climbing components. The wheel axles and gears are driven by motors to drive the construction platform to move up and down along the standard sections. There are some functional deficiencies in actual use and there is room for improvement. For example, the construction platform is generally equipped with a roof and guardrails. The roof prevents falling objects from high altitudes, and the guardrails prevent construction workers from falling. The height of the ceiling is fixed, which also limits the operating range of workers. The equipment height needs to be adjusted frequently to match the construction needs. If there are differences in the work progress of multiple workers on a construction platform, the lifting and lowering of the platform will affect all workers. It is not cost-effective to adjust the height of the roof, and the height of the roof cannot be adjusted as needed to expand the operating range of the construction. The function of facilitating the adjustment of the height of the roof is not available.
[0004] Now, a new type of external climbing construction operation platform is proposed to solve the above problems. Utility Model Content
[0005] The utility model aims to provide an external climbing construction operation platform to solve the problem that the above-mentioned background technology does not have the function of conveniently adjusting the height of the roof.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an external climbing construction operation platform, comprising a base, a plurality of groups of standard sections are fixedly connected to the top of the base, a tooth plate is vertically fixedly connected to the front end of the standard section, a lifting sleeve is sleeved on the outside of the standard section, four groups of side servo motors are respectively installed on both sides of the lifting sleeve, four groups of side driving wheels are respectively installed on both sides of the inside of the lifting sleeve, two groups of front servo motors are installed at the front end of the lifting sleeve, the output end of the front servo motor is fixedly connected with a driving gear, the top of the two groups of lifting sleeves are transversely fixedly connected with a construction platform plate, a bottom support frame is fixedly connected between the bottom of the construction platform plate and the side of the lifting sleeve, a front end guard plate is fixedly connected to the front end of the top of the construction platform plate, a top shed cover is arranged above the construction platform plate, and the bottoms of the two sides of the front end of the front end guard plate are respectively provided with picking grooves, a plurality of groups of convex frames are arranged on the top of the front end of the front end guard plate, and a shed height adjustment component is arranged at the bottom of the top shed cover.
[0007] The roof height adjustment assembly includes four groups of extension tubes, which are respectively fixedly connected to the four corners of the bottom of the top roof cover, and the four corners of the top of the construction platform plate are respectively fixedly connected with support tubes.
[0008] Preferably, there is a gap between the bottom end of the top canopy cover and the top end of the front protective plate, and the front protective plate and the top canopy cover are not connected.
[0009] Preferably, the inner diameter of the extension tube is consistent with the outer diameter of the support tube, and the extension tube can slide up and down along the outside of the support tube.
[0010] Preferably, an electric cylinder is installed inside the supporting barrel, and the top end of the electric cylinder is in contact with the bottom end of the top shed cover.
[0011] Preferably, the tops of both sides of the front end of the front protective plate are respectively fixedly connected to support frames, the top of the support frame is fixedly connected to a winch frame, a drum is laterally movably connected between the two sides inside the winch frame, a reduction motor is installed on one side of the winch frame, a nylon belt is wrapped around the outside of the drum, a hook is provided at the bottom of the nylon belt, and the output end of the reduction motor is connected to one side of the drum.
[0012] Preferably, a fan is installed at the front end of the convex frame, and the front end protective plate and the interior of the convex frame are connected.
[0013] Compared with the prior art, the utility model has the following beneficial effects: the external climbing construction operation platform not only realizes the function of facilitating the adjustment of the roof height and the function of facilitating the taking and placing of materials, but also realizes the function of ventilation and heat dissipation;
[0014] (1) By providing a top canopy cover, an extension tube, a support tube and an electric cylinder, when in use, a worker stands on the construction platform board, and the side servo motor drives the side drive wheel to rotate continuously. The side drive wheel fits the front and rear ends of the standard section, and drives the lifting sleeve to generate up and down power through friction. The front servo motor drives the drive gear to rotate, and the drive gear and the gear plate are meshed, and the friction generated by the side drive wheel drives the lifting sleeve to move up and down. The front protective plate can prevent workers from falling, and the top canopy cover can prevent falling objects from high altitude. According to construction needs, when the height of the top canopy cover needs to be adjusted, the electric cylinder inside the support tube is started and extended upward, and the electric cylinder is against the top canopy cover and pushed upward. The extension tube at the bottom of the top canopy cover slides upward along the support tube, and the height of the top canopy cover is increased, and the construction operation range of the workers is also expanded. The extension tube and the support tube can make the up and down displacement of the top canopy cover smoother, thereby realizing the function of facilitating the adjustment of the canopy roof height.
[0015] (2) By providing a picking trough, a support frame, a winch frame, a drum, a reduction motor, a nylon belt and a hook, when workers need to add concrete slurry or other building materials during construction, the staff below will prepare the corresponding building materials and hang them on the hook, and the reduction motor will drive the drum on the winch frame to rotate continuously, and the drum will reel in the nylon belt, and the nylon belt will lift the building materials to the picking trough below the support frame, which is convenient for workers to take, thus realizing the function of facilitating the taking and placing of materials.
[0016] (3) By providing an outward convex frame and a fan, when in use, during construction in hot summer weather, the front protective plate itself can isolate sunlight. As its own temperature rises, the fan on the outward convex frame can be started, and the fan continuously blows air into the platform, thereby increasing the air circulation speed to reduce the internal temperature, thereby preventing workers from overheating and heatstroke, and realizing the function of ventilation and heat dissipation. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is a front view structural schematic diagram of the utility model;
[0018] Figure 2 It is a schematic diagram of the enlarged structure of the lifting frame of the utility model from top view;
[0019] Figure 3 For the utility model Figure 1 A partial cross-section at the center is an enlarged structural diagram;
[0020] Figure 4 It is a partial enlarged structural schematic diagram of the top canopy cover of the utility model.
[0021] In the figure: 1. base; 2. standard section; 3. tooth plate; 4. lifting sleeve; 5. side servo motor; 6. side driving wheel; 7. front servo motor; 8. driving gear; 9. bottom support frame; 10. construction platform plate; 11. front protection plate; 12. top canopy cover; 13. extension bobbin; 14. support bobbin; 15. electric cylinder; 16. picking trough; 17. support frame; 18. winch frame; 19. reel; 20. reduction motor; 21. nylon belt; 22. hook; 23. convex frame; 24. fan. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] Example 1: Please refer to Figure 1-4 , an external climbing construction operation platform, comprising a base 1, a plurality of standard sections 2 are fixedly connected to the top of the base 1, a tooth plate 3 is vertically fixedly connected to the front end of the standard section 2, a lifting frame 4 is sleeved on the outside of the standard section 2, four groups of side servo motors 5 are respectively installed on both sides of the lifting frame 4, four groups of side driving wheels 6 are respectively installed on both sides of the inside of the lifting frame 4, two groups of front servo motors 7 are installed at the front end of the lifting frame 4, and a driving gear 8 is fixedly connected to the output end of the front servo motor 7, a construction platform plate 10 is transversely fixedly connected to the top of the two groups of lifting frames 4, a bottom support frame 9 is fixedly connected between the bottom of the construction platform plate 10 and the side of the lifting frame 4, a front protective plate 11 is fixedly connected to the front end of the top of the construction platform plate 10, a top shed cover 12 is arranged above the construction platform plate 10, and a shed height adjustment component is arranged at the bottom of the top shed cover 12;
[0024] See also Figure 1-4 An external climbing construction operation platform also includes a roof height adjustment component, which includes four groups of extension tubes 13, which are respectively fixedly connected to the four corners of the bottom of the top shed cover 12, and the four corners of the top of the construction platform board 10 are respectively fixedly connected with support tubes 14;
[0025] There is a gap between the bottom end of the top canopy cover 12 and the top end of the front protection plate 11. The front protection plate 11 and the top canopy cover 12 are not connected. The inner diameter of the extension tube 13 is consistent with the outer diameter of the support tube 14. The extension tube 13 can slide up and down along the outside of the support tube 14. The support tube 14 is equipped with an electric cylinder 15. The top end of the electric cylinder 15 is in contact with the bottom end of the top canopy cover 12, which is convenient for adjusting the height of the canopy to expand the construction operation range.
[0026] Specifically, Figure 1 , Figure 2 and Figure 4 As shown, the electric cylinder 15 inside the supporting tube 14 starts and extends upward, the electric cylinder 15 presses against the top canopy cover 12 and pushes it upward, the extension tube 13 at the bottom of the top canopy cover 12 slides upward along the supporting tube 14, the height of the top canopy cover 12 is increased, and the workers' construction operation range is expanded. The extension tube 13 and the supporting tube 14 can make the up and down displacement of the top canopy cover 12 smoother.
[0027] Embodiment 2: The bottom of both sides of the front end of the front guard plate 11 is respectively provided with a taking groove 16, the top of both sides of the front end of the front guard plate 11 is respectively fixedly connected with a supporting frame 17, the top of the supporting frame 17 is fixedly connected with a hoisting frame 18, a drum 19 is laterally movably connected between the two sides inside the hoisting frame 18, a reduction motor 20 is installed on one side of the hoisting frame 18, a nylon belt 21 is wound around the outside of the drum 19, a hook 22 is provided at the bottom of the nylon belt 21, and the output end of the reduction motor 20 is connected to one side of the drum 19, so as to facilitate the cooperation with the ground to take and put building materials;
[0028] Specifically, Figure 1 and Figure 3 As shown, the building materials are hung on the hook 22, and the reduction motor 20 drives the drum 19 on the winch frame 18 to rotate continuously. The drum 19 reels the nylon belt 21, and the nylon belt 21 lifts the building materials to the taking slot 16 under the supporting frame 17, which is convenient for workers to take.
[0029] Embodiment 3: A plurality of groups of convex frames 23 are arranged on the top of the front end of the front protection plate 11, and a fan 24 is installed at the front end of the convex frame 23. The interiors of the front protection plate 11 and the convex frame 23 are connected, and active ventilation and heat dissipation can be achieved in summer to prevent workers from overheating and heat stroke;
[0030] Specifically, Figure 1 and Figure 3 As shown, the fan 24 on the outer convex frame 23 is started, and the fan 24 continuously blows air into the inside of the platform, thereby reducing the internal temperature by increasing the air circulation speed and preventing workers from overheating and heat stroke.
[0031] Working principle: When the utility model is in use, first, the worker stands on the construction platform plate 10, and the side servo motor 5 drives the side driving wheel 6 to rotate continuously. The side driving wheel 6 fits the front and rear ends of the standard section 2, and drives the lifting sleeve 4 to generate up and down power through friction. The front end servo motor 7 drives the driving gear 8 to rotate, and the driving gear 8 is engaged with the tooth plate 3, and the friction force generated by the side driving wheel 6 drives the lifting sleeve 4 to move up and down. The front end protection plate 11 can prevent the workers from falling, and the top shed cover 12 can prevent falling objects from high altitude. According to construction needs, when the height of the top shed cover 12 needs to be adjusted, the electric cylinder 15 inside the supporting barrel 14 is started and extended upward, and the electric cylinder 15 is against the top shed cover 12 and pushed upward. The extension barrel 13 at the bottom of the top shed cover 12 slides upward along the supporting barrel 14, and the height of the top shed cover 12 is improved, and the construction operation range of the workers is also expanded. The extension barrel 13 and the supporting barrel 14 can make the up and down displacement of the top shed cover 12 smoother. When workers need to add concrete slurry or other building materials during the construction process, the staff below will prepare the corresponding building materials and hang them on the hook 22. The reduction motor 20 drives the drum 19 on the winch frame 18 to rotate continuously. The drum 19 reels the nylon belt 21, and the nylon belt 21 lifts the building materials to the access slot 16 below the support frame 17 for workers to take. During construction in hot summer weather, the front protection plate 11 itself can isolate sunlight. As its own temperature rises, the fan 24 on the convex frame 23 can be started. The fan 24 continuously blows air into the platform to reduce the internal temperature by increasing the air circulation speed to prevent workers from overheating and heatstroke.
[0032] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-limiting from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
Claims
1. An external climbing construction operation platform, comprising a base (1), characterized in that: A plurality of standard sections (2) are fixedly connected to the top of the base (1), a tooth plate (3) is vertically fixedly connected to the front end of the standard section (2), a lifting frame (4) is sleeved on the outside of the standard section (2), four groups of side servo motors (5) are respectively installed on both sides of the lifting frame (4), four groups of side driving wheels (6) are respectively installed on both sides of the inside of the lifting frame (4), two groups of front servo motors (7) are installed at the front end of the lifting frame (4), the output end of the front servo motor (7) is fixedly connected to a driving gear (8), and the top of the two groups of lifting frames (4) are horizontally connected to the front end of the lifting frame (4). A construction platform plate (10) is fixedly connected to the top of the construction platform plate (10), a bottom support frame (9) is fixedly connected between the bottom of the construction platform plate (10) and the side of the lifting sleeve frame (4), a front end protection plate (11) is fixedly connected to the front end of the top of the construction platform plate (10), a top canopy cover (12) is arranged above the construction platform plate (10), and the bottoms of both sides of the front end of the front end protection plate (11) are respectively provided with taking grooves (16), the top of the front end of the front end protection plate (11) is provided with multiple groups of convex frames (23), and the bottom of the top canopy cover (12) is provided with a canopy height adjustment component; The roof height adjustment assembly comprises four groups of extension tubes (13), the four groups of extension tubes (13) are respectively fixedly connected to the four corners of the bottom of the top roof cover (12), and the four corners of the top of the construction platform plate (10) are respectively fixedly connected to support tubes (14).
2. The external climbing construction operation platform according to claim 1 is characterized in that: There is a gap between the bottom end of the top canopy cover (12) and the top end of the front protection plate (11), and the front protection plate (11) and the top canopy cover (12) are not connected.
3. The external climbing construction operation platform according to claim 1 is characterized in that: The inner diameter of the extension tube (13) is consistent with the outer diameter of the support tube (14), and the extension tube (13) can slide up and down along the outside of the support tube (14).
4. The external climbing construction operation platform according to claim 1 is characterized in that: An electric cylinder (15) is installed inside the supporting tube (14), and the top end of the electric cylinder (15) is in contact with the bottom end of the top canopy cover (12).
5. The external climbing construction operation platform according to claim 1 is characterized in that: The tops of both sides of the front end of the front protection plate (11) are respectively fixedly connected to support frames (17), the top of the support frame (17) is fixedly connected to a hoisting frame (18), a drum (19) is movably connected transversely between the two sides inside the hoisting frame (18), a reduction motor (20) is installed on one side of the hoisting frame (18), a nylon belt (21) is wound around the outside of the drum (19), a hook (22) is arranged at the bottom of the nylon belt (21), and the output end of the reduction motor (20) is connected to one side of the drum (19).
6. The external climbing construction operation platform according to claim 1, characterized in that: A fan (24) is installed at the front end of the outer convex frame (23), and the front end protection plate (11) and the interior of the outer convex frame (23) are connected.