Group pipe positioning and mounting device
Through the use of group pipe positioning and installation devices, the welding positioning mold and casing form a whole, solving the problem of multiple measurement positioning and decorative surface cracking in traditional construction, achieving efficient and accurate group pipe installation, saving construction time and cost .
Patent Information
- Application Number
- CN202420126154.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-18
- Publication Date
- 2024-12-17
- Estimated Expiration
- 2034-01-18
AI Technical Summary
The traditional group pipe reserved hole construction method requires multiple measurements and positioning, resulting in positioning deviations and secondary installation, increasing construction time cost, and the decoration surface is prone to cracking and is not accurate enough.
A group pipe positioning and installation device is provided, including a positioning mold and a group pipe body, and a rigid whole is formed by welding the positioning mold and sleeve, reducing the number of measurements, and improving installation accuracy and efficiency.
The casing is formed and installed in one go, saving construction time and labor costs, improving construction efficiency and installation accuracy, and avoiding the problem of decorative surface cracking.
Smart Images

Figure CN222186059U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building construction, and in particular to a group pipe positioning and installation device. Background Art
[0002] In the construction of reserved holes for water, heating and fire-fighting pipes during the construction of the main structure of the building, group pipe construction is a difficult problem. The traditional method of group pipe reserved hole construction is to reserve construction holes on the concrete slab and install the casing after the structure is completed. This method not only requires multiple measurements and positioning during the installation of the group pipe, but also requires secondary installation of the casing later. In order to ensure the smooth installation of the casing, the reserved hole is often larger than the reserved casing. After the casing is installed, the gap between the casing and the reserved hole needs to be sealed, and the decorative surface at the sealing point is prone to cracking. Multiple positioning often leads to positioning deviations, and positioning deviations require secondary drilling. Traditional construction methods cannot save the time cost of later installation, and construction positioning is often not very accurate. Utility Model Content
[0003] In view of this, an embodiment of the present application provides a group pipe positioning and installation device, in which the casing is formed in one construction, and only 3-4 measurements and positioning are required during the installation process. The casing is well bonded with the surrounding concrete, and there is no problem of cracking of the decorative surface, which saves subsequent construction steps and improves construction efficiency.
[0004] The embodiment of the present application provides a group pipe positioning and installation device, including a positioning mold and a group pipe body;
[0005] Wherein, the positioning mold comprises a bottom bar and a plurality of positioning members arranged on the bottom bar;
[0006] The group pipe body comprises a plurality of sleeves respectively arranged in a plurality of groups of the positioning members and fixing members fixed on the outer walls of the plurality of sleeves, wherein the fixing members connect the plurality of sleeves into a whole.
[0007] According to a specific implementation of the embodiment of the present application, the bottom rod is made of square steel or angle steel.
[0008] According to a specific implementation method of the embodiment of the present application, the positioning member includes a first positioning rod and a second positioning rod that are parallel to each other and spaced apart, one end of the first positioning rod and the second positioning rod are both fixed on the bottom rod, and the sleeve is vertically arranged between the first positioning rod and the second positioning rod.
[0009] According to a specific implementation of the embodiment of the present application, a plurality of groups of the positioning members are spaced apart and distributed along the length direction of the bottom rod.
[0010] According to a specific implementation of the embodiment of the present application, both the first positioning rod and the second positioning rod are made of steel bars.
[0011] According to a specific implementation of the embodiment of the present application, the first positioning rod and the second positioning rod are fixed to the bottom rod by welding.
[0012] According to a specific implementation of the embodiment of the present application, the fixing member includes a first fixing rod and a second fixing rod horizontally welded on the outer wall of the sleeve and distributed on both sides of the sleeve.
[0013] According to a specific implementation of the embodiment of the present application, both the first fixing rod and the second fixing rod are made of steel bars.
[0014] According to a specific implementation of the embodiment of the present application, the first fixing rod and the second fixing rod are fixed to the sleeve by welding.
[0015] Compared with the prior art, this application has the following characteristics and beneficial effects:
[0016] A group pipe positioning and installation device provided in an embodiment of the present application first arranges the group pipes according to a drawing, then welds a positioning mold according to the arrangement size, after the positioning mold is manufactured, places the sleeve in the mold for positioning, and welds the group pipes with fixing parts to form a rigid whole, after the group pipes are welded and fixed, separates the group pipe body from the mold, and takes the group pipe to the construction site for installation, during on-site installation, since the group pipes are already a whole, all the sleeves can be installed at one time after measurement and positioning, which greatly saves installation time and improves positioning accuracy, has high construction efficiency, and saves labor costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0018] Figure 1 This is a structural schematic diagram of a group pipe positioning and installation device according to an embodiment of the present application;
[0019] Figure 2 for Figure 1 A schematic structural diagram of a positioning mold in a group pipe positioning and installation device is shown;
[0020] Figure 3 for Figure 1 A schematic diagram of the structure of a group pipe body in a group pipe positioning and installation device is shown;
[0021] In the figure, 1, positioning mold; 11, bottom rod; 121, first positioning rod; 122, second positioning rod; 2, group pipe body; 21, sleeve; 221, first fixing rod; 222, second fixing rod. DETAILED DESCRIPTION
[0022] The embodiments of the present application are described in detail below with reference to the accompanying drawings.
[0023] It should be clear that the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0024] like Figure 1 , Figure 2 and Figure 3 As shown, an embodiment of the present application provides a group pipe positioning and installation device, including a positioning mold 1 and a group pipe body 2; wherein the positioning mold 1 may include a bottom rod 11 and a plurality of groups of positioning parts arranged on the bottom rod 11, and the plurality of groups of positioning parts are spaced apart along the length direction of the bottom rod 11.
[0025] The group pipe body 2 includes a plurality of sleeves 21 respectively arranged in a plurality of groups of positioning members and fixing members fixed on the outer walls of the plurality of sleeves 21 , and the fixing members connect the plurality of sleeves 21 into a whole.
[0026] In one embodiment, the bottom bar 11 may be made of square steel or angle steel.
[0027] In one implementation of the present embodiment, the positioning member includes a first positioning rod 121 and a second positioning rod 122 which are parallel to each other and spaced apart. One end of the first positioning rod 121 and the second positioning rod 122 are both fixed on the bottom rod 11, and the sleeve 21 is vertically arranged between the first positioning rod 121 and the second positioning rod 122.
[0028] The first positioning rod 121 and the second positioning rod 122 are both made of steel bars and fixed to the bottom rod 11 by welding.
[0029] In one implementation of this embodiment, the fixing member includes a first fixing rod 221 and a second fixing rod 222 horizontally welded to the outer wall of the sleeve 21 and distributed on both sides of the sleeve 21. The first fixing rod 221 and the second fixing rod 222 are both made of steel bars and fixed to the sleeve 21 by welding.
[0030] The above embodiment describes a positioning and installation device for a group of pipes arranged in a straight line. It should be noted that, due to the different arrangements of the group pipes at the construction site, the positioning mold 1 needs to be made according to the actual arrangement of the group pipes. For example, a straight mold can be made using a bottom rod 11, that is, as described in the above embodiment. Two bottom rods 11 can also be welded into a T-shape, an L-shape or other special shapes. Regardless of whether it is a T-shape, an L-shape or other special shapes, the positioning parts are also welded according to the arrangement of the group pipes in the construction drawings to ensure that the final group pipe body 2 can be smoothly installed at the construction site at one time. The attached figure shows an L-shaped arrangement.
[0031] During the use of this embodiment at the construction site, the high quality and high efficiency of the installation of the group pipe sleeve 21 are well achieved, and the effect of saving labor is also achieved. The device can be welded with square steel and angle steel, and processed with the common waste steel bars on the construction site. The production is simple and easy to understand. Since the start of construction, the device has been well applied on site and achieved the expected effect. Practice has proved that the device is feasible.
[0032] The embodiment of the present application provides a group pipe positioning and installation device. First, the group pipes are arranged according to the drawings, and then the positioning mold 1 is welded according to the size and method of the arrangement. After the positioning mold 1 is manufactured, the sleeve 21 is placed in the mold for positioning, and the group pipes are welded and connected with steel bars to form a rigid whole. The welded group pipe sleeve 21 is installed at one time, and the installation positioning accuracy is high, the construction efficiency is high, and the labor cost is saved. The device is made of materials that can be found everywhere on the construction site, which greatly shortens the time for group pipe installation and ensures the quality of group pipe installation. During the existing group pipe construction, each pipe needs to be measured and positioned separately. Multiple measurements are often prone to errors, so that the verticality of the sleeve 21 between layers does not meet the predetermined requirements. In addition, the existing construction method is to reserve the opening of the group pipe sleeve 21, and the sleeve 21 needs to be installed twice and the gap between the sleeve 21 and the concrete needs to be blocked during subsequent construction. This method is installed and formed once, and the pipe fittings can be directly installed in subsequent construction without the need for secondary installation of the sleeve 21. This method not only reduces the number of measurements and saves installation time, but also improves the verticality of the interlayer casing 21 and saves subsequent construction steps.
[0033] It should be noted that, in this article, the emphasis of the scheme described between the various embodiments is different, but the various embodiments have a certain interrelated relationship. When understanding the scheme of the present application, the various embodiments can refer to each other; in addition, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that there is any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that the process, method, article or device including a series of elements includes not only those elements, but also other elements that are not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "including one..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0034] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be based on the protection scope of the claims.
Claims
1. A group pipe positioning and installation device, characterized in that: It comprises a positioning mold (1) and a group pipe body (2); Wherein, the positioning mold (1) comprises a bottom rod (11) and a plurality of groups of positioning parts arranged on the bottom rod (11); The group pipe body (2) comprises a plurality of sleeves (21) respectively arranged in a plurality of groups of positioning members and a fixing member fixed on the outer wall of the plurality of sleeves (21), wherein the fixing member connects the plurality of sleeves (21) into a whole.
2. A group pipe positioning and installation device according to claim 1, characterized in that: The bottom rod (11) is made of square steel or angle steel.
3. A group pipe positioning and installation device according to claim 1, characterized in that: The positioning member comprises a first positioning rod (121) and a second positioning rod (122) which are parallel to each other and spaced apart, one end of each of the first positioning rod (121) and the second positioning rod (122) is fixed on the bottom rod (11), and the sleeve (21) is vertically arranged between the first positioning rod (121) and the second positioning rod (122).
4. A group pipe positioning and installation device according to claim 3, characterized in that: A plurality of groups of positioning members are distributed at intervals along the length direction of the bottom rod (11).
5. A group pipe positioning and installation device according to claim 3, characterized in that: The first positioning rod (121) and the second positioning rod (122) are both made of steel bars.
6. A group pipe positioning and installation device according to claim 3, characterized in that: The first positioning rod (121) and the second positioning rod (122) are fixed to the bottom rod (11) by welding.
7. A group pipe positioning and installation device according to claim 1, characterized in that: The fixing member comprises a first fixing rod (221) and a second fixing rod (222) which are horizontally welded on the outer wall of the sleeve (21) and are distributed on both sides of the sleeve (21).
8. A group pipe positioning and installation device according to claim 7, characterized in that: The first fixing rod (221) and the second fixing rod (222) are both made of steel bars.
9. A group pipe positioning and installation device according to claim 7, characterized in that: The first fixing rod (221) and the second fixing rod (222) are fixed to the sleeve (21) by welding.