Cast-in-place pile main reinforcement straight thread connector sizing tool

By setting the ruler tool of the annular hoop and ruler on the cast pile steel cage, the synchronous alignment of the main bars of the steel cage is achieved, solving the problems of long welding connection time and poor quality, improving construction efficiency and saving steel raw materials. Suitable for steel cages of different specifications.

CN222295729UActive Publication Date: 2025-01-03THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420863956.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-24
Publication Date
2025-01-03
Estimated Expiration
2034-04-24

AI Technical Summary

Technical Problem

In building foundation and foundation pit support projects, the welding connection time of the drilled pile steel cage is long and the quality is difficult to guarantee. The dimension tolerance rate when connecting straight thread sleeves is small, which makes the joints difficult to match, affecting construction efficiency and economy.

Method used

A straight thread joint joint of the main rib of the cast pile was designed. By setting an annular hoop and a ruler on the steel cage, the fasteners were used to realize the synchronous alignment of each ruler with the main rib, ensuring the precise docking of the joints and the elastic metal material. The ring hoops are made to suit different specifications.

Benefits of technology

It effectively solves the problems of long connection time and poor quality of steel cages, improves construction efficiency and applicability, saves steel bar raw materials, and achieves economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222295729U_ABST
    Figure CN222295729U_ABST
Patent Text Reader

Abstract

The utility model discloses a cast-in-place pile main reinforcement straight thread joint sizing tool which comprises two adjacent reinforcement cages, the butt joint ends of the two reinforcement cages are provided with annular hoops matched with the reinforcement cages in diameter, one side of each annular hoop is provided with a plurality of sections of scales, the plurality of sections of scales are fixed through fastening pieces, and the fastening pieces are connected with the annular hoops. Each section of ruler is distributed along the position of the main reinforcement direction of the reinforcement cage, so that the end of each ruler is flush with the end of the main reinforcement and is fastened through a fastener, and the end parts of the adjacent reinforcement cages are synchronously butted through the rulers, so that the problems of long orifice connection time of the reinforcement cages, poor connection quality, high construction efficiency and the like in the construction process of the cast-in-place pile are solved. And the construction efficiency is low. By using the sizing tool, the problem of synchronous alignment of two sections of reinforcement cage main reinforcements when the reinforcement cage is mechanically connected is solved, and the sizing tool is adjustable and high in applicability. Meanwhile, the diameter of the main reinforcement of the cast-in-place pile is generally large, reinforcement raw materials can be saved through mechanical connection, and good economic benefits can be obtained by using the tool.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a sizing tool for a straight threaded joint of a main reinforcement of a cast-in-place pile. Background Art

[0002] Nowadays, bored piles are often used in building foundation and foundation pit support projects. Due to the long steel cage, it is often necessary to connect the hole mouth. The commonly used connection method is the main reinforcement lap welding. The main reinforcement diameter of the cast-in-place pile steel cage is generally large and the lap welding is vertical welding. The welding time is long and the technical level of the welder is relatively high. There is a quality risk of poor welding quality and the interval between the bored pile hole and the concrete pouring is too long, resulting in the collapse of the hole.

[0003] In order to avoid the quality risk of welding connection of the steel cage hole, another steel cage connection method is adopted, that is, straight thread sleeve connection. However, the steel cage of the whole pile is very long, and the size tolerance is small when the joint is connected with straight thread. When the two sections of the steel cage are connected, it is impossible to ensure that each joint is exactly matched, and the steel cage is not easy to adjust after forming, resulting in rework and delays in construction. Pre-assembly is often required during processing, which requires a large enough processing site, a long post-processing time, and is not very applicable to the construction site. Utility Model Content

[0004] The utility model aims to provide a sizing tool for straight threaded joints of main reinforcements of cast-in-place piles in view of the deficiencies in the prior art, comprising two adjacent reinforcement cages, an annular hoop matching the diameter of the reinforcement cages being arranged on one end of the two reinforcement cages being butted, a plurality of sections of rulers being installed on one side of the annular hoop, the plurality of sections of the rulers being fixed by fasteners, each section of the rulers being distributed along the main reinforcement direction of the reinforcement cages, so that the end of each ruler is flush with the end of the main reinforcement and is fastened by the fasteners, and the ends of adjacent reinforcement cages are synchronously butted by the rulers.

[0005] Preferably, the fastener comprises a fastener body, which is used to pass through the ruler and fix the annular hoop. Both sides of the fastener body are provided with fastening screws, which are installed on the fastening screw rod. The annular hoop and the ruler are fixed by rotating the fastening screw on the fastening screw rod.

[0006] Preferably, the length of each section of the ruler is consistent, each ruler is connected to the annular hoop by a fastener, and the number of rulers is the same as the number of main bars of the cast-in-place pile reinforcement cage.

[0007] Preferably, the annular hoop is made of elastic metal material and is circular in shape with adjustable size.

[0008] Preferably, a reinforcing hoop is provided inside the steel cage.

[0009] Compared with the prior art, the utility model has the following beneficial effects: the utility model solves the problems of long connection time, poor connection quality and low construction efficiency of the steel cage hole in the process of cast-in-place pile construction; by using the sizing tool, the problem of synchronous alignment of the main bars of the two steel cages when the steel cage is mechanically connected is solved, and the tool is adjustable and has strong applicability. At the same time, the main bars of the cast-in-place pile are usually larger in diameter, and mechanical connection can save steel raw materials, so the use of the tool can achieve better economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0011] Figure 1 This is a schematic diagram of the butt joint structure of the steel cage of the utility model;

[0012] Figure 2 yes Figure 1 1-1 sectional view;

[0013] Figure 3 yes Figure 2 Sectional view 2-2.

[0014] In the figure: 1. ruler, 2. annular hoop, 3. main reinforcement, 4. stiffening hoop, 5. fastener body, 6. fastening screw. DETAILED DESCRIPTION

[0015] The technical solution of the utility model is described in detail below with reference to the accompanying drawings, but the protection scope of the utility model is not limited to the embodiments.

[0016] Reference Figures 1 to 3 The utility model is a sizing tool for straight threaded joints of main reinforcements of bored piles, which aims to solve the quality risks existing in the welding connection of bored pile steel cages, and at the same time solves the problem that the main reinforcements of steel cages are difficult to accurately align when the straight threaded sleeves of steel cages are connected. It has high practical and economic value, and specifically comprises two adjacent steel cages, wherein a reinforcing hoop 4 is arranged inside the steel cages to improve the strength of the steel cages, and an annular hoop 2 matching the diameter of the steel cages is arranged on one end of the two steel cages that are butted, and a plurality of sections of rulers 1 are installed on one side of the annular hoop 2, and the plurality of sections of the rulers are fixed by fasteners, and the position distribution of each section of the rulers along the direction of the main reinforcement 3 of the steel cages makes the end of each ruler flush with the end of the main reinforcement and fastened by the fasteners, and the synchronous butt connection of the ends of adjacent steel cages is achieved by the rulers.

[0017] The working steps of the utility model are as follows: after the first section of the steel cage (steel cage A) is processed, the annular hoop 2 of the sizing tool is adjusted to match the diameter of the steel cage;

[0018] Install the ruler 1 onto the annular hoop 2, the number of the ruler 1 being consistent with the number of the main bars 3 of the steel cage;

[0019] The ruler 1 is fixed to the annular hoop 2 by fasteners, and the position of the ruler 1 corresponds to the main reinforcement 3 of the reinforcement cage one by one;

[0020] Put the sizing tool on the steel cage, adjust the position of each ruler along the main reinforcement direction, make the end of each ruler 1 flush with the end of the main reinforcement 3, and fasten it with fasteners to keep the ruler position unchanged;

[0021] Remove the sizing tool from steel cage A. When processing the next section of steel cage (steel cage B), put the sizing tool on the first main bar of steel cage B, with the other end of the ruler flush with the main bar, and install the other main bars of steel cage B one by one, keeping each main bar flush with the other end of the ruler at the corresponding position;

[0022] After the main reinforcement of steel cage B and the reinforcement hoop of steel cage are all welded, the sizing tool is removed. At this time, one end of the sizing tool of steel cage A and one end of the sizing tool of steel cage B can be synchronously connected;

[0023] After the steel cage B is processed, put the sizing tool on the other end, adjust the ruler so that each end of the ruler is flush with each end of the main reinforcement, and tighten it;

[0024] Remove the sizing tool, put it on the next section of the steel cage, repeat the above steps, and repeat them back and forth to make the joints of each section of the steel cage perfectly connected.

[0025] The fastener includes a fastener body 5, which is used to pass through the ruler and fix the annular hoop. Fastening screws 6 are provided on both sides of the fastener body. The fastening screws are installed on the fastening screw rod. The annular hoop and the ruler are fixed by rotating the fastening screw on the fastening screw rod. In the present technical solution, the fastener can be fastened at different positions of the annular hoop and at different positions of the ruler, as long as the annular hoop and the ruler are fixed.

[0026] In addition, the length of each section of the ruler is consistent, each ruler is connected to the annular hoop by a fastener, and the number of rulers is the same as the number of main bars of the cast-in-place pile reinforcement cage, so that the utility model can adapt to reinforcement cages of different specifications.

[0027] Finally, the annular hoop is made of elastic metal material and is in a circular shape with adjustable size to be suitable for the specifications of the cast-in-place pile reinforcement cage.

[0028] Therefore, the utility model solves the problem of long connection time, poor connection quality and low construction efficiency of the steel cage hole in the process of cast-in-place pile construction; by using the sizing tool, the problem of synchronous alignment of the main bars of the two sections of the steel cage when the steel cage is mechanically connected is solved, which is adjustable and has strong applicability. At the same time, the main bars of the cast-in-place pile are usually larger in diameter, and mechanical connection can save steel raw materials, so the use of the tool can achieve better economic benefits.

[0029] As above, although the present invention has been shown and described with reference to specific preferred embodiments, it should not be interpreted as limiting the present invention itself. Various changes can be made to it in form and detail without departing from the spirit and scope of the present invention defined in the attached claims.

Claims

1. A sizing tool for straight threaded joints of cast-in-place pile main reinforcements, comprising two adjacent reinforcement cages, characterized in that: An annular hoop matching the diameter of the steel cage is provided on one end of the two steel cages being connected. A plurality of ruler sections are installed on one side of the annular hoop. The ruler sections are fixed by fasteners. Each ruler section is distributed along the main reinforcement direction of the steel cage so that the end of each ruler is flush with the end of the main reinforcement and is fastened by fasteners. The ends of adjacent steel cages are synchronously connected through the rulers.

2. A sizing tool for straight threaded joints of cast-in-place pile main reinforcement according to claim 1, characterized in that: The fastener comprises a fastener body, which is used to pass through the ruler and fix the annular hoop. Both sides of the fastener body are provided with fastening screws, which are installed on the fastening screw rod. The annular hoop and the ruler are fixed by rotating the fastening screw on the fastening screw rod.

3. A sizing tool for straight threaded joints of cast-in-place pile main reinforcement according to claim 2, characterized in that: The length of each section of the ruler is consistent, each ruler is connected to the annular hoop through a fastener, and the number of rulers is the same as the number of main bars of the cast-in-place pile reinforcement cage.

4. A sizing tool for straight threaded joints of cast-in-place pile main reinforcement according to claim 3, characterized in that: The annular hoop is made of elastic metal material and is in a circular shape with adjustable size.

5. A sizing tool for straight threaded joints of cast-in-place pile main reinforcement according to claim 4, characterized in that: A reinforcing hoop is arranged inside the steel cage.