Support pile with anti-floating structure
By using a combined structure of steel pile rods, positioning bars and fixing hoops in reinforced concrete support piles, the problem of floating up during the pouring process is solved, the stability and stress of the support piles are ensured, and the anti-floating effect is achieved.
Patent Information
- Application Number
- CN202421132648.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-23
- Publication Date
- 2025-01-17
- Estimated Expiration
- 2034-05-23
AI Technical Summary
Reinforced concrete support piles are prone to float during concrete pouring, resulting in weak stress at the bottom of the support pile after forming.
Adopt a supporting pile structure including steel pile rods, positioning bars and fixing hoops. By welding the positioning bars and fixing hoops on the outside of the steel pile rods, and screws, threaded barrels, top rods and top plates are installed on both sides of the fixing hoops, and the top plates are inserted. The inner wall of the pile hole is combined with the stop mechanism and the connecting rod to ensure that the pile rod is fixed in the middle of the pile hole during grouting, and avoiding upward and deflection.
It effectively prevents the reinforced concrete support piles from floating during grouting, strengthens the bottom of the support pile after forming, avoids deflection, and improves the overall floating resistance.
Smart Images

Figure CN222362495U_ABST
Abstract
Description
Technical Field
[0001] This patent relates to the technical field of supporting piles, specifically a supporting pile with an anti-floating structure. Background Art
[0002] Before excavation, a support structure is usually set up around the foundation pit to prevent landslides during the subsequent excavation of the foundation pit. For ordinary soil or hard soil, the current support structure mostly uses reinforced concrete support piles or steel sheet piles. During the construction of reinforced concrete support piles, a pile hole is first drilled, and then a steel cage is placed in the pile hole. Then concrete is poured into the pile hole. After the concrete is formed, a reinforced concrete support pile is formed.
[0003] However, in the process of pouring concrete into the pile hole, the steel cage tends to float up, resulting in weak force on the bottom of the formed reinforced concrete support pile. Therefore, this needs to be improved. Utility Model Content
[0004] The purpose of this patent is to provide a supporting pile with an anti-floating structure to solve the problems raised in the above background technology.
[0005] To achieve the above purpose, this patent provides the following technical solutions: a supporting pile with an anti-floating structure, comprising a steel bar pile rod, a positioning rib and a fixing hoop, a fixing hoop is welded on the outside of the steel bar pile rod, a positioning rib is welded on the outside of the steel bar pile rod, and the steel bar pile rod is inserted into an external pile hole;
[0006] A fixing tube is inserted and installed on both the left and right sides of the outer side of the fixing hoop, a connecting tube is installed inside the fixing hoop, and the two ends of the connecting tube are respectively connected with the two fixing tubes, screws are rotatably installed in the two fixing tubes, and a connecting rod is rotatably installed in the connecting tube, and the two ends of the connecting rod are respectively connected with the side walls of the two screws;
[0007] One end of the two screw rods located outside the fixed tube is sleeved with a threaded tube, the side wall of the threaded tube is installed with a push rod, the side wall of the push rod is installed with a top plate, and the top plate can be inserted into the inner wall of the external pile hole.
[0008] Preferably, the side wall of the fixing hoop is installed with a anti-rotation mechanism, and the anti-rotation mechanism includes a square rod, a square hole and a limit block. The inner wall of the threaded barrel is installed with a square rod, and the side wall of the screw rod is provided with a square hole. The square rod is inserted and installed in the square hole. A limit block is installed at one end of the square rod located in the square hole, and the limit block can slide in the square hole.
[0009] Preferably, it also includes a primary grouting pipe and a secondary grouting pipe, the upper wall of the fixing hoop is provided with a main hole and a secondary hole, the steel pile rod is inserted and installed in the main hole, there are two secondary holes, and the primary grouting pipe and the secondary grouting pipe are respectively inserted into the two secondary holes.
[0010] Preferably, a spherical groove is formed on the side wall of the limit block, a ball is installed in the spherical groove, and the ball fits against the inner wall of the square hole.
[0011] Preferably, a threaded hole is provided on the side wall of the threaded barrel, a bolt is rotatably installed in the threaded hole, and the bolt can fit with the side wall of the screw rod.
[0012] Preferably, the top plate is arc-shaped, and pins are welded to the side walls of the top plate.
[0013] Compared with the prior art, the beneficial effects of this patent are:
[0014] The device achieves the purpose of fixing the steel pile rod by arranging screws, threaded tubes, top rods and top plates on both sides of the fixing hoop, and inserting the top plates into the inner wall of the pile hole, thereby preventing the device from floating up during grouting and preventing the bottom of the formed support pile from being weakly stressed.
[0015] In addition, the device also provides a rotation-stopping mechanism in the threaded barrel, which prevents the threaded barrel from rotating with the screw rod. The other two screw rods are connected by a connecting rod so that the two screw rods can rotate synchronously, so that the fixing hoop is always in the middle of the pile hole, avoiding the deflection of the steel pile rod. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a schematic diagram of the structure of this patent.
[0017] Figure 2 This is a schematic diagram of the fixing hoop structure of this patent.
[0018] Figure 3 This is a top sectional view of the fixing hoop of this patent.
[0019] Figure 4 for Figure 1 Schematic diagram of the structure at point A in the middle.
[0020] In the figure: 1 steel bar pile, 2 positioning bar, 3 fixing hoop, 4 fixing tube, 5 connecting tube, 6 screw, 7 connecting rod, 8 threaded tube, 9 top rod, 10 top plate, 11 anti-rotation mechanism, 111 square rod, 112 square hole, 113 limit block, 12 primary grouting pipe, 13 secondary grouting pipe, 14 main hole, 15 auxiliary hole, 16 spherical groove, 17 ball, 18 threaded hole, 19 bolt, 20 nail. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of this patent to clearly and completely describe the technical solutions in the embodiments of this patent. Obviously, the described embodiments are only part of the embodiments of this patent, not all of them. Based on the embodiments in this patent, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this patent.
[0022] See also Figure 1-4 , this patent provides a technical solution: a supporting pile with an anti-floating structure, comprising a steel bar pile rod 1, a positioning rib 2 and a fixing hoop 3, the fixing hoop 3 is welded on the outside of the steel bar pile rod 1, the positioning rib 2 is welded on the outside of the steel bar pile rod 1, and the steel bar pile rod 1 is inserted into an external pile hole;
[0023] The steel bar pile rod 1 is inserted into the external pile hole by an external crane. At this time, the positioning bar 2 will fit with the inner wall of the pile hole to improve the strength of the device. After the device is sunk into the pile hole, grouting can be injected into the pile hole through the primary grouting pipe 12. During the grouting process, the primary grouting pipe 12 needs to be pulled out at a uniform speed, and it is necessary to ensure that the primary grouting pipe 12 is always located below the slurry surface;
[0024] After the first grouting is completed, after waiting for a period of time, the second high-pressure grouting is performed through the second grouting pipe 13;
[0025] A fixing tube 4 is inserted and installed on both the left and right sides of the outer side of the fixing hoop 3, a connecting tube 5 is installed inside the fixing hoop 3, and the two ends of the connecting tube 5 are respectively connected with the two fixing tubes 4, a screw 6 is rotatably installed in the two fixing tubes 4, and a connecting rod 7 is rotatably installed in the connecting tube 5, and the two ends of the connecting rod 7 are respectively connected to the side walls of the two screws 6;
[0026] The anti-floating structure of the device is formed by the screw 6, the threaded tube 8, the top rod 9 and the top plate 10;
[0027] After the device is sunk into the pile hole and before grouting, the screw 6 needs to be rotated to move the threaded tube 8 outside the screw 6 outward so that the top plate 10 is pushed into the side wall of the pile hole to fix the device and prevent the device from floating up during grouting.
[0028] Because the device connects two screw rods 6 together through a connecting rod 7, when one screw rod 6 is rotated, the other screw rod 6 will also rotate accordingly, so that the fixing hoop 3 is always in the middle of the pile hole, avoiding the deflection of the steel pile rod 1;
[0029] The ends of the two screw rods 6 outside the fixed tube 4 are sleeved with a threaded tube 8, the side wall of the threaded tube 8 is installed with a push rod 9, and the side wall of the push rod 9 is installed with a top plate 10, which can be inserted into the inner wall of the external pile hole.
[0030] Specifically, the side wall of the fixing hoop 3 is installed with a rotation-stopping mechanism 11, which includes a square rod 111, a square hole 112 and a limit block 113. The inner wall of the threaded tube 8 is installed with a square rod 111, and the side wall of the screw rod 6 is provided with a square hole 112. The square rod 111 is inserted and installed in the square hole 112. The limit block 113 is installed at one end of the square rod 111 located in the square hole 112, and the limit block 113 can slide in the square hole 112.
[0031] The cooperation between the square rod 111 and the square hole 112 can prevent the threaded barrel 8 from rotating together with the screw rod 6 when the screw rod 6 is rotated.
[0032] Specifically, it also includes a primary grouting pipe 12 and a secondary grouting pipe 13. The upper wall of the fixing hoop 3 is provided with a main hole 14 and a secondary hole 15. The steel pile rod 1 is inserted and installed in the main hole 14. There are two secondary holes 15. The primary grouting pipe 12 and the secondary grouting pipe 13 are respectively inserted into the two secondary holes 15.
[0033] Specifically, a spherical groove 16 is formed on the side wall of the limit block 113, and a ball 17 is installed in the spherical groove 16, and the ball 17 fits with the inner wall of the square hole 112;
[0034] By providing the ball 17 , the limit block 113 can slide more smoothly in the square hole 112 , thus avoiding the jamming phenomenon.
[0035] Specifically, a threaded hole 18 is provided on the side wall of the threaded barrel 8, and a bolt 19 is rotatably installed in the threaded hole 18, and the bolt 19 can fit with the side wall of the screw rod 6;
[0036] After the top plate 10 is inserted into the side wall of the pile hole, the bolt 19 can be screwed to fix the position of the threaded barrel 8 to prevent the threaded barrel 8 from moving.
[0037] Specifically, the top plate 10 is arc-shaped, and the side wall of the top plate 10 is welded with a pin 20;
[0038] The nails 20 can further increase the friction between the top plate 10 and the inner wall of the pile hole, and further improve the anti-floating ability of the device.
[0039] Working principle: insert the steel bar pile rod 1 into the external pile hole through an external crane, at which time the positioning rib 2 will fit with the inner wall of the pile hole to improve the strength of the device. After sinking the device into the pile hole, rotate the screw 6 to move the threaded tube 8 outside the screw 6 outward so that the top plate 10 is pushed into the side wall of the pile hole to fix the device, and fix the position of the threaded tube 8 through the bolt 19. Then, grouting is performed into the pile hole through the primary grouting pipe 12. During the grouting process, the primary grouting pipe 12 needs to be pulled out at a uniform speed, and it is necessary to ensure that the primary grouting pipe 12 is always below the slurry surface. After the primary grouting is completed, wait for a period of time, and then perform secondary high-pressure grouting through the secondary grouting pipe 13, and then maintain the concrete support piles. After the maintenance is completed, the support piles are completed.
[0040] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0041] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A support pile with an anti-floating structure, comprising a steel bar pile rod (1), a positioning rib (2) and a fixing hoop (3), characterized in that: A fixing hoop (3) is welded to the outside of the steel bar pile rod (1), a positioning rib (2) is welded to the outside of the steel bar pile rod (1), and the steel bar pile rod (1) is inserted into an external pile hole; A fixing tube (4) is inserted and installed on both left and right sides of the outer side of the fixing hoop (3); a connecting tube (5) is installed inside the fixing hoop (3); two ends of the connecting tube (5) are respectively connected to the two fixing tubes (4); screw rods (6) are rotatably installed in the two fixing tubes (4); a connecting rod (7) is rotatably installed in the connecting tube (5); and two ends of the connecting rod (7) are respectively connected to the side walls of the two screw rods (6); One end of the two screw rods (6) located outside the fixed tube (4) is sleeved with a threaded tube (8), a top rod (9) is installed on the side wall of the threaded tube (8), and a top plate (10) is installed on the side wall of the top rod (9), and the top plate (10) can be inserted into the inner wall of the external pile hole.
2. The supporting pile with an anti-floating structure according to claim 1, characterized in that: The side wall of the fixing hoop (3) is provided with a rotation-stopping mechanism (11), the rotation-stopping mechanism (11) comprising a square rod (111), a square hole (112) and a stop block (113); the inner wall of the threaded cylinder (8) is provided with a square rod (111), the side wall of the screw rod (6) is provided with a square hole (112), the square rod (111) is inserted and installed in the square hole (112), one end of the square rod (111) located in the square hole (112) is provided with a stop block (113), and the stop block (113) can slide in the square hole (112).
3. The supporting pile with an anti-floating structure according to claim 1, characterized in that: It also includes a primary grouting pipe (12) and a secondary grouting pipe (13); the upper wall of the fixing hoop (3) is provided with a main hole (14) and a secondary hole (15); the steel bar pile rod (1) is inserted and installed in the main hole (14); there are two secondary holes (15); the primary grouting pipe (12) and the secondary grouting pipe (13) are respectively inserted into the two secondary holes (15).
4. The supporting pile with an anti-floating structure according to claim 2, characterized in that: A spherical groove (16) is provided on the side wall of the limit block (113), a ball (17) is installed in the spherical groove (16), and the ball (17) is in contact with the inner wall of the square hole (112).
5. The supporting pile with an anti-floating structure according to claim 1, characterized in that: The side wall of the threaded barrel (8) is provided with a threaded hole (18), a bolt (19) is rotatably installed in the threaded hole (18), and the bolt (19) can be fitted with the side wall of the screw rod (6).
6. The supporting pile with an anti-floating structure according to claim 1, characterized in that: The top plate (10) is in an arc shape, and a pin (20) is welded to the side wall of the top plate (10).