Hanging basket sliding construction platform
By designing a hanging basket sliding construction platform, using the rollers and inclined rollers on the guide rail frame and guide beam, and making it on-site according to the inclination angle of the concrete beam on site, the problems of high construction difficulty and low installation efficiency in the existing technology are solved. It achieves the effects of material saving, low cost and high construction efficiency.
Patent Information
- Application Number
- CN202420827123.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2025-01-21
- Estimated Expiration
- 2034-04-19
AI Technical Summary
The prior art is difficult to construct and complex in the construction of cable-stayed bridge concrete beams, and the number of embedded sleeves is large. The current construction method is too low to install, which affects the construction progress.
A hanging basket sliding construction platform is designed, which includes a bottom construction platform, an upper moving beam and a ladder connected between the upper moving beam and the construction platform. By installing guide rail frames and rollers and inclined rollers on the guide beams, construction can be facilitated. The platform can be fabricated on-site according to the specific angle of the on-site concrete beam bevel.
Through this hanging basket sliding construction platform, the material consumption is small, the cost is low, the production is simple, and the time is less time-consuming, which greatly reduces the construction cost and improves the construction efficiency of the cable stays at the concrete beam ends. After the device is used, it is easy to dismantle and does not require any maintenance. affect subsequent construction.
Smart Images

Figure CN222375930U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of hanging basket construction platforms, and specifically to a hanging basket sliding construction platform. Background Art
[0002] The hanging basket sliding construction platform is a kind of equipment used for high-altitude operations. It is usually composed of one or more hanging baskets and can move vertically and horizontally on the outer walls of buildings or other high-altitude structures. The hanging basket sliding construction platform has the characteristics of safety, reliability, easy operation, high efficiency and energy saving. It is widely used in construction, bridges, mining, electric power and other industries.
[0003] The current method of tensioning concrete beams for cable-stayed bridges is to install and tension concrete beam anchors by using aerial platforms or bridge maintenance vehicles. This method is difficult to construct and complicated to operate. The distance between beam ends in a single construction is difficult to control, and the cost of using bridge maintenance vehicles for a long time is high.
[0004] In addition, there are a large number of pre-embedded sleeves in concrete in the engineering project, and the installation efficiency of the current construction method is too low, which seriously affects the construction progress. In this regard, a hanging basket sliding construction platform is proposed to solve the above problems. Utility Model Content
[0005] In view of the shortcomings of the prior art, the present application provides a hanging basket sliding construction platform, which has the advantages of less material consumption, simple production and less time consumption.
[0006] To achieve the above-mentioned purpose, the present application provides the following technical solutions: a hanging basket sliding construction platform, comprising a bottom construction platform, an upper moving beam and a ladder connected between the upper moving beam and the construction platform, a guide rail frame for project site guide rails to penetrate is fixedly installed at the bottom of the upper moving beam, a roller is installed below the guide rail frame, and an inclined beam angle bracing structure is also provided on the upper moving beam;
[0007] The diagonal beam angle bracing structure comprises a guide beam located on the upper movable beam and a bracing rod member arranged on the guide beam for adjustment.
[0008] Further, the ladder comprises a square steel tube fixedly connected between the bottom construction platform and the upper movable beam, wherein the square steel tube comprises two parallel arranged ones;
[0009] The ladder also includes a number of channel steels continuously arranged between two of the square tube steels, and the channel steels are used to provide support gripping points for easy climbing.
[0010] Furthermore, a connecting frame is fixedly installed on the upper movable beam, and the connecting frame is used to cooperate with the manual hoist.
[0011] Furthermore, a reinforcement railing is installed on the bottom construction platform, a reinforcement rod is connected between the upper movable beam and the square tube steel, there is also one reinforcement rod between the square tube steel and the bottom construction platform, and both reinforcement rods are inclined.
[0012] Furthermore, the guide beam comprises a fixed beam fixed on the upper movable beam and a movable beam hinged to the fixed beam, and the movable beam can deflect by a certain amplitude relative to the fixed beam.
[0013] Furthermore, the guide beam also includes an inclined roller fixed to the end of the movable beam through an external bracket, and the inclined roller is also used to fit the side span box beam on site.
[0014] Furthermore, the bracing member includes a second square tube rotatably mounted on the fixed beam and a first square tube rotatably mounted on the movable beam, and the second square tube opens toward a side surface of the first square tube.
[0015] Furthermore, a driving member is provided on the surface of the first square tube, and the driving member includes a screw motor fixed on the surface of the first square tube and a connecting plate fixed on the inner wall of the second square tube. A threaded rod should be installed on the power end of the screw motor, and the connecting plate thread is matched with the threaded rod.
[0016] Furthermore, a guide structure is installed on the first square tube, and the guide structure includes a bracket fixed on the surface of the first square tube and a first guide wheel rotatably installed on the bracket. The guide structure also includes a connecting pin fixed on the first square tube and a second guide wheel rotatably installed on the connecting pin.
[0017] Compared with the prior art, the technical solution of this application has the following beneficial effects:
[0018] The hanging basket sliding construction platform is composed of an upper moving beam, a bottom construction platform connected to a square tube steel to form a hanging basket platform, and rollers and inclined rollers are installed on the guide rail frame and the guide beam, so that the construction platform can be made on-site according to the specific angle of the concrete beam on site. Since the required materials are all simple and easy to obtain materials on the construction site, the material consumption is small, the cost is low, the production is simple, and the time consumption is short, which greatly reduces the construction cost. After the platform device is used, it is easy to dismantle and will not affect the subsequent construction. It can not only improve the construction efficiency of the inclined cable at the end of the concrete beam, but also reduce the construction cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a schematic diagram of the overall structure of this application;
[0020] Figure 2 This is a schematic diagram of the structure of the guide beam of this application;
[0021] Figure 3 This is a side view of the structure of the first square tube connected to the second square tube of the present application;
[0022] Figure 4 This is a structural stereogram of the second square tube of this application.
[0023] In the figure: 1. upper moving beam; 2. connecting frame; 3. guide frame; 4. roller; 5. square tube steel; 6. channel steel; 7. bottom construction platform; 8. reinforcing rail; 9. reinforcing rod; 10. guide beam; 101. fixed beam; 102. movable beam; 103. inclined roller; 11. first square tube; 12. second square tube; 13. screw motor; 14. connecting plate; 15. bracket; 16. first guide wheel; 17. connecting pin; 18. second guide wheel. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0025] See also Figure 1-4 A hanging basket sliding construction platform in this embodiment includes a bottom construction platform 7, an upper moving beam 1 and a ladder connected between the upper moving beam 1 and the construction platform 7.
[0026] It should be noted that the ladder includes a square steel tube 5 fixedly connected between the bottom construction platform 7 and the upper movable beam 1, wherein the square steel tube 5 includes two parallel arranged ones;
[0027] The ladder further comprises a plurality of channel steels 6 which are continuously arranged between two square steel tubes 5. The channel steels 6 are used to provide support gripping points for easy climbing.
[0028] Preferably, a connecting frame 2 is fixedly mounted on the upper movable beam 1, and the connecting frame 2 is used for assisting fixation in cooperation with a manual hoist.
[0029] Specifically, the hand chain hoist is fixed by the cable guide in the direction to be moved, and the connecting frame 2 is hung by the hand chain hoist to drag the entire platform to move, and it is fixed at one end with a wire rope to ensure safety.
[0030] It should be supplemented that a reinforcing railing 8 is installed on the bottom construction platform 7 to improve the stability of the bottom construction platform 7. A reinforcing rod 9 is connected between the upper movable beam 1 and the square tube steel 5. There is also a reinforcing rod 9 between the square tube steel 5 and the bottom construction platform 7, and the two reinforcing rods 9 are both inclined.
[0031] Such a design enables the reinforcing rod 9 to be supported between the upper moving beam 1 and the square steel tube 5, and between the square steel tube 5 and the bottom construction platform 7, thereby forming a triangular stable structure.
[0032] In this embodiment, a guide rail frame 3 for the project site guide rail to pass through is fixedly installed at the bottom of the upper movable beam 1, and a roller 4 is installed below the guide rail frame 3. The roller 4 is adapted to fit the side span box beam at the site, thereby improving the stability of the overall movement of the hanging basket.
[0033] The upper movable beam 1 in this embodiment is also provided with an inclined beam angle bracing structure to facilitate auxiliary guiding according to the specific angle of the on-site concrete beam. The inclined beam angle bracing structure includes a guide beam 10 located on the upper movable beam 1 and a support rod component arranged on the guide beam 10 for adjustment.
[0034] In this embodiment, the guide beam 10 includes a fixed beam 101 fixed on the upper movable beam 1 and a movable beam 102 hinged to the fixed beam 101. The movable beam 102 can deflect by a certain amplitude relative to the fixed beam 101, thereby adjusting the specific angle of the inclined beam angle on site;
[0035] The guide beam 10 also includes an inclined roller 103 fixed to the end of the movable beam 102 through an external bracket. The inclined roller 103 is also used to fit the side span box beam on site, so that the stability of the overall movement of the hanging basket is improved.
[0036] It should be noted that the support rod component includes a second square tube 12 rotatably mounted on the fixed beam 101 and a first square tube 11 rotatably mounted on the movable beam 102. The second square tube 12 opens toward one side of the first square tube 11 and slides against the surface of the first square tube 11.
[0037] Furthermore, a driving member is provided on the surface of the first square tube 11 for pulling the second square tube 12 to slide and extend relative to the first square tube 11;
[0038] The driving member includes a screw motor 13 fixed on the surface of the first square tube 11 and a connecting plate 14 fixed on the inner wall of the second square tube 12. A threaded rod should be installed on the power end of the screw motor 13, and the connecting plate 14 is threadedly engaged with the threaded rod, so that under the push of the screw motor 13, the second square tube 12 can be pulled to slide and extend relative to the first square tube 11.
[0039] In order to guide the movement of the second square tube 12 relative to the first square tube 11, a guide structure is installed on the first square tube 11 in this embodiment, and the guide structure includes a bracket 15 fixed on the surface of the first square tube 11 and a first guide wheel 16 rotatably installed on the bracket 15. The first guide wheel 16 extends to the surface of the second square tube 12 and fits the surface of the second square tube 12.
[0040] The guide structure also includes a connecting pin 17 fixed on the first square tube 11 and a second guide wheel 18 rotatably mounted on the connecting pin 17 . The second guide wheel 18 rolls against the inner wall of the second square tube 12 to limit the moving track of the second square tube 12 .
[0041] In this embodiment, the extended end of the connecting plate 14 and the connecting pin 17 do not overlap each other, so that when the second square tube 12 slides relative to the first square tube 11, motion interference can be avoided.
[0042] The working principle of the above embodiment is:
[0043] First, the upper movable beam 1 and the bottom construction platform 7 are connected on site through the square tube steel 5 that constitutes the ladder, and then the guide beam 10 is fixed on the upper movable beam 1. By controlling the screw motor 13, the power end of the screw motor 13 is threadedly matched with the connecting plate 14. At this time, the second square tube 12 slides relative to the first square tube 11 to change the length between the two end points. At this time, the first square tube 11 and the second square tube 12 are moved and stretched, so that the movable beam 102 swings and unfolds relative to the fixed beam 101, and the angle of the inclined roller 103 is adjusted to achieve on-site adjustment and assembly and adapt to the specific angle of the on-site concrete beam bevel for on-site production. The hand chain hoist is fixed through the cable guide tube in the direction to be moved, and the platform is dragged to move by the hand chain hoist, and it is fixed at one end with a wire rope to ensure safety.
[0044] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0045] Although the embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the appended claims and their equivalents.
Claims
1. A hanging basket sliding construction platform, comprising a bottom construction platform (7), an upper moving beam (1) and a ladder connected between the upper moving beam (1) and the construction platform (7), characterized in that: A guide rail frame (3) for project site guide rails to pass through is fixedly installed at the bottom of the upper movable beam (1), a roller (4) is installed below the guide rail frame (3), and an inclined beam angle bracing structure is also provided on the upper movable beam (1); The diagonal beam angle bracing structure comprises a guide beam (10) located on the upper movable beam (1) and a bracing rod component arranged on the guide beam (10) for adjustment.
2. The hanging basket sliding construction platform according to claim 1, characterized in that: The ladder comprises a square steel tube (5) fixedly connected between the bottom construction platform (7) and the upper movable beam (1), wherein the square steel tube (5) comprises two parallel arranged ones; The ladder further comprises a plurality of channel steels (6) arranged continuously between two of the square steel tubes (5), wherein the channel steels (6) are used to provide support gripping points for facilitating climbing.
3. The hanging basket sliding construction platform according to claim 1, characterized in that: A connecting frame (2) is fixedly mounted on the upper movable beam (1), and the connecting frame (2) is used to cooperate with a manual hoist.
4. The hanging basket sliding construction platform according to claim 2, characterized in that: A reinforcing bar (8) is installed on the bottom construction platform (7), a reinforcing rod (9) is connected between the upper movable beam (1) and the square tube steel (5), one reinforcing rod (9) is also provided between the square tube steel (5) and the bottom construction platform (7), and both reinforcing rods (9) are arranged at an angle.
5. The hanging basket sliding construction platform according to claim 1 is characterized by: The guide beam (10) comprises a fixed beam (101) fixed on the upper movable beam (1) and a movable beam (102) hinged to the fixed beam (101); the movable beam (102) can deflect with a certain amplitude relative to the fixed beam (101).
6. The hanging basket sliding construction platform according to claim 5, characterized in that: The guide beam (10) further comprises an inclined roller (103) fixed to the end of the movable beam (102) via an external bracket, and the inclined roller (103) is also used to fit the side span box beam on site.
7. The hanging basket sliding construction platform according to claim 5, characterized in that: The bracing rod component comprises a second square tube (12) rotatably mounted on the fixed beam (101) and a first square tube (11) rotatably mounted on the movable beam (102), wherein the second square tube (12) opens toward a side surface of the first square tube (11).
8. The hanging basket sliding construction platform according to claim 7, characterized in that: A driving member is provided on the surface of the first square tube (11), the driving member comprising a screw motor (13) fixed on the surface of the first square tube (11) and a connecting plate (14) fixed on the inner wall of the second square tube (12); a threaded rod is installed on the power end of the screw motor (13), and the connecting plate (14) is threadedly matched with the threaded rod.
9. The hanging basket sliding construction platform according to claim 7, characterized in that: A guide structure is installed on the first square tube (11), the guide structure comprising a bracket (15) fixed to the surface of the first square tube (11) and a first guide wheel (16) rotatably mounted on the bracket (15), the guide structure also comprising a connecting pin (17) fixed to the first square tube (11) and a second guide wheel (18) rotatably mounted on the connecting pin (17).