Cooling coagulating tank for industrial silicon processing

By setting up vibration boards and partitions in the mold of industrial silicon cooling molding device, the intermittent motion of the motor is used to reduce the adhesion of silicon and mold, solving the problem of molding difficulties in existing technologies, and improving production efficiency.

CN222403405UActive Publication Date: 2025-01-28XINJIANG GCL SILICON IND CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421206079.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-30
Publication Date
2025-01-28
Estimated Expiration
2034-05-30

AI Technical Summary

Technical Problem

In the existing industrial silicon cooling forming devices, the adhesion between silicon and the mold is relatively large, which leads to difficulty in demolding, increases downtime during the production process, and reduces overall production efficiency.

Method used

The cooling solidification slot for industrial silicon processing is designed. By setting up vibration boards and partitions in the mold, using the motor to drive the intermittent motion of gears and racks to make the vibration board impact on the bottom of the mold, reduce the silicon and the mold between the silicon and the mold Adhesive force, so as to facilitate release.

Benefits of technology

Effectively reduce the adhesion between silicon and molds, simplify the processed process, reduce the stop time, and improve the overall production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222403405U_ABST
    Figure CN222403405U_ABST
Patent Text Reader

Abstract

The utility model discloses a cooling coagulating tank for industrial silicon processing, and relates to the technical field of industrial silicon processing, the cooling coagulating tank for industrial silicon processing comprises a frame, a rotating mechanism comprises a rotating shaft, a gear, a motor, an open hole and a rack, a vibrating plate is arranged, the motor drives the gear to rotate, and when the gear is meshed with the rack, the vibrating plate is driven to rotate. When the gear is meshed with the rack, the rack is driven by the gear to move upwards, at the moment, the vibration plate is driven by the rack to move upwards to impact the bottom of the mold, when the gear is not meshed with the rack, the vibration plate moves downwards, the gear and the rack form an intermittent movement mechanism, and the vibration plate can intermittently move up and down along with the rack. The vibration plate moves upwards to impact the bottom of the mold, so that the adhesive force between the silicon and the mold is reduced so as to facilitate demolding of a worker, when the silicon moves in the mold, the worker can take the silicon out of the mold at the moment, the demolding difficulty is reduced, and the situation that the overall production efficiency is affected due to the fact that shutdown time is prolonged is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of industrial silicon processing, in particular to a cooling and solidifying tank for industrial silicon processing. Background Art

[0002] At present, there is an existing high-efficiency heat dissipation industrial silicon cooling molding device (such as patent number: CN216858200U), which discloses a high-efficiency heat dissipation industrial silicon cooling molding device, wherein both front and rear ends of the rectangular frame are fixedly equipped with cover plates, a rectangular window is opened in the middle of the upper surface of the rectangular frame, a molding mold is clamped in the rectangular window, a refrigeration and heat dissipation structure is installed at the upper end of the inner wall of the rectangular frame, a serpentine pipe assembly plate is inserted and inserted in the middle of the inner cavity of the rectangular frame for horizontal sliding, a wind heat dissipation structure is installed at the lower end of the rectangular frame, and a water flow driving structure is fixedly installed on the front wall of the cover plate; the molding mold used is clamped and set at the upper end of the rectangular frame, a refrigeration and heat dissipation structure is provided above the inner cavity of the rectangular frame, a semiconductor refrigerator is used to cool the cooling water flow, a wind heat dissipation structure is provided below the rectangular frame, and the wind is used to take away the heat of the water flow flowing through the serpentine elbow; the two heat dissipation methods cooperate to keep the circulating cooling water at the cooling temperature, thereby improving work efficiency.

[0003] However, during the implementation of the above technical solution, it was found that there were at least the following problems: after the molten silicon was cooled and solidified in the mold, the adhesion between the silicon and the mold was relatively large, which made demolding more difficult, resulting in increased downtime in the production process and reduced overall production efficiency. Utility Model Content

[0004] 1. Technical issues to be solved

[0005] In view of the deficiencies in the prior art, the utility model provides a cooling and solidification tank for industrial silicon processing, which solves the technical problem that the strong adhesion between silicon and the mold increases the difficulty of demoulding, resulting in increased downtime in the production process and reduced overall production efficiency.

[0006] (II) Technical solution

[0007] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:

[0008] A cooling and solidification tank for industrial silicon processing comprises a frame, wherein an installation groove is provided on the upper surface of the frame, a mold is slidably connected inside the installation groove, two partitions are clamped on the inner side of the mold, a vibration plate is slidably connected inside the installation groove, and the vibration plate is located below the mold. A rotating mechanism is arranged outside the frame, and the rotating mechanism comprises a rotating shaft, a gear, a motor, an opening and a rack. The rotating shaft is rotatably connected to the outside of the frame, the gear is fixedly installed on the outside of the rotating shaft, the motor output shaft is fixedly connected to one end of the rotating shaft away from the frame, the opening is provided on a side of the frame close to the rotating shaft, the rack is slidably connected to the inside of the opening, the gear is meshed with the rack, and the vibration plate is fixedly connected to the outside of the rack.

[0009] A circular groove is provided on the outside of the frame, and one end of the rotating shaft away from the motor output shaft is slidably connected to the inside of the circular groove. Two screws are fixedly installed on the outside of the frame, and the two screws are located below the rotating shaft. A nut is connected to the external thread of each screw, and the two ends of the motor are respectively slidably connected to the outside of the two screws. A protective box is provided on the outside of the frame, and the motor, rotating shaft, gear and rack are all located on the inner side of the protective box.

[0010] Preferably, a card slot is provided on the outside of the protection box, a card block is fixedly installed on the outside of the frame, and the protection box is connected to the outside of the card block through the card slot.

[0011] Preferably, a threaded rod is fixedly mounted on the outside of the clamping block, a threaded sleeve is threadedly connected to the outside of the threaded rod, and the threaded sleeve is fitted with the surface of the protective box.

[0012] (III) Beneficial effects

[0013] 1. By setting a vibration plate and cooperating with a partition, the liquid silicon enters the mold and is cooled and solidified. At this time, the solid silicon is located on the side close to the two partitions. At this time, the partition is pulled to release the connection between the partition and the mold. At this time, the motor starts to drive the gear to rotate. When the gear and the rack are meshed, the rack moves upward driven by the gear. At this time, the vibration plate moves upward driven by the rack and hits the bottom of the mold. When the gear and the rack are not meshed, the vibration plate moves downward, and the gear and the rack form an intermittent motion mechanism. The vibration plate will also move up and down intermittently with the rack. As the vibration plate moves upward and hits the bottom of the mold, the adhesion between the silicon and the mold is reduced to facilitate demolding by the staff. When the silicon moves in the mold, the staff can take the silicon out of the mold at this time, reducing the difficulty of demolding work and avoiding increased downtime that affects the overall production efficiency.

[0014] 2. By setting up a protective box and cooperating with a threaded sleeve, when the equipment is working, the protective box is connected to the outside of the card block through the card slot. At this time, the threaded sleeve is threaded onto the outside of the threaded rod until the threaded sleeve fits with the surface of the protective box. At this time, the protective box is installed. At this time, the protective box is used to cover the rotating mechanism to avoid harm to the staff when the rotating mechanism is working. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] The above description is only an overview of the technical solution of the utility model. In order to more clearly understand the technical means of the utility model and implement it according to the contents of the specification, the following is a detailed description of the preferred embodiments of the utility model in conjunction with the accompanying drawings.

[0016] Figure 1 It is a structural diagram of the utility model;

[0017] Figure 2 For this utility model Figure 1 Structural diagram of the middle frame;

[0018] Figure 3 For this utility model Figure 2 A magnified structural diagram of the middle part;

[0019] Figure 4 For this utility model Figure 2 Structural diagram of the vibration plate.

[0020] Legend: 1. Frame; 2. Mounting groove; 3. Mold; 4. Partition; 5. Vibrating plate; 6. Rotating shaft; 7. Gear; 8. Motor; 9. Opening; 10. Rack; 11. Circular groove; 12. Screw; 13. Nut; 14. Protective box; 15. Slot; 16. Block; 17. Threaded rod; 18. Threaded sleeve. DETAILED DESCRIPTION

[0021] The embodiment of the present application provides a cooling and solidification tank for industrial silicon processing, which effectively solves the technical problem that the strong adhesion between silicon and the mold 3 increases the difficulty of demoulding, resulting in increased downtime in the production process and reduced overall production efficiency.

[0022] Example

[0023] like Figure 1 , Figure 2 , Figure 3 and Figure 4 The technical solution in the embodiment of the present application effectively solves the technical problem that the adhesion between silicon and the mold 3 is large, which increases the difficulty of demoulding, increases the downtime in the production process, and reduces the overall production efficiency. The overall idea is as follows:

[0024] In view of the problems existing in the prior art, the utility model provides a cooling and solidification tank for industrial silicon processing, which comprises a frame 1, a mounting groove 2 is provided on the upper surface of the frame 1, a mold 3 is slidably connected inside the mounting groove 2, two partitions 4 are clamped on the inner side of the mold 3, a vibration plate 5 is slidably connected inside the mounting groove 2, and the vibration plate 5 is located below the mold 3. A rotating mechanism is arranged on the outside of the frame 1, and the rotating mechanism comprises a rotating shaft 6, a gear 7, a motor 8, an opening 9 and a rack 10. The rotating shaft 6 is rotatably connected to the outside of the frame 1, the gear 7 is fixedly installed on the outside of the rotating shaft 6, the output shaft of the motor 8 is fixedly connected to one end of the rotating shaft 6 away from the frame 1, the opening 9 is provided on a side of the frame 1 close to the rotating shaft 6, the rack 10 is slidably connected to the inside of the opening 9, the gear 7 is meshed with the rack 10, and the vibration plate 5 is fixedly connected to the outside of the rack 10.

[0025] By setting the vibration plate 5 and cooperating with the partition 4, the liquid silicon enters the mold 3 and is cooled and solidified. At this time, the solid silicon is located on the side close to the two partitions 4. At this time, the partition 4 is pulled to release the connection between the partition 4 and the mold 3. At this time, the motor 8 starts to drive the gear 7 to rotate. When the gear 7 is meshed with the rack 10, the rack 10 moves upward under the drive of the gear 7. At this time, the vibration plate 5 moves upward under the drive of the rack 10 to hit the bottom of the mold 3. When the gear 7 is not meshed with the rack 10, the vibration plate 5 moves downward, and the gear 7 and the rack 10 form an intermittent motion mechanism. The vibration plate 5 will also follow the rack 10 to move up and down intermittently. As the vibration plate 5 moves upward and hits the bottom of the mold 3, the adhesion between the silicon and the mold 3 is reduced to facilitate the demolding of the staff. When the silicon moves in the mold 3, the staff can take the silicon out of the mold 3 at this time, reducing the difficulty of demolding work and avoiding the increase of downtime affecting the overall production efficiency.

[0026] A circular groove 11 is provided on the outside of the frame 1, and one end of the rotating shaft 6 away from the output shaft of the motor 8 is slidably connected to the inside of the circular groove 11, which is convenient for the disassembly and assembly of the rotating shaft 6. Two screws 12 are fixedly installed on the outside of the frame 1, and the two screws 12 are both located below the rotating shaft 6. A nut 13 is connected to the external thread of each screw 12, and the two ends of the motor 8 are respectively slidably connected to the outside of the two screws 12, which is convenient for the disassembly and assembly of the motor 8.

[0027] A protective box 14 is arranged outside the frame 1, and the motor 8, the rotating shaft 6, the gear 7 and the rack 10 are all located inside the protective box 14 to prevent the rotating mechanism from causing harm to the staff. At the same time, a number of vents are provided outside the protective box 14 so as not to affect the heat dissipation of the motor 8. A card slot 15 is provided outside the protective box 14, and a card block 16 is fixedly installed outside the frame 1. The protective box 14 is connected to the outside of the card block 16 through the card slot 15, which is convenient for the disassembly and assembly of the protective box 14. A threaded rod 17 is fixedly installed outside the card block 16, and the outside of the threaded rod 17 is fixedly installed. The threaded sleeve 18 is threadedly connected to the protective box 14, and the threaded sleeve 18 fits with the surface of the protective box 14 to facilitate fixing the protective box 14. By setting the protective box 14 and matching the threaded sleeve 18, when the equipment is working, the protective box 14 is clamped on the outside of the clamping block 16 through the clamping groove 15. At this time, the threaded sleeve 18 is threadedly connected to the outside of the threaded rod 17 until the threaded sleeve 18 fits with the surface of the protective box 14. At this time, the protective box 14 is installed. At this time, the protective box 14 and the rotating mechanism are used to cover the rotating mechanism to avoid injuries to the staff when the rotating mechanism is working.

[0028] Working principle:

[0029] The first step is to insert the end of the rotating shaft 6 away from the motor 8 into the inside of the circular groove 11. At this time, the two ends of the motor 8 are respectively slidably connected to the outside of the two screws 12. At this time, the two nuts 13 are respectively threadedly connected to the outside of the two screws 12 until the nuts 13 and the motor 8 fit together. At this time, the motor 8 is installed. The protective box 14 is connected to the outside of the block 16 through the card slot 15. At this time, the threaded sleeve 18 is threadedly connected to the outside of the threaded rod 17 until the threaded sleeve 18 fits the surface of the protective box 14. At this time, the protective box 14 is installed. At this time, the protective box 14 and the rotating mechanism are covered to prevent the rotating mechanism from causing harm to the staff when the working;

[0030] In the second step, by setting the vibration plate 5 and cooperating with the partition 4, the liquid silicon enters the mold 3 and is cooled and solidified. At this time, the solid silicon is located on the side close to the two partitions 4. At this time, the partition 4 is pulled to release the connection between the partition 4 and the mold 3. At this time, the motor 8 starts to drive the gear 7 to rotate. When the gear 7 is meshed with the rack 10, the rack 10 moves upward under the drive of the gear 7. At this time, the vibration plate 5 moves upward under the drive of the rack 10 to hit the bottom of the mold 3. When the gear 7 is not meshed with the rack 10, the vibration plate 5 moves downward, and the gear 7 and the rack 10 form an intermittent motion mechanism. The vibration plate 5 will also follow the rack 10 to move up and down intermittently. As the vibration plate 5 moves upward, it hits the bottom of the mold 3 to reduce the adhesion between the silicon and the mold 3 to facilitate the demolding of the staff. When the silicon moves in the mold 3, the staff can take the silicon out of the mold 3 at this time, reducing the difficulty of demolding work and avoiding the increase of downtime affecting the overall production efficiency.

[0031] Finally, it should be noted that: Obviously, the above embodiments are only examples for clearly explaining the present invention, and are not intended to limit the implementation methods. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the scope of protection of the present invention.

Claims

1. A cooling and solidification tank for industrial silicon processing, comprising a frame (1), wherein the upper surface of the frame (1) is provided with a mounting groove (2), characterized in that: The interior of the installation groove (2) is slidably connected to a mold (3), the inner side of the mold (3) is clamped with two partitions (4), the interior of the installation groove (2) is slidably connected to a vibration plate (5), the vibration plate (5) is located below the mold (3), and a rotating mechanism is arranged outside the frame (1); The rotating mechanism comprises a rotating shaft (6), a gear (7), a motor (8), an opening (9) and a rack (10); The rotating shaft (6) is rotatably connected to the outside of the frame (1), the gear (7) is fixedly installed on the outside of the rotating shaft (6), the output shaft of the motor (8) is fixedly connected to the end of the rotating shaft (6) away from the frame (1), the opening (9) is opened on a side of the frame (1) close to the rotating shaft (6), the rack (10) is slidably connected to the inside of the opening (9), and the gear (7) is meshed with the rack (10); The vibration plate (5) is fixedly connected to the outside of the rack (10).

2. A cooling and solidification tank for industrial silicon processing as claimed in claim 1, characterized in that: A circular groove (11) is formed on the outside of the frame (1); The end of the rotating shaft (6) away from the output shaft of the motor (8) is slidably connected inside the circular groove (11).

3. The cooling and solidification tank for industrial silicon processing according to claim 1, characterized in that: Two screw rods (12) are fixedly mounted on the outside of the frame (1), and the two screw rods (12) are both located below the rotating shaft (6). The outer thread of each screw rod (12) is connected to a nut (13); The two ends of the motor (8) are respectively slidably connected to the outside of the two screw rods (12).

4. The cooling and solidification tank for industrial silicon processing according to claim 1, characterized in that: A protective box (14) is arranged outside the frame (1); The motor (8), the rotating shaft (6), the gear (7) and the rack (10) are all located inside the protective box (14).

5. A cooling and solidification tank for industrial silicon processing as claimed in claim 4, characterized in that: The protection box (14) is provided with a card slot (15) on its exterior, and a card block (16) is fixedly mounted on the exterior of the frame (1); The protection box (14) is clamped on the outside of the clamping block (16) via the clamping slot (15).

6. A cooling and solidification tank for industrial silicon processing as claimed in claim 5, characterized in that: A threaded rod (17) is fixedly mounted on the outside of the clamping block (16), and a threaded sleeve (18) is threadedly connected to the outside of the threaded rod (17); The threaded sleeve (18) is fitted with the surface of the protection box (14).

Citation Information

Patent Citations

  • High-efficiency heat dissipation industrial silicon cooling forming device

    CN216858200U