Rapid lifting tool for photovoltaic panel steel support
By designing a fast improvement tool for photovoltaic board installation, the problem of large steel dosage and complex construction conditions during the installation of photovoltaic boards, realizing the effects of reducing construction difficulties and costs, improving work efficiency and safety.
Patent Information
- Application Number
- CN202421276051.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-05
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-06-05
AI Technical Summary
During the installation of photovoltaic panels, the steel consumption is large, the construction conditions are complex, the existing equipment is high and difficult to use in remote areas, resulting in high construction difficulty and high cost.
Design a photovoltaic plate steel bracket rapid improvement tool, including the base, vertical rod, fixed component, rolling machine and ropes. The steel structure of the photovoltaic board steel structure is used to simplify the construction process.
The difficulty and cost of construction have been reduced, the efficiency is improved, the construction is safe, and the installation of photovoltaic boards suitable for various environments.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of photovoltaic panel installation, and more specifically, to a photovoltaic panel steel bracket quick lifting tool. Background Art
[0002] The installation of photovoltaic brackets and photovoltaic panels on roofs and carports requires large amounts of steel, complex construction conditions, and a single weight of ≤150KG and a length of less than 6m.
[0003] Due to the characteristics of photovoltaic panel installation, hiring a tire crane is costly on the one hand, and cranes cannot directly reach remote areas on the other hand; manual construction work is too heavy and the lifting is too high, making construction extremely difficult. To address this pain point, the project department has developed a small lifting equipment, which has greatly improved work efficiency, reduced project construction costs, and reduced construction difficulty.
[0004] Therefore, a photovoltaic panel steel support quick lifting tool is proposed. Utility Model Content
[0005] In order to overcome the above-mentioned defects of the prior art, the utility model provides a photovoltaic panel steel bracket quick lifting tool to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a photovoltaic panel steel bracket quick lifting tool, comprising a base, a vertical pole inserted at the top of the base, a fixing component connected between the vertical pole and the base, a bracket welded to one side of the vertical pole, a winch installed on the bracket, a rope provided on the winch, a hook fixed at the end of the rope, and a support component for connecting with the rope welded to the top of the vertical pole.
[0007] Preferably, the base includes a first transverse plate, a second transverse plate, a third transverse plate and a connecting tube, two second transverse plates are welded on one side of the first transverse plate, a third transverse plate is welded on the other side of the first transverse plate, and a connecting tube is vertically welded on the top of the first transverse plate.
[0008] Preferably, a notch is provided on one side of the connecting tube, and insertion holes are evenly provided on the connecting tube.
[0009] Preferably, a plurality of through holes are evenly formed at the bottom end of the vertical rod, and the distance between adjacent through holes is the same as the distance between adjacent insertion holes.
[0010] Preferably, the fixing assembly includes a connecting plate, a bolt rod, a nut and a handle. Two bolt rods are symmetrically provided on one side of the connecting plate. The two bolt rods are plugged into two adjacent sockets. A nut is sleeved on the end of each bolt rod. A handle is welded on the other side of the connecting plate.
[0011] Preferably, the support assembly includes a fixed block, a fixed frame, a first pulley and a second pulley, the fixed block is welded to the top of the vertical pole, and a fixed frame is welded to one side of the fixed block, the first pulley is installed on the fixed frame, and the second pulley is arranged inside the first pulley.
[0012] Preferably, the top end of the rope is crimped onto the first pulley, and the second pulley is arranged outside the rope.
[0013] Technical effects and advantages of the utility model:
[0014] The utility model adopts 100*150 square steel as a stable foundation and DN80 galvanized steel pipe as a lifting pole. The winch is connected to the lower part of the lifting pole by welding. A pulley is placed on the top of the lifting pole. The winch rope is led out by the winch, connected to the steel structure support to be lifted through the pulley, and driven by the winch to pull the material to be lifted. In construction applications, when moving and lifting heavy objects, the safety risk is reduced, and at the same time the construction progress is accelerated, the construction cost is saved, and the work efficiency is improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model.
[0016] Figure 2 It is a structural schematic diagram of the base of the utility model.
[0017] Figure 3 It is a structural schematic diagram of the fixing component of the utility model.
[0018] Figure 4 It is a structural schematic diagram of the support assembly of the utility model.
[0019] Figure 5 It is a structural schematic diagram of the vertical pole of the utility model.
[0020] The accompanying drawings are marked as follows: 1. base; 101. first horizontal plate; 102. second horizontal plate; 103. third horizontal plate; 104. connecting tube; 2. vertical pole; 3. fixing assembly; 301. connecting plate; 302. bolt rod; 303. nut; 304. handle; 4. bracket; 5. winch; 6. supporting assembly; 601. fixing block; 602. fixing frame; 603. first pulley; 604. second pulley; 7. rope; 8. hook; 9. through hole. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] As attached Figure 1-5 A photovoltaic panel steel bracket quick lifting tool shown in the figure includes a base 1, a vertical pole 2 is inserted into the top of the base 1, a fixing component 3 is connected between the vertical pole 2 and the base 1, a bracket 4 is welded to one side of the vertical pole 2, a winch 5 is installed on the bracket 4, a rope 7 is arranged on the winch 5, a hook 8 is fixed to the end of the rope 7, and a supporting component 6 for connecting with the rope 7 is welded to the top of the vertical pole 2.
[0023] During the specific implementation, a base 1 composed of 100*150 square steel and 0.5-meter-long galvanized steel pipe DN100 is used as the supporting foundation, and a 4-meter-long DN80 galvanized steel pipe is used as the lifting pole 2, so that the pole 2 is inserted into the long galvanized steel pipe DN100 and fixed by a fixing component 3. A supporting component 6 is welded on the top of the pole 2 to support the rope 7 led out by the winch 6 to prevent the rope 7 from detaching. At the same time, a hook 8 is installed at the end of the rope 7. When the photovoltaic panel steel structure is lifted, it is fixed to the photovoltaic panel steel structure through the hook 8, and the winch 5 is running to reel in the rope 7, so that the photovoltaic panel steel structure can be lifted.
[0024] As attached Figure 2 and Figure 5 As shown, the base 1 includes a first transverse plate 101, a second transverse plate 102, a third transverse plate 103 and a connecting tube 104, two second transverse plates 102 are welded on one side of the first transverse plate 101, and a third transverse plate 103 is welded on the other side of the first transverse plate 101. A connecting tube 104 is vertically welded to the top of the first transverse plate 101, a notch is provided on one side of the connecting tube 104, and sockets are evenly provided on the connecting tube 104. A plurality of through holes 9 are evenly provided on the bottom end of the vertical pole 2, and the distance between adjacent through holes 9 is the same as the distance between adjacent sockets.
[0025] When the base 1 is specifically manufactured, two 1m 100*150 square steels are used as the second horizontal plate 102, a 1.5m 100*150 square steel is used as the first horizontal plate 101, and a 0.6m 100*150 square steel is used as the third horizontal plate 103 for welding to form a square steel support plane, and a connecting tube 104 formed by a 0.5m long DN100 galvanized steel pipe is welded to the top of the middle part of the 1.5m 100*150 square steel, and a notch is cut on one side of the connecting tube 104 to avoid obstruction to the lifting of the bracket 4. At the same time, a socket is drilled on the connecting tube 104 to cooperate with the through hole 9 opened at the bottom end of the vertical pole 2, so as to facilitate the installation of the fixing component 3. At the same time, the overall lifting height can be adjusted by inserting the vertical pole 2 in the connecting tube 104.
[0026] As attached Figure 3 As shown, the fixing assembly 3 includes a connecting plate 301, a bolt rod 302, a nut 303 and a handle 304. Two bolt rods 302 are symmetrically provided on one side of the connecting plate 301. The two bolt rods 302 are plugged into two adjacent sockets. A nut 303 is sleeved on the end of each bolt rod 302. A handle 304 is welded on the other side of the connecting plate 301.
[0027] In specific implementation, the two bolt rods 302 are inserted into the corresponding sockets, enter the corresponding through holes 9, and then pass through the sockets on the other side of the connecting tube 104. The bolt rods 302 are fixed with nuts, so that the connection between the connecting tube 104 and the vertical pole 2 can be fixed. The handle 304 is opened to facilitate pulling out the bolt rods 302.
[0028] As attached Figure 4 As shown, the support assembly 6 includes a fixed block 601, a fixed frame 602, a first pulley 603 and a second pulley 604. The fixed block 601 is welded to the top of the vertical pole 2, and the fixed frame 602 is welded to one side of the fixed block 601. The first pulley 603 is installed on the fixed frame 602, and the second pulley 604 is arranged on the inner side of the first pulley 603. The top end of the rope 7 is crimped on the first pulley 603, and the second pulley 604 is arranged on the outer side of the rope 7.
[0029] During specific implementation, the rope 7 is crimped onto the first pulley 603, and the first pulley 603 supports the rope 7 so that the winch 5 can smoothly reel in the rope 7, while the second pulley 604 limits the rope 7 to prevent the rope 7 from detaching from the first pulley 603, thereby ensuring operational stability and improving safety at work.
[0030] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A photovoltaic panel steel support quick lifting tool, comprising a base (1), characterized in that: A vertical pole (2) is inserted into the top of the base (1); a fixing assembly (3) is connected between the vertical pole (2) and the base (1); a bracket (4) is welded to one side of the vertical pole (2); a winch (5) is mounted on the bracket (4); a rope (7) is arranged on the winch (5); a hook (8) is fixed to the end of the rope (7); and a supporting assembly (6) for connecting to the rope (7) is welded to the top of the vertical pole (2).
2. A photovoltaic panel steel support quick lifting tool according to claim 1, characterized in that: The base (1) comprises a first transverse plate (101), a second transverse plate (102), a third transverse plate (103) and a connecting tube (104); two second transverse plates (102) are welded to one side of the first transverse plate (101); a third transverse plate (103) is welded to the other side of the first transverse plate (101); and a connecting tube (104) is vertically welded to the top of the first transverse plate (101).
3. A photovoltaic panel steel support quick lifting tool according to claim 2, characterized in that: A notch is provided on one side of the connecting tube (104), and insertion holes are evenly provided on the connecting tube (104).
4. A photovoltaic panel steel support quick lifting tool according to claim 3, characterized in that: A plurality of through holes (9) are evenly arranged at the bottom end of the vertical rod (2), and the distance between adjacent through holes (9) is the same as the distance between adjacent insertion holes.
5. A photovoltaic panel steel support quick lifting tool according to claim 4, characterized in that: The fixing assembly (3) comprises a connecting plate (301), a bolt rod (302), a nut (303) and a handle (304); two bolt rods (302) are symmetrically provided on one side of the connecting plate (301); the two bolt rods (302) are plugged into two adjacent sockets; a nut (303) is sleeved on the end of each bolt rod (302); and a handle (304) is welded on the other side of the connecting plate (301).
6. A photovoltaic panel steel support quick lifting tool according to claim 5, characterized in that: The support assembly (6) comprises a fixed block (601), a fixed frame (602), a first pulley (603) and a second pulley (604); the fixed block (601) is welded to the top of the vertical pole (2); the fixed frame (602) is welded to one side of the fixed block (601); the first pulley (603) is mounted on the fixed frame (602); and the second pulley (604) is arranged inside the first pulley (603).
7. A photovoltaic panel steel support quick lifting tool according to claim 6, characterized in that: The top end of the rope (7) is pressed onto the first pulley (603), and the second pulley (604) is arranged outside the rope (7).