Indoor anti-seepage floor structure of industrial building in non-ferrous metal processing project

Through the use of the anti -seepage floor structure of the multi -layer anti -seepage protection system indoors in the industrial building room of the non -ferrous metal processing project, the environment and health risks caused by the leakage of hazardous waste and dangerous goods are solved, and the effective anti -seepage and waterproof effects are achieved. , Meet strict environmental protection requirements.

CN222413149UActive Publication Date: 2025-01-28CHINA NON-FERROUS METALS PROCESSING TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421153944.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-24
Publication Date
2025-01-28
Estimated Expiration
2034-05-24

AI Technical Summary

Technical Problem

In non-ferrous metal processing projects, if hazardous waste and hazardous goods in industrial buildings leak, they may lead to environmental pollution and human health risks, and it is difficult to meet increasingly stringent environmental protection requirements.

Method used

The multi -layer anti -seepage protection system is adopted, including compacting rammed soil layers, fine stone concrete layers, waterproof blanket layers, geomantic membrane layers, geomantic layers, and non -fire finestone concrete layers. Through the combination of these levels Floor structure.

Benefits of technology

Effectively prevent ground leakage, prevent the environment and health risks brought by the leakage of danger, protect the ecological environment and human life safety, and meet strict environmental protection requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222413149U_ABST
    Figure CN222413149U_ABST
Patent Text Reader

Abstract

The utility model discloses an industrial building indoor anti-seepage terrace structure in a non-ferrous metal processing project, which comprises a compacted rammed earth layer, a fine aggregate concrete layer is arranged on the upper surface of the compacted rammed earth layer, a waterproof blanket layer is arranged on the upper surface of the fine aggregate concrete layer, a geomembrane layer is arranged on the upper surface of the waterproof blanket layer, and a geomembrane layer is arranged on the upper surface of the geomembrane layer. The geotextile layer is arranged on the upper surface of the geomembrane layer, the misfire fine aggregate concrete layer is arranged on the upper side of the geotextile layer, and the geotextile layer serves as a protective layer of the geomembrane layer, so that the geomembrane layer, the waterproof blanket layer and the like which are used for preventing seepage below the geotextile layer and the waterproof blanket layer are not damaged; the geomembrane layer can effectively prevent water, oil, waste and the like from permeating underground; the waterproof blanket layer is used as an anti-seepage liner, the problems of isolation and seepage prevention can be solved, and damage resistance is high. By using the multi-layer anti-seepage protection system, ground leakage can be better prevented, environmental and health risks caused by dangerous object leakage are effectively prevented, and the ecological environment and the life safety of people are protected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of anti-seepage flooring, in particular to an indoor anti-seepage flooring structure for industrial buildings in non-ferrous metal processing projects. Background Art

[0002] With the implementation of new environmental protection regulations and standards, the country's requirements for environmental protection are getting higher and higher, especially for projects involving hazardous waste and dangerous goods. From design to construction and acceptance, the standards and requirements have been raised accordingly. In the hazardous waste warehouses, dangerous goods warehouses, and aluminum slag storage rooms in the industrial plant area of ​​non-ferrous metal processing projects, if the hazardous waste and dangerous goods stored therein leak, it will cause serious pollution to the environment. Once leaked into the soil, it may cause soil acidification, excessive heavy metals, and other problems, and will also pose a threat to human health, and it does not meet the increasingly stringent environmental protection requirements. Therefore, we propose an indoor anti-seepage floor structure for industrial buildings in non-ferrous metal processing projects. Utility Model Content

[0003] The technical problem to be solved by the utility model is to overcome the existing defects and provide an indoor anti-seepage floor structure for industrial buildings in non-ferrous metal processing projects. The use of a multi-layer anti-seepage protection system can better prevent ground leakage, effectively prevent the environmental and health risks caused by the leakage of dangerous substances, protect the ecological environment and people's life safety, and can effectively solve the problems in the background technology.

[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an indoor anti-seepage floor structure of an industrial building in a non-ferrous metal processing project, comprising a compacted rammed earth layer, a fine stone concrete layer is arranged on the upper surface of the compacted rammed earth layer, a waterproof blanket layer is arranged on the upper surface of the fine stone concrete layer, a geomembrane layer is arranged on the upper surface of the waterproof blanket layer, a geotextile layer is arranged on the upper surface of the geomembrane layer, and a non-pyrophoric fine stone concrete layer is arranged on the upper side of the geotextile layer.

[0005] As a preferred technical solution of the utility model, a concrete cushion layer is arranged between the geotextile layer and the non-pyrophoric fine stone concrete layer.

[0006] As a preferred technical solution of the utility model, a cement slurry layer is arranged between the concrete cushion layer and the non-pyrophoric fine stone concrete layer.

[0007] As a preferred technical solution of the utility model, the waterproof blanket layer is a GCL natural sodium-based bentonite waterproof blanket.

[0008] As a preferred technical solution of the utility model, the geomembrane layer is a high-density polyethylene anti-seepage layer.

[0009] As a preferred technical solution of the utility model, the geotextile layer is a filament geotextile layer.

[0010] Compared with the prior art, the utility model has the following beneficial effects: using the geotextile layer as the protective layer of the geomembrane layer can prevent the geomembrane layer and waterproof blanket layer used for anti-seepage below from being damaged; the geomembrane layer can effectively prevent water, oil, waste, etc. from penetrating into the ground; the waterproof blanket layer, as an anti-seepage liner, can solve the problems of isolation and anti-leakage, and has strong anti-destructive properties. The use of a multi-layer anti-seepage protection system can better prevent ground leakage, effectively prevent the environmental and health risks caused by the leakage of dangerous substances, and protect the ecological environment and people's life safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a structural schematic diagram of the utility model;

[0012] Figure 2 It is a side structural schematic diagram of the utility model.

[0013] In the figure: 1 compacted earth layer, 2 fine stone concrete layer, 3 waterproof blanket layer, 4 geomembrane layer, 5 geotextile layer, 6 concrete cushion layer, 7 cement slurry layer, 8 non-pyrophoric fine stone concrete layer. DETAILED DESCRIPTION

[0014] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0015] See also Figure 1-2 The utility model provides a technical solution: an indoor anti-seepage floor structure of an industrial building in a non-ferrous metal processing project, comprising a compacted rammed earth layer 1 with a compaction coefficient of not less than 90%, the compacted rammed earth layer 1 being rammed into the soil by crushed stones with a thickness of 150 mm; a fine stone concrete layer 2 is arranged on the upper surface of the compacted rammed earth layer 1, specifically, a 30 mm thick C20 fine stone concrete slope leveling layer is used to smooth the thinnest part of the compacted rammed earth layer 1.

[0016] The upper surface of the fine stone concrete layer 2 is provided with a waterproof blanket layer 3, which is a GCL natural sodium-based bentonite waterproof blanket with a tensile strength of not less than 400N, a peeling strength of not less than 65N, and a permeability coefficient of not more than 5×10 -9 cm / s, bentonite content ≥5.0kg / m 2 .

[0017] Natural sodium-based bentonite waterproof blanket, as an anti-seepage liner, can solve the problems of isolation and anti-leakage and has strong anti-destructive properties.

[0018] The upper surface of the waterproof blanket layer 3 is provided with a geomembrane layer 4, which is a high-density polyethylene anti-seepage layer with a thickness of 1.5 mm. As an anti-seepage membrane, the HDPE geomembrane can effectively prevent water, oil, waste, etc. from penetrating into the ground.

[0019] The upper surface of the geomembrane layer 4 is provided with a geotextile layer 5, and the geotextile layer 5 is 400g / m 2 The filament geotextile layer is used as the protective layer of the geomembrane to protect the anti-seepage layer from damage.

[0020] A 40 mm thick C20 non-pyrophoric fine stone concrete layer 8 is arranged on the upper side of the geotextile layer 5, which is smoothed as soon as it is laid. Its aggregates include limestone and dolomite, etc., as the surface layer. The specific method can be adjusted according to the storage or process conditions.

[0021] The non-pyrophoric fine stone concrete layer 8 can withstand impact without sparks. When metal materials, hard stones and other objects undergo friction and impact with this type of concrete, no red-hot sparks or sparks will be generated. Therefore, flammable substances are not likely to cause the risk of explosion in fire. It can be used in petrochemical plants, chemical companies and other buildings where fire sources are prohibited or have certain fire safety requirements.

[0022] This application uses a multi-layer anti-seepage protection system to better prevent ground leakage. At the same time, according to the requirements of Articles 2.0.3, 2.0.4 and 2.0.6 of the "General Specification for Waterproofing of Buildings and Municipal Engineering" GB 55030-2022, the ground engineering waterproofing category in indoor station buildings such as hazardous waste warehouses, dangerous goods warehouses, and aluminum slag storage rooms is Class A, the engineering waterproofing use environment is Class III, and the waterproofing level is secondary waterproofing, which requires 1 waterproofing method. According to Article 3.6 on pages 2-6 of the atlas "Engineering Practices" 23J909, natural sodium-based bentonite waterproof blanket can be used as a waterproof layer for secondary waterproofing. Therefore, the anti-seepage floor structure of this application can meet the requirements of the waterproofing level while meeting the anti-seepage requirements.

[0023] According to a preferred technical solution, a 120mm thick C20 concrete cushion layer 6 is provided between the geotextile layer 5 and the non-pyrophoric fine stone concrete layer 8, and the thickness of the cushion layer can be adjusted according to storage or process conditions.

[0024] According to a preferred technical solution, a cement slurry layer 7 mixed with construction adhesive is provided between the concrete cushion layer 6 and the non-pyrophoric fine stone concrete layer 8 .

[0025] The undisclosed parts in the present utility model are all prior art, and their specific structures, materials and working principles are not described in detail. Although the embodiments of the present utility model have been shown and described, it is understood by those skilled in the art that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principles and spirit of the present utility model, and the scope of the present utility model is defined by the attached claims and their equivalents.

Claims

1. An indoor anti-seepage floor structure of an industrial building in a non-ferrous metal processing project, comprising a compacted rammed earth layer (1), characterized in that: A fine stone concrete layer (2) is arranged on the upper surface of the compacted rammed earth layer (1), a waterproof blanket layer (3) is arranged on the upper surface of the fine stone concrete layer (2), a geomembrane layer (4) is arranged on the upper surface of the waterproof blanket layer (3), a geotextile layer (5) is arranged on the upper surface of the geomembrane layer (4), and a non-pyrophoric fine stone concrete layer (8) is arranged on the upper side of the geotextile layer (5).

2. The indoor anti-seepage floor structure of an industrial building in a non-ferrous metal processing project according to claim 1 is characterized by: A concrete cushion layer (6) is provided between the geotextile layer (5) and the non-pyrophoric fine stone concrete layer (8).

3. The indoor anti-seepage floor structure of an industrial building in a non-ferrous metal processing project according to claim 2 is characterized by: A cement slurry layer (7) is provided between the concrete cushion layer (6) and the non-pyrophoric fine stone concrete layer (8).

4. The indoor anti-seepage floor structure of an industrial building in a non-ferrous metal processing project according to claim 1 is characterized by: The waterproof blanket layer (3) is a GCL natural sodium-based bentonite waterproof blanket.

5. The indoor anti-seepage floor structure of an industrial building in a non-ferrous metal processing project according to claim 1 is characterized by: The geomembrane layer (4) is a high-density polyethylene anti-seepage layer.

6. The indoor anti-seepage floor structure of an industrial building in a non-ferrous metal processing project according to claim 1 is characterized by: The geotextile layer (5) is a filament geotextile layer.