Platform for improving slag loading efficiency of slope ramp

By designing the mines on the slope of the mines, including the dregs of the car wall and one -third of the three -hearted three -hearted arches, it solves the problem of being difficult to effectively load the slag stones due to height and space restrictions. The process of slag has shortened the construction time.

CN222414861UActive Publication Date: 2025-01-28YUNNAN CHIHONG ZN & GE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421596529.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-08
Publication Date
2025-01-28
Estimated Expiration
2034-07-08

AI Technical Summary

Technical Problem

During the construction of underground slopes in the mine, mining trucks are difficult to effectively load slag stones due to their high height and limited ramp space, resulting in low loading efficiency and long cleaning time, which affects the ramp excavation efficiency.

Method used

A platform that includes a slope, car wall, and caravan chamber is designed. The room is one -third of the three -hearted arch structure. The wall blocking wall is set in the middle of the puppet room. Perform the residue operation to avoid dependence of specific venues.

Benefits of technology

The rapid formation of slag installation conditions on the slope can be achieved, shortening the construction time and difficulty of the slag installation platform, improving the loading efficiency and safety, and reducing construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222414861U_ABST
    Figure CN222414861U_ABST
Patent Text Reader

Abstract

The platform for improving the slag loading efficiency of the slope ramp comprises the slope ramp, a vehicle stopping wall and a chamber, the chamber is arranged on the plane and is perpendicular to the slope ramp, the vehicle stopping wall is arranged in the middle, close to one side of the chamber, in the slope ramp, and a gap for shovel loading equipment to pass through is formed between an opening of the chamber and the vehicle stopping wall; shoveling and loading equipment goes between the slope ramp and the chamber from the interval; according to the on-site rock condition and the shoveling distance, the reverse chamber is formed in the place with the good rock condition, the vehicle stopping wall is additionally arranged in the slope ramp reverse chamber to prevent the conditions of vehicle sliding, untimely braking and the like, the slope ramp slag stone loading function is achieved, and the problems that the mining truck is high, the slope ramp space is limited, and the loading efficiency is high are effectively solved. The problems that the existing slope ramp slag loading platform needs a specific site to load slag and stone, the specific slag loading platform is long in construction period and slow in construction, and slope ramp construction is restricted are solved, and the construction time and construction difficulty of the slope ramp slag loading platform are greatly shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of mining equipment, and in particular to a platform for improving the efficiency of slag loading on a ramp. Background Art

[0002] During the construction of underground mine ramps, the use of slag loading platforms is a common loading method. However, when loading slag with mining trucks, due to the high height of mining trucks and limited ramp space, a specific site is often required for slag loading. Each time the slag is loaded, the shovel needs to be driven to the platform, which not only affects the loading efficiency of slag, but also prolongs the time for cleaning the slag on the ramp, and may even cause the slag on the ramp to be cleaned in time, affecting the efficiency of ramp excavation. Therefore, how to effectively improve the loading efficiency of ramp slag, improve the efficiency of cleaning the slag on the ramp, and thus speed up the ramp excavation efficiency has always been a problem that needs to be solved in the field of mine ramp construction technology. Utility Model Content

[0003] In order to solve or partially solve the problems existing in the related art, the present application provides a platform for improving the slag loading efficiency of the ramp.

[0004] The first aspect of the present application provides a platform for improving the efficiency of ramp slag loading, comprising a ramp, a car blocking wall and a chamber, wherein the chamber is set as a one-third three-center arch with a length of 10m, a cross section of 3m width and 3m height;

[0005] Among them, the chamber is set perpendicular to the ramp on the plane, the car-blocking wall is set in the middle of the ramp close to one side of the chamber, and a gap for shoveling equipment to pass through is set between the chamber entrance and the car-blocking wall. The shoveling equipment travels between the ramp and the chamber through the gap.

[0006] Optionally, the chamber is provided with a supporting structure, which includes an anchor net and anchor rods; the anchor net is a metal net made of φ6mm steel bars with a length of 2m, a width of 1.2m, and a mesh size of 0.1m×0.1m; the anchor rod is a φ43mm, 1.8m long seamed steel pipe, and the anchor net is fixed by a pipe seam anchor rod.

[0007] Optionally, the vehicle blocking wall has a length of 1.5 m, a wall thickness of 0.5 m, a height of 0.5 m, and is cast with unreinforced C20 concrete.

[0008] The technical solution provided by this application may have the following beneficial effects:

[0009] In the process of excavating and discharging slag on the ramp, when the ramp is far from the slag loading, the reverse chamber can be opened in a place with better rock conditions according to the on-site rock conditions and the shoveling distance, and the function of loading slag on the ramp is realized by adding a car blocking wall in the reverse chamber of the ramp to prevent the car from slipping and untimely braking, etc., effectively avoiding the problem that the mining truck is high in height, the ramp space is limited, and a specific site is required for slag loading, and the specific slag loading platform has a long construction period and slow construction, which restricts the construction of the ramp, greatly shortening the construction time and construction difficulty of the ramp slag loading platform. At the same time, the utility model has simple construction, low investment cost, convenient slag loading, and is safer and more reliable during the slag loading process, and has a wide range of application prospects.

[0010] It should be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] The above and other objects, features and advantages of the present application will become more apparent through a more detailed description of exemplary embodiments of the present application in conjunction with the accompanying drawings, wherein the same reference numerals generally represent the same components in the exemplary embodiments of the present application.

[0012] Figure 1 It is a structural schematic diagram shown in an embodiment of the present application;

[0013] Figure 2 It is a plan view showing an embodiment of the present application;

[0014] Figure 3 This is an AA cross-sectional view of an embodiment of the present application.

[0015] Reference numerals:

[0016] A ramp (1), a chamber (2), an anchor net (3), an anchor rod (4), a shoveling device (5), a slag transportation device (6), and a vehicle blocking wall (7). DETAILED DESCRIPTION

[0017] The embodiments of the present application will be described in more detail below with reference to the accompanying drawings. Although the embodiments of the present application are shown in the accompanying drawings, it should be understood that the present application can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to make the present application more thorough and complete, and to fully convey the scope of the present application to those skilled in the art.

[0018] It should be understood that although the terms "first", "second", "third", etc. may be used in this application to describe various information, this information should not be limited to these terms. These terms are only used to distinguish the same type of information from each other. For example, without departing from the scope of this application, the first information may also be referred to as the second information, and similarly, the second information may also be referred to as the first information. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "multiple" is two or more, unless otherwise clearly and specifically defined.

[0019] In the description of the present application, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0020] Unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0021] In view of the problems in the above background, the embodiment of the present application provides a platform for improving the efficiency of ramp slag loading, which can effectively avoid the problem that the height of mining trucks is high, the ramp space is limited, and a specific site is required for slag loading, as well as the problem that the construction period of a specific slag loading platform is long and the construction is slow, which restricts the construction of the ramp, greatly shortening the construction time and difficulty of the ramp slag loading platform. At the same time, the utility model has simple construction, low investment cost, convenient slag loading, and is safer and more reliable during the slag loading process, and has a wide range of application prospects.

[0022] The technical solution of the embodiments of the present application is described in detail below with reference to the accompanying drawings.

[0023] like Figure 1 and Figure 2 The platform for improving the slag loading efficiency of the ramp shown in the figure comprises a ramp 1, a car blocking wall 7 and a chamber 2. The chamber 2 is set as a three-center arch with a length of 10m, a cross section of 3m wide and 3m high. Specifically, the cross section of the chamber 2 is as follows Figure 3As shown, the overall height is 3m, of which the bottom 2m is a square, and the top 1m is an arc arch, and the depth is 10m. In this way, the chamber 2 has enough space for the shoveling equipment 5 to enter and perform slag dumping operations.

[0024] The chamber 2 of the present application is arranged perpendicularly to the ramp 1 on a plane, and the car-blocking wall 7 is arranged in the middle of the ramp 1 close to one side of the chamber 2. A gap for the shoveling equipment 5 to pass through is arranged between the entrance of the chamber 2 and the car-blocking wall 7, and the shoveling equipment 5 travels between the ramp 1 and the chamber 2 through the gap.

[0025] In the present application, during the excavation of the ramp 1, the opening of the chamber 2 is selected according to the site requirements and rock conditions. After the excavation and support of the chamber 2 are completed, the car-blocking wall 7 at the mouth of the chamber 2 is cast. After 72 hours of mold maintenance, the car-blocking wall 7 can be removed from the mold for use. The chamber 2 and the car-blocking wall 7 are combined with the ramp 1 to form a slag loading platform, which can quickly form slag loading conditions. The slag transportation equipment 6 normally transports slag in the ramp 1, and the shoveling equipment 5 normally travels back and forth between the ramp 1 and the chamber 2. When the shoveling equipment 5 enters the chamber 2, the slag collected by the front end can be poured forward into the slag transportation equipment. In this way, there is no need to go to a distant fixed slag transfer platform, which greatly shortens the construction time of the ramp slag loading platform and makes the slag loading process safer and more reliable. In addition, the slag loading platform can also be used for material storage in the later stage.

[0026] In one embodiment, in order to provide sufficient support for the chamber 2, the chamber 2 of the present application adopts full-section anchor mesh support. Specifically, the support structure includes an anchor mesh 3 and an anchor rod 4, wherein the anchor mesh 3 is a metal mesh made of φ6mm steel bars with a length of 2m, a width of 1.2m, and a mesh size of 0.1m×0.1m; the anchor rod 4 is a φ43mm, 1.8m long seam steel pipe; the anchor mesh 3 is fixed by the pipe seam anchor rod 4, so that the surrounding rock of the chamber is more stable.

[0027] In one embodiment, the car-blocking wall 7 of the present application has a length of 1.5 m, a wall thickness of 0.5 m, and a height of 0.5 m. It is cast with unreinforced C20 concrete. The length of the car-blocking wall is smaller than the width of the reverse chamber mouth, and travel space is left for the shovel loading equipment 5, facilitating the travel of the shovel loading equipment 5.

[0028] In the process of excavating and discharging slag on the ramp, when the ramp is far from the slag loading, the reverse chamber can be opened in a place with better rock conditions according to the on-site rock conditions and the shoveling distance, and the function of loading slag on the ramp is realized by adding a car blocking wall in the reverse chamber of the ramp to prevent the car from slipping and untimely braking, etc., effectively avoiding the problem that the mining truck is high in height, the ramp space is limited, and a specific site is required for slag loading, and the specific slag loading platform has a long construction period and slow construction, which restricts the construction of the ramp, greatly shortening the construction time and construction difficulty of the ramp slag loading platform. At the same time, the utility model has simple construction, low investment cost, convenient slag loading, and is safer and more reliable during the slag loading process, and has a wide range of application prospects.

[0029] Finally, it should be noted that, in this article, relationships such as first and second, etc. are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms include, include or any other variations are intended to cover non-exclusive inclusion, so that a process, method, article or device that includes a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0030] The embodiments of the present application have been described above, and the above description is exemplary, not exhaustive, and is not limited to the disclosed embodiments. Many modifications and changes will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The selection of terms used herein is intended to best explain the principles of the embodiments, practical applications, or improvements to the technology in the market, or to enable other persons of ordinary skill in the art to understand the embodiments disclosed herein.

Claims

1. A platform for improving the efficiency of slag loading on a ramp, comprising a shovel loading device (5), characterized in that: The platform for improving the slag loading efficiency of the ramp comprises a ramp (1), a car blocking wall (7) and a chamber (2), wherein the chamber (2) is configured as a one-third three-center arch with a length of 10 m, a cross section of 3 m in width and 3 m in height; The chamber (2) is arranged perpendicularly to the ramp (1) on a plane, the vehicle blocking wall (7) is arranged in the middle of the ramp (1) near the chamber (2), and a gap for the shoveling equipment (5) to pass through is arranged between the chamber opening of the chamber (2) and the vehicle blocking wall (7), and the shoveling equipment (5) travels between the ramp (1) and the chamber (2) through the gap.

2. A platform for improving the efficiency of ramp slag loading according to claim 1, characterized in that: The chamber (2) is provided with a supporting structure, which includes an anchor net (3) and an anchor rod (4); the anchor net (3) is a metal net made of φ6 mm steel bars with a length of 2 m, a width of 1.2 m, and a mesh size of 0.1 m×0.1 m; the anchor rod (4) is a seamed steel pipe with a diameter of φ43 mm and a length of 1.8 m; the anchor net (3) is fixed by a pipe seam anchor rod (4).

3. A platform for improving the slag loading efficiency of a ramp according to claim 1, characterized in that: The vehicle blocking wall (7) has a length of 1.5 m, a wall thickness of 0.5 m, a height of 0.5 m, and is cast using unreinforced C20 concrete.