Bamboo grid filler cooling tower
By designing the electric push pole vibration system, scraper cleaning system and rotation water spray system of the bamboo grid filler cooling tower, it solves the problems of the accumulation of the surface impurities of bamboo filler, the inner wall pollution of the inner wall of the pond The long life of the grid, the cleaning and cooling efficiency of the recycling pool.
Patent Information
- Application Number
- CN202421132218.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-23
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-05-23
AI Technical Summary
After long-term use, bamboo grid filler can easily accumulate impurities and dirt in the water, reducing service life; impurities can easily accumulate in the inner wall of the recycling pool to produce algae, polluting the environment; existing cooling towers spray hot water unevenly, affecting cooling efficiency.
Design a kind of bamboo filler cooling tower, using electric push rods to drive the transmission block and spring system to vibrate the bamboo grid filler to remove the surface impurities; set the scraper to clean up the inner wall of the recycling pool to prevent algae production; through the rotating water pipe and the nozzle header Realize the uniform spray of water.
The service life of bamboo grid filled is extended, preventing the inner wall of the pond, and improving the cooling efficiency of the cooling tower.
Smart Images

Figure CN222418633U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of cooling towers, in particular to a cooling tower with bamboo lattice fillers. Background Art
[0002] A cooling tower is a device that uses water as a circulating coolant to absorb heat from a system and discharge it into the atmosphere to lower the water temperature. It uses the heat exchange between water and air flow to generate steam, and the steam evaporates and takes away the heat to achieve the principles of evaporative heat dissipation, convection heat transfer and radiation heat transfer to dissipate the waste heat generated in industry or refrigeration and air conditioning to lower the water temperature. The device is generally barrel-shaped, hence the name cooling tower.
[0003] The working mode of the cooling tower is usually to spray hot water on the bamboo lattice filler, and the airflow generated by the fan takes away the heat of the hot water on the bamboo lattice filler, thereby achieving cooling and cooling. The cooled water falls into the recovery pool under the action of gravity. After long-term use, the surface of the bamboo lattice filler is prone to accumulate impurities and dirt in the water, which will reduce the service life of the bamboo lattice filler. After long-term use, the inner wall of the recovery pool is prone to accumulate impurities and algae, which is easy to pollute the environment. The existing cooling tower is not convenient for uniform spraying when spraying hot water, which affects the cooling efficiency. Therefore, a bamboo lattice filler cooling tower is proposed. Utility Model Content
[0004] The main purpose of the utility model is to provide a bamboo lattice filling cooling tower, which solves the problem that after long-term use, the surface of the bamboo lattice filling is prone to accumulation of impurities and dirt in the water, which will reduce the service life of the bamboo lattice filling, and the inner wall of the recovery pool is prone to accumulation of impurities and algae after long-term use, which is easy to pollute the environment; the existing cooling tower is not convenient for uniform spraying of hot water, which affects the cooling efficiency.
[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0006] A bamboo lattice filling cooling tower comprises a cooling cylinder, wherein an upper side of the cooling cylinder is fixedly connected to a first mounting plate, one side of the first mounting plate is fixedly connected to an electric push rod, a lower output end of the electric push rod is fixedly connected to a connecting ring, four fourth transmission blocks are fixedly connected equidistantly below the connecting ring, the inner sides of the four fourth transmission blocks are all abutted against a third transmission block, the inner sides of the four third transmission blocks are fixedly connected to a first spring, the middle of the four first springs are fixedly connected to the cooling cylinder, the inner sides of the four third transmission blocks are fixedly connected to a transmission rod, four transmission holes are equidistantly provided on the circumferential outer surface of the cooling cylinder, the four transmission rods pass through the four transmission holes respectively, the inner ends of the four transmission rods are fixedly connected to a second transmission block, and the four second transmission blocks are all arranged in the cooling cylinder, the lower sides of the four second transmission blocks are all abutted against the first transmission block, the lower sides of the four second transmission blocks are fixedly connected to a fixed cage, and bamboo lattice filling is installed inside the fixed cage.
[0007] Furthermore, four connecting rods are equidistantly fixedly connected to the bottom of the fixed cage, and a second spring is fixedly connected to the bottom of the four connecting rods. Limiting sleeves are movably sleeved on the circumferential outer surfaces of the four connecting rods, and a second mounting plate is fixedly connected to the bottom of the four limiting sleeves, and the outer sides of the four second mounting plates are fixedly connected to the inner wall of the cooling cylinder.
[0008] Furthermore, a connecting bracket is fixedly connected to the top of the cooling cylinder, a water inlet pipe is fixedly connected to the inner side of the connecting bracket, a connecting pipe is movably sleeved at the bottom of the water inlet pipe, a third mounting plate is fixedly connected to the top side of the cooling cylinder, a first motor is fixedly connected to one side of the second mounting plate, a second gear is fixedly connected to the bottom output end of the first motor, a first gear is toothed on one side of the second gear, the first gear is fixedly sleeved on the outside of the connecting pipe, a mounting hole is opened at the top of the cooling cylinder, the connecting pipe is movably sleeved in the mounting hole, a clamping plate is fixedly sleeved on the circumferential outer surface of the connecting pipe, and the clamping plate abuts against the cooling cylinder at the bottom.
[0009] Furthermore, a water distribution pipe is fixedly connected below the connecting pipe, the internal spaces of the water distribution pipe and the connecting pipe are interconnected, and a plurality of nozzles are fixedly connected equidistantly below the water distribution pipe.
[0010] Furthermore, a rotating shaft is fixedly connected to the middle of the lower part of the water distribution pipe, the rotating shaft is movably sleeved in the fixed cage, the rotating shaft is movably sleeved in the bamboo grid filler, and the lower end of the rotating shaft is fixedly connected to a scraper.
[0011] Furthermore, an air intake cylinder is fixedly connected below the cooling cylinder, a recovery pool is fixedly connected below the air intake cylinder, a drainage pipe is fixedly connected below the recovery pool, four legs are fixedly connected equidistantly below the recovery pool, and the scraper abuts against the inner wall of the recovery pool.
[0012] Furthermore, two fans are fixedly connected to the top of the cooling cylinder at equal distances, and a control panel is fixedly connected to the side wall of the cooling cylinder. The control panel is electrically connected to the electric push rod, the first motor and the two fans.
[0013] Compared with the prior art, the utility model has the following beneficial effects:
[0014] 1. The utility model is convenient for vibrating the bamboo lattice filler by setting the second spring, removing impurities and dirt on the surface of the bamboo lattice filler, and extending the service life of the bamboo lattice filler. The electric push rod is started by the control panel, and the electric push rod pushes the connecting ring to move downward, and the connecting ring drives the fourth transmission block to move downward, and the fourth transmission block squeezes the third transmission block to move inward, and the third transmission block drives the first spring to compress, and at the same time the third transmission block drives the second transmission block to move inward through the transmission rod, and the second transmission block squeezes the first transmission block to move downward, and the first transmission block drives the bamboo lattice filler to move downward through the fixed cage, and at the same time the fixed cage drives the second spring to compress through the connecting rod, and the electric push rod is started to move in the opposite direction by the control panel, and the fixed cage is no longer subjected to the downward force but is pushed upward by the second spring, and the fixed cage drives the bamboo lattice filler to move upward, and as the electric push rod is repeatedly pushed, the bamboo lattice filler repeatedly moves up and down to achieve vibration, and the vibration causes the impurities and dirt on the surface of the bamboo lattice filler to fall off, and through such a setting, it is convenient to vibrate the bamboo lattice filler, remove impurities and dirt on the surface of the bamboo lattice filler, extend the service life of the bamboo lattice filler, and prevent the bamboo lattice filler from being blocked.
[0015] 2. The utility model facilitates the cleaning of the inner wall of the recycling pool by setting a scraper, prevents the deposition of debris on the inner wall of the recycling pool to generate algae, and prevents environmental pollution. The first motor is started through the control panel, and the first motor drives the first gear to rotate through the second gear. The first gear drives the rotating shaft to rotate through the connecting pipe and the water distribution pipe, and the rotating shaft drives the scraper to scrape the inner wall of the recycling pool. The scraped debris is discharged from the drain pipe with the water flow to prevent the formation of algae. Through such a setting, it is convenient to clean the inner wall of the recycling pool, prevent the deposition of debris on the inner wall of the recycling pool to generate algae, and prevent environmental pollution.
[0016] 3. The utility model provides a nozzle, which makes it convenient for the cooling tower to spray water evenly on the bamboo lattice filler, thereby improving work efficiency. Water to be cooled is added through the water inlet pipe, and the water flows into the water distribution pipe through the connecting pipe. The water in the water distribution pipe is discharged through the nozzle. When the water distribution pipe rotates, the water distribution pipe can continuously change the spraying position of the nozzle, so that the water is evenly sprayed on the bamboo lattice filler. Through such a setting, it is convenient for the cooling tower to spray water evenly on the bamboo lattice filler, thereby improving work efficiency.
[0017] The parts not involved in the device are the same as those in the prior art or can be implemented by using the prior art. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 This is a schematic diagram of the overall structure of a bamboo lattice filler cooling tower according to the utility model from a first angle.
[0019] Figure 2 This is a schematic diagram of the overall structure of a bamboo lattice filler cooling tower of the utility model from a second angle.
[0020] Figure 3 This is a schematic diagram of the overall structure of a bamboo lattice filler cooling tower of the utility model from a third angle.
[0021] Figure 4 The utility model is a schematic diagram of the internal structure of a cooling cylinder of a bamboo lattice filling cooling tower.
[0022] Figure 5 The utility model is a partial structural schematic diagram of a bamboo lattice filler of a bamboo lattice filler cooling tower.
[0023] Figure 6 The utility model is a partial structural schematic diagram of a rotating shaft of a bamboo lattice filling cooling tower.
[0024] Figure 7 It is a partial structural schematic diagram of a second transmission block of a bamboo lattice filling cooling tower of the utility model.
[0025] Figure 8 It is a partial structural schematic diagram of the first gear of a bamboo lattice filling cooling tower of the utility model.
[0026] In the figure: 1. water inlet pipe; 2. first gear; 3. water distribution pipe; 4. nozzle; 5. rotating shaft; 6. scraper; 7. fixed cage; 8. first transmission block; 9. second transmission block; 10. first spring; 11. third transmission block; 12. fourth transmission block; 13. connecting ring; 14. electric push rod; 15. first motor; 16. fan; 17. cooling cylinder; 18. control panel; 19. air inlet cylinder; 20. supporting leg; 21. drain pipe; 22. connecting rod; 23. second spring; 24. bamboo grid filler; 25. second gear. DETAILED DESCRIPTION
[0027] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.
[0028] like Figure 1-Figure 7 As shown, a bamboo lattice filling cooling tower comprises a cooling cylinder 17, a first mounting plate is fixedly connected to one side of the upper side of the cooling cylinder 17, an electric push rod 14 is fixedly connected to one side of the first mounting plate, a connecting ring 13 is fixedly connected to the lower output end of the electric push rod 14, four fourth transmission blocks 12 are fixedly connected equidistantly below the connecting ring 13, the inner sides of the four fourth transmission blocks 12 are all abutted against the third transmission blocks 11, the inner sides of the four third transmission blocks 11 are all fixedly connected with the first spring 10, the middle of the four first springs 10 is fixedly connected to the cooling cylinder 17, the inner sides of the four third transmission blocks 11 are all fixedly connected with a transmission rod, four transmission holes are equidistantly opened on the circumferential outer surface of the cooling cylinder 17, the four transmission rods pass through the four transmission holes respectively, the inner ends of the four transmission rods are fixedly connected to the second transmission blocks 9, and the four second transmission blocks 9 are all arranged in the cooling cylinder 17, the lower sides of the four second transmission blocks 9 are all abutted against the first transmission block 8, the four second transmission blocks 9 is fixedly connected with a fixed cage 7 below, and a bamboo lattice filler 24 is installed inside the fixed cage 7. Through such an arrangement, the electric push rod 14 is started through the control panel 18, and the electric push rod 14 pushes the connecting ring 13 to move downward, and the connecting ring 13 drives the fourth transmission block 12 to move downward, and the fourth transmission block 12 squeezes the third transmission block 11 to move inward, and the third transmission block 11 drives the first spring 10 to compress, and at the same time, the third transmission block 11 drives the second transmission block 9 to move inward through the transmission rod, and the second transmission block 9 squeezes the first transmission block 8 to move downward, and the first transmission block 8 drives the bamboo lattice filler 24 to move downward through the fixed cage 7, and at the same time, the fixed cage 7 drives the second spring 23 to compress through the connecting rod 22, and the electric push rod 14 is started to move in the opposite direction through the control panel 18. Through such an arrangement, it is convenient to vibrate the bamboo lattice filler 24, remove impurities and dirt on the surface of the bamboo lattice filler 24, extend the service life of the bamboo lattice filler 24, and prevent the bamboo lattice filler 24 from being blocked.
[0029] like Figure 1-Figure 7 As shown, four connecting rods 22 are equidistantly fixedly connected to the bottom of the fixed cage 7, and second springs 23 are fixedly connected to the bottom of the four connecting rods 22. Limiting sleeves are movably sleeved on the circumferential outer surfaces of the four connecting rods 22, and second mounting plates are fixedly connected to the bottom of the four limiting sleeves. The outer sides of the four second mounting plates are fixedly connected to the inner wall of the cooling cylinder 17. Through such an arrangement, the second springs 23 are movably arranged in the limiting sleeves to prevent exposure to the air and being corroded and contaminated.
[0030] like Figure 1-Figure 8As shown, a connecting bracket is fixedly connected to the top of the cooling cylinder 17, a water inlet pipe 1 is fixedly connected to the inner side of the connecting bracket, a connecting pipe is movably sleeved at the bottom of the water inlet pipe 1, a third mounting plate is fixedly connected to one side of the top of the cooling cylinder 17, a first motor 15 is fixedly connected to one side of the second mounting plate, a second gear 25 is fixedly connected to the lower output end of the first motor 15, a first gear 2 is toothed on one side of the second gear 25, the first gear 2 is fixedly sleeved on the outside of the connecting pipe, a mounting hole is provided on the top of the cooling cylinder 17, the connecting pipe is movably sleeved in the mounting hole, a clamping plate is fixedly sleeved on the circumferential outer surface of the connecting pipe, and the bottom of the clamping plate abuts against the cooling cylinder 17. Through such an arrangement, because the connecting pipe is movably sleeved on the water inlet pipe 1, the water inlet pipe 1 will not be driven to rotate when the connecting pipe rotates, and the clamping plate can limit the movement of the connecting pipe.
[0031] like Figure 1-Figure 8 As shown, a water distribution pipe 3 is fixedly connected to the bottom of the connecting pipe, and the internal spaces of the water distribution pipe 3 and the connecting pipe are interconnected. A plurality of nozzles 4 are fixedly connected to the bottom of the water distribution pipe 3 at equal intervals. Through such an arrangement, water to be cooled is added through the water inlet pipe 1, and the water flows into the water distribution pipe 3 through the connecting pipe. The water in the water distribution pipe 3 is discharged through the nozzle 4. When the water distribution pipe 3 rotates, the water distribution pipe 3 can continuously change the spraying position of the nozzle 4, so as to achieve uniform spraying of water on the bamboo lattice filler 24. Through such an arrangement, it is convenient for the cooling tower to spray water evenly on the bamboo lattice filler 24, thereby improving work efficiency.
[0032] like Figure 1-Figure 7 As shown, a rotating shaft 5 is fixedly connected to the middle of the lower part of the water distribution pipe 3, and the rotating shaft 5 is movably sleeved in the fixed cage 7. The rotating shaft 5 is movably sleeved in the bamboo grid filler 24. The lower end of the rotating shaft 5 is fixedly connected to a scraper 6. Through such a setting, the first motor 15 is started through the control panel 18, and the first motor 15 drives the first gear 2 to rotate through the second gear 25. The first gear 2 drives the rotating shaft 5 to rotate through the connecting pipe and the water distribution pipe 3. The rotating shaft 5 drives the scraper 6 to scrape the inner wall of the recovery pool. The scraped debris is discharged from the drain pipe 21 with the water flow to prevent the formation of algae. Through such a setting, it is convenient to clean the inner wall of the recovery pool, prevent the deposition of debris on the inner wall of the recovery pool to produce algae, and prevent environmental pollution.
[0033] like Figure 1-Figure 4 As shown, an air intake cylinder 19 is fixedly connected to the bottom of the cooling cylinder 17, a recovery pool is fixedly connected to the bottom of the air intake cylinder 19, a drainage pipe 21 is fixedly connected to the bottom of the recovery pool, four legs 20 are fixedly connected at equal intervals below the recovery pool, and the scraper 6 abuts against the inner wall of the recovery pool. Through such an arrangement, a plurality of air inlets are opened on the surface of the air intake cylinder 19, and the fan 16 can draw outside air through the air inlets to cool the water in the cooling tower. At the same time, the arrangement of the air inlets can prevent external dirt from entering the cooling tower.
[0034] like Figure 1-Figure 3 As shown, two fans 16 are fixedly connected equidistantly above the cooling cylinder 17 , and a control panel 18 is fixedly connected to the side wall of the cooling cylinder 17 . The control panel 18 is electrically connected to the electric push rod 14 , the first motor 15 and the two fans 16 .
[0035] It should be noted that when in use, the support leg 20 is placed on a horizontal plane, an external power supply is connected through the control panel 18, water to be cooled is added through the water inlet pipe 1, the water flows through the connecting pipe into the water distribution pipe 3, the first motor 15 is started through the control panel 18, the first motor 15 drives the first gear 2 to rotate through the second gear 25, the first gear 2 drives the water distribution pipe 3 to rotate through the connecting pipe, the water in the water distribution pipe 3 is discharged through the nozzle 4, the water is sprayed on the bamboo lattice filler 24, the fan 16 is started through the control panel 18, the fan 16 draws outside air through the air intake pipe 19 to generate airflow to cool the water on the bamboo lattice filler 24, the cooled water on the bamboo lattice filler 24 falls into the recovery pool due to gravity, and the water in the recovery pool can be discharged through the drain pipe 21.
[0036] When it is necessary to clean the impurities and dirt on the surface of the bamboo lattice filler 24, the electric push rod 14 is started through the control panel 18, and the electric push rod 14 pushes the connecting ring 13 to move downward, and the connecting ring 13 drives the fourth transmission block 12 to move downward, and the fourth transmission block 12 squeezes the third transmission block 11 to move inward, and the third transmission block 11 drives the first spring 10 to compress, and at the same time, the third transmission block 11 drives the second transmission block 9 to move inward through the transmission rod, and the second transmission block 9 squeezes the first transmission block 8 to move downward, and the first transmission block 8 drives the bamboo lattice filler 24 to move downward through the fixed cage 7. At the same time, the fixed cage 7 drives the second spring 23 to compress through the connecting rod 22, and the electric push rod 14 is started to move in the opposite direction through the control panel 18. The fixed cage 7 is no longer subjected to the downward force but is pushed upward by the second spring 23. The fixed cage 7 drives the bamboo lattice filler 24 to move upward. As the electric push rod 14 is repeatedly pushed, the bamboo lattice filler 24 repeatedly moves up and down to achieve vibration, and the vibration causes the impurities and dirt on the surface of the bamboo lattice filler 24 to fall off.
[0037] When the inner wall of the recovery pool needs to be cleaned, the first motor 15 is started through the control panel 18. The first motor 15 drives the first gear 2 to rotate through the second gear 25. The first gear 2 drives the rotating shaft 5 to rotate through the connecting pipe and the water distribution pipe 3. The rotating shaft 5 drives the scraper 6 to scrape the inner wall of the recovery pool. The scraped debris is discharged from the drain pipe 21 with the water flow to prevent the formation of algae.
[0038] The utility model relates to the technical field of cooling towers and provides a bamboo lattice filler cooling tower, which solves the problem that after long-term use of the bamboo lattice filler 24, impurities and dirt in water are easily accumulated on the surface of the bamboo lattice filler 24, which will reduce the service life of the bamboo lattice filler, and impurities and algae are easily accumulated on the inner wall of the recovery pool after long-term use, which is easy to pollute the environment, and the existing cooling tower is not convenient for uniform spraying when spraying hot water, which affects the cooling efficiency. The utility model is more practical.
[0039] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A bamboo lattice packing cooling tower, comprising a cooling cylinder (17), characterized in that: A first mounting plate is fixedly connected to one side of the upper side of the cooling cylinder (17), an electric push rod (14) is fixedly connected to one side of the first mounting plate, a connecting ring (13) is fixedly connected to the output end below the electric push rod (14), four fourth transmission blocks (12) are fixedly connected equidistantly below the connecting ring (13), the inner sides of the four fourth transmission blocks (12) are all in contact with the third transmission blocks (11), the inner sides of the four third transmission blocks (11) are fixedly connected to the first springs (10), the middle of the four first springs (10) are fixedly connected to the cooling cylinder (17), and the four The inner sides of the third transmission blocks (11) are fixedly connected with transmission rods, and the outer circumferential surface of the cooling cylinder (17) is provided with four transmission holes at equal intervals. The four transmission rods pass through the four transmission holes respectively, and the inner ends of the four transmission rods are fixedly connected with second transmission blocks (9), and the four second transmission blocks (9) are arranged in the cooling cylinder (17). The lower sides of the four second transmission blocks (9) are abutted with the first transmission blocks (8), and the lower sides of the four second transmission blocks (9) are fixedly connected with a fixed cage (7), and the interior of the fixed cage (7) is installed with a bamboo grid filler (24).
2. A bamboo lattice packing cooling tower according to claim 1, characterized in that: Four connecting rods (22) are fixedly connected at equal intervals below the fixed cage (7), and second springs (23) are fixedly connected below the four connecting rods (22). Limiting sleeves are movably sleeved on the circumferential outer surfaces of the four connecting rods (22), and second mounting plates are fixedly connected below the four limiting sleeves. The outer sides of the four second mounting plates are fixedly connected to the inner wall of the cooling cylinder (17).
3. A bamboo lattice packing cooling tower according to claim 2, characterized in that: A connecting bracket is fixedly connected to the top of the cooling cylinder (17), a water inlet pipe (1) is fixedly connected to the inner side of the connecting bracket, a connecting pipe is movably sleeved at the bottom of the water inlet pipe (1), a third mounting plate is fixedly connected to one side of the top of the cooling cylinder (17), a first motor (15) is fixedly connected to one side of the second mounting plate, a second gear (25) is fixedly connected to the output end at the bottom of the first motor (15), a first gear (2) is toothed at one side of the second gear (25), the first gear (2) is fixedly sleeved on the outside of the connecting pipe, a mounting hole is provided at the top of the cooling cylinder (17), the connecting pipe is movably sleeved in the mounting hole, a clamping plate is fixedly sleeved on the circumferential outer surface of the connecting pipe, and the bottom of the clamping plate abuts against the cooling cylinder (17).
4. A bamboo lattice packing cooling tower according to claim 3, characterized in that: A water distribution pipe (3) is fixedly connected below the connecting pipe, the internal spaces of the water distribution pipe (3) and the connecting pipe are interconnected, and a plurality of spray heads (4) are fixedly connected at equal intervals below the water distribution pipe (3).
5. A bamboo lattice packing cooling tower according to claim 4, characterized in that: A rotating shaft (5) is fixedly connected to the middle of the lower part of the water distribution pipe (3); the rotating shaft (5) is movably sleeved in the fixed cage (7); the rotating shaft (5) is movably sleeved in the bamboo grid filler (24); and a scraper (6) is fixedly connected to the lower end of the rotating shaft (5).
6. A bamboo lattice packing cooling tower according to claim 5, characterized in that: An air intake cylinder (19) is fixedly connected below the cooling cylinder (17), a recovery pool is fixedly connected below the air intake cylinder (19), a drainage pipe (21) is fixedly connected below the recovery pool, four legs (20) are fixedly connected at equal intervals below the recovery pool, and the scraper (6) abuts against the inner wall of the recovery pool.
7. A bamboo lattice packing cooling tower according to claim 6, characterized in that: Two fans (16) are fixedly connected at equal distances above the cooling cylinder (17), and a control panel (18) is fixedly connected to the side wall of the cooling cylinder (17). The control panel (18) is electrically connected to the electric push rod (14), the first motor (15) and the two fans (16).