Device for improving lateral pipe outlet and warehouse delivery efficiency of steel pipe corrosion prevention factory

By designing a lateral pipe outlet storage efficiency improvement device in the steel pipe anti-corrosion factory, the electronically controlled opening and closing connecting rods are used to connect the first and second steel pipe treads, the frequent switching caused by the small number of steel pipes in the lateral tread is solved. The problem has significantly improved the efficiency of lifting and delivery.

CN222475158UActive Publication Date: 2025-02-14SINOPEC OILFIELD EQUIP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420332230.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-22
Publication Date
2025-02-14
Estimated Expiration
2034-02-22

AI Technical Summary

Technical Problem

In steel pipe anti-corrosion plants, the number of lateral tread storage steel pipes is small, which causes the trolley to frequently switch stacking and shipping positions, and the overall efficiency of lifting and shipping is inefficient.

Method used

Design a steel pipe anti-corrosion factory lateral pipe outlet storage efficiency improvement device, including the first steel pipe tread in the steel pipe production plant and the second steel pipe tread in the steel pipe stacking plant, the two are connected by electrically controlled opening and closing The rod docking, and the skycar only performs the lifting task after the second steel pipe trench is filled with more steel pipes.

Benefits of technology

Through this device, Tianche has plenty of time to carry out the task of lifting stacked steel pipes to the delivery vehicle, which significantly improves the efficiency of lifting and warehouse delivery, and improves the overall efficiency several times.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222475158U_ABST
    Figure CN222475158U_ABST
Patent Text Reader

Abstract

The utility model relates to a steel pipe corrosion prevention plant lateral pipe outlet and warehouse delivery efficiency improving device which comprises a first steel pipe rack installed in a steel pipe production plant and a second steel pipe rack installed in a steel pipe stacking plant, the steel pipe production plant and the steel pipe stacking plant are arranged side by side in a spaced mode, and a crown block for hoisting steel pipes is arranged in the steel pipe stacking plant; one end of the first steel pipe rack extends out of the steel pipe production plant and is parallel to the second steel pipe rack, and the end, close to the second steel pipe rack, of the first steel pipe rack is rotationally connected with an electric control opening and closing connecting rod in butt joint with the second steel pipe rack. After the first steel pipe rack and the second steel pipe rack are in butt joint through the electric control opening and closing connecting rod, the crown block can execute the task of hoisting and stacking the steel pipes on the second steel pipe rack until the second steel pipe rack is full of multiple steel pipes, so that the crown block has enough time to execute the task of hoisting and stacking the steel pipes to a forwarding vehicle, and the working efficiency is improved. And the hoisting and transferring efficiency is improved by multiple times.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of steel pipe plant production facilities, and in particular to a device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant. Background Art

[0002] The construction of domestic steel pipe anti-corrosion plants is partially limited by the length of the plant land. The finished product delivery area and the production line plant are not in a straight line, but in a parallel line, and the pipe delivery area of ​​the plant is close to the delivery area. The delivery method of this type of steel pipe anti-corrosion production line is mostly adopted in China: open a door along the side wall of the plant at the last process of the plant, set up a side stand that slightly extends out of the side wall by about 2-3 meters, and store the finished anti-corrosion pipes on the side stand. 3-4 steel pipes are stored, and the delivery crane needs to move to the side stand to lift the steel pipes on the side stand to the stacking area for storage, and then the crane will lift the stacked steel pipes to the shipping truck.

[0003] The disadvantages of this method are: (1) Whenever a few steel pipes are stored on the side rack, the overhead crane must be moved to the side rack area in time to lift the steel pipes on the rack to the warehouse stack. When the production rhythm is fast, the overhead crane cannot lift them in time, and the side rack is full of pipes and blocked, causing the production line to stop. (2) Since the overhead crane frequently moves to perform the task of lifting steel pipes from the rack to the stack, the maintenance cycle of the overhead crane is reduced. (3) The time for the overhead crane to lift the stacked steel pipes to the shipping vehicle is relatively tight, and the overall efficiency of lifting, shipping and warehouse delivery is low. Summary of the invention

[0004] The embodiment of the present application provides a device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant, so as to solve the problem in the related art that the number of steel pipes stored on the lateral rack is small, resulting in the need for the overhead crane to frequently switch between the stacking and shipping positions, and the overall lifting, shipping and delivery efficiency is low.

[0005] The present application embodiment provides a device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant, comprising:

[0006] A first steel pipe stand installed in a steel pipe production plant, and a second steel pipe stand installed in a steel pipe stacking plant, the steel pipe production plant and the steel pipe stacking plant are arranged side by side and spaced apart, and a crane for hoisting steel pipes is provided in the steel pipe stacking plant;

[0007] One end of the first steel pipe rack extends out of the steel pipe production plant and is parallel to the second steel pipe rack. One end of the first steel pipe rack close to the second steel pipe rack is rotatably connected to an electrically controlled opening and closing connecting rod that docks with the second steel pipe rack.

[0008] In some embodiments: the electrically controlled opening and closing connecting rod is connected to a first driving mechanism that drives it to rotate around the first steel pipe stand, and the first driving mechanism is electrically connected to a first sensor that monitors whether the electrically controlled opening and closing connecting rod is in a docking state, and a second sensor that monitors whether the electrically controlled opening and closing connecting rod is in a disconnected state.

[0009] In some embodiments: it also includes a PLC controller, the PLC controller is connected to a digital input module and a digital output module, the first sensor and the second sensor are both connected to the digital input module, and the digital output module is connected to the first drive mechanism through a relay circuit.

[0010] In some embodiments: one end of the overhead crane is connected to an overhead crane limit sensor, and both sides of the first steel pipe stand are respectively provided with a sensing iron plate for monitoring the moving position of the overhead crane limit sensor, and a second driving mechanism for driving the telescopic movement of the sensing iron plate.

[0011] In some embodiments: the second driving mechanism is electrically connected to a third sensor for monitoring whether the sensing iron plate is in an extended state, and a fourth sensor for monitoring whether the sensing iron plate is in a retracted state, the third sensor and the fourth sensor are both connected to a digital quantity input module, and the second driving mechanism is connected to a digital quantity output module through a relay circuit.

[0012] In some embodiments: the digital output module is connected to a wireless transmission module, and a wireless alarm is provided in the cab of the overhead crane, which is wirelessly connected to the wireless transmission module by signal, and when the first sensor monitors that the electrically controlled opening and closing connecting rod is in a docking state, the wireless transmission module sends an alarm signal to the wireless alarm.

[0013] In some embodiments: the overhead crane is provided with two groups, and the two groups of the overhead crane are respectively located on both sides of the second steel pipe rack, and the height of the first steel pipe rack gradually decreases towards the direction approaching the second steel pipe rack.

[0014] In some embodiments: one end of the electrically controlled opening and closing connecting rod is rotatably connected to the first steel pipe stand via a hinge shaft, and the electrically controlled opening and closing connecting rod flips up and down or rotates horizontally around the hinge shaft.

[0015] In some embodiments: one end of the first steel pipe rack close to the second steel pipe rack is rotatably connected to a stopper that prevents the steel pipe from rolling toward the second steel pipe rack, and a driving motor that drives the stopper to rotate up and down.

[0016] In some embodiments: the drive motor is connected to the digital output module through a relay circuit. When the second sensor detects that the electrically controlled opening and closing connecting rod is in a disconnected state, the PLC controller controls the drive motor through the relay circuit to drive the stop seat to flip upward.

[0017] The beneficial effects of the technical solution provided by this application include:

[0018] An embodiment of the present application provides a device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant. The device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant of the present application is provided with a first steel pipe stand installed in a steel pipe production plant, and a second steel pipe stand installed in a steel pipe stacking plant. The steel pipe production plant and the steel pipe stacking plant are arranged side by side, and a crane for lifting steel pipes is provided in the steel pipe stacking plant. One end of the first steel pipe stand extends out of the steel pipe production plant and is parallel to the second steel pipe stand. An end of the first steel pipe stand close to the second steel pipe stand is rotatably connected to an electrically controlled opening and closing connecting rod that docks with the second steel pipe stand.

[0019] Therefore, the device for improving the efficiency of lateral pipe delivery to the warehouse in the steel pipe anti-corrosion plant of the present application is located in the second steel pipe stand in the steel pipe stacking plant, one end of the first steel pipe stand extends out of the steel pipe production plant and is parallel to the second steel pipe stand, and the end of the first steel pipe stand close to the second steel pipe stand is rotatably connected to an electrically controlled opening and closing connecting rod that docks with the second steel pipe stand. After the first steel pipe stand and the second steel pipe stand are docked by the electrically controlled opening and closing connecting rod, the overhead crane can wait until the second steel pipe stand is full of many steel pipes before performing the task of lifting the steel pipes on the second steel pipe stand to the stack, so that the overhead crane has ample time to perform the task of lifting the stacked steel pipes to the shipping vehicle, and the efficiency of lifting and delivering to the warehouse is improved several times. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0021] Figure 1 It is a schematic diagram of the structure of an embodiment of the present application.

[0022] Reference numerals:

[0023] 1. Steel pipe production plant; 2. Steel pipe stacking plant; 3. The first steel pipe stand; 4. The second steel pipe stand; 5. Overhead crane; 6. Electric control opening and closing connecting rod; 7. The first driving mechanism; 8. The first sensor; 9. The second sensor; 10. PLC controller; 11. Digital input module; 12. Digital output module; 13. Relay circuit; 14. Induction iron plate; 15. The second driving mechanism; 16. The third sensor; 17. The fourth sensor; 18. Overhead crane limit sensor; 19. Wireless transmission module; 20. Wireless alarm. DETAILED DESCRIPTION

[0024] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0025] An embodiment of the present application provides a device for improving the efficiency of lateral pipe delivery to the warehouse in a steel pipe anti-corrosion plant, which can solve the problem in the related art that the number of steel pipes stored on the lateral rack is small, resulting in the need for the overhead crane to frequently switch between the stacking and shipping positions, and the overall low efficiency of lifting, shipping and delivery to the warehouse.

[0026] See also Figure 1 As shown, the embodiment of the present application provides a device for improving the efficiency of lateral pipe delivery to a steel pipe anti-corrosion plant, comprising:

[0027] A first steel pipe stand 3 is installed in a steel pipe production plant 1, and a second steel pipe stand 4 is installed in a steel pipe stacking plant 2, wherein the steel pipe production plant 1 and the steel pipe stacking plant 2 are arranged side by side, and a crane 5 for lifting steel pipes is provided in the steel pipe stacking plant 2. The crane 5 is a portal crane, and a track for the portal crane is provided on the ground of the steel pipe stacking plant 2, which is used to lift the steel pipes stored on the second steel pipe stand 4 into the steel pipe stacking plant 2 for stacking, and lift the stacked steel pipes onto a shipping vehicle.

[0028] One end of the first steel pipe rack 3 extends out of the steel pipe production plant 1 and is parallel to the second steel pipe rack 4 and tries to keep it in the same line. An end of the first steel pipe rack 3 close to the second steel pipe rack 4 is rotatably connected to an electrically controlled opening and closing connecting rod 6 that docks with the second steel pipe rack 4.

[0029] The electrically controlled opening and closing connecting rod 6 realizes the docking of the first steel pipe rack 3 and the second steel pipe rack 4 by rotation, and then the steel pipes on the first steel pipe rack 3 are rolled and stored on the second steel pipe rack 4 via the electrically controlled opening and closing connecting rod 6, thereby realizing the transfer of the steel pipes in the steel pipe production plant 1 to the steel pipe stacking plant 2, and doubling the storage quantity of the steel pipes.

[0030] The device for improving the efficiency of lateral pipe delivery to the warehouse in a steel pipe anti-corrosion plant in an embodiment of the present application is located on a second steel pipe rack 4 in a steel pipe stacking building 2, one end of the first steel pipe rack 3 extends out of the steel pipe production building 1 and is parallel to the second steel pipe rack 4, and one end of the first steel pipe rack 3 close to the second steel pipe rack 4 is rotatably connected to an electrically controlled opening and closing connecting rod 6 that docks with the second steel pipe rack 4.

[0031] When the first steel pipe rack 3 and the second steel pipe rack 4 are connected by the electrically controlled opening and closing connecting rod 6, the overhead crane 5 can wait until the second steel pipe rack 4 is filled with a large number of steel pipes before performing the task of lifting the steel pipes on the second steel pipe rack 4 to the stack, so that the overhead crane 5 has ample time to perform the task of lifting the stacked steel pipes to the shipping vehicle, and the efficiency of lifting and delivering to the warehouse is improved several times.

[0032] In some alternative embodiments: See Figure 1 As shown, an embodiment of the present application provides a device for improving the efficiency of lateral pipe delivery to the warehouse in a steel pipe anti-corrosion plant. The electrically controlled opening and closing connecting rod 6 of the device is connected to a first driving mechanism 7 that drives it to rotate around a first steel pipe stand 3. The first driving mechanism 7 is preferably but not limited to any one or more of a pneumatic cylinder, an oil cylinder, an electric cylinder, and a rack and pinion mechanism.

[0033] The first driving mechanism 7 is electrically connected to a first sensor 8 for monitoring the electrically controlled opening and closing connecting rod 6 in a docking state, and a second sensor 9 for monitoring the electrically controlled opening and closing connecting rod 6 in a disconnected state. When the first sensor 8 monitors that the electrically controlled opening and closing connecting rod 6 is in a docking state, the first sensor 8 sends a stop signal to the first driving mechanism 7, and when the second sensor 9 monitors that the electrically controlled opening and closing connecting rod 6 is in a disconnected state, the second sensor 9 sends a stop signal to the first driving mechanism 7.

[0034] In some alternative embodiments: See Figure 1 As shown, the embodiment of the present application provides a device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant, and the device also includes a PLC controller 10, and the PLC controller 10 is connected to a digital quantity input module 11 and a digital quantity output module 12. Among them, the first sensor 8 and the second sensor 9 are both connected to the digital quantity input module 11, and the digital quantity output module 12 is connected to the first drive mechanism 7 through a relay circuit 13.

[0035] One end of the overhead crane 5 is connected to an overhead crane limit sensor 18, and both sides of the first steel pipe stand 3 are respectively provided with a sensing iron plate 14 for monitoring the moving position of the overhead crane limit sensor 18, and a second driving mechanism 15 for driving the telescopic movement of the sensing iron plate 14. The second driving mechanism 15 is electrically connected to a third sensor 16 for monitoring the sensing iron plate 14 in an extended state, and a fourth sensor 17 for monitoring the sensing iron plate 14 in a retracted state. The third sensor 16 and the fourth sensor 17 are both connected to the digital quantity input module 11, and the second driving mechanism 15 is connected to the digital quantity output module 12 through a relay circuit 13.

[0036] The digital output module 12 is also connected to the wireless transmission module 19. A wireless alarm 20 connected to the wireless transmission module 19 by wireless signal is arranged in the cab of the overhead crane 5. When the first sensor 8 monitors that the electrically controlled opening and closing connecting rod 6 is in a docking state, the wireless transmission module 19 sends an alarm signal to the wireless alarm 20 to remind the personnel in the cab of the overhead crane 5 to prevent the overhead crane 5 from moving toward the first steel pipe stand 3 and causing a collision.

[0037] There are two sets of overhead cranes 5, which are respectively located on both sides of the second steel pipe rack 4. The two sets of overhead cranes 5 can work alternately to improve the lifting and transportation efficiency of steel pipes. The height of the first steel pipe rack 3 gradually decreases towards the second steel pipe rack 4. When the steel pipes processed in the steel pipe production plant 1 fall onto the first steel pipe rack 3, they can automatically roll freely toward the second steel pipe rack 4 and be stored on the second steel pipe rack 4.

[0038] One end of the electric opening and closing connecting rod 6 is rotatably connected to the first steel pipe stand 3 through a hinge shaft, and the electric opening and closing connecting rod 6 is turned upside down or rotated horizontally around the hinge shaft. When the electric opening and closing connecting rod 6 is disconnected from the second steel pipe stand 4 through rotation, the overhead crane 5 can move through the passage between the first steel pipe stand 3 and the second steel pipe stand 4.

[0039] One end of the first steel pipe rack 3 close to the second steel pipe rack 4 is rotatably connected to a stopper (not shown in the figure) for preventing the steel pipe from rolling toward the second steel pipe rack 4, and a drive motor (not shown in the figure) for driving the stopper to rotate up and down. When the electric-controlled opening and closing connecting rod 6 is disconnected from the second steel pipe rack 4 by rotation, the drive motor drives the stopper to rotate upward, so that the steel pipes that have been produced and processed are temporarily stored on the first steel pipe rack 3.

[0040] The drive motor is connected to the digital output module 12 via the relay circuit 13. When the second sensor 9 detects that the electrically controlled opening and closing connecting rod 6 is in the disconnected state, the PLC controller 10 controls the drive motor via the relay circuit 13 to drive the stop seat to flip upward.

[0041] How it works

[0042] When the first steel pipe rack 3 is filled with accumulated steel pipes, the "rack vertical" button is operated, and the button signal is transferred by the digital input module 11 and then acquired by the PLC controller 10. The PLC controller 10 sends a command to the digital output module 12, and the digital output module 12 sends a drive signal to the relay circuit 13. The relay circuit 13 sends a signal to the first drive mechanism 7, causing the first drive mechanism 7 to extend.

[0043] The push rod of the first driving mechanism 7 is connected to the electrically controlled opening and closing connecting rod 6 through the ear shaft. After the electrically controlled opening and closing connecting rod 6 rotates to the vertical position, it docks with the second steel pipe rack 4. After the first sensor 8 senses the electrically controlled opening and closing connecting rod 6, it sends a sensor signal to the PLC controller 10, and the PLC controller 10 sends an instruction to stop the output signal to the first driving mechanism 7, and the first driving mechanism 7 stops moving. At this time, the first steel pipe rack 3 is connected to the second steel pipe rack 4 through the electrically controlled opening and closing connecting rod 6, and the steel pipes on the first steel pipe rack 3 can be transported to the second steel pipe rack 4 for storage.

[0044] When the electrically controlled opening and closing connecting rod 6 is in the docking state, the PLC controller 10 receives the signal from the first sensor 8 and gives a driving signal to the relay circuit 13. After receiving the signal, the relay circuit 13 drives the second driving mechanism 15. The second driving mechanism 15 extends the sensing iron plate 14 and stops when it extends to the position of the third sensor 16. At this time, when the overhead crane 5 moves to the extended position of the sensing iron plate 14, the overhead crane limit sensor 18 stops moving after sensing the sensing iron plate 14 to prevent it from hitting the closed electrically controlled opening and closing connecting rod 6.

[0045] When the electric-controlled opening and closing connecting rod 6 is in the docking state, the PLC controller 10 will simultaneously send a signal to the wireless transmitting module 19 through the digital quantity input module 11, and the wireless transmitting module 19 will send a wireless signal to the wireless alarm 20 on the overhead crane 5, and the wireless alarm 20 will send a light alarm signal to the overhead crane operator to remind the operator that the electric-controlled opening and closing connecting rod 6 is in the docking state, and the overhead crane 5 is prohibited from moving toward the electric-controlled opening and closing connecting rod 6. At this time, the overhead crane 5 can perform the task of lifting the steel pipes on both sides of the electric-controlled opening and closing connecting rod 6 to the shipping vehicle.

[0046] When the second steel pipe rack 4 is just full, the following operations are performed:

[0047] When the second steel pipe rack 4 is filled with accumulated steel pipes, the button "rack flat" is operated on the control cabinet. The button signal is transferred by the digital input module 11 and then acquired by the PLC controller 10. The PLC controller 10 sends a command to the digital output module 12, and the digital output module 12 sends a drive signal to the relay circuit 13. The relay circuit 13 sends a signal to the first drive mechanism 7, causing the first drive mechanism 7 to retract.

[0048] The push rod of the first driving mechanism 7 is connected to the electrically controlled opening and closing connecting rod 6 through the ear shaft. After the electrically controlled opening and closing connecting rod 6 rotates to the horizontal position, the second sensor 9 senses the electrically controlled opening and closing connecting rod 6, and sends a sensor signal to the PLC controller 10. The PLC controller 10 sends an instruction to stop the output signal to the first driving mechanism 7, and the first driving mechanism 7 stops moving. At this time, the electrically controlled opening and closing connecting rod 6 is in the horizontal position, and the first steel pipe stand 3 and the second steel pipe stand 4 are in a disconnected state.

[0049] When the electrically controlled opening and closing connecting rod 6 is in a horizontal position, the PLC controller 10 receives the sensing signal from the second sensor 9 and sends a driving signal to the relay circuit 13. The relay circuit 13 sends a retraction signal to the second driving mechanism 15, causing the second driving mechanism 15 to retract and stop at the position of the fourth sensor 17. At this time, during the movement of the overhead crane 5 toward the first steel pipe stand 3, the distance between the sensing iron plate 14 and the overhead crane limit sensor 18 is greater than the maximum sensing distance of the stop limit, allowing the overhead crane 5 to move to the second steel pipe stand 4 to carry out the task of lifting the steel pipes on the second steel pipe stand 4.

[0050] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.

[0051] It should be noted that, in this application, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0052] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.

Claims

1. A device for improving the efficiency of lateral pipe delivery in a steel pipe anti-corrosion plant, characterized in that: include: A first steel pipe stand (3) installed in a steel pipe production plant (1), and a second steel pipe stand (4) installed in a steel pipe stacking plant (2), wherein the steel pipe production plant (1) and the steel pipe stacking plant (2) are arranged side by side and spaced apart, and a crane (5) for hoisting steel pipes is provided in the steel pipe stacking plant (2); One end of the first steel pipe rack (3) extends out of the steel pipe production plant (1) and is parallel to the second steel pipe rack (4); one end of the first steel pipe rack (3) close to the second steel pipe rack (4) is rotatably connected to an electrically controlled opening and closing connecting rod (6) that docks with the second steel pipe rack (4).

2. A device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant as claimed in claim 1, characterized in that: The electrically controlled opening and closing connecting rod (6) is connected to a first driving mechanism (7) for driving it to rotate around the first steel pipe stand (3); the first driving mechanism (7) is electrically connected to a first sensor (8) for monitoring whether the electrically controlled opening and closing connecting rod (6) is in a docking state, and a second sensor (9) for monitoring whether the electrically controlled opening and closing connecting rod (6) is in a disconnected state.

3. A device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant as claimed in claim 2, characterized in that: The invention also comprises a PLC controller (10), wherein the PLC controller (10) is connected to a digital quantity input module (11) and a digital quantity output module (12), wherein the first sensor (8) and the second sensor (9) are both connected to the digital quantity input module (11), and the digital quantity output module (12) is connected to the first driving mechanism (7) via a relay circuit (13).

4. A device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant as claimed in claim 3, characterized in that: One end of the overhead crane (5) is connected to an overhead crane limit sensor (18), and both sides of the first steel pipe stand (3) are respectively provided with a sensing iron plate (14) for monitoring the moving position of the overhead crane limit sensor (18), and a second driving mechanism (15) for driving the sensing iron plate (14) to telescope.

5. A device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant as claimed in claim 4, characterized in that: The second driving mechanism (15) is electrically connected to a third sensor (16) for monitoring whether the sensing iron plate (14) is in an extended state, and a fourth sensor (17) for monitoring whether the sensing iron plate (14) is in a retracted state. The third sensor (16) and the fourth sensor (17) are both connected to a digital quantity input module (11). The second driving mechanism (15) is connected to a digital quantity output module (12) via a relay circuit (13).

6. A device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant as claimed in claim 4, characterized in that: The digital quantity output module (12) is connected to a wireless transmission module (19), and a wireless alarm (20) connected to the wireless transmission module (19) via a wireless signal is arranged in the cab of the overhead crane (5); when the first sensor (8) detects that the electrically controlled opening and closing connecting rod (6) is in a docking state, the wireless transmission module (19) sends an alarm signal to the wireless alarm (20).

7. A device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant as claimed in claim 1, characterized in that: The overhead crane (5) is provided with two groups, and the two groups of the overhead crane (5) are respectively located on both sides of the second steel pipe stand (4), and the height of the first steel pipe stand (3) gradually decreases towards the direction approaching the second steel pipe stand (4).

8. The device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant according to claim 1, characterized in that: One end of the electrically controlled opening and closing connecting rod (6) is rotatably connected to the first steel pipe stand (3) via a hinge shaft, and the electrically controlled opening and closing connecting rod (6) performs upside-down flipping or horizontal rotation movement with the hinge shaft as the center.

9. A device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant as claimed in claim 3, characterized in that: One end of the first steel pipe stand (3) close to the second steel pipe stand (4) is rotatably connected to a stopper for preventing the steel pipe from rolling toward the second steel pipe stand (4), and a driving motor for driving the stopper to rotate up and down.

10. A device for improving the efficiency of lateral pipe delivery to a warehouse in a steel pipe anti-corrosion plant as claimed in claim 9, characterized in that: The drive motor is connected to the digital output module (12) via a relay circuit (13); when the second sensor (9) detects that the electrically controlled opening and closing connecting rod (6) is in a disconnected state, the PLC controller (10) controls the drive motor via the relay circuit (13) to drive the stop seat to flip upward.