Flood prevention plate reinforcing mechanism

By designing a flood control plate reinforcement mechanism with adjustable height, the problems of existing flood control plates are solved, and higher flood resistance and stability are achieved.

CN222477344UActive Publication Date: 2025-02-14济南市莱芜雪野水库管理处
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421293433.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-06
Publication Date
2025-02-14
Estimated Expiration
2034-06-06

AI Technical Summary

Technical Problem

The existing flood control plates are fixed in height and cannot be adjusted according to the actual water level. They are of low strength and are prone to deformation and damage under water pressure.

Method used

A flood control plate reinforcement mechanism is designed, including flood control plate one and flood control plate two. The flood control plate two can be slidably installed on the flood control plate one, and the height adjustment of the flood control plate two is achieved through the support mechanism and the adjustment parts. The support mechanism consists of locking parts, clamps, fixing frames, forward and reverse lead screws and rotors. By operating the rotors and forward and reverse lead screws, the opposite direction of the fixing frame is realized, thereby adjusting the height of the support mechanism.

Benefits of technology

It effectively improves the flood control board's flood resistance ability, avoids damage to the flood control board due to changes in water level, and improves the stability and flexibility of the flood control board.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222477344U_ABST
    Figure CN222477344U_ABST
Patent Text Reader

Abstract

The utility model provides a flood control plate reinforcing mechanism, and relates to the technical field of flood control plates. The flood control plate reinforcing mechanism comprises a first flood control plate, a stabilizing seat is fixedly installed below one side of the first flood control plate, supporting ribs are arranged on the two sides of the upper portion of the stabilizing seat, one sides of the supporting ribs are fixedly connected with the first flood control plate, and a second flood control plate is slidably arranged on the inner side of the first flood control plate. Supporting mechanisms are arranged at the two ends, away from the center position, of one side of the second flood prevention plate. The supporting mechanism comprises locking pieces, the two sets of locking pieces are rotationally arranged at the two ends of the supporting mechanism correspondingly, a first clamping block and a second clamping block are rotationally arranged on the outer sides of the two sets of locking pieces correspondingly, a second fixing frame is fixedly installed on one side of the first clamping block, and a first fixing frame is fixedly installed on one side of the second clamping block; the first fixing frame and the second fixing frame are oppositely arranged, and threaded holes are formed in the first fixing frame and the second fixing frame. The flood prevention plate reinforcing mechanism has the advantages of being convenient to use and high in flood prevention plate stability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of flood control boards, in particular to a flood control board reinforcement mechanism. Background Art

[0002] Flood control devices are needed in water conservancy projects to improve their safety. Flood retaining boards are a type of flood control facility that are easy to install and disassemble. They can block small floods and are suitable for blocking floods along rivers and roads.

[0003] However, the height of today's flood control boards is mostly fixed. During use, the height of the flood control boards cannot be adjusted according to the actual water level. In addition, the flood control boards themselves have low strength, and the vertical water retaining surface is easily deformed by the pressure of the water body, causing damage to the flood control boards.

[0004] Therefore, it is necessary to provide a new flood control board reinforcement mechanism to solve the above technical problems. Utility Model Content

[0005] The technical problem solved by the utility model is to provide a flood control board reinforcement mechanism which is easy to use and has high flood control board stability.

[0006] In order to solve the above technical problems, the flood prevention board reinforcement mechanism provided by the utility model includes a flood prevention board, a stabilizing seat is fixedly installed below one side of the flood prevention board, support ribs are arranged on both sides above the stabilizing seat, one side of the support ribs is fixedly connected to the flood prevention board, a flood prevention board 2 is slidably arranged inside the flood prevention board, and support mechanisms are arranged at both ends of one side of the flood prevention board 2 away from the center;

[0007] The supporting mechanism includes a locking piece, and the locking piece has two groups that are rotatably arranged at two ends of the supporting mechanism respectively, and a clamping block 1 and a clamping block 2 are rotatably arranged on the outer sides of the two groups of locking pieces respectively, a fixing frame 2 is fixedly installed on one side of the clamping block 1, and a fixing frame 1 is fixedly installed on one side of the clamping block 2, the fixing frame 1 and the fixing frame 2 are arranged opposite to each other, threaded holes are provided on the fixing frames 1 and 2, and forward and reverse screws are rotatably arranged on the inner sides of the fixing frames 1 and 2, and the forward and reverse screws are respectively engaged with the two threaded holes, and limiting rings are fixedly installed on both ends of the forward and reverse screws, and the diameter of the limiting rings is larger than the diameter of the threaded holes, and a rotating wheel is fixedly installed on the middle part of the outer sides of the forward and reverse screws.

[0008] Preferably, a fixing seat is provided on one side of the flood control board, a fixing platform is fixedly installed on the fixing seat and the top of the flood control board, and the locking member is provided on the fixing platform;

[0009] The locking member includes two support platforms, a connecting column is fixedly installed between the top ends of the two support platforms, through holes are provided on the first and second card blocks, and the first and second card blocks are movably connected to the outside of the connecting column through the through holes, two groups of guide holes are provided under the two support platforms, plug-in rods are inserted into the inner sides of the two groups of guide holes, a fixing block is fixedly installed at one end of the two plug-in rods, and a return spring is arranged on the outside of the two groups of plug-in rods, and the two ends of the return spring are respectively fixedly connected to the support platform and one side of the fixing block.

[0010] Preferably, an adjustment member is provided between the first flood protection board and the second flood protection board;

[0011] The adjusting member includes a fixing cylinder, a supporting plate 2 is fixedly installed at the bottom of one side of the flood control plate 1, a fixing cylinder is fixedly installed in the middle of the upper part of the supporting plate 2, a stabilizing block is arranged on the outer side of the fixing cylinder, the fixing cylinder is fixedly installed on one side of the flood control plate 1 through the stabilizing block, a threaded rod is rotatably arranged on the inner side of the fixing cylinder, a fixing plate 2 is fixedly installed on the top of one side of the flood control plate 2, a brake motor is fixedly installed on the upper part of the fixing plate 2, and one end of the threaded rod and the output end of the brake motor are connected to each other.

[0012] Preferably, protrusions are fixedly installed on both sides of the interior of the first flood protection board, and sliding grooves are opened on both sides of the second flood protection board, and the protrusions are slidably arranged on the inner sides of the sliding grooves.

[0013] Preferably, fixing hole one and fixing hole two are respectively provided at the two ends of the upper part of the stabilizing seat and the fixing seat, two groups of locking grooves are provided in the middle of the stabilizing seat, a connecting block is fixedly installed in the middle of the fixing seat, and a V-shaped groove is provided on the connecting block.

[0014] Preferably, auxiliary parts are provided on the flood control board 1 and the flood control board 2 on the side opposite to the adjusting part, and the auxiliary parts include a support plate 1, and the support plate 1 is fixedly installed on the flood control board 1 on the side opposite to the support plate 2, and a stabilizing rod is fixedly installed on the top of the support plate 1, and a fixing plate 1 is fixedly installed on the flood control board 2 on the side opposite to the fixing plate 2, and a limiting cylinder is fixedly installed below the fixing plate 1, and the stabilizing rod is slidably arranged on the inner side of the limiting cylinder, and the outer side of the stabilizing rod is close to the inner wall of the limiting cylinder.

[0015] Preferably, locking holes are provided on both sides of the fixing platform, one end of the plug-in rod is plugged into the inner side of the locking hole, and the plug-in rod and the locking hole are matched.

[0016] Compared with the related art, the flood control board reinforcement mechanism provided by the utility model has the following advantages:

[0017] Beneficial effects:

[0018] The utility model provides a flood control board reinforcement mechanism. An operator manually rotates a rotating wheel, and the rotation of the rotating wheel drives the rotation of the forward and reverse screws. The rotation of the forward and reverse screws causes the fixed frame 1 and the fixed frame 2 located on the outside to move in different directions, thereby increasing the distance between the fixed frame 1 and the fixed frame 2, so that the supporting mechanism as a whole can change with the height of the flood control board 2, effectively improving the flood resistance of the flood control board 1 and the flood control board 2, and avoiding damage to the flood control board 1 and the flood control board 2 due to changes in water levels. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 A structural schematic diagram of a preferred embodiment of the flood control board reinforcement mechanism provided by the utility model;

[0020] Figure 2 A structural schematic diagram of the flood control board reinforcement mechanism provided by the utility model from another perspective;

[0021] Figure 3 for Figure 1 A schematic diagram of the structure of the support mechanism shown;

[0022] Figure 4 for Figure 3 The structural schematic diagram of the locking member shown;

[0023] Figure 5 for Figure 1 An enlarged schematic diagram of part A is shown.

[0024] Numbers in the figure: 1, flood control board 1; 2, flood control board 2; 3, fixed platform; 301, locking hole; 4, fixed plate 1; 5, support mechanism; 501, fixed frame 1; 502, rotating wheel; 503, fixed frame 2; 504, positive and negative lead screw; 505, clamping block 1; 506, clamping block 2; 507, through hole; 6, locking piece; 601, support platform; 602, connecting column; 603, guide hole; 604, plug rod; 605, complex Position spring; 606, fixing block; 7, fixing seat; 8, fixing hole one; 9, stabilizing seat; 10, support plate one; 11, stabilizing rod; 12, limiting cylinder; 13, brake motor; 14, fixing plate two; 15, threaded rod; 16, fixing cylinder; 17, stabilizing block; 18, support plate two; 19, fixing hole two; 20, connecting block; 21, V-shaped groove; 22, locking groove; 23, supporting rib; 24, slide groove; 25, protrusion. DETAILED DESCRIPTION

[0025] The utility model is further described below in conjunction with the accompanying drawings and implementation modes.

[0026] Please refer to Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 ,in, Figure 1 A structural schematic diagram of a preferred embodiment of the flood control board reinforcement mechanism provided by the utility model; Figure 2 A structural schematic diagram of the flood control board reinforcement mechanism provided by the utility model from another perspective; Figure 3 for Figure 1 A schematic diagram of the structure of the support mechanism shown; Figure 4 for Figure 3 The structural schematic diagram of the locking member shown; Figure 5 for Figure 1The flood-proof board reinforcement mechanism includes a flood-proof board 1, a stabilizing seat 9 is fixedly installed at the bottom of one side of the flood-proof board 1, support ribs 23 are arranged on both sides above the stabilizing seat 9, one side of the support ribs 23 is fixedly connected to the flood-proof board 1, a flood-proof board 2 is slidingly arranged on the inner side of the flood-proof board 1, a protrusion 25 is fixedly installed on both sides of the inside of the flood-proof board 1, a slide groove 24 is provided on both sides of the flood-proof board 2, and the protrusion 25 is slidably arranged inside the slide groove 24 to improve the stability of the flood-proof board 2 when moving, a fixed seat 7 is arranged on one side of the flood-proof board 1, and a fixing hole 18 and a fixing hole 219 are respectively arranged at both ends above the stabilizing seat 9 and the fixing seat 7, and a fixing hole 19 is arranged in the middle of the stabilizing seat 9. Two sets of locking grooves 22 are provided, a connecting block 20 is fixedly installed in the middle of the fixing seat 7, and a V-shaped groove 21 is provided on the connecting block 20. When using the flood control board 1 and the flood control board 2, first fix the flood control board 1 and the fixing seat 7. When fixing, insert locking bolts into the fixing hole 18 and the fixing hole 219 respectively, fix them with bolts, and then place locking pins in the locking grooves 22 and the V-shaped grooves 21 to fix the flood control board 1 and the fixing platform 3 at the same time. The fixing seat 7 and the top of the flood control board 2 are fixedly installed with the fixing platform 3, and the locking member is arranged on the fixing platform 3; the locking member 6 includes two supporting platforms 601, two supporting platforms A connecting column 602 is fixedly installed between the tops of the platforms 601, through holes 507 are provided on the first block 505 and the second block 506, and the first block 505 and the second block 506 are movably sleeved on the outside of the connecting column 602 through the through holes 507. Two groups of guide holes 603 are provided under the two support platforms 601, and plug-in rods 604 are plugged into the inner sides of the two groups of guide holes 603. A fixed block 606 is fixedly installed at one end of the two plug-in rods 604. Reset springs 605 are provided on the outer sides of the two groups of plug-in rods 604. The two ends of the reset spring 605 are fixedly connected to the support platform 601 and one side of the fixed block 606 respectively. Locking holes 33 are provided on both sides of the fixed platform 603. 01, one end of the plug-in rod 604 is plugged into the inner side of the locking hole 301, and the plug-in rod 604 and the locking hole 301 are adapted to each other. After being fixed, the supporting mechanism 5 is installed on the flood control plate 2 and the fixing platform 3 on the fixing seat 7 through the locking piece 6. When locking, the operator pulls the fixing blocks 606 on both sides of the supporting platform 601, and the fixing blocks 606 are forced to move backward, so that the plug-in rod 604 can be pulled outward, and then the supporting platform 601 is moved close to the fixing platform 3, and the fixing blocks 606 are released, so that the reset spring 605 located on the outside is reset, so that the plug-in rod 604 is plugged into the inner side of the locking hole 301, thereby fixing the supporting mechanism 5.

[0027] An adjusting member is provided between flood control board 1 and flood control board 2; the adjusting member comprises a fixing cylinder 16, a supporting plate 2 18 is fixedly installed at the bottom of one side of flood control board 1, a fixing cylinder 16 is fixedly installed at the middle part above supporting plate 2 18, a stabilizing block 17 is provided on the outside of the fixing cylinder 16, the fixing cylinder 16 is fixedly installed on one side of flood control board 1 through the stabilizing block 17, a threaded rod 15 is rotatably provided on the inner side of the fixing cylinder 16, a fixing plate 2 14 is fixedly installed on the top of one side of flood control board 2, a brake motor 13 is fixedly installed above the fixing plate 2 14, one end of the threaded rod 15 and the output end of the brake motor 13 are connected to each other, when the height of flood control board 2 2 needs to be adjusted, the brake motor 13 works, and the rotation of the output end drives the lower threaded rod 15 to rotate, thereby making The threaded rod 15 moves upward on the inner side of the fixed tube 16. When the threaded rod 15 moves, the flood control board 2 2 is lifted upward. Auxiliary parts are provided on the flood control board 1 and the flood control board 2 on the side opposite to the adjusting part. The auxiliary parts include a support plate 10. The support plate 10 is fixedly installed on the flood control board 1 on the side opposite to the support plate 2 18. A stabilizing rod 11 is fixedly installed on the top of the support plate 10. A fixing plate 4 is fixedly installed on the side opposite to the fixing plate 2 14 on the flood control board 2. A limiting tube 12 is fixedly installed below the fixing plate 4. The stabilizing rod 11 is slidably arranged on the inner side of the limiting tube 12. The outer side of the stabilizing rod 11 is close to the inner wall of the limiting tube 12. When the threaded rod 15 is lifted, the limiting tube 12 on the other side will move outward on the outside of the stabilizing rod 11.

[0028] A support mechanism 5 is provided at both ends of one side of the flood control board 2, away from the center position; the support mechanism 5 includes a locking member 6, and the locking member 6 has two groups that are rotatably arranged at both ends of the support mechanism 5, and a clamping block 505 and a clamping block 506 are rotatably arranged on the outer sides of the two groups of locking members 6, and a fixing frame 503 is fixedly installed on one side of the clamping block 505, and a fixing frame 501 is fixedly installed on one side of the clamping block 506. The fixing frame 501 and the fixing frame 503 are arranged opposite to each other, and threaded holes are provided on the fixing frame 501 and the fixing frame 503, and positive and negative threads are rotatably arranged on the inner sides of the fixing frame 501 and the fixing frame 503. Rod 504, the forward and reverse screws 504 are respectively engaged with the two threaded holes, and limit rings are fixedly installed at both ends of the forward and reverse screws 504. The diameter of the limit rings is larger than the diameter of the threaded holes. A rotating wheel 502 is fixedly installed in the middle of the outer side of the forward and reverse screws 504. When the height of the flood control plate 2 is adjusted, the supporting mechanism 5 needs to be adjusted at the same time. The operator manually rotates the rotating wheel 502, and the rotation of the rotating wheel 502 drives the forward and reverse screws 504 to rotate. The rotation of the forward and reverse screws 504 will cause the fixed frame 1 501 and the fixed frame 2 503 located on the outside to move in different directions, thereby increasing the distance between the fixed frame 1 501 and the fixed frame 2 503.

[0029] The working principle of the flood control board reinforcement mechanism provided by the utility model is as follows:

[0030] When using flood control board 1 and flood control board 2, first fix flood control board 1 and fixing seat 7. When fixing, insert locking bolts into fixing hole 1 8 and fixing hole 2 19 respectively, fix them with bolts, and then place locking pins in locking groove 22 and V-shaped groove 21 to fix flood control board 1 and fixing platform 3 at the same time.

[0031] After fixing, the supporting mechanism 5 is installed on the flood control plate 2 and the fixing platform 3 on the fixing seat 7 through the locking piece 6. When locking, the operator pulls the fixing blocks 606 on both sides of the supporting platform 601, and the fixing blocks 606 are forced to move backward, so that the plug-in rod 604 can be pulled outward, and then the supporting platform 601 is moved close to the fixing platform 3, and the fixing blocks 606 are released, so that the reset spring 605 located on the outside is reset, so that the plug-in rod 604 is plugged into the inner side of the locking hole 301, thereby fixing the supporting mechanism 5.

[0032] When the height of the flood control board 2 needs to be adjusted, the brake motor 13 works, and the output end rotates to drive the threaded rod 15 below to rotate, so that the threaded rod 15 moves upward inside the fixed tube 16. When the threaded rod 15 moves, the flood control board 2 2 will be lifted upward, and when the threaded rod 15 is lifted, the limit tube 12 on the other side will move outward on the outside of the stabilizing rod 11.

[0033] When the height of the flood control board 2 is adjusted, the supporting mechanism 5 needs to be adjusted at the same time. The operator manually rotates the rotating wheel 502, and the rotation of the rotating wheel 502 drives the forward and reverse screws 504 to rotate. The rotation of the forward and reverse screws 504 will cause the fixed frame 1 501 and the fixed frame 2 503 located on the outside to move in different directions, thereby increasing the distance between the fixed frame 1 501 and the fixed frame 2 503.

[0034] Compared with the related art, the flood control board reinforcement mechanism provided by the utility model has the following advantages:

[0035] Beneficial effects:

[0036] The utility model provides a flood control board reinforcement mechanism. An operator manually rotates a rotating wheel 502. The rotation of the rotating wheel 502 drives the forward and reverse screws 504 to rotate. The rotation of the forward and reverse screws 504 causes the fixed frame 1 501 and the fixed frame 2 503 located on the outside to move in different directions, thereby increasing the distance between the fixed frame 1 501 and the fixed frame 2 503, so that the supporting mechanism 5 as a whole can change with the height of the flood control board 2, effectively improving the flood resistance of the flood control board 1 1 and the flood control board 2 2, and avoiding damage to the flood control board 1 1 and the flood control board 2 2 due to changes in water levels.

[0037] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A flood prevention board reinforcement mechanism, comprising a flood prevention board, a stabilizing seat is fixedly installed below one side of the flood prevention board, support ribs are arranged on both sides above the stabilizing seat, one side of the support ribs is fixedly connected to the flood prevention board, and the characteristics are as follows: A flood prevention board 2 is slidably arranged inside the flood prevention board 1, and support mechanisms are arranged at both ends of one side of the flood prevention board 2 away from the center; The supporting mechanism includes a locking piece, and the locking piece has two groups that are rotatably arranged at two ends of the supporting mechanism respectively, and a clamping block 1 and a clamping block 2 are rotatably arranged on the outer sides of the two groups of locking pieces respectively, a fixing frame 2 is fixedly installed on one side of the clamping block 1, and a fixing frame 1 is fixedly installed on one side of the clamping block 2, the fixing frame 1 and the fixing frame 2 are arranged opposite to each other, threaded holes are provided on the fixing frames 1 and 2, and forward and reverse screws are rotatably arranged on the inner sides of the fixing frames 1 and 2, and the forward and reverse screws are respectively engaged with the two threaded holes, and limiting rings are fixedly installed on both ends of the forward and reverse screws, and the diameter of the limiting rings is larger than the diameter of the threaded holes, and a rotating wheel is fixedly installed on the middle part of the outer sides of the forward and reverse screws.

2. The flood protection board reinforcement mechanism according to claim 1, characterized in that: A fixing seat is provided on one side of the flood control board, a fixing platform is fixedly installed on the fixing seat and the top of the flood control board, and the locking member is provided on the fixing platform; The locking member includes two support platforms, a connecting column is fixedly installed between the top ends of the two support platforms, through holes are provided on the first and second card blocks, and the first and second card blocks are movably connected to the outside of the connecting column through the through holes, two groups of guide holes are provided under the two support platforms, plug-in rods are inserted into the inner sides of the two groups of guide holes, a fixing block is fixedly installed at one end of the two plug-in rods, and a return spring is arranged on the outside of the two groups of plug-in rods, and the two ends of the return spring are respectively fixedly connected to the support platform and one side of the fixing block.

3. The flood protection board reinforcement mechanism according to claim 1, characterized in that: An adjusting member is provided between the first flood control board and the second flood control board; The adjusting part includes a fixing cylinder, a supporting plate 2 is fixedly installed at the bottom of one side of the flood control plate 1, a fixing cylinder is fixedly installed in the middle above the supporting plate 2, a stabilizing block is arranged on the outside of the fixing cylinder, the fixing cylinder is fixedly installed on one side of the flood control plate 1 through the stabilizing block, a threaded rod is rotatably arranged on the inside of the fixing cylinder, a fixing plate 2 is fixedly installed on the top of one side of the flood control plate 2, a brake motor is fixedly installed above the fixing plate 2, and one end of the threaded rod and the output end of the brake motor are connected to each other.

4. The flood protection board reinforcement mechanism according to claim 1, characterized in that: Both sides of the interior of the first flood protection plate are fixedly mounted with protrusions, and both sides of the second flood protection plate are provided with sliding grooves, and the protrusions are slidably arranged inside the sliding grooves.

5. The flood protection board reinforcement mechanism according to claim 2, characterized in that: The two ends of the upper part of the stabilizing seat and the fixing seat are respectively provided with a fixing hole one and a fixing hole two, the middle part of the stabilizing seat is provided with two sets of locking grooves, the middle part of the fixing seat is fixedly installed with a connecting block, and the connecting block is provided with a V-shaped groove.

6. The flood protection board reinforcement mechanism according to claim 3, characterized in that: An auxiliary part is arranged on the side of the flood control plate 1 and the flood control plate 2 opposite to the adjusting part, and the auxiliary part includes a support plate 1, and the support plate 1 is fixedly installed on the side of the flood control plate 1 opposite to the support plate 2, and a stabilizing rod is fixedly installed on the top of the support plate 1, and a fixing plate 1 is fixedly installed on the side of the flood control plate 2 opposite to the fixing plate 2, and a limiting cylinder is fixedly installed below the fixing plate 1, and the stabilizing rod is slidably arranged on the inner side of the limiting cylinder, and the outer side of the stabilizing rod is close to the inner wall of the limiting cylinder.

7. The flood protection board reinforcement mechanism according to claim 2, characterized in that: Locking holes are provided on both sides of the fixing platform, one end of the plug-in rod is plugged into the inner side of the locking hole, and the plug-in rod and the locking hole are matched.