Hydraulic engineering construction guardrail

By designing the connection device and height adjustment mechanism of the water conservancy engineering construction guardrail, the problem of inconvenient connection and height adjustment of guardrails in the existing technology is solved, and a more efficient and flexible protective effect is achieved.

CN222478342UActive Publication Date: 2025-02-14XINJIANG ZHUTAI CONSTRUCTION ENGINEERING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420202043.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2025-02-14
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

The existing water conservancy project construction guardrail is inconvenient to connect multiple guardrails when used, and the height of the guardrail cannot be adjusted as needed, making it inconvenient to use.

Method used

A water conservancy project construction guardrail is designed, including a guardrail main body, a connecting device and a limiting device. These components are used to facilitate the connection of multiple guardrail main bodies, and the height adjustment of the guardrail main body is achieved through slide rods, top plates and adjustment rods.

Benefits of technology

It realizes convenient connection and height adjustment of multiple guardrail bodies, improves the practicality and adaptability of the device, and is suitable for different protective height requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222478342U_ABST
    Figure CN222478342U_ABST
Patent Text Reader

Abstract

The utility model discloses a hydraulic engineering construction guardrail, which relates to the technical field of hydraulic engineering, and comprises a guardrail main body, the inner side surface of the guardrail main body is fixedly connected with a fence net, a top plate is arranged above the guardrail main body, the two sides of the lower part of the top plate are fixedly connected with sliding rods, and the outer surfaces of the lower ends of the two sliding rods are provided with limiting cavities; an adjusting rod is movably connected into the limiting cavity, a connecting device is arranged on one side of the guardrail body, and a limiting device is arranged on the side, away from the connecting device, of the guardrail body. By arranging the guardrail main bodies, the connecting devices and the limiting devices, the multiple guardrail main bodies of the same structure can be conveniently connected, the guardrail main bodies can conveniently isolate a water conservancy project area, personnel are prevented from being hurt, and the height of the guardrail main bodies can be conveniently adjusted by arranging the sliding rods, the top plate and the adjusting rods; and the device is suitable for different protection heights, and the practicability of the device is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of water conservancy projects, in particular to a water conservancy project construction guardrail. Background Art

[0002] Water conservancy engineering mainly studies the basic knowledge and skills in engineering hydrology, water conservancy engineering surveying, water conservancy reinforced concrete, hydraulic structures, engineering drawing, etc., and conducts engineering planning and design, on-site construction, engineering budgeting, and maintenance and repair of water conservancy equipment in the field of water conservancy engineering. For example: building different types of hydraulic structures such as dams, dikes, spillways, sluices, channels, ferry canals, rafts, fishways, etc. During the construction of water conservancy projects, there will be some dangerous areas that are prohibited for people to enter. At this time, guardrails will be used to isolate these areas to avoid harm to people.

[0003] For example, the Chinese patent with application number "CN202220126096.6", whose name is "A guardrail for water conservancy project construction", includes a first fixing rod and a second fixing rod, the bottom of the first fixing rod and the second fixing rod are fixedly connected to a support block, the support block is provided with a fixing hole, the top of the fixing hole is provided with a rotating rod and a rotating block, the bottom of the rotating rod is fixedly connected to the top of the rotating block, the bottom of the rotating block is fixedly connected to a fixing nail, the bottom of the fixing nail passes through the fixing hole and extends to the bottom of the support block, the fixing nail is threadedly connected to the fixing hole, and the right side of the first fixing rod and the left side of the second fixing rod are fixedly connected to the mounting block. The utility model pulls the pulling block, and the pulling block drives the movable rod to disengage from the round hole and the groove, so that the cross bar is released from the restriction and can be taken out from the mounting groove, thereby completing the disassembly of the cross bar. The operation is simple, provides convenience for the staff, and reduces their workload.

[0004] When in use, this structure removes the crossbar by pulling the pull block, thereby reducing the workload of the staff. However, in actual use, a large number of guardrails are required to protect the water conservancy project area. When in use, this device is not convenient for connecting multiple guardrails, and the height of the guardrail cannot be adjusted according to the required protection height, which is very inconvenient to use. Utility Model Content

[0005] In view of the deficiencies in the prior art, the utility model provides a water conservancy project construction guardrail. By providing a guardrail body, a connecting device and a limiting device, it is convenient to connect multiple guardrail bodies of the same structure, and the guardrail body can isolate the water conservancy project area to avoid harm to personnel. A sliding rod, a top plate and an adjusting rod are provided to facilitate adjusting the height of the guardrail body, so that the device is suitable for different protection heights, thereby improving the practicality of the device.

[0006] The utility model also provides a water conservancy project construction guardrail, comprising: a guardrail body, a fence net is fixedly connected to the inner side of the guardrail body, grooves are arranged on both sides above the guardrail body, through holes are arranged on both sides of the guardrail body, a top plate is arranged above the guardrail body, sliding rods are fixedly connected to both sides below the top plate, and a limited cavity is arranged on the outer surface of the lower ends of the two sliding rods, an adjustment rod is movably connected in the limited cavity, and a reset spring is fixedly connected to one end of the adjustment rod located at the inner wall of the limited cavity, a lighting assembly is fixedly connected above the top plate, a connecting device is arranged on one side of the guardrail body, and a limited device is arranged on the side of the guardrail body away from the connecting device. By arranging the guardrail body, the connecting device and the limiting device, it is convenient to connect multiple guardrail bodies of the same structure, and it is convenient for the guardrail body to isolate the water conservancy project area to avoid harm to personnel. The sliding rod, the top plate and the adjusting rod are arranged, and it is convenient to adjust the height of the guardrail body, so that the device is suitable for different protection heights, and the practicality of the device is improved.

[0007] According to the hydraulic engineering construction guardrail, the connection device includes a connection rod fixedly connected to one side of the guardrail body, one side of the connection rod is fixedly connected to a connection column, and one side of the connection column is fixedly connected to a support. The guardrail body is easily connected through the connection device.

[0008] According to the hydraulic engineering construction guardrail, the limiting device includes a limiting rod fixedly connected to one side of the guardrail body, one side of the limiting rod is fixedly connected to a limiting shell, one side of the limiting shell is provided with a first limiting groove, the end of the first limiting groove and a second limiting groove is provided on the limiting shell, and the front and rear sides of the limiting shell are threadedly connected to limiting bolts. The limiting device is used to facilitate the limiting of the connection device and the connection of the guardrail body.

[0009] According to the hydraulic engineering construction guardrail, the connecting column is slidably connected to the first limiting groove, and the supporting column is slidably connected to the second limiting groove. The supporting column is conveniently limited inside the first limiting groove, thereby connecting multiple guardrail bodies.

[0010] According to the hydraulic engineering construction guardrail, the limiting bolt passes through one side of the first limiting groove, and the limiting bolt is threadedly connected to the outer wall of the connecting column. The limiting bolt is used to limit the connecting column inside the first limiting groove.

[0011] According to the water conservancy project construction guardrail, the guardrail body is affixed with reflective stickers on both sides, and the lighting component is an LED lamp. The reflective stickers and the lighting component improve the visibility of the device, which is convenient for pedestrians to pay attention to.

[0012] According to the water conservancy project construction guardrail, a bottom plate is fixedly connected to the bottom of the guardrail body, and four fixing nails are threadedly connected to the top of the bottom plate, and the four fixing nails are symmetrically arranged. The bottom plate and the fixing nails are used to fix the bottom of the guardrail body, thereby improving the stability of the guardrail body.

[0013] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The utility model is further described below in conjunction with the accompanying drawings and embodiments;

[0015] Figure 1 This is a schematic diagram of the overall structure of a water conservancy project construction guardrail of the utility model;

[0016] Figure 2 This is a schematic diagram of the overall unfolded structure of a water conservancy project construction guardrail of the utility model;

[0017] Figure 3 This is a schematic diagram of the structure of a connection device and a limit device for a water conservancy project construction guardrail of the utility model;

[0018] Figure 4 The utility model is a schematic diagram of the internal structure of a slide bar of a water conservancy project construction guardrail.

[0019] Legend:

[0020] 1. Guardrail body; 2. Fence net; 3. Groove; 4. Through hole; 5. Top plate; 6. Sliding rod; 7. Limiting cavity; 8. Adjusting rod; 9. Reset spring; 10. Lighting assembly; 11. Connecting device; 12. Limiting device; 111. Connecting rod; 112. Connecting column; 113. Pillar; 121. Limiting rod; 122. Limiting shell; 123. First limiting groove; 124. Second limiting groove; 125. Limiting bolt; 100. Reflective tape; 101. Bottom plate; 102. Fixing nail. DETAILED DESCRIPTION

[0021] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.

[0022] Reference Figure 1-4The utility model embodiment of a water conservancy project construction guardrail comprises: a guardrail body 1, an inner side surface of the guardrail body 1 is fixedly connected with a fence net 2, grooves 3 are arranged on both sides above the guardrail body 1, through holes 4 are arranged on both sides of the guardrail body 1, and the through holes 4 run through one side of the groove 3, a top plate 5 is arranged above the guardrail body 1, and sliding rods 6 are fixedly connected on both sides below the top plate 5, and the sliding rods 6 are slidably connected to the grooves 3, and a limited cavity 7 is arranged on the outer surface of the lower ends of the two sliding rods 6, and an adjusting rod 8 is movably connected in the limiting cavity 7, and the adjusting rod 8 is slidably connected to the through holes 4, and the adjusting rod 8 is located at one end of the inner wall of the limiting cavity 7 and is fixedly connected with a return spring 9, and the return spring 9 facilitates the adjustment rod 8 to shrink inside the limiting cavity 7, and a lighting assembly 10 is fixedly connected above the top plate 5, and the lighting assembly 10 facilitates the display of the guardrail body 1 to be improved, a connecting device 11 is arranged on one side of the guardrail body 1, and a limiting device 12 is arranged on the side of the guardrail body 1 away from the connecting device 11.

[0023] The connecting device 11 comprises a connecting rod 111 fixedly connected to one side of the guardrail body 1, a connecting column 112 fixedly connected to one side of the connecting rod 111, and a support column 113 fixedly connected to one side of the connecting column 112. The connecting device 11 facilitates connecting a plurality of guardrail bodies 1 of the same structure.

[0024] The limiting device 12 includes a limiting rod 121 fixedly connected to one side of the guardrail body 1, one side of the limiting rod 121 is fixedly connected to a limiting shell 122, one side of the limiting shell 122 is provided with a first limiting groove 123, and the first limiting groove 123 is slidably connected to the connecting column 112, a second limiting groove 124 is provided at the end of the first limiting groove 123 and located on the limiting shell 122, and the second limiting groove 124 is slidably connected to the support column 113, and the front and rear sides of the limiting shell 122 are threadedly connected with limiting bolts 125.

[0025] Working principle: When used for the first time, the guardrail body 1 is moved to the water conservancy project area to be protected, and then the bottom of the guardrail body 1 is fixed by the fixing nail 102 to improve the stability of the guardrail body 1 when in use. When multiple guardrail bodies 1 need to be connected, the connecting column 112 and the support 113 on one side of multiple guardrail bodies 1 of the same structure can be slid into the first limiting groove 123 and the second limiting groove 124, and the connecting column 112 is clamped into the first limiting groove 123 by the support 113, and then the connecting column 112 is fixed by rotating the limiting bolt 125, so as to complete the connection of multiple guardrail bodies 1. When the height of the guardrail body 1 needs to be adjusted, the adjusting rod 8 can be pressed to make the adjusting rod 8 shrink to the limiting cavity 7 under the action of the return spring 9. After the top plate 5 on the slide rod 6 is pulled out and reaches the specified height, the adjusting rod 8 pops out from the limiting cavity 7 under the action of the return spring 9 and passes through the through hole 4. The through hole 4 plays a limiting role on the adjusting rod 8, thereby completing the adjustment of the height of the guardrail body 1.

[0026] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of ordinary technicians in the relevant technical field without departing from the purpose of the present invention.

Claims

1. A water conservancy project construction guardrail, comprising: A guardrail body (1) is characterized in that a fence net (2) is fixedly connected to the inner side surface of the guardrail body (1), grooves (3) are arranged on both sides of the upper part of the guardrail body (1), through holes (4) are arranged on both sides of the guardrail body (1), a top plate (5) is arranged on the upper part of the guardrail body (1), sliding rods (6) are fixedly connected to both sides of the lower part of the top plate (5), limiting cavities (7) are arranged on the outer surfaces of the lower ends of the two sliding rods (6), an adjusting rod (8) is movably connected in the limiting cavity (7), a return spring (9) is fixedly connected to one end of the adjusting rod (8) located on the inner wall of the limiting cavity (7), a lighting assembly (10) is fixedly connected to the upper part of the top plate (5), a connecting device (11) is arranged on one side of the guardrail body (1), and a limiting device (12) is arranged on the side of the guardrail body (1) away from the connecting device (11).

2. A water conservancy project construction guardrail according to claim 1, characterized in that: The connecting device (11) comprises a connecting rod (111) fixedly connected to one side of the guardrail body (1), one side of the connecting rod (111) is fixedly connected to a connecting column (112), and one side of the connecting column (112) is fixedly connected to a support column (113).

3. A water conservancy project construction guardrail according to claim 1, characterized in that: The limiting device (12) comprises a limiting rod (121) fixedly connected to one side of the guardrail body (1); one side of the limiting rod (121) is fixedly connected to a limiting shell (122); one side of the limiting shell (122) is provided with a first limiting groove (123); a second limiting groove (124) is provided at the end of the first limiting groove (123) and located on the limiting shell (122); and the limiting bolts (125) are threadedly connected to the front and rear sides of the limiting shell (122).

4. A water conservancy project construction guardrail according to claim 2, characterized in that: The connecting column (112) is slidably connected to the first limiting groove (123), and the supporting column (113) is slidably connected to the second limiting groove (124).

5. A water conservancy project construction guardrail according to claim 3, characterized in that: The limiting bolt (125) passes through one side of the first limiting groove (123), and the limiting bolt (125) is threadedly connected to the outer side wall of the connecting column (112).

6. A water conservancy project construction guardrail according to claim 1, characterized in that: Reflective stickers (100) are attached to the front and rear sides of the guardrail body (1), and the lighting component (10) is an LED lamp.

7. A water conservancy project construction guardrail according to claim 1, characterized in that: A bottom plate (101) is fixedly connected to the bottom of the guardrail body (1), and four fixing nails (102) are threadedly connected to the top of the bottom plate (101), and the four fixing nails (102) are symmetrically arranged.

Citation Information

Patent Citations

  • Protective fence for hydraulic engineering construction

    CN217353828U