Assembly type shear wall sleeve-free connecting structure
By setting up installation grooves on the end surface of the main body of the shear wall, the connection of the shear wall is achieved by using the combination of the connecting ring of the first embedded part, the socket and the rotary part, which solves the complicated operation of the traditional shear wall sleeve structure. , the problem of inefficiency improves construction efficiency and structural stability.
Patent Information
- Application Number
- CN202420398248.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-01
- Publication Date
- 2025-02-18
- Estimated Expiration
- 2034-03-01
AI Technical Summary
The traditional shear wall sleeve structure is cumbersome and inefficient.
Adopting a prefabricated shear wall sleeve-free connection structure, by setting up installation grooves on the end surface of the main body of the shear wall, the connection of the shear wall is achieved by using the combination of the connecting ring of the first embedded member and the socket and the rotary member. , avoiding the use of traditional sleeves.
The connection structure is simplified, construction efficiency is improved, operation complexity is reduced, and structural stability is enhanced through the design of the second and third embedded parts and the project quality is improved.
Smart Images

Figure CN222500680U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of assembled buildings, in particular to an assembled shear wall sleeve-free connection structure. Background Art
[0002] Walls can be divided into load-bearing walls and shear walls according to their stress characteristics. The former mainly bears vertical loads, such as masonry walls, while the latter mainly bears horizontal loads. In earthquake-resistant areas, horizontal loads are mainly generated by horizontal earthquakes, so shear walls are sometimes also called earthquake-resistant walls.
[0003] Prefabricated shear walls are prefabricated in factories and assembled on site, which can improve construction efficiency and reduce environmental pollution. Traditional shear walls are connected by sleeve structures, which requires multiple steel bars to be connected one by one with sleeves, which is cumbersome and inefficient. Summary of the invention
[0004] In order to overcome the problem of "the traditional shear wall sleeve structure is cumbersome to operate and inefficient" existing in the above-mentioned background technology, the utility model provides an assembled shear wall sleeve-free connection structure.
[0005] The technical solution adopted by the utility model to solve the above-mentioned technical problems is: an assembled shear wall sleeve-free connection structure, comprising a shear wall body and a first embedded part, a mounting groove is provided in the middle of the side end surface of the body; one end of the first embedded part is fixedly connected to the interior of the body, and the other end of the first embedded part is provided with a connecting ring, and the connecting ring is located in the mounting groove; the first embedded part comprises a sleeve and a spin-on part, the sleeve is a cylindrical structure, the outer surface of the sleeve is fixedly connected to the body, and the inner surface of the sleeve is connected to the spin-on part by a thread; it also includes a second embedded part, the second embedded part is a plate-like structure; the second embedded part is provided with a first through hole, and the first through hole is sleeved with the outer surface of the sleeve; the end of the sleeve away from the spin-on part is fixedly connected with an abutment plate, and the abutment plate and the spin-on part are respectively arranged on both sides of the second embedded part.
[0006] As a further optimization scheme of the utility model, it also includes a third embedded part, which is an L-shaped rod structure; the third embedded part includes a first pull rod and a second pull rod which are vertically fixedly connected to each other, and the length direction of the first pull rod is arranged parallel to the axial direction of the first embedded part; the second embedded part is provided with a second through hole, and the first pull rod is plugged into the second through hole.
[0007] As a further optimization solution of the present invention, the length direction of the second tie rod is perpendicular to the axial direction of the first embedded part, and the second tie rod points in a direction away from the first embedded part.
[0008] As a further optimization solution of the present invention, the second embedded part is provided with a load-bearing protrusion, and the load-bearing protrusion abuts against the side wall of the second tension rod.
[0009] As a further optimization solution of the present invention, the first connecting rod is located on the side of the abutting plate.
[0010] As a further optimization solution of the present invention, the second embedded part is circular; the load-bearing protrusion is located at the edge of the second embedded part; the load-bearing protrusion is located on the side of the second embedded part away from the abutment plate.
[0011] As a further optimization solution of the present invention, three second through holes are provided; the three second through holes are distributed in an equiangular circular array.
[0012] As a further optimization solution of the present utility model, three third embedded parts are provided, and the three third embedded parts are respectively arranged in three second through holes.
[0013] As a further optimization solution of the present invention, the second embedded part is provided with a reinforcement hole.
[0014] As a further optimization solution of the present invention, the installation groove is trapezoidal or V-shaped.
[0015] In summary, the benefits of the utility model lie in: an assembled shear wall sleeve-free connection structure, comprising a shear wall body and a first embedded part, a mounting groove is provided in the middle of the side end face of the body; one end of the first embedded part is fixedly connected to the interior of the body, and the other end of the first embedded part is provided with a connecting ring, which is located in the mounting groove; the first embedded part comprises a sleeve and a spin-on part, the sleeve is a cylindrical structure, the outer surface of the sleeve is fixedly connected to the body, and the inner surface of the sleeve is connected to the spin-on part by a thread; it also includes a second embedded part, which is a plate-like structure; the second embedded part is provided with a first through hole, which is sleeved with the outer surface of the sleeve; the end of the sleeve away from the spin-on part is fixedly connected with an abutment plate, and the abutment plate and the spin-on part are respectively arranged on both sides of the second embedded part. The utility model utilizes adjacent connecting rings as fulcrums to achieve the connection of the shear walls, thus avoiding the use of traditional sleeves, and has a simple structure and convenient installation. At the same time, the utility model utilizes the second embedded parts and the third embedded parts to enhance the pulling force of the main body on the first embedded parts, thereby enhancing the structural stability and improving the engineering quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The present application is further described below with reference to the accompanying drawings:
[0017] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0018] Figure 2 is a schematic diagram of the structure of the second embedded part and the third embedded part;
[0019] Figure 3 It is a cross-sectional schematic diagram of the connection structure of adjacent shear walls;
[0020] Figure 4 It is a schematic diagram of the vertical section of the adjacent shear wall connection structure;
[0021] Figure 5 This is a cross-sectional structural diagram of the template installation position;
[0022] Figure 6 It is a schematic diagram of the structure of the second embedded part.
[0023] Description of reference numerals:
[0024] In the figure, 1, main body; 11, mounting groove; 2, first embedded part; 20, connecting ring; 21, sleeve; 211, abutment plate; 22, screw-on part; 3, second embedded part; 31, first through hole; 32, second through hole; 33, load-bearing protrusion; 34, reinforcement hole; 4, third embedded part; 41, first pull rod; 42, second pull rod; 5, connecting rod; 6, template. DETAILED DESCRIPTION
[0025] Based on the above structural features of the present application, the implementation methods of the present application are further described:
[0026] Reference Figure 1 This embodiment provides a prefabricated shear wall sleeve-free connection structure, including a shear wall body 1 and a first embedded part 2. A mounting groove 11 is provided in the middle of the side end surface of the body 1, and planes are provided at the ends of the body 1 on both sides of the mounting groove 11 to facilitate later alignment and pouring. One end of the first embedded part 2 is fixedly connected to the inside of the body 1, and the other end of the first embedded part 2 is provided with a connecting ring 20, which is located in the mounting groove 11. The body 1 is a hardened concrete or reinforced concrete structure.
[0027] Reference Figure 1 and 2 The first embedded part 2 includes a sleeve 21 and a screw-on part 22. The sleeve 21 is a straight cylindrical structure. The outer surface of the sleeve 21 is fixedly connected to the main body 1 (for example, by pre-embedded fixed connection), and the inner surface of the sleeve 21 is connected to the screw-on part 22 by threads. The inner surface of the sleeve 21 is provided with an internal thread, and the outer surface of the screw-on part 22 is provided with an external thread. The internal thread and the external thread are meshed with each other to achieve fine adjustment of the extension length of the screw-on part 22 to ensure convenient construction.
[0028] Reference Figure 2The utility model further includes a second embedded part 3, which is in a straight plate structure; the second embedded part 3 is provided with a first through hole 31, which is sleeved with the outer surface of the sleeve 21. The end of the sleeve 21 away from the rotating part 22 is fixedly connected with an abutment plate 211 (for example, connected by integral molding), and the abutment plate 211 and the rotating part 22 are respectively arranged on both sides of the second embedded part 3. The abutment plate 211 fits with the second embedded part 3, so that the second embedded part 3 can transmit resistance to the abutment plate 211, so that the second embedded part 3 can assist the first embedded part 2 in bearing force, thereby improving the structural stability of the utility model.
[0029] Reference Figure 2 The utility model also includes a third embedded part 4, which is an L-shaped rod structure; the third embedded part 4 includes a first pull-connecting rod 41 and a second pull-connecting rod 42 that are vertically fixed to each other (for example, connected by bending and integrally forming), and the length direction of the first pull-connecting rod 41 is arranged parallel to the axial direction of the first embedded part 2; the second embedded part 3 is provided with a second through hole 32, and the first pull-connecting rod 41 is plugged into the second through hole 32.
[0030] Reference Figure 2 The length direction of the second tie rod 42 is perpendicular to the axial direction of the first embedded part 2, and the second tie rod 42 points in a direction away from the first embedded part 2, so that the total side projection area of the first embedded part 2, the second embedded part 3 and the third embedded part 4 is increased, thereby improving the pulling force transmitted from the main body 1 to the first embedded part 2 through the second tie rod 42.
[0031] Reference Figure 2 The second embedded part 3 is provided with a load-bearing protrusion 33, and the load-bearing protrusion 33 abuts against the side wall of the second tie rod 42. Since the first tie rod 41 and the second tie rod 42 are formed by bending, there must be a rounded corner at the connection position of the first tie rod 41 and the second tie rod 42. Therefore, the side of the second tie rod 42 cannot be directly fitted with the second embedded part 3, causing the rounded corner to abut against the sharp corner position of the end of the second through hole 32 and form a situation of concentrated force. Therefore, the load-bearing protrusion 33 is provided to enable the load-bearing protrusion 33 to transmit force between the second embedded part 3 and the second tie rod 42, thereby improving the stability and service life of the utility model.
[0032] Reference Figure 2 The first connecting rod 41 is located on the side of the abutting plate 211 , and a protrusion is provided on the surface of the first connecting rod 41 to increase the friction between the main body 1 and the first connecting rod 41 , thereby improving the force transmission effect from the main body 1 to the third embedded part 4 .
[0033] Reference Figure 3 and 4 The adjacent edges of two adjacent shear walls are close to each other so that the adjacent connecting rings 20 are located on the same axis, and then the connecting rod 5 is used to penetrate the two connecting rings 20 to achieve connection.
[0034] Reference Figure 6 The second embedded part 3 is circular; the bearing protrusion 33 is located at the edge of the second embedded part 3; the bearing protrusion 33 is located on the side of the second embedded part 3 away from the abutment plate 211. There are three second through holes 32; the three second through holes 32 are arranged in an equiangular circular array. There are three third embedded parts 4, and the three third embedded parts 4 are arranged in the three second through holes 32 to improve the uniformity and stability of force transmission.
[0035] The second embedded part 3 is provided with a reinforcement hole 34, through which the main bodies 1 on both sides of the second embedded part 3 can be connected to increase the connection strength of the main bodies 1 on both sides of the second embedded part 3. A plurality of reinforcement holes 34 are provided and arranged in an equiangular circular array inside the load-bearing protrusion 33 to improve uniformity.
[0036] The mounting groove 11 is trapezoidal or V-shaped to fit the installation of the screw-on component 22 .
[0037] Installation steps: ① Place several shear walls upright so that the ends of adjacent shear walls are close to each other and the connecting rings 20 of adjacent shear walls are in a coaxial state; ② Intersperse the connecting rod 5 and the connecting ring 20; ③ Install the formwork 6 on both sides of the end of the shear wall; ④ Pour concrete in the installation groove 11, and remove the formwork 6 after the concrete is cured.
[0038] The utility model utilizes adjacent connecting rings 20 as fulcrums to achieve the connection of the shear wall, avoiding the use of traditional sleeves, having a simple structure, convenient installation, and improved construction efficiency; at the same time, the utility model utilizes the second embedded part 3 and the third embedded part 4 to enhance the pulling force of the main body 1 on the first embedded part 2, thereby enhancing the structural stability and improving the engineering quality.
[0039] In the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "up", "down", "left" and "right" are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.
[0040] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection, a mechanical connection, an electrical connection, a direct connection, or a connection through an intermediate medium, or the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0041] To sum up, for those skilled in the art, according to the guidance of the present invention, without departing from the principle and spirit of the present invention, the changes, modifications, replacements and deformations made to the present invention still fall within the protection scope of the present invention.
Claims
1. An assembled shear wall sleeve-free connection structure, characterized in that: The shear wall comprises a shear wall body (1) and a first embedded part (2), wherein a mounting groove (11) is provided in the middle of a side end surface of the body (1); one end of the first embedded part (2) is fixedly connected to the inside of the body (1), and the other end of the first embedded part (2) is provided with a connecting ring (20), and the connecting ring (20) is located in the mounting groove (11); The first embedded part (2) comprises a sleeve part (21) and a screw-on part (22); the sleeve part (21) is a cylindrical structure; the outer surface of the sleeve part (21) is fixedly connected to the main body (1); and the inner surface of the sleeve part (21) is connected to the screw-on part (22) via a thread; It also comprises a second embedded part (3), the second embedded part (3) is a plate-shaped structure; the second embedded part (3) is provided with a first through hole (31), and the first through hole (31) is sleeved with the outer surface of the sleeve part (21); An end of the sleeve member (21) away from the rotating member (22) is fixedly connected to an abutment plate (211), and the abutment plate (211) and the rotating member (22) are arranged on both sides of the second embedded member (3).
2. The assembled shear wall sleeve-free connection structure according to claim 1 is characterized in that: The invention also comprises a third embedded part (4), the third embedded part (4) being an L-shaped rod-shaped structure; the third embedded part (4) comprises a first connecting rod (41) and a second connecting rod (42) which are vertically fixedly connected to each other, the length direction of the first connecting rod (41) being arranged parallel to the axial direction of the first embedded part (2); the second embedded part (3) is provided with a second through hole (32), the first connecting rod (41) being plugged into the second through hole (32).
3. The assembled shear wall sleeve-free connection structure according to claim 2 is characterized in that: The length direction of the second tie rod (42) is arranged perpendicular to the axial direction of the first embedded part (2), and the second tie rod (42) points in a direction away from the first embedded part (2).
4. The assembled shear wall sleeve-free connection structure according to claim 3 is characterized in that: The second embedded part (3) is provided with a load-bearing protrusion (33), and the load-bearing protrusion (33) abuts against a side wall of the second tension rod (42).
5. The assembled shear wall sleeve-free connection structure according to claim 4 is characterized in that: The first connecting rod (41) is located on a side surface of the abutment plate (211).
6. The assembled shear wall sleeve-free connection structure according to claim 4 is characterized in that: The second embedded part (3) is circular; the load-bearing protrusion (33) is located at the edge of the second embedded part (3); the load-bearing protrusion (33) is located on the side of the second embedded part (3) away from the abutment plate (211).
7. The assembled shear wall sleeve-free connection structure according to claim 6 is characterized in that: Three second through holes (32) are provided; the three second through holes (32) are distributed in an equiangular circular array.
8. The assembled shear wall sleeve-free connection structure according to claim 7 is characterized in that: Three third embedded parts (4) are provided, and the three third embedded parts (4) are respectively arranged in three second through holes (32).
9. The assembled shear wall sleeve-free connection structure according to claim 8, characterized in that: The second embedded part (3) is provided with a reinforcement hole (34).
10. The assembled shear wall sleeve-free connection structure according to any one of claims 1 to 9, characterized in that: The mounting groove (11) is trapezoidal or V-shaped.