Leakage-proof non-breakdown liquid alarm gas drainer
By designing buffer pipe fittings and liquid alarm components in the gas drainer, the problem of gas drainer being easily broken down when the pressure rises instantly is solved, the effect of anti-leakage and safety alarm is achieved, and safety performance is improved.
Patent Information
- Application Number
- CN202421149486.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-24
- Publication Date
- 2025-02-18
- Estimated Expiration
- 2034-05-24
AI Technical Summary
Existing gas drains are easily broken down when the gas pressure rises instantly, resulting in large-scale gas leakage and serious accidents.
A leak-proof and breakdown-free liquid alarm gas drainage is designed, using buffer pipe fittings and liquid alarm components. The buffer pipe fittings are equipped with buffer parts, including a pair of upper and lower orifices and guide rods, which are buffered by compression and recovery of springs. Pressure changes, the liquid alarm assembly is used for monitoring and alarm.
It effectively avoids the instant increase in the pressure in the high-pressure chamber, prevents the gas drain from being penetrated, avoids large-scale gas leakage, and improves safety performance.
Smart Images

Figure CN222503496U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of gas drainers, in particular to a leakage-proof gas drainer without breakdown liquid alarm. Background Art
[0002] Large-diameter and long-distance pipelines are required to transport gas from its generation to its use point. Since blast furnace, coke oven and converter gas will produce a large amount of condensed water due to temperature changes during transportation, if it is not discharged in time, it will cause combustion interruptions, affect combustion effects or cause accidents. Therefore, a gas condensate drainer must be used.
[0003] However, existing gas drainers generally do not have pressure buffer components. In actual production conditions, the gas pressure may rise a lot instantly and then recover quickly. In this case, the gas drainer is easily punctured, causing a large amount of gas leakage and causing serious accidents. Utility Model Content
[0004] In view of the above problems, the purpose of the utility model is to provide a leakage-proof gas drainer without breakdown liquid alarm, aiming to solve the problem of poor safety performance of existing gas drainers.
[0005] The utility model adopts the following technical scheme: a leak-proof and non-breakdown liquid alarm gas drainer comprises a tank body, wherein a plurality of cavities are arranged in the tank body, wherein one cavity is a high-pressure cavity, and the other cavities are low-pressure cavities, a water collecting pipe is arranged in the high-pressure cavity, an inner drainage pipe is arranged in each low-pressure cavity, the inner drainage pipe is connected with the previous cavity, and a drainage pipe is connected with the bottom of the last low-pressure cavity, and the tank body is also connected with an air inlet pipe, characterized in that a buffer pipe fitting is connected between the air inlet pipe and the water collecting pipe by a flange, a buffer member is arranged in the buffer pipe fitting, a liquid alarm assembly is arranged in the lower part of the high-pressure cavity, the buffer member comprises an upper and lower pair of orifice plates, a plurality of slots are opened on the orifice plates, wherein the lower orifice plate is fixedly installed, a guide rod is inserted from the top of the upper orifice plate, the bottom of the guide rod is fixed to the lower orifice plate, a spring is arranged between the two orifice plates on the guide rod, and a guide sleeve is arranged on the top of the guide rod.
[0006] Furthermore, the liquid alarm assembly includes a base installed on the side wall of the tank body, the outer wall of the base is provided with a wiring port, a circular groove is opened at the central axis position of the base, a ferrule is formed in the circular groove, a sensor is inserted and sealed in the ferrule, and the sensor is electrically connected to the wiring port.
[0007] Furthermore, a shallow groove is opened in the top of the ferrule, a clamping ring is inserted into the shallow groove, and the clamping ring presses the sensor.
[0008] Furthermore, a liquid level gauge is provided on the upper portion of the side wall of the high-pressure chamber.
[0009] Furthermore, a switch valve is provided on the air intake pipe.
[0010] The beneficial effect of the utility model is that when the production conditions change and the gas pressure increases instantly, the buffer can be used to perform corresponding buffering at this time to avoid the pressure in the high-pressure chamber from increasing instantly, causing the gas drainer to be punctured, resulting in a large amount of gas leakage, and causing serious accidents. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 The utility model provides a front view of a gas drainer with leakage prevention and no breakdown liquid alarm.
[0012] Figure 2 The utility model provides a partial cross-sectional view of a buffer pipe.
[0013] Figure 3 The utility model provides a schematic diagram of the structure of a liquid alarm assembly.
[0014] Figure 4 The utility model provides a schematic diagram of wiring port installation. DETAILED DESCRIPTION
[0015] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.
[0016] In order to illustrate the technical solution of the present invention, specific embodiments are provided below for illustration.
[0017] For the convenience of explanation, only the parts related to the embodiment of the present utility model are shown.
[0018] Combination Figure 1-4 As shown, the leak-proof and non-breakdown liquid alarm gas drainer comprises a tank body 1, wherein a plurality of cavities are arranged in the tank body, wherein one cavity is a high-pressure cavity, and the other cavities are low-pressure cavities, wherein a water collecting pipe 4 is arranged in the high-pressure cavity, and an inner drainage pipe 5 is arranged in each low-pressure cavity, wherein the inner drainage pipe 5 is connected to the previous cavity, and a drainage pipe 6 is connected to the bottom of the last low-pressure cavity, wherein the tank body 1 is also connected to an air inlet pipe 7, and is characterized in that: a buffer pipe 2 is connected between the air inlet pipe 7 and the water collecting pipe 4 through a flange, and the A buffer member 8 is provided in the buffer tube 2, and a liquid alarm assembly 9 is provided in the lower part of the high-pressure chamber. The buffer member 8 includes a pair of upper and lower orifice plates, wherein the upper orifice plate is marked as 81 and the lower orifice plate is marked as 811. A plurality of slot holes 82 are provided on the orifice plates, wherein the lower orifice plate 811 is fixedly installed, and a guide rod 83 is inserted from the top of the upper orifice plate 81, and the bottom of the guide rod 83 is fixed to the lower orifice plate. A spring 84 is provided on the guide rod 83 between the two orifice plates, and a guide sleeve 85 is provided on the top of the guide rod 83.
[0019] As we all know, large-diameter and long-distance pipelines are required to transport gas from its generation to its use point. Since blast furnace, coke oven and converter gas will produce a large amount of condensed water due to temperature changes during transportation, the condensed water can be discharged through this gas drainer, thereby ensuring its combustion effect and avoiding accidents.
[0020] In the embodiment, the air inlet pipe is connected to a gas main (not shown in the figure), and a switch valve 10 is provided on the air inlet pipe 7. An explosion-proof device 12 is installed on the drain pipe 6, and the drain pipe and the explosion-proof device constitute an overflow device.
[0021] When working, the switch valve is opened, and sealing water is filled in each cavity of the tank body. The gas enters the water collecting pipe from the switch valve and reaches the high-pressure cavity in the cylinder body. Under normal circumstances, the sealing water in each cavity is full. Since the density of gas is smaller than that of water, water and gas separation is achieved, thereby achieving the effect of gas blocking and drainage. The separated condensed water reaches each low-pressure chamber through the drainage pipe in turn, and finally flows into the drainage pipe and is discharged through the explosion-proof device.
[0022] When production conditions change and the gas pressure rises a lot instantly, the buffer can be used to provide corresponding buffering to avoid the pressure in the high-pressure chamber increasing instantly, causing the gas drainer to be punctured, resulting in a large amount of gas leakage and causing serious accidents.
[0023] Specifically, when the gas pressure increases instantly, the gas can only enter the water collecting pipe through the slots on the orifice plate. At this time, the gas with increased pressure will squeeze the upper orifice plate, and the upper orifice plate moves toward the lower orifice plate along the guide rod. The spring is gradually compressed, playing a buffering role until the gas pressure returns to a stable state. When the spring recovers its deformation, the upper orifice plate is reset under the action of the spring. The guide sleeve plays the role of limiting the upper orifice plate.
[0024] The buffer pipe is connected between the air inlet pipe 7 and the water collecting pipe 4 through a flange, which is convenient for later disassembly and replacement of the entire buffer pipe.
[0025] As a preferred structure, Figure 1 , Figure 3 , Figure 4 The liquid alarm assembly 9 includes a base 91 mounted on the side wall of the tank body, the outer wall of the base 91 is provided with a wiring port 92, a circular groove 93 is opened at the central axis of the base 91, a ferrule 94 is formed in the circular groove, a sensor 95 is inserted and sealed in the ferrule 94, and the sensor 95 is electrically connected to the wiring port 92. The alarm is connected to the wiring port through wires.
[0026] When the water level in the high pressure chamber is abnormal, such as when the water level is low, the sensor senses and transmits the signal to the alarm, which then sends an alarm to alert people, thereby further improving the safety performance of the gas drainer.
[0027] In this structure, the sensor is inserted into and sealed to the ferrule for installation. The ferrule serves to install and protect the sensor.
[0028] At the same time, a shallow groove is opened in the top of the clamping sleeve 94, and a clamping ring 13 is inserted into the shallow groove, and the clamping ring 13 presses the sensor 95. When the sensor is installed in the clamping sleeve, the clamping ring is inserted into the shallow groove as required, and the clamping ring presses the sensor. Under the action of the clamping ring, the sensor is installed more stably.
[0029] The upper part of the high pressure chamber side wall is also provided with a liquid level gauge 14. By providing the liquid level gauge in the high pressure chamber, the liquid level in the high pressure chamber is monitored in real time by the liquid level gauge, so that relevant staff can understand the specific liquid level in the high pressure chamber at any time through the liquid level gauge.
[0030] In addition, if Figure 1 The top of the high-pressure chamber of the drainer is also connected to a water replenishment device, which includes a check valve 15 and a water inlet valve 16. The top of each chamber is also connected to an exhaust valve 17. When water replenishment is needed, the water inlet valve is opened to replenish water, and the exhaust valve is opened to exhaust air. After the water replenishment is completed, the water inlet valve and the exhaust valve are closed.
[0031] The above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the utility model should be included in the protection scope of the present utility model.
Claims
1. A leak-proof gas drainer without liquid breakdown alarm, comprising a tank body, wherein a plurality of chambers are arranged in the tank body, wherein one chamber is a high-pressure chamber, and the other chambers are low-pressure chambers, wherein a water collecting pipe is arranged in the high-pressure chamber, and an inner drainage pipe is arranged in each low-pressure chamber, wherein the inner drainage pipe is connected to the previous chamber, and the bottom of the last low-pressure chamber is connected to a drainage pipe, and the tank body is also connected to an air inlet pipe, characterized in that: A buffer pipe fitting is connected between the air inlet pipe and the water collecting pipe through a flange, and a buffer part is arranged inside the buffer pipe fitting. A liquid alarm assembly is arranged at the lower part of the high-pressure chamber, and the buffer part comprises an upper and lower pair of orifice plates, each of which has a plurality of slot holes, wherein the lower orifice plate is fixedly installed, and a guide rod is inserted through the top of the upper orifice plate, and the bottom of the guide rod is fixed to the lower orifice plate, and a spring is arranged on the guide rod between the two orifice plates, and a guide sleeve is arranged on the top of the guide rod.
2. A leak-proof gas drainer without liquid breakdown alarm as claimed in claim 1, characterized in that: The liquid alarm assembly includes a base installed on the side wall of the tank body, the outer wall of the base is provided with a wiring port, a circular groove is opened at the central axis position of the base, a ferrule is formed in the circular groove, a sensor is inserted and sealed in the ferrule, and the sensor is electrically connected to the wiring port.
3. A leak-proof gas drainer without liquid breakdown alarm as claimed in claim 2, characterized in that: A shallow groove is provided in the top opening of the ferrule, a clamping ring is inserted into the shallow groove, and the clamping ring presses the sensor.
4. A leak-proof gas drainer without liquid breakdown alarm as claimed in claim 3, characterized in that: A liquid level gauge is also provided on the upper part of the side wall of the high pressure chamber.
5. A leak-proof gas drainer without liquid breakdown alarm as claimed in claim 4, characterized in that: The air inlet pipe is provided with a switch valve.