Device for shortening working hours for replacing overhead ground wire clamp on power transmission line concrete pole

By designing a wing-shaped frame device that can adjust the distance between the overhead ground wire clamp and the top of the concrete rod, the problem of long time to replace the overhead ground wire clamp is solved and maintenance efficiency is improved.

CN222508568UActive Publication Date: 2025-02-18ZHONGWEI POWER SUPPLY COMPANY OF STATE GRID NINGXIA ELECTRIC POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420026095.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-04
Publication Date
2025-02-18
Estimated Expiration
2034-01-04

AI Technical Summary

Technical Problem

When replacing the overhead ground wire clamp, the replacement time is longer, which affects maintenance efficiency due to the small distance between the ground wire clamp from the top of the rod and the lack of suitable lifting tools.

Method used

An airfoil frame device is designed, including a telescopic mechanism and a bolt assembly, which can adjust the distance between the overhead ground wire clamp and the top of the concrete rod rod, adapt to concrete rods of different diameters, and connect the transmission line through the bolt assembly to fix the frame. body.

Benefits of technology

By adjusting the distance between the overhead ground wire clamp and the top of the concrete rod, the replacement time is shortened, the maintenance efficiency is improved, and the problem of long replacement time is solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222508568U_ABST
    Figure CN222508568U_ABST
Patent Text Reader

Abstract

The utility model provides a device for shortening working hours for replacing an overhead ground wire clamp on a power transmission line concrete pole. The device comprises a wing-shaped frame body; the wing-shaped frame body comprises a cross beam, a first telescopic mechanism, a second telescopic mechanism, a first bolt assembly and a second bolt assembly; a cross beam of the wing-shaped frame body is provided with a groove used for containing an overhead ground wire clamp, and the tops of the two side walls of the groove are provided with a first clamping end and a second clamping end which are used for clamping the overhead ground wire clamp. The first telescopic mechanism and the second telescopic mechanism are matched to adjust the width of the wing-shaped frame body so as to adapt to concrete rods with different diameters; the first bolt assembly and the second bolt assembly are symmetrically arranged on the two sides of the wing-shaped frame body. And the groove is matched with the first bolt assembly and the second bolt assembly to adjust the distance between the overhead ground wire clamp and the top of the concrete pole. According to the device, the distance between the ground wire clamp and the top of the concrete pole can be adjusted, the time for replacing the ground wire clamp is shortened, and the maintenance efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of replacing a ground wire clamp, in particular to a device for shortening the working time of replacing an overhead ground wire clamp on a concrete pole of a power transmission line. Background Art

[0002] Overhead ground wire is a device used to protect overhead power transmission lines from lightning strikes, also known as lightning arrester, or ground wire for short. Since overhead ground wire does not carry the function of transmitting current, it is not required to have the same conductivity and conductor cross-section as the conductor, and is usually made of steel stranded wire. The function of overhead ground wire clamp is to fix the overhead ground wire on the tower.

[0003] At present, when the staff of the Transmission Operation and Maintenance Center are replacing the overhead ground wire clamps, the average time to replace a single overhead ground wire clamp is long because the ground wire clamp is at a small distance from the top of the pole and there is no suitable load-bearing point for the lifting tool, which affects the efficiency of maintenance and fault elimination work.

[0004] Therefore, it is urgently necessary to provide a lifting tool capable of adjusting the distance between the ground wire clamp and the pole top, so as to shorten the time for replacing the overhead ground wire clamp on the concrete pole of the transmission line. Utility Model Content

[0005] The embodiment of the utility model provides a device for shortening the working time of replacing the overhead ground wire clamp of the concrete pole of the transmission line. The device can adjust the distance between the overhead ground wire clamp and the top of the concrete pole, shortening the time of replacing the overhead ground wire clamp of the concrete pole of the transmission line and improving the maintenance efficiency.

[0006] An embodiment of the utility model provides a device for shortening the working time of replacing an overhead ground wire clamp on a concrete pole of a power transmission line, comprising: a wing-shaped frame; the wing-shaped frame comprises: a crossbeam, a first retractable mechanism and a second retractable mechanism symmetrically arranged on both sides of the crossbeam, and a first bolt assembly connected to the first retractable mechanism and a second bolt assembly connected to the second retractable mechanism; a groove for accommodating the overhead ground wire clamp is arranged on the crossbeam of the wing-shaped frame, and a first clamping end and a second clamping end for clamping the overhead ground wire clamp are arranged on the top of the two side walls of the groove; the first retractable mechanism and the second retractable mechanism cooperate to adjust the width of the wing-shaped frame to adapt to concrete poles of different diameters; the first bolt assembly and the second bolt assembly are symmetrically arranged on both sides of the wing-shaped frame, and the first bolt assembly and the second bolt assembly are used to connect the power transmission line; the groove cooperates with the first bolt assembly and the second bolt assembly to adjust the distance between the overhead ground wire clamp and the top of the concrete pole.

[0007] Optionally, the first bolt assembly includes: a first nut, a first threaded column matched with the first nut, a first buckle, and a first wrench located on the first threaded column;

[0008] The second bolt assembly includes: a second nut, a second threaded column matched with the second nut, a second buckle, and a second wrench located on the second threaded column.

[0009] Optionally, the first nut and the second nut are connected to the crossbeam;

[0010] The first buckle is located at the bottom of the first threaded column, and the second buckle is located at the bottom of the second threaded column. The first buckle and the second buckle are used to fix the wing-shaped frame on the power transmission line.

[0011] Optionally, the first wrench includes a first handle and a first spiral hole, and the first spiral hole is sleeved on the first spiral column;

[0012] The first spiral hole is provided with a thread matching the first threaded column on the inner side, and the height of the first bolt assembly is controlled by rotating the first handle to adapt to the installation position of the overhead ground wire clamp;

[0013] The second wrench comprises a second handle and a second spiral hole, and the second spiral hole is sleeved on the second spiral column;

[0014] The inner side of the second spiral hole is provided with a thread matching the second threaded column, and the height of the second bolt assembly is controlled by rotating the second handle to adapt to the installation position of the overhead ground wire clamp.

[0015] Optionally, a plurality of fixing holes are symmetrically provided on the first telescopic mechanism and the second telescopic mechanism, and the fixing holes are used to fix the wing-shaped frame to the concrete rod through nuts.

[0016] Optionally, the thickness of the first clamping end and the second clamping end is greater than the thickness of the two side walls of the groove.

[0017] Compared with the prior art, this application has the following advantages:

[0018] The present application provides a device for shortening the working time of replacing an overhead ground wire clamp on a concrete pole of a power transmission line, comprising: a wing-shaped frame; the wing-shaped frame comprises: a crossbeam, a first retractable mechanism and a second retractable mechanism symmetrically arranged on both sides of the crossbeam, and a first bolt assembly connected to the first retractable mechanism and a second bolt assembly connected to the second retractable mechanism; a groove for accommodating the overhead ground wire clamp is arranged on the crossbeam of the wing-shaped frame, and a first clamping end and a second clamping end for clamping the overhead ground wire clamp are arranged on the top of the two side walls of the groove; the first retractable mechanism and the second retractable mechanism cooperate to adjust the width of the wing-shaped frame to adapt to concrete poles of different diameters; the first bolt assembly and the second bolt assembly are symmetrically arranged on both sides of the wing-shaped frame, and the first bolt assembly and the second bolt assembly are used to connect the power transmission line; the groove cooperates with the first bolt assembly and the second bolt assembly to adjust the distance between the overhead ground wire clamp and the top of the concrete pole.

[0019] The device for shortening the time required for replacing the overhead ground wire clamp on the concrete pole of the power transmission line described in the present application can adjust the width of the wing-shaped frame body to adapt to concrete poles of different diameters through the cooperation of the first retractable mechanism and the second retractable mechanism. At the same time, the device can also cooperate with the first bolt assembly and the second bolt assembly through the groove to adjust the distance between the overhead ground wire clamp and the top of the concrete pole. Therefore, the device for shortening the time required for replacing the overhead ground wire clamp on the concrete pole of the power transmission line can adjust the distance between the overhead ground wire clamp and the top of the concrete pole, shortening the time required for replacing the overhead ground wire clamp on the concrete pole of the power transmission line, and improving the maintenance efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the description of the embodiments of the utility model will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0021] Figure 1 It is a front structural schematic diagram of a device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines according to a preferred embodiment of the utility model;

[0022] Figure 2 It is a schematic diagram of the back structure of a device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines according to a preferred embodiment of the utility model;

[0023] Figure 3a It is a schematic diagram of the first state structure of the first retractable mechanism and the second retractable mechanism in a device for shortening the working time of replacing overhead ground wire clamps on concrete poles of a power transmission line in a preferred embodiment of the utility model;

[0024] Figure 3b It is a schematic diagram of the second state structure of the first retractable mechanism and the second retractable mechanism in a device for shortening the working time of replacing overhead ground wire clamps on concrete poles of a power transmission line in a preferred embodiment of the utility model;

[0025] Figure 3c It is a schematic diagram of the third state structure of the first retractable mechanism and the second retractable mechanism in a device for shortening the working time of replacing overhead ground wire clamps on concrete poles of a power transmission line in a preferred embodiment of the utility model;

[0026] Figure 4 The utility model is a partially enlarged bottom view of a groove in a device for shortening the working time of replacing an overhead ground wire clamp on a concrete pole of a power transmission line in a preferred embodiment of the utility model.

[0027] In the figure: 10-wing-shaped frame, 101-groove, 102-first clamping end, 103-second clamping end, 104-first bolt assembly, 104-1-first nut, 104-2-first threaded column, 104-3-first buckle, 104-4-first wrench, 104-4-1-first handle, 104-4-2-first spiral hole, 105-second bolt assembly, 105-1-second nut, 105-2-second threaded column, 105-3-second buckle, 105-4-second wrench, 105-4-1-second handle, 105-4-2-second spiral hole, 106-fixing hole, 107-first telescopic mechanism, 108-second telescopic mechanism DETAILED DESCRIPTION

[0028] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0029] The utility model embodiment provides a device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines, comprising: a wing-shaped frame 10; see Figure 1 and Figure 2 , Figure 1 This is a front structural schematic diagram of a device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines according to a preferred embodiment of the utility model. Figure 2The back structure diagram of the device for shortening the working time of replacing the overhead ground wire clamp of the concrete pole of the power transmission line according to a preferred embodiment of the utility model. The wing-shaped frame 10 comprises: a crossbeam (not shown in the figure), a first retractable mechanism 107 and a second retractable mechanism 108 symmetrically arranged on both sides of the crossbeam, and a first bolt assembly 104 connected to the first retractable mechanism 107 and a second bolt assembly 105 connected to the second retractable mechanism 108; a groove 101 for accommodating the overhead ground wire clamp is arranged on the crossbeam of the wing-shaped frame 10, see Figure 4 , Figure 4 It is a partial enlarged bottom view of a groove in a device for shortening the working time of replacing an overhead ground wire clamp on a concrete pole of a transmission line according to a preferred embodiment of the utility model. The top of the two side walls of the groove 101 are provided with a first clamping end 102 and a second clamping end 103 for clamping the overhead ground wire clamp. It should be noted that the thickness of the first clamping end 102 and the second clamping end 103 is greater than the thickness of the two side walls of the groove 10, in order to improve the lateral stress bearing capacity of the wing-shaped frame 10 and avoid being bent and unable to clamp the overhead ground wire clamp.

[0030] In the present application, the first telescopic mechanism 107 and the second telescopic mechanism 108 cooperate to adjust the width of the wing-shaped frame 10 to adapt to concrete poles of different diameters. When specifically adapting to different concrete poles, it can be achieved by the first telescopic mechanism 107 and the second telescopic mechanism 108. The first telescopic mechanism 107 and the second telescopic mechanism 108 are also symmetrically provided with a plurality of fixing holes 106, and the fixing holes 106 are used to fix the wing-shaped frame 10 on the concrete pole through nuts.

[0031] In specific implementation, according to the different diameters of the concrete rods, the first retractable mechanism 107 and the second retractable mechanism 108 can adjust the width of the wing-shaped frame 10 by adjusting the corresponding positions of the fixing holes 106. For details, see Figure 3a , Figure 3b , Figure 3c For example, for a concrete pole with a relatively large diameter, the states of the first telescopic mechanism 107 and the second telescopic mechanism 108 can be set to Figure 3a For a relatively small diameter concrete rod, the state of the first retractable mechanism 107 and the second retractable mechanism 108 can be set to Figure 3c Of course, according to the actual diameter of the concrete rod state, the state of the first retractable mechanism 107 and the second retractable mechanism 108 can also be set to Figure 3b It should be noted that the state change of the first telescopic mechanism 107 and the second telescopic mechanism 108 can be realized by a sliding telescopic member. For example, one of the two is used as a slider and the other is used as a slide groove.

[0032] It should be noted that when the wing-shaped frame 10 is fixed on the concrete pole, the steel bar can be wrapped around the concrete pole and then passed through the fixing hole 106 for fixing. After the fixing hole 106 is aligned, it is fixed by a nut. In addition, by providing the first telescopic mechanism 107 and the second telescopic mechanism 108, the wing-shaped frame 10 can be adapted to concrete poles of different sizes, thereby expanding the scope of use of the wing-shaped frame 10.

[0033] In the present application, the first bolt assembly 104 and the second bolt assembly 105 are symmetrically arranged on both sides of the wing-shaped frame 10, and the first bolt assembly 104 and the second bolt assembly 105 are used to connect the transmission line; the groove 101 cooperates with the first bolt assembly 104 and the second bolt assembly 105 to adjust the distance between the overhead ground wire clamp and the top of the concrete pole. It should be noted that the reason why the present application sets up a lifting tool that can adjust the distance between the overhead ground wire clamp and the top of the concrete pole is mainly because when the staff of the power transmission operation and inspection center replace the overhead ground wire clamp, the ground wire clamp is at a small distance from the top of the pole, and there is no suitable lifting tool bearing point, resulting in a long average time for replacing a single overhead ground wire clamp, which affects the efficiency of maintenance and troubleshooting. Based on this, the wing-shaped frame 10 described in the present application can adjust the distance between the overhead ground wire clamp and the top of the concrete pole, shortening the time for replacing the overhead ground wire clamp on the concrete pole of the transmission line, and improving the maintenance efficiency.

[0034] Among them, the first bolt assembly 104 includes: a first nut 104-1, a first threaded column 104-2 matched with the first nut 104-1, a first buckle 104-3 and a first wrench 104-4 located on the first threaded column 104-2; the second bolt assembly 105 includes: a second nut 105-1, a second threaded column 105-2 matched with the second nut 105-1, a second buckle 105-3 and a second wrench 105-4 located on the second threaded column 105-2.

[0035] Specifically, the first nut 104-1 and the second nut 105-1 are connected to the crossbeam; the first clip 104-3 is located at the bottom of the first threaded column 104-2, and the second clip 105-3 is located at the bottom of the second threaded column 105-2. The first clip 104-3 and the second clip 105-3 are used to fix the wing-shaped frame 10 on the transmission line, wherein the first clip 104-3 and the second clip 105-3 each include a U-shaped part and a fixing bolt. When the first clip 104-3 and the second clip 105-3 are used to fix the wing-shaped frame 10 on the transmission line, the fixing bolt is first removed, the transmission line is placed in the U-shaped part, and then the fixing bolt is used to fix the transmission line in the U-shaped part.

[0036] In the present application, the first wrench 104-4 includes a first handle 104-4-1 and a first spiral hole 104-4-2, and the first spiral hole 104-4-2 is sleeved on the first spiral column 104-2; the inner side of the first spiral hole 104-4-2 is provided with a thread matching the first threaded column 104-2, and by rotating the first handle 104-4-1, the height of the first bolt assembly 104 is controlled to adapt to the installation position of the overhead ground wire clamp; the second wrench 105-4 includes a second handle 105-4-1 and a second spiral hole 105-4-2, and the second spiral hole 105-4-2 is sleeved on the second spiral column 105-2; the inner side of the second spiral hole 105-4-2 is provided with a thread matching the second threaded column 105-2, and by rotating the second handle 105-4-1, the height of the second bolt assembly 105 is controlled to adapt to the installation position of the overhead ground wire clamp.

[0037] The above is only a specific implementation of the utility model, but the protection scope of the utility model is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the utility model, which should be included in the protection scope of the utility model. Therefore, the protection scope of the utility model should be based on the protection scope of the claims.

Claims

1. A device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines, characterized in that: include: Wing-shaped frame; The wing-shaped frame comprises: a crossbeam, a first retractable mechanism and a second retractable mechanism symmetrically arranged on both sides of the crossbeam, and a first bolt assembly connected to the first retractable mechanism and a second bolt assembly connected to the second retractable mechanism; A groove for accommodating the overhead ground wire clamp is provided on the cross beam of the wing-shaped frame, and a first clamping end and a second clamping end for clamping the overhead ground wire clamp are provided on the top of the two side walls of the groove; The first telescopic mechanism and the second telescopic mechanism cooperate to adjust the width of the wing-shaped frame to adapt to concrete poles of different diameters; The first bolt assembly and the second bolt assembly are symmetrically arranged on both sides of the airfoil frame, and the first bolt assembly and the second bolt assembly are used to connect the transmission line; The groove cooperates with the first bolt assembly and the second bolt assembly to adjust the distance between the overhead ground wire clamp and the top of the concrete pole.

2. The device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines according to claim 1 is characterized in that: The first bolt assembly includes: a first nut, a first threaded column matched with the first nut, a first buckle, and a first wrench located on the first threaded column; The second bolt assembly includes: a second nut, a second threaded column matched with the second nut, a second buckle, and a second wrench located on the second threaded column.

3. The device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines according to claim 2 is characterized in that: The first nut and the second nut are connected to the crossbeam; The first buckle is located at the bottom of the first threaded column, and the second buckle is located at the bottom of the second threaded column. The first buckle and the second buckle are used to fix the wing-shaped frame on the power transmission line.

4. The device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines according to claim 2 is characterized in that: The first wrench comprises a first handle and a first spiral hole, wherein the first spiral hole is sleeved on a first spiral column; The first spiral hole is provided with a thread matching the first threaded column on the inner side, and the height of the first bolt assembly is controlled by rotating the first handle to adapt to the installation position of the overhead ground wire clamp; The second wrench comprises a second handle and a second spiral hole, and the second spiral hole is sleeved on the second spiral column; The inner side of the second spiral hole is provided with a thread matching the second threaded column, and the height of the second bolt assembly is controlled by rotating the second handle to adapt to the installation position of the overhead ground wire clamp.

5. The device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines according to claim 1 is characterized in that: The first telescopic mechanism and the second telescopic mechanism are also symmetrically provided with a plurality of fixing holes, and the fixing holes are used to fix the wing-shaped frame body on the concrete rod through nuts.

6. The device for shortening the working time of replacing overhead ground wire clamps on concrete poles of power transmission lines according to claim 1 is characterized in that: The thickness of the first clamping end and the second clamping end is greater than the thickness of the two side walls of the groove.