Quenching tower of gas furnace
By installing flushing water and cooling water packs in the gas furnace quench tower, and using the nozzle to rinse and cool down, the problem of coal powder tar agglomeration and blockage in the quench tower is solved, and effective coal ash cleaning and temperature control are achieved. Reduces cost and security risks.
Patent Information
- Application Number
- CN202421172183.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-27
- Publication Date
- 2025-02-25
- Estimated Expiration
- 2034-05-27
AI Technical Summary
The gas furnace quench tower is blocked due to the agglomeration of coal powder and tar in the coke oven, which affects the process parameter control and gas supply. The existing solutions are costly and not thorough enough.
Design a gas furnace quench tower. By installing flushing water packs and cooling water packs on the gas inlet and outlet pipelines, and equipped with a spray head, the spray head sprays water into the quench tower for flushing and cooling, to solve the ash and tar agglomeration question.
It realizes effective flushing of coal ash on the inner wall and nozzle of the quench tower, reduces the temperature in the quench tower of the gas furnace, avoids blockage, is convenient to operate, is low in cost, and is energy-saving and environmentally friendly.
Smart Images

Figure CN222524446U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of gas furnace equipment, in particular to a gas furnace quenching tower. Background Art
[0002] In my country's coal coking industry, the coke oven gas from the coal gas suction pipeline generally contains impurities such as coke oven coal powder. After the coke oven gas enters the quenching tower, coal powder tar frequently agglomerates and blocks the vertical pipe, causing the gas pressure in the lower section of the gasifier to rise to 3600pa and the gas temperature in the upper section to rise by 170°C, resulting in the inability to effectively control the process parameters of the gasifier and reducing the supply of gas to the vertical furnace.
[0003] In the prior art, the gas furnace quenching tower can be divided into two chambers. The upper chamber is for combustion. When the ash, tar, etc. are lifted to the lower chamber, they are purged. That is, air or oxygen is blown into the lower chamber along the tangent direction of the chamber to make the ash and tar burn more fully. However, this treatment method is relatively expensive. The agitation of air can prevent the coke oven coal powder from compacting. Another method is to install a slag crusher, connect the pipeline and add a conveyor belt to the bottom of the gas furnace quenching tower, and first break or remove the compacted coal tar at the bottom. This method is not thorough enough, and the cost of funds and manpower invested is also high, which is not conducive to promotion. Utility Model Content
[0004] The utility model aims to provide a gas furnace quenching tower which has reasonable structural design, convenient operation, low processing cost, energy saving and environmental protection, can clean coal powder tar agglomerates online, save time and labor, and reduce safety risks.
[0005] The utility model discloses a coal gas furnace quenching tower, comprising a first quenching tower, a second quenching tower fixedly connected to the side wall of the first quenching tower, a coal gas inlet pipeline fixedly connected to the surface of the first quenching tower; a coal gas outlet pipeline fixedly connected to the surface of the second quenching tower, a first flushing water bag installed on the coal gas inlet pipeline, a first flushing water nozzle fixedly installed between the first flushing water bag and the first quenching tower; a second flushing water bag installed on the coal gas outlet pipeline, a second flushing water nozzle fixedly installed between the second flushing water bag and the second quenching tower.
[0006] A first cooling water bag is installed on the outer wall of the first quenching tower, and a first cooling water nozzle is fixedly connected between the first cooling water bag and the first quenching tower; a second cooling water bag is installed on the outer wall of the second quenching tower, and a second cooling water nozzle is fixedly connected between the second cooling water bag and the second quenching tower; the first cooling water bag and the second cooling water bag are connected by a connecting pipe.
[0007] The first flushing water bag and the second flushing water bag installed on the gas inlet pipeline and the gas outlet pipeline can spray water into the first quenching tower and the second quenching tower through the first flushing water nozzle and the second flushing water nozzle, respectively, so as to continuously flush the coal ash adhering to the inner wall of the first quenching tower and the second quenching tower and the first cooling water nozzle and the second cooling water nozzle. The flushing effect is good and the operation is convenient. The flushing can be achieved by simply opening the first flushing water nozzle and the second flushing water nozzle, which saves time and effort, and can also achieve the cooling of the first quenching tower and the second quenching tower. The cooling is to further reduce the temperature of the lower section of the gas furnace entering the quenching tower, so that the temperature of the pressurized fan casing entering the next link can operate more stably; it can solve the problem of coal powder tar agglomeration blocking the vertical pipe in the quenching tower, eliminate the fault at the first cooling water nozzle and the second cooling water nozzle, and at the same time, it can also reduce the temperature in the quenching tower of the gas furnace by 6-10°C;
[0008] The first cooling water bag and the second cooling water bag can spray water into the first quenching tower and the second quenching tower through the first flushing water nozzle and the second flushing water nozzle to cool the first quenching tower and the second quenching tower.
[0009] The inner walls of the pipes of the first flushing water nozzle and the second flushing water nozzle are fixedly connected with a cross rod, and the cross rod is located at the outlet ends of the first flushing water nozzle and the second flushing water nozzle.
[0010] A cross rod is fixedly connected to the inner wall of the pipe of the first flushing water nozzle and the second flushing water nozzle, which is more conducive to the dispersion of water after passing through the cross rod, and the interior of the first quenching tower and the second quenching tower can be fully flushed, making the flushing more thorough.
[0011] The first flushing water bag and the second flushing water bag are connected through a pipeline, and the second flushing water bag is connected to the second cooling water bag through a pipeline.
[0012] By connecting the first flushing water bag and the second flushing water bag through a pipeline, water can be injected into the first flushing water bag and the second flushing water bag at the same time, which is convenient for water injection and saves installation cost; by connecting the second flushing water bag and the second cooling water bag through a pipeline, the water inlet pipeline of the quenching tower of the two can be shared, and a separate water supply pump and pipeline are no longer required. When the water pressure is unbalanced, the valves of the outlet pipelines of the second flushing water bag and the second cooling water bag can be adjusted, which simplifies the installation steps and saves installation raw materials.
[0013] The bottom of the second cooling water bag is connected with a domestic water inlet pipeline.
[0014] The domestic water inlet pipe is provided to carry the water in the first cooling water bag and the second cooling water bag into the living area through the domestic water inlet pipe for people to use.
[0015] Inspection manholes are fixedly installed on the bottom surfaces of the first quenching tower and the second quenching tower.
[0016] The maintenance manhole is provided to timely inspect and handle the faults in the first quenching tower and the second quenching tower.
[0017] A hot circulating water outlet pipe is fixedly installed on the bottom surface of the first quenching tower and the second quenching tower.
[0018] The heat circulating water outlet pipe is arranged to allow the flushing water and cooling water in the first quenching tower and the second quenching tower to flow out through the heat circulating water outlet pipe and enter the heat circulating water pool.
[0019] Beneficial effects of the utility model:
[0020] 1) The first flushing water bag and the second flushing water bag installed on the gas inlet pipe and the gas outlet pipe can spray water into the first quenching tower and the second quenching tower respectively through the first flushing water nozzle and the second flushing water nozzle, so as to continuously flush the coal ash adhering to the inner wall of the first quenching tower and the second quenching tower and the first cooling water nozzle and the second cooling water nozzle. The flushing effect is good and the operation is convenient. The flushing can be achieved by simply opening the first flushing water nozzle and the second flushing water nozzle, which saves time and effort, and can also achieve the cooling of the first quenching tower and the second quenching tower. The cooling is to further reduce the temperature of the lower section of the gas furnace entering the quenching tower, so that the temperature of the pressurized fan casing entering the next link is more stable. It can solve the problem of coal powder tar agglomeration blocking the vertical pipe in the quenching tower, eliminate the fault at the first cooling water nozzle and the second cooling water nozzle, and at the same time, it can also reduce the temperature in the quenching tower of the gas furnace by 6-20℃.
[0021] 2) The first cooling water bag and the second cooling water bag are set up to spray water into the first quenching tower and the second quenching tower through the first flushing water nozzle and the second flushing water nozzle to cool the first quenching tower and the second quenching tower.
[0022] 3) The first flushing water bag and the second flushing water bag are connected by a pipeline, so that water can be injected into the first flushing water bag and the second flushing water bag at the same time, which is convenient for water injection and saves installation cost; the second flushing water bag is connected with the second cooling water bag through a pipeline, so that the water inlet pipeline of the quenching tower of the two can be shared, and there is no need to set up a separate water supply pump and pipeline. When the water pressure is unbalanced, the valves of the outlet pipelines of the second flushing water bag and the second cooling water bag can be adjusted, which simplifies the installation steps and saves installation raw materials.
[0023] 4) The domestic water inlet pipe is set up to allow the water in the first cooling water bag and the second cooling water bag to enter the living area through the domestic water inlet pipe for people to use, which is energy-saving and environmentally friendly.
[0024] 5) The device has a reasonable structural design, convenient operation, low processing cost, energy saving and environmental protection. It can clean the coal powder tar agglomerates online, saving time and effort, and reducing the safety risks caused by the blockage of coal powder tar agglomerates. At present, the device has been put into use with good results. It effectively solves the problem of blockage of the cooling water nozzles of the three quenching towers in the gas station, reduces the potential safety risks in the continuous production and operation of the gas furnace, and the cooling water nozzles of the quenching towers are no longer blocked, and the equipment runs stably. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the structure of the utility model;
[0026] Figure 2 It is a structural schematic diagram of the first flushing water nozzle in the utility model;
[0027] Figure 3 It is a structural schematic diagram of the second flushing water nozzle in the utility model.
[0028] In the figure: 1. first quenching tower; 2. first cooling water bag; 3. first cooling water nozzle; 4. first flushing water bag; 5. first flushing water nozzle; 6. gas inlet pipeline; 7. second quenching tower; 8. second cooling water bag; 9. second cooling water nozzle; 10. second flushing water bag; 11. second flushing water nozzle; 12. gas outlet pipeline; 13. inspection manhole; 14. domestic water inlet pipeline; 15. hot circulating water outlet pipeline; 16. connecting pipeline; 17. cross rod. DETAILED DESCRIPTION
[0029] Example 1.
[0030] The utility model comprises a first quenching tower 1; a first cooling water bag 2; a first cooling water nozzle 3; a first flushing water bag 4; a first flushing water nozzle 5; a gas inlet pipeline 6; a second quenching tower 7; a second cooling water bag 8; a second cooling water nozzle 9; a second flushing water bag 10; a second flushing water nozzle 11; a gas outlet pipeline 12; and a hot circulating water outlet pipeline 15. The utility model comprises a first quenching tower 1, a side wall of the first quenching tower 1 is fixedly connected to the second quenching tower 7, a surface of the first quenching tower 1 is fixedly connected to the gas inlet pipeline 6; a surface of the second quenching tower 7 is fixedly connected to the gas outlet pipeline 12, a first flushing water bag 4 is installed on the gas inlet pipeline 6, a first flushing water nozzle 5 is fixedly installed between the first flushing water bag 4 and the first quenching tower 1; a second flushing water bag 10 is installed on the gas outlet pipeline 12, and a second flushing water nozzle 11 is fixedly installed between the second flushing water bag 10 and the second quenching tower 7.
[0031] A first cooling water bag 2 is installed on the outer wall of the first quenching tower 1, and a first cooling water nozzle 3 is fixedly connected between the first cooling water bag 2 and the first quenching tower 1; a second cooling water bag 8 is installed on the outer wall of the second quenching tower 7, and a second cooling water nozzle 9 is fixedly connected between the second cooling water bag 8 and the second quenching tower 7; the first cooling water bag 2 and the second cooling water bag 8 are connected by a connecting pipe 16.
[0032] The inner walls of the first flushing water nozzle 5 and the second flushing water nozzle 11 are fixedly connected with a cross rod 17 , and the cross rod 17 is located at the outlet ends of the first flushing water nozzle 5 and the second flushing water nozzle 11 .
[0033] The first flushing water bag 4 and the second flushing water bag 10 are connected through a pipeline, and the second flushing water bag 10 is connected to the second cooling water bag 8 through a pipeline.
[0034] A hot circulating water outlet pipe 15 is fixedly installed on the bottom surface of the first quenching tower 1 and the second quenching tower 7 .
[0035] Method of use: Install the first cooling water bag 2 and the second cooling water bag 8 on the gas inlet pipe 6 and the gas outlet pipe 12 above the first quenching tower 1 and the second quenching tower 7, respectively spray water into the first quenching tower 1 and the second quenching tower 7 through the first flushing water nozzle 5 and the second flushing water nozzle 11, so as to continuously flush the coal ash adhering to the inner wall of the first quenching tower 1 and the second quenching tower 7 and the first cooling water nozzle 3 and the second cooling water nozzle 9; A cross rod 17 is fixedly connected to the inner wall of the pipe, which is more conducive to the dispersion of water after passing through the cross rod 17, and the first quenching tower 1 and the second quenching tower 7 can be fully flushed inside, making the flushing more thorough; the number of the first flushing water nozzle 5 and the second flushing water nozzle 11 is four groups, and the specification is: DN20; it can also achieve the cooling of the first quenching tower 1 and the second quenching tower 7, eliminate the faults at the first flushing water nozzle 5 and the second flushing water nozzle 11, and at the same time, it can also reduce the temperature in the gas furnace quenching tower by 6-20°C.
[0036] The first cooling water bag 2 and the second cooling water bag 8 can spray water into the first quenching tower 1 and the second quenching tower 7 through the first flushing water nozzle 5 and the second flushing water nozzle 11 to cool the first quenching tower 1 and the second quenching tower 7, and the flushing water and cooling water in the first quenching tower 1 and the second quenching tower 7 flow out through the hot circulating water outlet pipe 15 and enter the hot circulating water pool.
[0037] Example 2.
[0038] The utility model comprises a first quenching tower 1; a first cooling water bag 2; a first cooling water nozzle 3; a first flushing water bag 4; a first flushing water nozzle 5; a gas inlet pipeline 6; a second quenching tower 7; a second cooling water bag 8; a second cooling water nozzle 9; a second flushing water bag 10; a second flushing water nozzle 11; a gas outlet pipeline 12; a maintenance manhole 13; a domestic water inlet pipeline 14; a hot circulating water outlet pipeline 15, and a specific structure comprises a first quenching tower 1, a first quenching tower 1 having a side wall fixed A second quenching tower 7 is connected, and a gas inlet pipe 6 is fixedly connected to the surface of the first quenching tower 1; a gas outlet pipe 12 is fixedly connected to the surface of the second quenching tower 7, a first flushing water bag 4 is installed on the gas inlet pipe 6, and a first flushing water nozzle 5 is fixedly installed between the first flushing water bag 4 and the first quenching tower 1; a second flushing water bag 10 is installed on the gas outlet pipe 12, and a second flushing water nozzle 11 is fixedly installed between the second flushing water bag 10 and the second quenching tower 7.
[0039] A first cooling water bag 2 is installed on the outer wall of the first quenching tower 1, and a first cooling water nozzle 3 is fixedly connected between the first cooling water bag 2 and the first quenching tower 1; a second cooling water bag 8 is installed on the outer wall of the second quenching tower 7, and a second cooling water nozzle 9 is fixedly connected between the second cooling water bag 8 and the second quenching tower 7; the first cooling water bag 2 and the second cooling water bag 8 are connected by a connecting pipe 16.
[0040] The inner walls of the first flushing water nozzle 5 and the second flushing water nozzle 11 are fixedly connected with a cross rod 17 , and the cross rod 17 is located at the outlet ends of the first flushing water nozzle 5 and the second flushing water nozzle 11 .
[0041] The first flushing water bag 4 and the second flushing water bag 10 are connected through a pipeline, and the second flushing water bag 10 is connected to the second cooling water bag 8 through a pipeline.
[0042] A maintenance manhole 13 is fixedly installed on the bottom surface of the first quenching tower 1 and the second quenching tower 7 .
[0043] The bottom of the second cooling water bag 8 is connected to a domestic water inlet pipe 14 .
[0044] A hot circulating water outlet pipe 15 is fixedly installed on the bottom surface of the first quenching tower 1 and the second quenching tower 7 .
[0045] Method of use: Install the first cooling water bag 2 and the second cooling water bag 8 on the gas inlet pipe 6 and the gas outlet pipe 12 above the first quenching tower 1 and the second quenching tower 7, respectively spray water into the first quenching tower 1 and the second quenching tower 7 through the first flushing water nozzle 5 and the second flushing water nozzle 11, so as to continuously flush the coal ash adhering to the inner wall of the first quenching tower 1 and the second quenching tower 7 and the first cooling water nozzle 3 and the second cooling water nozzle 9. A cross rod 17 is fixedly connected to the inner wall of the pipe, which is more conducive to the dispersion of water after passing through the cross rod 17, and the first quenching tower 1 and the second quenching tower 7 can be fully flushed inside, making the flushing more thorough; the number of the first flushing water nozzle 5 and the second flushing water nozzle 11 is four groups, and the specification is: DN20; it can also achieve the cooling of the first quenching tower 1 and the second quenching tower 7, eliminate the faults at the first flushing water nozzle 5 and the second flushing water nozzle 11, and at the same time, it can also reduce the temperature in the gas furnace quenching tower by 6-20°C.
[0046] The first cooling water bag 2 and the second cooling water bag 8 can spray water into the first quenching tower 1 and the second quenching tower 7 through the first flushing water nozzle 5 and the second flushing water nozzle 11 to cool the first quenching tower 1 and the second quenching tower 7, and the flushing water and cooling water in the first quenching tower 1 and the second quenching tower 7 flow out through the hot circulating water outlet pipe 15 and enter the hot circulating water pool.
[0047] The domestic water inlet pipe 14 is provided, and the water in the first cooling water bag 2 and the second cooling water bag 8 can enter the living area through the domestic water inlet pipe 14 for people to use, which is energy-saving and environmentally friendly; through the inspection manhole 13, the faults in the first quenching tower 1 and the second quenching tower 7 can be promptly inspected and handled.
Claims
1. A gas furnace quenching tower, comprising a first quenching tower (1), a second quenching tower (7) being fixedly connected to the side wall of the first quenching tower (1), a gas inlet pipeline (6) being fixedly connected to the surface of the first quenching tower (1); and a gas outlet pipeline (12) being fixedly connected to the surface of the second quenching tower (7), characterized in that: A first flushing water bag (4) is installed on the gas inlet pipeline (6), and a first flushing water nozzle (5) is fixedly installed between the first flushing water bag (4) and the first quenching tower (1); a second flushing water bag (10) is installed on the gas outlet pipeline (12), and a second flushing water nozzle (11) is fixedly installed between the second flushing water bag (10) and the second quenching tower (7).
2. A gas furnace quenching tower as claimed in claim 1, characterized in that: A first cooling water bag (2) is installed on the outer wall of the first quenching tower (1), and a first cooling water nozzle (3) is fixedly connected between the first cooling water bag (2) and the first quenching tower (1); a second cooling water bag (8) is installed on the outer wall of the second quenching tower (7), and a second cooling water nozzle (9) is fixedly connected between the second cooling water bag (8) and the second quenching tower (7); the first cooling water bag (2) and the second cooling water bag (8) are connected via a connecting pipe (16).
3. A gas furnace quenching tower as claimed in claim 2, characterized in that: The inner walls of the first flushing water nozzle (5) and the second flushing water nozzle (11) are fixedly connected with a cross rod (17), and the cross rod (17) is located at the outlet ends of the first flushing water nozzle (5) and the second flushing water nozzle (11).
4. A gas furnace quenching tower as claimed in claim 3, characterized in that: The first flushing water bag (4) and the second flushing water bag (10) are connected via a pipeline, and the second flushing water bag (10) is connected to the second cooling water bag (8) via a pipeline.
5. A gas furnace quenching tower as claimed in claim 4, characterized in that: The bottom of the second cooling water bag (8) is connected to a domestic water inlet pipe (14).
6. A gas furnace quenching tower as claimed in claim 5, characterized in that: Inspection manholes (13) are fixedly installed on the bottom surfaces of the first quenching tower (1) and the second quenching tower (7).
7. A gas furnace quenching tower as claimed in claim 6, characterized in that: A hot circulating water outlet pipe (15) is fixedly installed on the bottom surface of the first quenching tower (1) and the second quenching tower (7).