Inclination early warning and monitoring device for deep foundation pit support pipe pile
By using a bubble level to monitor the inclination of concrete crown beams and prestressed concrete pipe piles in deep foundation pit construction, the problems of untimely monitoring and large connection errors in the existing technology are solved, and timely warning of the inclination of pipe piles and guaranteeing construction safety are achieved.
Patent Information
- Application Number
- CN202421655045.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-13
- Publication Date
- 2025-04-25
- Estimated Expiration
- 2034-07-13
AI Technical Summary
The state monitoring of prestressed concrete pipe piles during the construction of deep foundation pits has problems such as untimely data collection and large connection errors of measuring instruments, which leads to the inclination of pipe piles that cannot be discovered in time, affecting construction safety.
A tilt warning monitoring device for deep foundation pit enclosing pipe piles was designed. By setting up an observation box body at the top of the concrete crown beam and installing a bubble level in the box body, the tilt of the crown beam and pipe piles is monitored in real time, and early warning signals are issued in a timely manner.
Real-time monitoring of the enclosed pipe piles is realized, timely detection of tilt phenomena is reduced, the monitoring work time and labor cost is reduced, and the safety of foundation pit construction is ensured.
Smart Images

Figure CN222796542U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a deep foundation pit retaining pipe pile, in particular to a tilt early warning monitoring device for the deep foundation pit retaining pipe pile. Background Art
[0002] Some deep foundation pits are surrounded by prefabricated prestressed concrete pipe piles. Concrete crown beams are cast on the tops of the prestressed concrete pipe piles. During the entire construction process of the foundation pit, the status of the prestressed concrete pipe piles needs to be monitored to ensure the safety of the construction in the foundation pit. The existing technology monitors the status of prestressed concrete pipe piles by measuring the verticality of the prestressed concrete pipe piles manually by inspectors using measuring instruments at irregular intervals on the ground outside the foundation pit, and collects the verticality data of the concrete pipe piles. Due to the wide working surface of the foundation pit construction and the complex on-site construction environment, data collection is not timely, and the on-site connection error between the measuring instrument and the prestressed concrete pipe piles is large, resulting in the inclination of the prestressed concrete pipe piles not being discovered in time, and the on-site early warning signal being issued with a lag, which affects the normal and safe construction work in the foundation pit. Summary of the invention
[0003] The utility model provides a tilt early warning monitoring device for deep foundation pit retaining pipe piles, which solves the technical problem that the on-site early warning signal is delayed and affects the normal and safe progress of construction work in the foundation pit.
[0004] The utility model solves the above technical problems through the following technical solutions:
[0005] A tilt early warning monitoring device for deep foundation pit retaining pipe piles comprises a deep foundation pit and a bubble level, wherein prestressed concrete pipe piles are arranged in the deep foundation pit, and a concrete casting crown beam is arranged at the top of the prestressed concrete pipe piles; embedded bolts are arranged on the top surface of the concrete casting crown beam, an observation box body is connected to the embedded bolts, and a bubble level is arranged in the observation box body; a reversible box cover is arranged on the upper port of the observation box body, and the reversible box cover is connected to the upper port of the observation box body through a hinge.
[0006] A bubble level mounting base is arranged on the bottom end surface of the observation box body, and the bubble level is arranged on the bubble level mounting base; three leveling nut embedding holes are respectively arranged on the bottom plate of the observation box body, and the three leveling nut embedding holes are arranged on a concentric circle, and leveling nuts are fixedly arranged in the leveling nut embedding holes, and leveling bolt legs are connected to the leveling nuts; a center through hole is arranged at the center of the bottom end surface of the observation box body, and the upper end of the embedded bolt passes through the center through hole and is connected with the locking nut.
[0007] The utility model sets an observation box body through the embedded bolts on the crown beam, and a bubble level is arranged in the observation box body. The bubble level is used to monitor the inclination displacement of the crown beam, so as to timely discover whether the retaining pipe piles have inclination displacement phenomenon, and timely warn. The permanent observation mechanism of the utility model realizes close monitoring of the retaining pipe piles. The operator can monitor at any time, which effectively reduces the time and labor cost of the monitoring work, and can timely discover the hidden dangers of the inclination of the retaining pipe piles. When the foundation pit construction is completed, the observation box body can be conveniently removed as a whole and transported to the next observation point for installation. BRIEF DESCRIPTION OF THE DRAWINGS
[0008] Figure 1 It is a structural schematic diagram of the utility model;
[0009] Figure 2 It is a schematic diagram of the structure of the observation box body 5 of the utility model in a top view direction;
[0010] Figure 3 It is a schematic diagram of the installation structure of the utility model on the top crown beam of the foundation pit maintenance pile. DETAILED DESCRIPTION
[0011] The utility model is described in detail below with reference to the accompanying drawings:
[0012] A tilt early warning monitoring device for deep foundation pit retaining pipe piles comprises a deep foundation pit 1 and a bubble level 8, wherein prestressed concrete pipe piles 2 are arranged in the deep foundation pit 1, and a concrete casting crown beam 3 is arranged at the top end of the prestressed concrete pipe piles 2; embedded bolts 4 are arranged on the top end surface of the concrete casting crown beam 3, an observation box body 5 is connected to the embedded bolts 4, and a bubble level 8 is arranged in the observation box body 5, and the bubble level 8 monitors the tilt of the concrete casting crown beam 3 and the prestressed concrete pipe piles 2 in real time; a reversible box cover 10 is arranged on the upper end of the observation box body 5, and the reversible box cover 10 is connected to the upper end of the observation box body 5 through a hinge 11, and the inspection personnel only need to open the reversible box cover 10 to read the bubble level 8 in the observation box body 5 to determine whether the prestressed concrete pipe pile 2 is tilted.
[0013] A bubble level mounting base 7 is arranged on the bottom end surface of the observation box body 5, and the bubble level 8 is arranged on the bubble level mounting base 7; three leveling nut embedding holes 12 are respectively arranged on the bottom plate of the observation box body 5, and the three leveling nut embedding holes 12 are arranged on a concentric circle, and a leveling nut 13 is fixedly arranged in the leveling nut embedding hole 12, and a leveling bolt leg 14 is connected to the leveling nut 13, and a center through hole 6 is arranged at the center of the bottom end surface of the observation box body 5, and the upper end of the embedded bolt 4 passes through the center through hole 6 and is connected with the locking nut 9; the process of installing the observation box body 5 on the top end surface of the crown beam 3 for the first time is: first, the embedded bolt 4 The top end passes through the central through hole 6, and the observation box body 5 is installed above the top end surface of the crown beam 3. The three leveling bolt legs 14 are adjusted respectively to make the bubble level 8 indicate the center position, that is, the observation box body 5 is leveled above the concrete casting crown beam 3, because three points determine a plane, and then, the locking nut 9 is connected between the upper end of the embedded bolt 4 and the bottom end surface of the observation box body 5, so that the observation box body 5 is stably fixed on the concrete casting crown beam 3; if the prestressed concrete pipe pile 2 is tilted, the concrete casting crown beam 3 also tilts with the prestressed concrete pipe pile 2, and the bubble level 8 can timely measure the tilt direction and tilt, and issue a warning signal according to construction safety.
Claims
1. A tilt early warning monitoring device for deep foundation pit retaining pipe piles, comprising a deep foundation pit (1) and a bubble level (8), wherein prestressed concrete pipe piles (2) are arranged in the deep foundation pit (1), and a concrete pouring cap beam (3) is arranged at the top of the prestressed concrete pipe piles (2); the device is characterized in that: An embedded bolt (4) is provided on the top surface of the concrete cast crown beam (3), an observation box body (5) is connected to the embedded bolt (4), and a bubble level (8) is provided inside the observation box body (5); a reversible box cover (10) is provided on the upper end of the observation box body (5), and the reversible box cover (10) is connected to the upper end of the observation box body (5) via a hinge (11).
2. The inclination early warning monitoring device for deep foundation pit retaining pipe piles according to claim 1 is characterized in that: A bubble level mounting base (7) is arranged on the bottom end surface of the observation box body (5), and the bubble level (8) is arranged on the bubble level mounting base (7); three leveling nut embedding holes (12) are respectively arranged on the bottom plate of the observation box body (5), and the three leveling nut embedding holes (12) are arranged on a concentric circle. A leveling nut (13) is fixedly arranged in the leveling nut embedding hole (12), and a leveling bolt leg (14) is connected to the leveling nut (13); a central through hole (6) is arranged at the center of the bottom end surface of the observation box body (5), and the upper end of the embedded bolt (4) passes through the central through hole (6) and is connected to the locking nut (9).