Prefabricated steel beam and floor flush assembly structure

By using prefabricated steel beams and floor slabs to assemble structures in the building structure and using the fixing method of embedded bolts and nuts, the problems of slow construction progress and low space utilization in the prior art are solved, and efficient construction and higher space utilization are achieved.

CN222796826UActive Publication Date: 2025-04-25ZHEJIANG HONGXIANG STEEL STRUCTURE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421667826.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2025-04-25
Estimated Expiration
2034-07-15

AI Technical Summary

Technical Problem

In the existing building structure, the connection between prefabricated steel beams and floor slabs leads to a reduced space utilization rate, and the construction progress is slow, requiring on-site support and pouring concrete.

Method used

The prefabricated steel beams are flush with the floor slabs, and the prefabricated steel beams are welded pads on both sides. Prefabricated bolts and nuts are provided in the prefabricated floor slabs. The floor slabs are tightened and fixed by the nuts and embedded bolts, and reinforcement blocks and bumps are used to improve structural strength and lifting convenience.

Benefits of technology

The flush assembly of prefabricated steel beams and floor slabs is achieved, which improves the utilization rate of building space, reduces on-site construction time, and avoids the steps of supporting formwork and pouring concrete.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222796826U_ABST
    Figure CN222796826U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building structures, in particular to a prefabricated steel beam and floor flush assembly structure which comprises a prefabricated steel beam and a prefabricated floor, base plates are welded to the two sides of the prefabricated steel beam in advance, the prefabricated floor is arranged at the top ends of the base plates, and a plurality of embedded bolts are arranged in the prefabricated floor. The bottom ends of the multiple embedded bolts penetrate through the prefabricated floor slab, nuts are arranged on the multiple embedded bolts, multiple through holes matched with the embedded bolts are formed in the two base plates, and the upper plane of the prefabricated floor slab is flush with the upper plane of the prefabricated steel beam; during construction, firstly, the nuts are taken down from the embedded bolts, the bottom ends of the embedded bolts on the prefabricated floor slab penetrate through the through holes in the base plate, the nuts are arranged on the embedded bolts in a sleeving mode and then tightened, the base plate can support the prefabricated floor slab, the embedded bolts and the nuts can fix the prefabricated floor slab, and on-site formwork erecting and concrete pouring are not needed; and the construction time is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building structures, in particular to a prefabricated steel beam and floor slab flush assembly structure. Background Art

[0002] In building engineering structures, the connection method between prefabricated steel beams and floor slabs is crucial and directly related to space utilization, construction progress and project cost. Most prefabricated beam-slab connection methods are to place the slabs on top of the beams in different ways to complete the construction of the floor system, but this reduces the space utilization rate to a certain extent. Making the floor slab flush with the upper surface of the steel beam can improve the space utilization rate, but it requires on-site formwork and concrete pouring during construction, which slows down the construction progress. Therefore, a prefabricated steel beam and floor slab flush assembly structure is proposed to facilitate construction and save construction time. Utility Model Content

[0003] In view of the problems in the prior art, the utility model provides a prefabricated steel beam and floor slab flush assembly structure.

[0004] The technical solution adopted by the utility model to solve its technical problems is a prefabricated steel beam and floor slab flush assembly structure, comprising a prefabricated steel beam and a prefabricated floor slab, both sides of the prefabricated steel beam are pre-welded with pads, the prefabricated floor slab is arranged on the top of the pads, a plurality of embedded bolts are arranged in the prefabricated floor slab, the bottom ends of the plurality of embedded bolts all penetrate the prefabricated floor slab, nuts are arranged on the plurality of embedded bolts, a plurality of through holes adapted to the embedded bolts are opened on the two pads, and the upper plane of the prefabricated floor slab is flush with the upper plane of the prefabricated steel beam.

[0005] By adopting the above technical scheme, prefabricated steel beams and prefabricated floor slabs are all prefabricated in the factory. During construction, the nuts are first removed from the embedded bolts, and the bottom ends of the multiple embedded bolts on the prefabricated floor slabs are passed through the multiple through holes on the pad. The nuts are put on the embedded bolts and tightened. The pad can support the prefabricated floor slab, and the embedded bolts and nuts can fix the prefabricated floor slab. Not only can the prefabricated floor slab be flush with the upper plane of the prefabricated steel beam, thereby improving the space utilization rate of the building, but also there is no need for on-site formwork and concrete pouring, thus saving construction time.

[0006] Specifically, a plurality of reinforcing blocks are fixed to the bottom ends of the two pads, and the side walls of the plurality of reinforcing blocks close to the prefabricated steel beam are welded to the prefabricated steel beam.

[0007] By adopting the above technical solution and setting the reinforcement block, the strength and load resistance of the pad can be improved.

[0008] Specifically, each of the plurality of embedded bolts is provided with a gasket, and the gasket is located above the nut.

[0009] By adopting the above technical solution and setting the gasket, the stability of the nut can be improved.

[0010] Specifically, an embedded block is provided in the prefabricated floor slab, a convex block is integrally formed on the top of the embedded block, the convex block extends outside the prefabricated floor slab, and a through hole is formed on the convex block.

[0011] By adopting the above technical solution, the provision of the through hole on the protrusion is conducive to the insertion of the hook of the lifting equipment, and then facilitates the use of the lifting equipment to lift the prefabricated floor slab. After the prefabricated floor slab is in place, the protrusion protruding from the prefabricated floor slab can be cut off by a cutting machine.

[0012] Specifically, a reinforcing plate is welded and fixed inside the prefabricated steel beam, and the cross-section of the reinforcing plate is H-shaped.

[0013] By adopting the above technical solution and setting the reinforcing plate, the strength and deformation resistance of the prefabricated steel beam can be improved.

[0014] Beneficial effects of the utility model:

[0015] (1) The utility model discloses a prefabricated steel beam and floor slab flush assembly structure. The prefabricated steel beam and the prefabricated floor slab are prefabricated in a factory. During construction, the nuts are first removed from the embedded bolts, and the bottom ends of the multiple embedded bolts on the prefabricated floor slab are passed through the multiple through holes on the pad. The nuts are then put on the embedded bolts and tightened. The pad can support the prefabricated floor slab, and the embedded bolts and nuts can fix the prefabricated floor slab. This not only makes the prefabricated floor slab flush with the upper plane of the prefabricated steel beam, thereby improving the space utilization rate of the building, but also eliminates the need for on-site formwork and concrete pouring, thereby saving construction time.

[0016] (2) The utility model discloses a prefabricated steel beam and floor slab flush assembly structure. The through hole on the protrusion is convenient for the hook of the lifting equipment to penetrate into the prefabricated floor slab, and then it is convenient to lift the prefabricated floor slab by the lifting equipment. After the prefabricated floor slab is in place, the protrusion protruding from the prefabricated floor slab can be cut off by a cutting machine. The reinforcement block can improve the strength and load resistance of the pad. The reinforcement plate can improve the strength and deformation resistance of the prefabricated steel beam. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0018] Figure 1 It is a schematic diagram of the structure of the utility model;

[0019] Figure 2 For the utility model Figure 1 A magnified view of the structure at center A;

[0020] Figure 3 This is a schematic diagram of the structure of the prefabricated floor slab of the utility model;

[0021] Figure 4 It is a structural schematic diagram of the embedded block of the utility model.

[0022] In the figure: 1. prefabricated steel beam; 2. pad; 3. prefabricated floor slab; 4. reinforcement block; 5. reinforcement plate; 6. protrusion; 60. embedded block; 7. embedded bolt; 8. nut; 9. gasket. DETAILED DESCRIPTION

[0023] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0024] In order to facilitate construction and save time, as an embodiment of the utility model, Figure 1 , Figure 2 , Figure 3 As shown, a prefabricated steel beam and floor slab flush assembly structure described in the utility model comprises a prefabricated steel beam 1 and a prefabricated floor slab 3, both sides of the prefabricated steel beam 1 are pre-welded with pads 2, the prefabricated floor slab 3 is arranged on the top of the pads 2, a plurality of embedded bolts 7 are arranged in the prefabricated floor slab 3, the bottom ends of the plurality of embedded bolts 7 all penetrate the prefabricated floor slab 3, nuts 8 are arranged on the plurality of embedded bolts 7, a plurality of through holes adapted to the embedded bolts 7 are opened on the two pads 2, and the upper plane of the prefabricated floor slab 3 is flush with the upper plane of the prefabricated steel beam 1.

[0025] When the prefabricated floor 3 is prefabricated in the factory, the top ends of multiple embedded bolts 7 are welded to the steel bars in the prefabricated floor 3. The prefabricated steel beam 1 and the prefabricated floor 3 are all prefabricated in the factory. During construction, the nuts 8 are first removed from the embedded bolts 7, and the bottom ends of the multiple embedded bolts 7 on the prefabricated floor 3 are passed through the multiple through holes on the pad 2. The nuts 8 are put on the embedded bolts 7 and tightened. The pad 2 can support the prefabricated floor 3, and the embedded bolts 7 and the nuts 8 can fix the prefabricated floor 3, which not only makes the prefabricated floor 3 flush with the upper plane of the prefabricated steel beam 1, thereby improving the space utilization rate of the building, but also eliminates the need for on-site formwork and concrete pouring, saving construction time.

[0026] In order to improve the strength and bearing capacity of the pad 2, for example, Figure 2 As shown, a plurality of reinforcing blocks 4 are welded and fixed to the bottom ends of the two pads 2 , and the side walls of the plurality of reinforcing blocks 4 close to the prefabricated steel beam 1 are welded to the prefabricated steel beam 1 .

[0027] In order to improve the stability of the nut 8, exemplary, as Figure 3 As shown, a plurality of the embedded bolts 7 are each provided with a gasket 9 , and the gasket 9 is located above the nut 8 .

[0028] In order to facilitate the lifting of the prefabricated floor slab 3, for example, Figure 2 , Figure 4 As shown, an embedded block 60 is provided in the prefabricated floor 3 , a convex block 6 is integrally formed at the top of the embedded block 60 , the convex block 6 extends to the outside of the prefabricated floor 3 , and a through hole is opened on the convex block 6 .

[0029] During construction, the through hole on the projection 6 is convenient for the hook of the lifting equipment to penetrate, and then it is convenient to lift the prefabricated floor 3 by the lifting equipment. After the prefabricated floor 3 is in place, the projection 6 protruding from the prefabricated floor 3 can be cut off by a cutting machine.

[0030] In order to improve the strength of the prefabricated steel beam 1, for example, Figure 2 As shown, a reinforcing plate 5 is welded and fixed inside the prefabricated steel beam 1, and the cross-section of the reinforcing plate 5 is H-shaped.

[0031] During construction of the utility model, the nut 8 and the gasket 9 are first removed from the embedded bolt 7, and the through hole on the protrusion 6 is provided to facilitate the insertion of the hook of the lifting equipment, thereby facilitating the lifting of the prefabricated floor slab 3 by the lifting equipment;

[0032] The bottom ends of the multiple embedded bolts 7 on the prefabricated floor 3 are passed through the multiple through holes on the backing plate 2, and the gaskets 9 are put on the embedded bolts 7, and then the nuts 8 are put on the embedded bolts 7 and tightened. The backing plate 2 can support the prefabricated floor 3, and the embedded bolts 7 and the nuts 8 can fix the prefabricated floor 3;

[0033] After the prefabricated floor 3 is installed, the protrusion 6 protruding from the prefabricated floor 3 can be cut off by a cutting machine, which not only makes the prefabricated floor 3 flush with the upper plane of the prefabricated steel beam 1, thereby improving the space utilization rate of the building, but also eliminates the need for on-site formwork and concrete pouring, thereby saving construction time;

[0034] The provision of the reinforcing block 4 can improve the strength of the pad 2 , and the provision of the reinforcing plate 5 can improve the strength and deformation resistance of the prefabricated steel beam 1 .

[0035] The above shows and describes the basic principles, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and the description in the specification are only to illustrate the principles of the utility model. Without departing from the spirit and scope of the utility model, the utility model will have various changes and improvements, and these changes and improvements fall within the scope of protection claimed by the utility model. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents. The contents not described in detail in the utility model belong to the prior art known to those skilled in the art.

Claims

1. A prefabricated steel beam and floor slab flush assembly structure, characterized in that: The invention comprises a prefabricated steel beam (1) and a prefabricated floor slab (3), wherein pads (2) are pre-welded on both sides of the prefabricated steel beam (1), the prefabricated floor slab (3) is arranged on the top of the pads (2), a plurality of embedded bolts (7) are arranged in the prefabricated floor slab (3), the bottom ends of the plurality of embedded bolts (7) all pass through the prefabricated floor slab (3), nuts (8) are arranged on the plurality of embedded bolts (7), a plurality of through holes adapted to the embedded bolts (7) are opened on the two pads (2), and the upper plane of the prefabricated floor slab (3) is flush with the upper plane of the prefabricated steel beam (1).

2. The prefabricated steel beam and floor slab flush assembly structure according to claim 1, characterized in that: A plurality of reinforcing blocks (4) are fixed to the bottom ends of the two pads (2), and the side walls of the plurality of reinforcing blocks (4) close to the prefabricated steel beam (1) are welded to the prefabricated steel beam (1).

3. The prefabricated steel beam and floor slab flush assembly structure according to claim 1, characterized in that: A gasket (9) is provided on each of the plurality of embedded bolts (7), and the gasket (9) is located above the nut (8).

4. The prefabricated steel beam and floor slab flush assembly structure according to claim 1, characterized in that: An embedded block (60) is provided in the prefabricated floor slab (3), a convex block (6) is integrally formed at the top of the embedded block (60), the convex block (6) extends outside the prefabricated floor slab (3), and a through hole is provided on the convex block (6).

5. The prefabricated steel beam and floor slab flush assembly structure according to claim 1, characterized in that: A reinforcing plate (5) is welded and fixed inside the prefabricated steel beam (1), and the cross section of the reinforcing plate (5) is H-shaped.