Slope soil outlet PC construction method pile reinforcing device

By designing a PC-process pile reinforcement device for ramp excavation outlet with a simple structure, the existing reinforcement device is solved, and the construction efficiency is improved and the reinforcement effect is improved.

CN222822240UActive Publication Date: 2025-05-02浙江双资建设有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421609003.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2025-05-02
Estimated Expiration
2034-07-09

AI Technical Summary

Technical Problem

The existing PC pile reinforcement device has complex structure and cumbersome installation and disassembly, resulting in reduced construction efficiency.

Method used

A PC-process pile reinforcement device for ramp excavation outlet is designed, including steel pipe piles, Larsen steel sheet piles, reinforcement plates, electric telescopic rods, connecting steel columns and sliding grooves, which are quickly reinforced through simple structure and operation.

Benefits of technology

The reinforcement device is simple in structure, easy to install and disassemble, significantly improves construction efficiency, and further improves the reinforcement effect through the design of screw components and clamps.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222822240U_ABST
    Figure CN222822240U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building construction, in particular to a slope soil outlet PC construction method pile reinforcing device which comprises steel pipe piles and Larsen steel sheet piles, the Larsen steel sheet piles are arranged between the steel pipe piles, a first reinforcing plate is arranged at the upper ends of the steel pipe piles, a second reinforcing plate is arranged at the lower ends of the steel pipe piles, and a fixing plate is fixedly connected to the front end of the second reinforcing plate. A first screw assembly, a first inner thread sleeve, a first clamping plate, a second screw assembly, a second inner thread sleeve and a second clamping plate are fixedly connected to the upper end of the fixing plate, an electric telescopic rod is fixedly connected to the upper end of the fixing plate, and a connecting steel column is fixedly connected to the upper end of the electric telescopic rod. The first screw assembly drives the first clamping plate to rotate downwards, and the second screw assembly drives the second clamping plate to rotate upwards, so that the first clamping plate and the second clamping plate are matched with each other to reinforce the joint of the steel pipe pile and the Larsen steel sheet pile, and the overall reinforcing effect is improved again.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a PC method pile reinforcement device for a ramp excavation opening. Background Art

[0002] PC method piles are composite piles of various cross-sections formed by combining Larsen piles with steel pipes. They are suitable for the supporting structure of foundation pit support projects. PC method piles are adaptable to a wide range of strata, have significant water-stopping effects, high wall quality, high adjustability of profile spacing and insertion depth, save engineering workload, and have no mud pollution. They are being used more and more widely in foundation pit retaining in various complex environments.

[0003] During the foundation pit construction process, after the foundation pit is excavated, the slope range on both sides of the excavated ramp becomes larger and larger, and the PC method piles at the ramp excavation port will be stabilized using a reinforcement device. However, the existing PC method pile reinforcement device has a complex structure and is very cumbersome to install and disassemble, which wastes the time of construction workers and reduces the overall construction efficiency. Therefore, in response to the above problems, we propose a PC method pile reinforcement device for the ramp excavation port. Utility Model Content

[0004] The utility model aims to provide a PC method pile reinforcement device for a ramp excavation opening, so as to solve the problem that the existing PC method pile reinforcement device has a complex structure, and the installation and disassembly is very cumbersome, thereby wasting the time of construction workers and reducing the overall construction efficiency.

[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0006] A PC construction method pile reinforcement device for a ramp exit, comprising a steel pipe pile and a Larsen steel sheet pile, wherein the Larsen steel sheet pile is arranged between the steel pipe piles, a first reinforcement plate is arranged at the upper end of the steel pipe pile, a second reinforcement plate is arranged at the lower end of the steel pipe pile, a fixing plate is fixedly connected to the front end of the second reinforcement plate, an electric telescopic rod is fixedly connected to the upper end of the fixing plate, a connecting steel column is fixedly connected to the upper end of the electric telescopic rod, a sliding groove is provided on the inner side of the front end of the fixing plate, a first anti-slip pad is fixedly connected to the inner side of the upper end of the second reinforcement plate, a second anti-slip pad is fixedly connected to the inner side of the lower end of the first reinforcement plate, a first screw assembly is arranged at the upper end of the first reinforcement plate, a first internal threaded sleeve is spirally connected to the outer side of the first screw assembly, a first clamping plate is fixedly connected to the lower end of the first screw assembly, a second screw assembly is arranged at the lower end of the second reinforcement plate, a second internal threaded sleeve is spirally connected to the outer side of the second screw assembly, and a second clamping plate is fixedly connected to the upper end of the second screw assembly.

[0007] Preferably, the steel pipe piles and Larsen steel sheet piles are arranged alternately, the first reinforcement plate and the second reinforcement plate are symmetrical about the transverse axis of the steel pipe piles, and the fixing plate is located at the front end of the first reinforcement plate.

[0008] Preferably, the number of the fixing plates is two, the number of the electric telescopic rods is two, the number of the connecting steel columns is two, and the rear end of the connecting steel columns is fixedly connected with a first reinforcement plate.

[0009] Preferably, the outer side of the connecting steel column is slidably connected with a sliding groove, the first anti-slip pad has a semi-circular arc shape, the inner side of the upper end of the first anti-slip pad fits with the outer side of the lower end of the steel pipe pile, and the second anti-slip pad has a semi-circular arc shape, the inner side of the lower end of the second anti-slip pad fits with the outer side of the upper end of the steel pipe pile.

[0010] Preferably, the number of the first screw assemblies is four, a first internal threaded sleeve is fixedly connected inside the first reinforcement plate, the first screw assembly passes through the first reinforcement plate, a second internal threaded sleeve is fixedly connected inside the second reinforcement plate, and the second screw assembly passes through the second reinforcement plate.

[0011] Compared with the prior art, the beneficial effects of the utility model are:

[0012] In the utility model, a reinforcement device is formed by arranging a first reinforcement plate, a second reinforcement plate, a fixed plate, an electric telescopic rod, a connecting steel column and a sliding groove. The steel pipe pile and the Larsen steel sheet pile form a PC method pile. When the PC method pile needs to be reinforced, the reinforcement device is sleeved on the outer side of the steel pipe pile. At this time, the inner side of the upper end of the first anti-skid pad and the outer side of the lower end of the steel pipe pile fit together. Then, the electric telescopic rod is started, and the electric telescopic rod drives the connecting steel column to slide downward along the sliding groove, thereby driving the first reinforcement plate to slide downward so that the inner side of the lower end of the second anti-skid pad and the outer side of the upper end of the steel pipe pile fit closely together, thereby clamping the first reinforcement plate and the second reinforcement plate together. It is fixed on the PC construction method pile to reinforce and protect the PC construction method pile. The fixing device has a simple structure and is convenient for construction personnel to install and disassemble, so that the overall construction efficiency is improved. By arranging the first screw assembly, the first internal threaded sleeve, the first clamping plate, the second screw assembly, the second internal threaded sleeve and the second clamping plate, the first screw assembly and the second screw assembly are rotated inward, the first screw assembly drives the first clamping plate to rotate downward, and the second screw assembly drives the second clamping plate to rotate upward, so that the first clamping plate and the second clamping plate cooperate with each other to reinforce the connection between the steel pipe pile and the Larsen steel sheet pile, thereby further improving the overall reinforcement effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0014] Figure 2 For this utility model Figure 1 A schematic diagram of the structure at A;

[0015] Figure 3 For this utility model Figure 1 Schematic diagram of the structure at B;

[0016] Figure 4 This is a schematic diagram of the cutaway structure of the fixed plate of the utility model from the left side;

[0017] Figure 5 This is a schematic diagram of the structure of the first screw assembly of the utility model;

[0018] Figure 6 This is a schematic diagram of the structure of the second screw assembly of the utility model.

[0019] In the figure: 1. steel pipe pile; 2. Larsen steel sheet pile; 3. first reinforcement plate; 4. second reinforcement plate; 5. fixed plate; 6. electric telescopic rod; 7. connecting steel column; 8. sliding groove; 9. first anti-skid pad; 10. second anti-skid pad; 11. first screw assembly; 12. first internal threaded sleeve; 13. first clamping plate; 14. second screw assembly; 15. second internal threaded sleeve; 16. second clamping plate. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] See also Figure 1-6 , the utility model provides a technical solution:

[0022] A PC construction method pile reinforcement device for a ramp excavation opening comprises a steel pipe pile 1 and a Larsen steel sheet pile 2, wherein the Larsen steel sheet pile 2 is arranged between the steel pipe piles 1, a first reinforcement plate 3 is arranged at the upper end of the steel pipe pile 1, a second reinforcement plate 4 is arranged at the lower end of the steel pipe pile 1, a fixing plate 5 is fixedly connected to the front end of the second reinforcement plate 4, an electric telescopic rod 6 is fixedly connected to the upper end of the fixing plate 5, a connecting steel column 7 is fixedly connected to the upper end of the electric telescopic rod 6, a sliding groove 8 is opened on the inner side of the front end of the fixing plate 5, and a second reinforcement plate 4 is fixedly connected to the inner side of the upper end of the fixing plate 5. There is a first anti-slip pad 9, a second anti-slip pad 10 is fixedly connected to the inner side of the lower end of the first reinforcement plate 3, a first screw assembly 11 is provided at the upper end of the first reinforcement plate 3, a first internal threaded sleeve 12 is spirally connected to the outer side of the first screw assembly 11, a first clamping plate 13 is fixedly connected to the lower end of the first screw assembly 11, a second screw assembly 14 is provided at the lower end of the second reinforcement plate 4, a second internal threaded sleeve 15 is spirally connected to the outer side of the second screw assembly 14, and a second clamping plate 16 is fixedly connected to the upper end of the second screw assembly 14.

[0023] The steel pipe piles 1 and the Larsen steel sheet piles 2 are arranged alternately, the first reinforcement plate 3 and the second reinforcement plate 4 are symmetrical about the transverse axis of the steel pipe pile 1, the fixed plate 5 is located at the front end of the first reinforcement plate 3, the number of the fixed plates 5 is two, the number of the electric telescopic rods 6 is two, the number of the connecting steel columns 7 is two, the rear end of the connecting steel column 7 is fixedly connected to the first reinforcement plate 3, the outer side of the connecting steel column 7 is slidably connected to the sliding groove 8, the first anti-skid pad 9 has a semicircular arc shape, the inner side of the upper end of the first anti-skid pad 9 is fitted with the outer side of the lower end of the steel pipe pile 1, the second anti-skid pad 10 has a semicircular arc shape, the inner side of the lower end of the second anti-skid pad 10 is fitted with the outer side of the upper end of the steel pipe pile 1, the number of the first screw assembly 11 is four, and the first reinforcement plate 3 is fixedly connected to the inside The internal threaded sleeve 12, the first screw assembly 11 passes through the first reinforcement plate 3, the second reinforcement plate 4 is fixedly connected with the second internal threaded sleeve 15, the second screw assembly 14 passes through the second reinforcement plate 4, and Larsen steel sheet piles 2 are arranged between the steel pipe piles 1. The upper end of the steel pipe pile 1 is provided with a first reinforcement plate 3, which is convenient for setting the first reinforcement plate 3, the second reinforcement plate 4, the fixed plate 5, the electric telescopic rod 6, the connecting steel column 7 and the sliding groove 8 to form a reinforcement device. The steel pipe pile 1 and the Larsen steel sheet pile 2 constitute a PC construction method pile. When the PC construction method pile needs to be reinforced, the reinforcement device is sleeved on the outside of the steel pipe pile 1. At this time, the inner side of the upper end of the first anti-slip pad 9 and the outer side of the lower end of the steel pipe pile 1 are fitted, and then the electric telescopic rod 6 is started, and the electric telescopic rod 6 The connecting steel column 7 is driven to slide downward along the sliding groove 8, thereby driving the first reinforcing plate 3 to slide downward so that the inner side of the lower end of the second anti-slip pad 10 and the outer side of the upper end of the steel pipe pile 1 are closely fitted, and then the first reinforcing plate 3 and the second reinforcing plate 4 are clamped and fixed on the PC construction method pile to reinforce and protect the PC construction method pile. The fixing device has a simple structure and is convenient for construction personnel to install and disassemble, so that the overall construction efficiency is improved; a second reinforcing plate 4 is provided at the lower end of the steel pipe pile 1, and a fixing plate 5 is fixedly connected to the front end of the second reinforcing plate 4, and an electric telescopic rod 6 is fixedly connected to the upper end of the fixing plate 5, and a connecting steel column 7 is fixedly connected to the upper end of the electric telescopic rod 6, and a sliding groove 8 is provided on the inner side of the front end of the fixing plate 5. A first anti-slip pad 9 is fixedly connected to the inner side, a second anti-slip pad 10 is fixedly connected to the inner side of the lower end of the first reinforcement plate 3, and a first screw assembly 11 is provided at the upper end of the first reinforcement plate 3, which is convenient for arranging the first screw assembly 11, the first internal threaded sleeve 12, the first clamping plate 13, the second screw assembly 14, the second internal threaded sleeve 15 and the second clamping plate 16. The first screw assembly 11 and the second screw assembly 14 are rotated inwardly, and the first screw assembly 11 drives the first clamping plate 13 to rotate downward, and the second screw assembly 14 drives the second clamping plate 16 to rotate upward, so that the first clamping plate 13 and the second clamping plate 16 cooperate with each other to reinforce the connection between the steel pipe pile 1 and the Larsen steel sheet pile 2, thereby further improving the overall reinforcement effect;The first screw assembly 11 is spirally connected to the outside with a first internal thread sleeve 12, the first screw assembly 11 is fixedly connected to the lower end with a first clamping plate 13, the second reinforcing plate 4 is provided with a second screw assembly 14 at the lower end, the second screw assembly 14 is spirally connected to the outside with a second internal thread sleeve 15, and the second screw assembly 14 is fixedly connected to the upper end with a second clamping plate 16. ;

[0024] Working process: When the device is in use, the steel pipe pile 1 and the Larsen steel sheet pile 2 constitute a PC method pile. When the PC method pile needs to be reinforced, the first reinforcement plate 3, the second reinforcement plate 4, the fixed plate 5, the electric telescopic rod 6, the connecting steel column 7 and the sliding groove 8 constitute a reinforcement device. The front end of the second reinforcement plate 4 is fixedly connected to the fixed plate 5, and the upper end of the fixed plate 5 is fixedly connected to the electric telescopic rod 6. A power supply is provided inside the electric telescopic rod 6 to supply power to the electric telescopic rod 6. The upper end of the electric telescopic rod 6 is fixedly connected to the connecting steel column 7. A sliding groove 8 is provided on the inner side of the front end of the fixed plate 5. The rear end of the connecting steel column 7 is fixedly connected to the first reinforcing plate 3, the outer side of the connecting steel column 7 is slidably connected to the sliding groove 8, the inner side of the upper end of the second reinforcing plate 4 is fixedly connected to the first anti-skid pad 9, and the inner side of the lower end of the first reinforcing plate 3 is fixedly connected to the second anti-skid pad 10. The reinforcing device is sleeved on the outer side of the steel pipe pile 1. At this time, the inner side of the upper end of the first anti-skid pad 9 and the outer side of the lower end of the steel pipe pile 1 are fitted, and then the electric telescopic rod 6 is started by the external controller, and the electric telescopic rod 6 drives the connecting steel column 7 to slide downward along the sliding groove 8, thereby driving the first reinforcing plate 3 to slide downward so that the second anti-skid pad 10 moves downward. The inner side of the end is tightly fitted with the outer side of the upper end of the steel pipe pile 1, and then the first reinforcement plate 3 and the second reinforcement plate 4 are clamped and fixed on the PC construction method pile to reinforce and protect the PC construction method pile. The fixing device has a simple structure, which is convenient for construction personnel to install and disassemble, so that the overall construction efficiency is improved. The first reinforcement plate 3 is fixedly connected with the first internal threaded sleeve 12, the inner side of the first internal threaded sleeve 12 is spirally connected with the outer side of the first screw assembly 11, the lower end of the first screw assembly 11 is fixedly connected with the first clamping plate 13, and the second reinforcement plate 4 is fixedly connected with the second internal threaded sleeve 15. The inner side of the second internal threaded sleeve 15 is spirally connected to the outer side of the second screw assembly 14, and the second clamping plate 16 is fixedly connected to the upper end of the second screw assembly 14. At this time, the first screw assembly 11 and the second screw assembly 14 are rotated inward, and the first screw assembly 11 drives the first clamping plate 13 to rotate downward, and the second screw assembly 14 drives the second clamping plate 16 to rotate upward, so that the first clamping plate 13 and the second clamping plate 16 cooperate with each other to reinforce the connection between the steel pipe pile 1 and the Larsen steel sheet pile 2, thereby further improving the overall reinforcement effect, making the PC method pile more solid and reliable when used.

[0025] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A PC pile reinforcement device for a ramp exit, comprising a steel pipe pile (1) and a Larsen steel sheet pile (2), characterized in that: Larsen steel sheet piles (2) are arranged between the steel pipe piles (1), a first reinforcement plate (3) is arranged at the upper end of the steel pipe pile (1), a second reinforcement plate (4) is arranged at the lower end of the steel pipe pile (1), a fixing plate (5) is fixedly connected to the front end of the second reinforcement plate (4), an electric telescopic rod (6) is fixedly connected to the upper end of the fixing plate (5), a connecting steel column (7) is fixedly connected to the upper end of the electric telescopic rod (6), a sliding groove (8) is provided on the inner side of the front end of the fixing plate (5), a first anti-slip pad (9) is fixedly connected to the inner side of the upper end of the second reinforcement plate (4), and the first A second anti-slip pad (10) is fixedly connected to the inner side of the lower end of the reinforcement plate (3); a first screw assembly (11) is provided at the upper end of the first reinforcement plate (3); a first internally threaded sleeve (12) is spirally connected to the outer side of the first screw assembly (11); a first clamping plate (13) is fixedly connected to the lower end of the first screw assembly (11); a second screw assembly (14) is provided at the lower end of the second reinforcement plate (4); a second internally threaded sleeve (15) is spirally connected to the outer side of the second screw assembly (14); and a second clamping plate (16) is fixedly connected to the upper end of the second screw assembly (14).

2. A PC pile reinforcement device for a ramp exit according to claim 1, characterized in that: The steel pipe piles (1) and the Larsen steel sheet piles (2) are arranged alternately, the first reinforcement plate (3) and the second reinforcement plate (4) are symmetrical about the transverse axis of the steel pipe piles (1), and the fixing plate (5) is located at the front end of the first reinforcement plate (3).

3. A PC pile reinforcement device for a ramp exit according to claim 1, characterized in that: The number of the fixing plates (5) is two, the number of the electric telescopic rods (6) is two, the number of the connecting steel columns (7) is two, and the rear end of the connecting steel columns (7) is fixedly connected to the first reinforcing plate (3).

4. The PC pile reinforcement device for ramp exit according to claim 1 is characterized in that: The outer side of the connecting steel column (7) is slidably connected with a sliding groove (8); the first anti-skid pad (9) has a semi-circular arc shape, and the inner side of the upper end of the first anti-skid pad (9) fits with the outer side of the lower end of the steel pipe pile (1); the second anti-skid pad (10) has a semi-circular arc shape, and the inner side of the lower end of the second anti-skid pad (10) fits with the outer side of the upper end of the steel pipe pile (1).

5. The PC pile reinforcement device for ramp excavation according to claim 1 is characterized in that: The number of the first screw assemblies (11) is four; a first internally threaded sleeve (12) is fixedly connected inside the first reinforcement plate (3); the first screw assembly (11) passes through the first reinforcement plate (3); a second internally threaded sleeve (15) is fixedly connected inside the second reinforcement plate (4); and the second screw assembly (14) passes through the second reinforcement plate (4).