Super high-rise concrete pumping pipe mounting structure
By designing an ultra-high-rise concrete pump pipe installation structure including an adjustment mechanism and a fixing component, the problem of insufficient flexibility in the installation position in the prior art is solved, flexible adjustment of the pump pipe position and reduction of maintenance costs are achieved, and the practicality of the installation structure is improved.
Patent Information
- Application Number
- CN202421983788.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2025-05-02
- Estimated Expiration
- 2034-08-15
AI Technical Summary
The existing ultra-high-rise concrete pump pipe installation structure is fixed at the installation position and cannot be adjusted according to construction needs, resulting in insufficient flexibility, cumbersome maintenance, high maintenance costs and low practicality.
An ultra-high-rise concrete pumping pipe installation structure including building layers, embedded parts, shock absorbing pads, bottom plates, adjustment mechanisms and fixing components is designed to fine-tune the pumping pipe position through height adjustment components and transverse adjustment components, and to improve the durability and safety of the pumping pipe through wear-resistant anti-corrosion coatings and fixing components.
It realizes flexible adjustment of the pump pipe position, simplifies the maintenance process, reduces maintenance costs, improves the safety of the installation structure and the durability of the pump pipe, and enhances the practicality of the ultra-high-rise concrete pump pipe installation structure.
Smart Images

Figure CN222823862U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of concrete pumping pipe installation, in particular to a super high-rise concrete pumping pipe installation structure. Background Art
[0002] In the field of super high-rise building construction, the installation and fixing technology of concrete pumping pipes has always been a key link in the construction. With the continuous increase in building height, the requirements for the stability, installation efficiency and maintenance cost of the pumping pipe installation structure are also increasing. When installing the pumping pipe, a super high-rise concrete pumping pipe installation structure is generally required.
[0003] In the actual use of the existing super-high-rise concrete pumping pipe installation structure, the installation position of the pumping pipe installation structure is generally fixed, so the installation position of the pumping pipe cannot be effectively adjusted according to the actual construction needs, resulting in insufficient flexibility in the installation of the pumping pipe. The subsequent inspection and maintenance process of the pumping pipe installation structure is also relatively cumbersome, and the pumping pipe may face problems such as wear and corrosion during long-term use. Therefore, the maintenance cost of the pumping pipe is generally high, reducing the practicality of the existing super-high-rise concrete pumping pipe installation structure. Utility Model Content
[0004] In response to the shortcomings of the prior art, the present application provides a super-high-rise concrete pumping pipe installation structure, which has the advantages of easily achieving fine-tuning of the pumping pipe position and reducing the maintenance cost of the pumping pipe, thereby solving the problem of low practicality of the super-high-rise concrete pumping pipe installation structure.
[0005] In order to achieve the above-mentioned purpose of being able to easily fine-tune the position of the pumping pipe and reducing the maintenance cost of the pumping pipe, the present application provides the following technical solutions: a super-high-rise concrete pumping pipe installation structure, including a building layer, an embedded part fixed inside the building layer, a shock-absorbing pad slidably connected to the top of the building layer, a base plate fixed on the top of the shock-absorbing pad, an adjustment mechanism installed on the top of the base plate for adjusting the pumping pipe, and a fixing assembly installed on the top of the adjustment mechanism for fixing the pumping pipe;
[0006] The adjustment mechanism includes a height adjustment component installed on the top of the base plate for adjusting the height of the pumping pipe, and a lateral adjustment component installed inside the base plate for fine-tuning the position of the pumping pipe;
[0007] The height adjustment assembly includes two bracket bodies fixed on the top of the base plate, a connecting column slidably connected to the inside of the bracket body, a plurality of adjustment slots respectively opened on opposite sides of the two connecting columns, a limit block slidably connected to the inside of the connecting column, two limit slots respectively opened on opposite sides of the two connecting columns, and a fastening bolt threadedly connected to the inside of the bracket body.
[0008] By adopting the above technical solution, the height of the pumping pipe can be adjusted conveniently and effectively.
[0009] Furthermore, the lateral adjustment assembly includes two fixing bolts threadedly connected to the inside of the base plate and a plurality of adjustment holes opened on the top of the base plate.
[0010] By adopting the above technical solution, the position of the pumping pipe can be effectively fine-tuned through multiple adjustment holes.
[0011] Furthermore, the fixing assembly includes a first clamping clamp fixed between the top ends of the two connecting columns, two connecting bolts threadedly connected to the left and right sides of the first clamping clamp, and a second clamping clamp threadedly connected between the outer sides of the two connecting bolts.
[0012] By adopting the above technical solution, the pumping pipe can be effectively fixed.
[0013] Furthermore, a pumping pipe body is slidably connected between the opposite sides of the first clamping clamp and the second clamping clamp, and a wear-resistant and anti-corrosion coating is fixed on the outer side of the pumping pipe body.
[0014] By adopting the above technical solution, it is ensured that the service life of the pumping pipe body is extended by the wear-resistant and anti-corrosion coating.
[0015] Furthermore, the bottom end of the fixing bolt passes through the base plate, the shock-absorbing pad, the building layer and the embedded part in sequence and extends to the interior of the embedded part to be threadedly connected to the embedded part.
[0016] By adopting the above technical solution, it is ensured that the installation structure can be stably and effectively fixed and installed by bolts and embedded parts.
[0017] Furthermore, the limiting block is slidably connected to the inside of the limiting groove, and opposite sides of the two limiting blocks are respectively fixed to the inner right side wall and the inner left side wall of the two bracket bodies.
[0018] By adopting the above technical solution, it is ensured that the connection column can be adjusted more stably in the bracket body through the limiting block and the limiting groove.
[0019] Furthermore, opposite ends of the two fastening bolts successively penetrate the bracket body, the connecting column and the adjusting groove and extend to the inside of the adjusting groove to be threadedly connected to the adjusting groove.
[0020] By adopting the above technical solution, it is ensured that the connecting column and the bracket body can be effectively fixed by tightening the bolts.
[0021] Furthermore, the diameter of the connecting column is equal to the inner diameter of the bracket body, and a plurality of reinforcing ribs are fixed between the outer side of the bracket body and the top of the bottom plate.
[0022] By adopting the above technical solution, the installation between the bracket body and the base plate is made more stable.
[0023] Compared with the prior art, this invention provides a super high-rise concrete pumping pipe installation structure, which has the following beneficial effects:
[0024] The super-high-rise concrete pumping pipe installation structure can easily achieve fine-tuning of the pumping pipe position during actual use through the coordinated use of building layers, embedded parts, the bracket body, the connecting column and the limit block in the adjustment mechanism, thereby ensuring that the installation position of the pumping pipe can be effectively adjusted according to the actual construction needs, thereby improving the flexibility of the pumping pipe installation and greatly simplifying the process of overhauling and maintaining the pumping pipe installation structure. In addition, through the coordinated use of the shock-absorbing pad, the wear-resistant and anti-corrosion coating and the first clamping clamp and the second clamping clamp in the fixing assembly, the pumping pipe can be effectively fixed, and the safety of the installation structure and the durability of the pumping pipe are further improved, thereby improving the practicality of the super-high-rise concrete pumping pipe installation structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a schematic diagram of the structure of this application;
[0026] Figure 2 It is a partial enlarged schematic diagram of the A part in the structure of the utility model;
[0027] Figure 3 It is a three-dimensional schematic diagram of the connecting column connection structure in the structure of the utility model.
[0028] In the figure: 1, building layer; 2, embedded parts; 3, shock-absorbing pads; 4, bottom plate; 5, pumping pipe body; 6, wear-resistant and anti-corrosion coating; 200, adjustment mechanism; 201, height adjustment assembly; 2011, bracket body; 2012, connecting column; 2013, adjustment slot; 2014, limit block; 2015, limit slot, 2016, fastening bolt; 202, lateral adjustment assembly; 2021, fixing bolt; 2022, adjustment hole; 300, fixing assembly; 301, first clamping clamp; 302, connecting bolt; 303, second clamping clamp. DETAILED DESCRIPTION
[0029] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present application.
[0030] See also Figures 1 to 3 The utility model provides a technical solution: a super high-rise concrete pumping pipe installation structure, comprising a building layer 1, an embedded part 2 fixed inside the building layer 1, a shock-absorbing pad 3 slidably connected to the top of the building layer 1, a bottom plate 4 fixed to the top of the shock-absorbing pad 3, an adjustment mechanism 200 installed on the top of the bottom plate 4 for adjusting the pumping pipe, and a fixing assembly 300 installed on the top of the adjustment mechanism 200 for fixing the pumping pipe;
[0031] Through the coordinated use of the building layer 1, the embedded parts 2, and the adjustment mechanism 200, in actual use, the position of the pumping pipe can be easily fine-tuned, thereby ensuring that the installation position of the pumping pipe can be effectively adjusted according to the actual construction needs, thereby improving the flexibility of the pumping pipe installation, greatly simplifying the process of inspection and maintenance of the pumping pipe installation structure, and through the coordinated use of the shock-absorbing pad 3, the wear-resistant and anti-corrosion coating 6 and the fixing component 300, the pumping pipe can be effectively fixed, and the safety of the installation structure and the durability of the pumping pipe are further improved, thereby improving the practicality of the super-high-rise concrete pumping pipe installation structure.
[0032] In this embodiment, the adjustment mechanism 200 is a structure for adjusting the pumping pipe.
[0033] like Figure 1 , Figure 2 and Figure 3 As shown, the adjustment mechanism 200 includes a height adjustment component 201 installed on the top of the base plate 4 for adjusting the height of the pumping pipe, and a lateral adjustment component 202 installed inside the base plate 4 for fine-tuning the position of the pumping pipe.
[0034] It should be noted that the shock-absorbing pad 3 can effectively reduce the impact of the vibration generated during the pumping process on the building structure, further improving the construction safety, and the material and thickness of the shock-absorbing pad 3 can also be adjusted according to actual conditions. By selecting materials of different hardness and thickness, the vibration absorption effect can be accurately controlled, thereby better protecting the building structure from the vibration generated during the pumping process.
[0035] In this embodiment, the height adjustment component 201 is a structure for adjusting the height of the pumping pipe.
[0036] like Figure 1 , Figure 2 and Figure 3 As shown, the height adjustment assembly 201 includes two bracket bodies 2011 fixed on the top of the base plate 4, a connecting column 2012 slidably connected to the inside of the bracket body 2011, a plurality of adjustment grooves 2013 respectively opened on the opposite sides of the two connecting columns 2012, a limit block 2014 slidably connected to the inside of the connecting column 2012, two limit grooves 2015 respectively opened on the opposite sides of the two connecting columns 2012, and a fastening bolt 2016 threadedly connected to the inside of the bracket body 2011.
[0037] It should be noted that the diameter of the connecting column 2012 is equal to the inner diameter of the bracket body 2011, the limit block 2014 is slidably connected to the inside of the limit groove 2015, and the opposite sides of the two limit blocks 2014 are respectively fixed to the inner right wall and the inner left wall of the two bracket bodies 2011, ensuring that the connecting column 2012 is adjusted more stably in the bracket body 2011 through the limit block 2014 and the limit groove 2015.
[0038] In addition, the opposite ends of the two fastening bolts 2016 pass through the bracket body 2011, the connecting column 2012 and the adjustment groove 2013 in sequence and extend to the interior of the adjustment groove 2013 to be threadedly connected to the adjustment groove 2013, ensuring that the connecting column 2012 and the bracket body 2011 can be effectively fixed by the fastening bolts 2016.
[0039] In addition, the installation between the bracket body 2011 and the base plate 4 is made more stable. The base plate 4, the bracket body 2011 and the connecting column 2012 are all made of high-strength steel, which realizes the stable fixation of the pumping pipe in the construction of super-high-rise buildings, thereby improving the construction safety.
[0040] In this embodiment, the lateral adjustment assembly 202 is a structure for fine-tuning the position of the pumping pipe.
[0041] like Figure 1 As shown, the lateral adjustment assembly 202 includes two fixing bolts 2021 threadedly connected to the inside of the bottom plate 4 and a plurality of adjustment holes 2022 opened on the top of the bottom plate 4 .
[0042] It should be noted that the bottom end of the fixing bolt 2021 passes through the base plate 4, the shock-absorbing pad 3, the building layer 1 and the embedded part 2 in sequence and extends to the interior of the embedded part 2 to be threadedly connected to the embedded part 2, ensuring that the installation structure can be stably and effectively fixed and installed by the bolt 2021 and the embedded part 2. By setting a plurality of adjustment holes 2022 on the base plate 4 and a plurality of adjustment grooves 2013 on the bracket body 2011, the installation height and angle of the pumping pipe body 5 can be flexibly adjusted, which not only adapts to different construction requirements, but also facilitates the later inspection and maintenance of the pumping pipe, effectively improving the installation efficiency and reducing maintenance costs.
[0043] In this embodiment, the fixing assembly 300 is a structure for fixing the pumping pipe.
[0044] like Figure 1 As shown, the fixing assembly 300 includes a first clamping clamp 301 fixed between the top ends of the two connecting columns 2012, two connecting bolts 302 threadedly connected to the left and right sides of the first clamping clamp 301, and a second clamping clamp 303 threadedly connected between the outer sides of the two connecting bolts 302.
[0045] It should be noted that a pumping pipe body 5 is slidably connected between the opposite sides of the first clamping clamp 301 and the second clamping clamp 303, which can effectively fix the pumping pipe. A wear-resistant and anti-corrosion coating 6 is fixed to the outer side of the pumping pipe body 5. The wear-resistant and anti-corrosion coating 6 can be an epoxy coal tar anti-corrosion coating layer, which is characterized by good corrosion resistance. The coating has excellent weather resistance and impact resistance, and it has beautiful appearance, easy maintenance, and moisture resistance. It enhances the wear resistance of the pumping pipe and also has anti-corrosion effect. It can resist corrosion factors in harsh construction environments, thereby extending the service life of the pumping pipe and significantly reducing maintenance costs.
[0046] The working principle of the above embodiment is:
[0047] When in use, the bottom plate 4 and the shock-absorbing pad 3 are placed on the shock-absorbing layer 1 to be fixed, and according to the position where the pumping pipe body 5 needs to be installed, the fixing bolt 2021 is passed through the corresponding adjustment hole 2022 and then fixed with the embedded part 2, so as to ensure that the pumping pipe body 5 is fixed in the specified position, and when the position of the pumping pipe body 5 needs to be fine-tuned later, it is only necessary to screw the fixing bolt 2021, pass it through another adjustment hole 2022 and then fix it with the embedded part 2, so as to achieve fine-tuning of the position of the pumping pipe body 5, and then when the pumping pipe body 5 needs to be adjusted When adjusting the height of the pipe body 5, first loosen the fastening bolt 2016 to separate the fastening bolt 2016 from the connecting column 2012, and then move the connecting column 2012 upward, thereby driving the pumping pipe body 5 to move upward. After moving to the designated location, tighten the fastening bolt 2016 again to re-fix it to the connecting column 2012 through the adjustment groove 2013, and under the action of the limit block 2014 and the limit groove 2015, the overall stability of the installation structure is ensured during the adjustment process, thereby realizing the position adjustment of the pumping pipe body 5.
[0048] Compared with the prior art, the super-high-rise concrete pumping pipe installation structure, through the coordinated use of the building layer 1, the embedded parts 2, the bracket body 2011, the connecting column 2012 and the limit block 2014 in the adjustment mechanism 200, can easily achieve fine-tuning of the pumping pipe position during actual use, thereby ensuring that the installation position of the pumping pipe can be effectively adjusted according to the actual construction needs, thereby improving the flexibility of the pumping pipe installation, greatly simplifying the process of inspection and maintenance of the pumping pipe installation structure, and through the coordinated use of the shock-absorbing pad 3, the wear-resistant and anti-corrosion coating 6 and the first clamping clamp 301 and the second clamping clamp 303 in the fixing assembly 300, the pumping pipe can be effectively fixed, and the safety of the installation structure and the durability of the pumping pipe are further improved, thereby improving the practicality of the super-high-rise concrete pumping pipe installation structure and solving the problem of low practicality of the super-high-rise concrete pumping pipe installation structure.
Claims
1. A super high-rise concrete pumping pipe installation structure, characterized in that: It comprises a building layer (1), an embedded part (2) fixed inside the building layer (1), a shock-absorbing pad (3) slidably connected to the top of the building layer (1), a base plate (4) fixed to the top of the shock-absorbing pad (3), an adjustment mechanism (200) installed on the top of the base plate (4) for adjusting a pumping pipe, and a fixing assembly (300) installed on the top of the adjustment mechanism (200) for fixing the pumping pipe; The adjustment mechanism (200) comprises a height adjustment component (201) installed on the top of the base plate (4) for adjusting the height of the pumping pipe, and a lateral adjustment component (202) installed inside the base plate (4) for fine-tuning the position of the pumping pipe; The height adjustment assembly (201) comprises two bracket bodies (2011) fixed to the top of the base plate (4), a connecting column (2012) slidably connected to the inside of the bracket body (2011), a plurality of adjustment slots (2013) respectively arranged on opposite sides of the two connecting columns (2012), a limit block (2014) slidably connected to the inside of the connecting column (2012), two limit slots (2015) respectively arranged on opposite sides of the two connecting columns (2012), and a fastening bolt (2016) threadedly connected to the inside of the bracket body (2011).
2. The super high-rise concrete pumping pipe installation structure according to claim 1 is characterized in that: The lateral adjustment component (202) comprises two fixing bolts (2021) threadedly connected to the interior of the base plate (4), and a plurality of adjustment holes (2022) opened at the top of the base plate (4).
3. The super high-rise concrete pumping pipe installation structure according to claim 1 is characterized in that: The fixing assembly (300) comprises a first clamping clamp (301) fixed between the top ends of the two connecting columns (2012), two connecting bolts (302) threadedly connected to the left and right sides of the first clamping clamp (301), and a second clamping clamp (303) threadedly connected between the outer sides of the two connecting bolts (302).
4. The super high-rise concrete pumping pipe installation structure according to claim 3 is characterized in that: A pumping pipe body (5) is slidably connected between opposite sides of the first clamping hoop (301) and the second clamping hoop (303), and a wear-resistant and anti-corrosion coating (6) is fixed to the outer side of the pumping pipe body (5).
5. The super high-rise concrete pumping pipe installation structure according to claim 2 is characterized in that: The bottom end of the fixing bolt (2021) passes through the base plate (4), the shock-absorbing pad (3), the building layer (1) and the embedded part (2) in sequence and extends into the interior of the embedded part (2) to be threadedly connected to the embedded part (2).
6. The super high-rise concrete pumping pipe installation structure according to claim 1 is characterized by: The limiting block (2014) is slidably connected inside the limiting groove (2015), and opposite sides of the two limiting blocks (2014) are respectively fixed to the inner right side wall and the inner left side wall of the two bracket bodies (2011).
7. The super high-rise concrete pumping pipe installation structure according to claim 1 is characterized by: The opposite ends of the two fastening bolts (2016) successively penetrate the bracket body (2011), the connecting column (2012) and the adjustment groove (2013) and extend into the interior of the adjustment groove (2013) to be threadedly connected to the adjustment groove (2013).
8. The super high-rise concrete pumping pipe installation structure according to claim 1 is characterized by: The diameter of the connecting column (212) is equal to the inner diameter of the bracket body (211), and a plurality of reinforcing ribs are fixed between the outer side of the bracket body (2011) and the top of the bottom plate (4).