Assembly type steel structure house PCF plate installation structure

By introducing a guide connecting table and telescopic rod into the PCF board installation structure, the problems of troubles in installation, waste of crane time and inconvenient adjustment of PCF board are solved, fast positioning and efficient adjustment are achieved, and installation efficiency is improved.

CN222909124UActive Publication Date: 2025-05-27CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421626120.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-10
Publication Date
2025-05-27
Estimated Expiration
2034-07-10

AI Technical Summary

Technical Problem

PCF exterior wall panels are troublesome when installing, waste crane time and inconvenient adjustment.

Method used

A prefabricated steel structure residential PCF board installation structure is designed, including a connecting table with guiding role and a telescopic rod, through which the rapid positioning and adjustment of the PCF board is achieved.

Benefits of technology

Through rapid positioning and adjustment, the complexity of PCF board installation and crane time are reduced, and the installation efficiency is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222909124U_ABST
    Figure CN222909124U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type steel structure house PCF plate installation structure, and belongs to the field of assembly type buildings. Comprising a PCF board body, connecting tables with a guiding function are symmetrically arranged on the two sides of the rear portion of the PCF plate body, the PCF plate body is positioned through telescopic rods with the ends extending into the lower portions of the connecting tables, adjusting bolts capable of adjusting gaps between the connecting tables and the ends of the telescopic rods are arranged on the connecting tables, and the telescopic rods on the same side are arranged on a steel column of a steel structure house. The PCF plate body and the telescopic rod are fixed through angle steel inserted into the inclined lower portions of the two sides of the connecting table and arranged in connecting plates on the two sides of the telescopic rod. The connecting table with the guiding function is arranged and matched with the telescopic rod with the end extending into the lower portion of the connecting table to position the PCF plate body, so that the PCF plate body can be rapidly positioned during hoisting, a crane can hoist the next PCF plate body after positioning is completed, and the PCF plate body is convenient to adjust through the design of the telescopic rod and the adjusting bolt.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model provides an installation structure for PCF boards of an assembled steel structure residence, belonging to the field of assembled buildings. Background Technique

[0002] The PCF board, namely the precast concrete external wall panel, plays a key role in the assembled steel structure residence. This kind of wall panel is precast in the factory, integrating a concrete structure, heat insulation materials and a decorative layer, and is designed to be seamlessly docked with the steel structure main body. The PCF board not only provides the support for the building's external enclosure structure, but also has the functions of heat insulation, waterproofing, moisture-proofing and beautifying the appearance. Through rapid on-site installation, the PCF board greatly shortens the construction period, reduces the complexity and pollution of on-site construction, and is an important part of realizing building industrialization and improving the efficiency of residential construction.

[0003] At present, when installing the PCF external wall panel, the positioning border line and control line are first popped out at the installation position, then the adjusting screws are used to level the bottom elevation, and then the waterproof rubber strip is laid at the specified position and the hoisting tools, locking tools and other preparatory work are checked, and then hoisting is carried out. After the PCF external wall panel is placed at the specified position, it is first temporarily fixed with a diagonal brace, and then the PCF external wall panel is finely adjusted with a crowbar according to the positioning border line and control line to ensure accurate position. Then, a straightedge is used to check the perpendicularity of the PCF external wall panel, and the perpendicularity of the external wall panel is adjusted through the diagonal brace. After the adjustment is completed, the diagonal brace is locked. Only after confirming firm and reliable can the hook of the crane be removed. Then, after hoisting the other external wall panels of the floor in the same way, vertical joint treatment is carried out. At the vertical joint position between two PCF external wall panels, a self-adhesive rubber sheet is pasted, and PCF external wall connectors are installed at the upper, middle and lower parts of the external wall panel. After the installation is completed, at the vertical joint position, A-level fireproof rock wool is laid. After such hoisting is completed, the wall reinforcement is tied inside the external wall panel, the aluminum alloy formwork is installed, and finally the concrete is poured layer by layer.

[0004] The PCF board installed in this way is troublesome to install, wastes crane time relatively, and is inconvenient to adjust. Content of the Utility Model

[0005] The technical problem to be solved by the utility model is that the current installation of the PCF external wall panel is troublesome, wastes crane time relatively, and is inconvenient to adjust.

[0006] To solve the above problems, the technical solution proposed by this utility model is: an installation structure of a PCF board for an assembled steel structure residence, including the PCF board body; on both sides of the rear of the PCF board body, there are symmetrically arranged connecting platforms with a guiding function. The PCF board body is positioned by telescopic rods whose ends extend into the lower part of the connecting platforms. On the connecting platforms, there are adjusting bolts that can adjust the gap between the connecting platforms and the ends of the telescopic rods. The telescopic rods on the same side are arranged on a steel column of the steel structure residence. The PCF board body and the telescopic rods are fixed by angle steels inserted into connecting plates arranged on both sides of the telescopic rods and obliquely below both sides of the connecting platforms.

[0007] As an improvement, on the upper side and one side of the PCF board body, there are convex platforms, and on the lower side and the other side, there are grooves. On both sides of the convex platform above the PCF board body, there are symmetrically arranged lifting holes for facilitating the lifting by a crane. There is no groove on the lower side of the PCF board body installed at the bottommost.

[0008] As an improvement, on the lower part of the connecting platform, there is a guiding groove that gradually narrows upward. From the guiding groove to the upper end face of the connecting platform, there are threaded holes that cooperate with the adjusting bolts.

[0009] As an improvement, the telescopic rod includes an outer rod fixedly arranged at one end on the steel column, and an inner rod slidably arranged inside the outer rod. At one end of the outer rod close to the inner rod, there is a threaded hole two, and a fastening bolt is threadedly connected in the threaded hole two. One end of the inner rod protrudes, and above the protruding end, there is a guiding block corresponding to the guiding groove.

[0010] As an improvement, the length of the threaded part of the adjusting bolt is greater than the depth of the threaded hole.

[0011] As an improvement, on the connecting plates, there are fixing grooves. The fixing grooves on both sides and obliquely below the connecting platforms open upward and towards the telescopic rods, and the fixing grooves on both sides of the telescopic rods open upward and towards the PCF board body. The angle steels are inserted and connected with two adjacent fixing grooves.

[0012] The beneficial effects of this utility model:

[0013] By arranging the connecting platforms with a guiding function and cooperating with the telescopic rods whose ends extend into the lower part of the connecting platforms to position the PCF board body, the PCF board body can be quickly positioned during hoisting. After positioning, the crane can hoist the next PCF board body. The design of the telescopic rods and the adjusting bolts makes it convenient to adjust the PCF board body. Description of the Drawings

[0014] Figure 1 It is a schematic structural diagram of an installation structure of a PCF board for an assembled steel structure residence of this utility model.

[0015] Figure 2 It is a cross-sectional view of the connecting platform of an installation structure of a PCF board for an assembled steel structure residence of this utility model.

[0016] Figure 3 Exploded view of the telescopic rod of an installation structure of a PCF board for an assembled steel structure residence of the present utility model.

[0017] Figure 4 Schematic diagram during the installation of an installation structure of a PCF board for an assembled steel structure residence of the present utility model.

[0018] 1. PCF board body; 101. Boss; 102. Groove; 103. Lifting hole; 2. Connecting platform; 201. Guide groove; 202. First threaded hole; 3. Telescopic rod; 301. Outer rod; 302. Inner rod; 303. Second threaded hole; 304. Fastening bolt; 305. Guide block; 4. Adjusting bolt; 5. Steel column; 6. Connecting plate; 601. Fixed groove; 7. Angle steel. Specific implementation manner

[0019] The present utility model will be further described below with reference to the accompanying drawings.

[0020] According to Figure 1 —4 shows: The present utility model provides an installation structure of a PCF board for an assembled steel structure residence: including a PCF board body 1; on both sides of the rear of the PCF board body 1, there are symmetrically arranged connecting platforms 2 with a guiding function. The PCF board body 1 is positioned by a telescopic rod 3 whose end extends into the lower part of the connecting platform 2. On the connecting platform 2, there is an adjusting bolt 4 that can adjust the gap between the connecting platform 2 and the end of the telescopic rod 3. The telescopic rods 3 on the same side are arranged on a steel column 5 of the steel structure residence. The PCF board body 1 and the telescopic rod 3 are fixed by angle steels 7 inserted into connecting plates 6 arranged on both sides of the lower part of the two sides of the connecting platform 2 and on both sides of the telescopic rod 3; by arranging the connecting platform 2 with a guiding function and cooperating with the telescopic rod 3 whose end extends into the lower part of the connecting platform 2 to position the PCF board body 1, the PCF board body 1 can be quickly positioned during hoisting, and after positioning, the crane can hoist the next PCF board body 1. The design of the telescopic rod 3 and the adjusting bolt 4 makes it convenient to adjust the PCF board body 1;

[0021] According to Figure 1 , 4 As shown: Above and on one side of the PCF board body 1, there are bosses 101, and below and on the other side, there are grooves 102. On both sides of the bosses 101 above the PCF board body 1, there are symmetrically arranged lifting holes 103 convenient for the crane to hoist. There is no groove 102 below the PCF board body 1 installed at the bottom; the bosses 101 and grooves 102 enable any two PCF board bodies 1 to be connected together, so the integrity is better;

[0022] According to Figure 1 , 2As shown in the figure: The lower part of the connecting platform 2 is provided with a guiding groove 201 that gradually narrows upward. From the guiding groove 201 to the upper end face of the connecting platform 2, there are threaded holes 202 that cooperate with the adjusting bolts 4; the telescopic rod 3 includes an outer rod 301 fixedly arranged at one end on the steel column 5, and an inner rod 302 slidably arranged inside the outer rod 301. At one end of the outer rod 301 close to the inner rod 302, there is a second threaded hole 303, and a fastening bolt 304 is threadedly connected inside the second threaded hole 303. One end of the inner rod 302 protrudes, and above the protruding end, there is a guiding block 305 corresponding to the guiding groove 201; the length of the threaded part of the adjusting bolt 4 is greater than the depth of the threaded hole 202; in this way, by changing the length of the inner rod 302 extending out of the outer rod 301 and then fixing it with the fastening bolt 303, the distance between the PCF board body 1 and the steel column 5 of the steel structure residence can be determined. Then, by screwing the adjusting bolt 4 into the first threaded hole 202, the lower end of the adjusting bolt 4 is made to abut against the lower end of the guiding block 305, and then by continuing to rotate, the connecting platform 2 can be lifted, thereby lifting the height of the PCF board body 1;

[0023] According to Figure 1 、 3 、As shown in Figure 4: The connecting plate 6 is provided with fixing grooves 601. The fixing grooves 601 located diagonally below both sides of the connecting platform 2 have openings facing upward and towards the telescopic rod 3, and the fixing grooves 601 located on both sides of the telescopic rod 3 have openings facing upward and towards the PCF board body 1. The angle steel 7 is inserted and connected with two adjacent fixing grooves 601. In this way, under the action of its own gravity, the guiding groove 201 will be stuck outside the guiding block 305, and then the PCF board body 1 and the telescopic rod 3 can be fixed through the angle steel 7, thereby preventing the PCF board body 1 from tipping over.

[0024] The principle of the present utility model: When in use, first weld one end of the outer rod 301 of the telescopic rod 3 to the same steel column 5 of the steel structure residence according to the installation height of the PCF board body 1 and the distance between two connecting platforms 2 on the same side. Then, adjust the length of the inner rod 302 extending out of the outer rod 301 according to the distance between the PCF board body 1 and the steel column 5. Then, after fixing it with the fastening bolt 303, hook the hook of the crane to the lifting hole 103 and connect the guy ropes. During the lifting operation, when it is necessary to lower the PCF board body 1, use the guy ropes to determine the angle of the PCF board body 1, so that the guiding block 305 is inserted into the guiding groove 201. The guiding groove 201 that gradually narrows upward cooperates with the guiding block 305 that gradually narrows upward, so that the guiding block 305 can be quickly inserted into the guiding groove 201. Then, insert the angle steel 7 into any two adjacent fixing grooves 601, and in this way, the position of the PCF board body 1 is fixed. If there is a deviation in the height during the welding of the telescopic rod 3, the PCF board body 1 can be slightly lifted by screwing the adjusting bolt 4 into the first threaded hole 202.

[0025] The above description is made on the present utility model and its implementation manners. Such description is not restrictive. What is shown in the drawings is only one of the implementation manners of the present utility model, and the actual structure is not limited thereto. Generally speaking, if those of ordinary skill in the art are inspired by it and design, without creative efforts, structural manners and embodiments similar to the technical solution without departing from the gist of the creation of the present utility model, they shall fall within the protection scope of the present utility model.

Claims

1. A PCF board installation structure for a prefabricated steel structure residence, comprising a PCF board body (1); characterized in that: The PCF board body (1) is symmetrically provided with connecting platforms (2) with guiding functions on both sides of the rear, and the PCF board body (1) is positioned by a telescopic rod (3) whose end extends into the lower part of the connecting platform (2). The connecting platform (2) is provided with an adjusting bolt (4) capable of adjusting the end gap between the connecting platform (2) and the telescopic rod (3). The telescopic rod (3) on the same side is arranged on a steel column (5) of the steel structure house. The PCF board body (1) and the telescopic rod (3) are fixed by angle steels (7) inserted into connecting plates (6) arranged at the lower side of the connecting platform (2) and at both sides of the telescopic rod (3).

2. The PCF board installation structure for a prefabricated steel structure house according to claim 1 is characterized by: The PCF board body (1) is provided with a boss (101) on the top and one side, and a groove (102) on the bottom and the other side. The boss (101) located above the PCF board body (1) is symmetrically provided with hoisting holes (103) on both sides for facilitating crane hoisting. The PCF board body (1) installed at the bottom is not provided with a groove (102) on the bottom.

3. The PCF board installation structure for a prefabricated steel structure house according to claim 1 is characterized by: The lower part of the connecting platform (2) is provided with a guide groove (201) which gradually decreases in size at the upper part, and a threaded hole (202) which matches with the adjusting bolt (4) is provided from the guide groove (201) to the upper end surface of the connecting platform (2).

4. The PCF board installation structure for a prefabricated steel structure house according to claim 3 is characterized by: The telescopic rod (3) comprises an outer rod (301) with one end fixedly arranged on a steel column (5), and an inner rod (302) slidably arranged inside the outer rod (301); a second threaded hole (303) is provided at one end of the outer rod (301) close to the inner rod (302); a fastening bolt (304) is connected to the inner thread of the second threaded hole (303); one end of the inner rod (302) protrudes, and a guide block (305) corresponding to the guide groove (201) is provided above the protruding end.

5. The PCF board installation structure for a prefabricated steel structure house according to claim 1 is characterized by: The connecting plate (6) is provided with fixing grooves (601), the fixing grooves (601) located at the lower side of the connecting platform (2) are opened upward and toward the telescopic rod (3), and the fixing grooves (601) located at the two sides of the telescopic rod (3) are opened upward and toward the PCF board body (1), and the angle steel (7) is plug-connected with two adjacent fixing grooves (601).