Scaffold structure for high and steep slope protection engineering construction

By using cantilever platforms and steel anchor pipe structures on ultra-high steep rocky slopes, the problem of the inability to build a facility cantilever platform in the existing technology is solved, and the safe and stable construction of high steep slope protection projects is achieved.

CN223061981UActive Publication Date: 2025-07-04CCCC SHEC DONGMENG ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422156858.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2025-07-04
Estimated Expiration
2034-09-04

AI Technical Summary

Technical Problem

The existing technology cannot build a cantilever platform frame on ultra-high steep rock slopes, resulting in difficulty in protective construction and poses major safety risks.

Method used

The cantilever platform and steel anchor pipe structure are used, and connected to the bottom of the frame vertical pole through the first steel anchor pipe, combined with the steel anchor rod and cable-stayed cable to form a stable scaffolding structure, which is suitable for high steep slope protection projects.

Benefits of technology

It realizes a safe and reliable construction cantilever platform frame on ultra-high steep rock slopes, improving stability and safety and reducing safety risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223061981U_ABST
    Figure CN223061981U_ABST
Patent Text Reader

Abstract

The utility model discloses a high and steep slope protection engineering construction scaffold structure, and relates to the technical field of construction scaffolds.The high and steep slope protection engineering construction scaffold structure comprises an overhanging platform, and the overhanging platform is fixed to a slope; the first steel anchor pipe is obliquely fixed to the side slope with the gradient larger than 55 degrees so that the section, extending out of the side slope, of the first steel anchor pipe can incline upwards, and the first steel anchor pipe is vertically fixed to the side slope with the gradient smaller than 55 degrees; a vertical rod of the frame body is supported on the cantilever platform, and the bottom of the vertical rod, close to the slope, of the frame body is connected with the first steel anchor pipe. The overall structure of the frame body is supported through the cantilever platform, and the vertical rods, close to the slope, on the frame body cannot be supported on the cantilever platform, so that the first steel anchor pipes are installed on the slope, the first steel anchor pipes are connected with the bottoms of the vertical rods of the frame body, and connection between the frame body and the slope is achieved; the scaffold structure can be erected on an abrupt slope and is better in stability and safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the technical field of construction scaffolding, and particularly to a construction scaffolding structure for high and steep slope protection projects. Background Art

[0002] The construction framework is a common temporary facility in construction. It is a framework erected for temporarily placing construction tools and building materials and facilitating the high-altitude operations of construction workers. It is widely used in engineering fields such as road and bridge construction, water conservancy and hydropower projects, and building construction. The construction framework faces significant safety risks during erection, use, and demolition. Especially for the construction cantilever platform framework used in high slope treatment projects, once problems occur, it is very likely to result in major production safety accidents with multiple fatalities.

[0003] In the construction activities of human society, continuous construction activities such as mining, excavation, and road building require dealing with various geological problems. Among them, for high and steep slopes, due to their unique characteristics such as irregular slope terrain, long service time, high possibility of secondary disasters during use, and a large number of operating personnel, the construction cantilever platform framework for high and steep slope protection projects faces even higher safety risks. Ensuring the construction safety of the construction cantilever platform framework for high and steep slope protection projects is particularly important, urgent, and of great significance.

[0004] For ultra-high and steep rocky slopes, especially those with an inclination angle exceeding 55°, it is impossible to erect a scaffolding on such ultra-high and steep rocky slopes in the prior art, resulting in extremely difficult or even impossible implementation of protection construction on ultra-high and steep rocky slopes. Summary of the Invention

[0005] This application aims to at least partly solve one of the above technical problems in the prior art. Therefore, an embodiment of this application provides a construction scaffolding structure for high and steep slope protection projects. This scaffolding structure can be erected on high and steep slopes, and has better stability and safety, enabling protection construction on ultra-high and steep rocky slopes.

[0006] A construction scaffolding structure for high and steep slope protection projects includes

[0007] A cantilever platform, which is fixed on the slope;

[0008] The first steel anchor pipe. For slopes with an inclination angle greater than 55°, the first steel anchor pipe is obliquely fixed on the slope so that the section of the first steel anchor pipe extending out of the slope inclines upward. For slopes with an inclination angle less than 55°, the first steel anchor pipe is vertically fixed on the slope;

[0009] A framework, the vertical poles of which are supported on the cantilever platform, and the bottom of the vertical poles of the framework close to the slope is connected to the first steel anchor pipe.

[0010] In an optional or preferred embodiment, the construction scaffolding structure for high-steep slope protection project further includes a second steel anchor pipe, which is obliquely fixed on the slope. The section of the second steel anchor pipe extending out of the slope inclines upward, and the second steel anchor pipe is connected to the vertical pole of the nearest frame body through a connecting piece.

[0011] In an optional or preferred embodiment, the depth of the first steel anchor pipe and the second steel anchor pipe anchored in the slope is greater than 2 meters.

[0012] In an optional or preferred embodiment, the construction scaffolding structure for high-steep slope protection project further includes a steel anchor rod, which is fixed on the slope. The section of the steel anchor rod extending out of the slope bends upward. The steel anchor rod is located below the first steel anchor pipe, and the bottom end of the vertical pole of the frame body close to the slope is sleeved on the bent section of the steel anchor rod.

[0013] In an optional or preferred embodiment, a bottom cross bar close to the slope is provided on the frame body, and the bottom cross bar is connected to each of the first steel anchor pipes.

[0014] In an optional or preferred embodiment, the end of the cantilever platform far from the slope is connected to the slope through a plurality of stay cables.

[0015] In an optional or preferred embodiment, the cantilever platform includes a plurality of cantilever brackets, and the cantilever brackets are arranged side by side at intervals. The cantilever brackets are connected by longitudinal I-beams.

[0016] In an optional or preferred embodiment, the cantilever bracket includes a horizontal I-beam, a diagonal bracing I-beam, an I-beam hinge socket and an I-beam reinforcing rod. The I-beam hinge socket is provided with an I-beam slot, and the I-beam hinge socket is provided with a rotating shaft seat. The end of the diagonal bracing I-beam is connected to the horizontal I-beam through the I-beam hinge socket. The middle parts of the horizontal I-beam and the diagonal bracing I-beam are both sleeved with the I-beam hinge socket, and the rotating shaft seats between the two I-beam sockets are connected by the I-beam reinforcing rod.

[0017] In an optional or preferred embodiment, the I-beam hinge socket is provided with a limit hole, which leads to the waist of the I-beam slot, and fasteners are used to be connected in the limit hole.

[0018] In an optional or preferred embodiment, a plurality of support channel steels are installed on the cantilever platform, and the bottom of the vertical pole of the frame body is supported in the support channel steels.

[0019] Based on the above technical solution, the embodiments of the present application at least have the following beneficial effects: In the above technical solution, the overall structure of the framework is supported by a cantilever platform. Since the vertical poles on the framework close to the slope cannot be supported on the cantilever platform, the present application installs the first steel anchor pipe on the slope and connects the bottom of the vertical pole of the framework to the first steel anchor pipe to realize the connection between the framework and the slope. This kind of scaffolding structure can be erected on a super-high and steep slope, and has better stability and safety, realizing the protection construction on a super-high and steep rocky slope. Description of the Drawings

[0020] The following further describes the present application in conjunction with the drawings and embodiments;

[0021] Figure 1 It is a schematic structural diagram of a construction scaffolding for high and steep slope protection engineering in an embodiment where the slope gradient in the present application is ≥55°;

[0022] Figure 2 It is Figure 1 A schematic connection diagram of the bottom of the vertical pole of the framework and the first steel anchor pipe and the steel anchor rod in the shown embodiment;

[0023] Figure 3 It is a schematic structural diagram of a construction scaffolding for high and steep slope protection engineering in an embodiment where the slope gradient in the present application is <55°;

[0024] Figure 4 It is a schematic structural diagram of the cantilever support in the present application;

[0025] Figure 5 It is a schematic structural diagram of the I-beam hinge socket on the cantilever support in the present application;

[0026] Figure 6 It is Figure 5 The schematic structural diagram in the A-A direction in Detailed Embodiment

[0027] In order to enable those skilled in the art to better understand the technical solutions in the present application, the following will clearly and completely describe the technical solutions in the embodiments of the present application in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present application.

[0028] The following further describes the implementation manners of the present application in conjunction with the drawings and embodiments. The following embodiments are used to illustrate the present application, but cannot be used to limit the scope of the present application.

[0029] In the description of the embodiments of the present application, it should be noted that the orientation or positional relationship indicated by the terms "center", "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. is based on the orientation or positional relationship shown in the drawings. It is only for the convenience of describing the embodiments of the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the embodiments of the present application. In addition, the terms "first", "second", and "third" are only used for descriptive purposes and should not be construed as indicating or implying relative importance.

[0030] In the description of the embodiments of the present application, it should be noted that unless otherwise clearly specified and defined, the terms "connected" and "coupled" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium. For those of ordinary skill in the art, the specific meanings of the above terms in the embodiments of the present application can be understood according to specific circumstances.

[0031] In the embodiments of the present application, unless otherwise clearly specified and defined, the first feature being "on" or "under" the second feature may be that the first and second features are in direct contact, or the first and second features are indirectly in contact through an intermediate medium. Moreover, the first feature being "above", "over" and "on top of" the second feature may be that the first feature is directly above or obliquely above the second feature, or simply means that the first feature has a higher horizontal height than the second feature. The first feature being "under", "beneath" and "underneath" the second feature may be that the first feature is directly below or obliquely below the second feature, or simply means that the first feature has a lower horizontal height than the second feature.

[0032] Construction scaffolding is a common temporary facility in construction. It is a framework erected for temporarily placing construction tools and building materials and facilitating high-altitude operations of construction workers. It is widely used in engineering fields such as road and bridge construction, water conservancy and hydropower projects, and building construction. Construction scaffolding faces significant safety risks during erection, use, and demolition processes. Especially for the construction cantilever platform scaffolding used in high-slope treatment projects, once problems occur, it is very likely to result in major work safety accidents with multiple fatalities and injuries.

[0033] In the construction activities of human society, continuous construction activities such as mining, excavation, and road construction are carried out. During the process, various geological problems need to be addressed. Among them, for high and steep slopes, due to their unique characteristics such as irregular slope terrain, long service time, high possibility of secondary disasters during use, and a large number of operating personnel, the construction of the cantilever platform scaffolding project for the high and steep slope protection project faces higher safety risks. Ensuring the construction safety of the cantilever platform scaffolding for the high and steep slope protection project is particularly important, urgent, and of great significance.

[0034] For ultra-high and steep rocky slopes, especially those with an inclination angle exceeding 55°, in the existing technology, it is impossible to erect a scaffolding on the ultra-high and steep rocky slope, resulting in extremely difficult or even impossible implementation of the protection construction on the ultra-high and steep rocky slope.

[0035] Refer to Figure 1 、 Figure 2 、 Figure 3 Accordingly, the present application provides a scaffolding structure for the construction of a high and steep slope protection project, including a cantilever platform 100, a first steel anchor pipe 200, and a framework 300.

[0036] The cantilever platform 100 is fixed on the slope 001. For a slope 001 with an inclination angle greater than 55°, the first steel anchor pipe 200 is obliquely fixed on the slope 001 so that the section of the first steel anchor pipe 200 extending out of the slope 001 inclines upward. For a slope 001 with an inclination angle less than 55°, the first steel anchor pipe 200 is vertically fixed on the slope 001. The vertical pole 301 of the framework 300 is supported on the cantilever platform 100, and the bottom of the vertical pole 301 of the framework 300 close to the slope 001 is connected to the first steel anchor pipe 200.

[0037] The overall structure of the framework 300 is supported by the cantilever platform 100. The vertical pole 301 of the framework 300 close to the slope 001 cannot be supported on the cantilever platform 100. Therefore, in the present application, the first steel anchor pipe 200 is installed on the slope 001, and the first steel anchor pipe 200 is connected to the bottom of the vertical pole 301 of the framework 300 to realize the connection between the framework 300 and the slope 001. This kind of scaffolding structure can be erected on the ultra-high and steep slope, and has better stability and safety, realizing the protection construction on the ultra-high and steep rocky slope.

[0038] Refer to Figure 1 For the first steel anchor pipe 200 on the steep vertical slope surface of the slope 001 with a slope ≥ 55°, a Φ48mm oblique steel anchor pipe is adopted. At each erection position of the vertical pole 301 of the slope 001, a φ55mm anchor pipe pre-buried hole is drilled in advance with a down-the-hole drill. After the first steel anchor pipe 200 is inserted, neat cement slurry (the water-cement ratio is controlled at 0.37 - 0.4:1) is injected into the hole for anchoring, and the effective rock-anchoring depth is not less than 2m.

[0039] The bottom of the first steel anchor pipe 200 and the vertical pole 301 is connected by fasteners, and the fasteners are of two types: cross fasteners and ring fasteners.

[0040] To ensure the stability of the vertical poles 301 of the framework 300, the connection part of the first steel anchor pipe 200 and the vertical pole 301 is as close as possible to the rock surface of the slope 001. At the same time, a cross bar 302 is added at a position 20 cm above the connection part of the vertical pole 301 and the first steel anchor pipe 200, and the added cross bar 302 and the vertical pole 301 are also connected by fasteners.

[0041] Refer to Figure 3 For a slope 001 with a gradient < 55°, the first steel anchor pipe 200 is a vertical anchor pipe with a diameter of φ28 mm vertically fixed on the slope 001. The rock-anchoring depth of the first steel anchor pipe 200 is not less than 2 m. The first steel anchor pipe 200 is anchored by a cement cartridge anchoring agent. The bottom of the vertical pole 301 of the framework 300 is inserted into the first steel anchor pipe 200, and the inserted length of the bottom of the vertical pole 301 is not less than 0.5 m. At the same time, it is ensured that the apron width (i.e., the horizontal distance between the bottom of the first steel anchor pipe 200 and the slope 001) is not less than 0.5 m. When the apron width does not meet the requirements, the first steel anchor pipe 200 should be lengthened.

[0042] Refer to Figure 2 To prevent the vertical poles 301 of the framework 300 from having vertical slip, in some embodiments, the construction scaffolding structure for the high-steep slope 001 protection project further includes steel anchor bolts 400. The steel anchor bolts 400 are fixed on the slope 001, and the section of the steel anchor bolts 400 extending out of the slope 001 is bent upward. The steel anchor bolts 400 are located below the first steel anchor pipe 200, and the bottom end of the vertical pole 301 of the framework 300 close to the slope 001 is sleeved on the bent section of the steel anchor bolts 400.

[0043] Specifically, steel anchor bolts 400 with a diameter of φ28 mm are added at the contact position between the bottom of the vertical pole 301 and the rock surface. The steel anchor bolts 400 are anchored to the slope 001 by a cement cartridge anchoring agent, and the effective anchoring depth is not less than 50 cm. The length of the steel anchor bolts 400 inserted into the vertical pole 301 is not less than 30 cm.

[0044] In some embodiments, the construction scaffolding structure for the high-steep slope 001 protection project further includes a second steel anchor pipe 500. The second steel anchor pipe 500 is obliquely fixed on the slope 001, and the section of the second steel anchor pipe 500 extending out of the slope 001 is inclined upward. The second steel anchor pipe 500 is connected to the vertical pole 301 of the nearest framework 300 through a connector 501. The connectivity between the framework 300 and the slope 001 is further improved.

[0045] Specifically, the second steel anchor pipe 500 is a Φ28mm anchor pipe anchored on the rock mass of the anchored slope 001. The second steel anchor pipe 500 is anchored to the mountain body using a cement cartridge anchoring agent, and the effective rock penetration depth is not less than 2m. The end of the second steel anchor pipe 500 extending out of the slope 001 is provided with an elbow with a length of 30cm, and the elbow angle is controlled at 45° to 60°. When installing the second steel anchor pipe 500, the elbow faces upward to facilitate the fixing of the connecting piece 501.

[0046] The connecting piece 501 includes a steel wire rope and a turnbuckle. The second steel anchor pipe 500 and the vertical pole 301 are connected by a steel wire rope and a turnbuckle. The connecting piece 501 is fixed by upward diagonal tension, and the diagonal tension angle is controlled at 45°, so that the frame body 300 and the second steel anchor pipe 500 are connected into a whole, playing a role in sectional unloading and preventing the scaffold from overturning outward under the action of the impact reaction force of the drill.

[0047] In this application, the depths of the first steel anchor pipe 200 and the second steel anchor pipe 500 anchored in the slope 001 are greater than 2 meters.

[0048] Refer to Figure 3 , in some embodiments, a bottom bar 600 close to the slope 001 is provided on the frame body 300, and the bottom bar 600 is connected to each first steel anchor pipe 200. Specifically, the bottom bar 600 is connected to each first steel anchor pipe 200 through a fastener, thereby further improving the stability of the frame body 300 on the slope 001.

[0049] To ensure that the safety reserve of the cantilever platform 100 meets the requirements, one end of the cantilever platform 100 far from the slope 001 is connected to the slope 001 through multiple stay cables 101.

[0050] Specifically, the stay cable 101 uses a φ20 stay steel wire rope to anchor the cantilever platform 100 to the slope 001. One end of the stay cable 101 is anchored in the slope 001 above the cantilever platform 100 by setting a ground anchor (anchored with a φ28 anchor rod + cement cartridge anchoring agent, and the rock anchoring depth is not less than 2m), and the other end is set at the end of the cantilever platform 100, and the angle is controlled at about 45°. The stay cable 101 plays a role in restricting the deformation of the end of the cantilever platform 100, thereby increasing the overall stability of the cantilever structure.

[0051] Refer to Figure 4 , Figure 5 , Figure 6 , in some embodiments, the cantilever platform 100 includes multiple cantilever brackets 110, and each cantilever bracket 110 is arranged side by side at intervals, and the cantilever brackets 110 are connected by longitudinal I-beams 120.

[0052] In some other embodiments, the cantilever support 110 includes a horizontal I-beam 111, a diagonal bracing I-beam 112, an I-beam hinge socket 113, and an I-beam reinforcing rod 114. The I-beam hinge socket 113 is provided with an I-beam slot 1131 and a rotating shaft seat 1132. The end of the diagonal bracing I-beam 112 is connected to the horizontal I-beam 111 through the I-beam hinge socket 113. The middle parts of both the horizontal I-beam 111 and the diagonal bracing I-beam 112 are sleeved with the I-beam hinge socket 113, and the rotating shaft seats 1132 between the two I-beam sockets are connected through the I-beam reinforcing rod 114.

[0053] Specifically, the cantilever platform 100 adopts a triangular bracket support form and is made of two I12 I-beams. One is horizontally arranged, namely the horizontal I-beam 111, and the other is obliquely arranged, namely the diagonal bracing I-beam 112. The inclination angle of the diagonal bracing I-beam 112 is 30°. The anchoring depth of the horizontal I-beam 111 in the slope 001 is 2 m, and the cantilever length is 4.5 m. The anchoring depth of the diagonal bracing I-beam 112 in the slope 001 is 1.5 m, and the cantilever length is 3.69 m.

[0054] The middle parts of both the horizontal I-beam 111 and the diagonal bracing I-beam 112 are sleeved with the I-beam hinge socket 113. The two ends of the I-beam reinforcing rod 114 are respectively connected to the rotating shaft seats 1132 of the two I-beam hinge sockets through rotating shafts, realizing the connection between the two I-beams. It should be noted that during the installation process, a part of the I-beam flange at both ends of the I-beam reinforcing rod 500 needs to be cut to prevent interference when the I-beam reinforcing rod 500 rotates.

[0055] In addition, the end of the diagonal bracing I-beam 112 is also connected to the horizontal I-beam 111 through the I-beam hinge socket 113. Specifically, the I-beam hinge socket 1 is sleeved on the horizontal I-beam 300, and the rotating shaft seat 200 on the I-beam hinge socket 1 is rotatably connected to the end of the diagonal bracing I-beam 400 through a rotating shaft. It should be noted that during the installation process, a part of the I-beam flange at the end of the diagonal bracing I-beam 400 needs to be cut to prevent interference when connecting to the rotating shaft seat 200.

[0056] The overall structure of the cantilever support 110 in this application is a detachable structure, eliminating the use of welded connection forms and facilitating subsequent disassembly, assembly, and recycling.

[0057] In the present application, the horizontal I-beam 111 includes a horizontal anchoring section and a horizontal cantilever section, and the diagonal bracing I-beam 112 includes a diagonal anchoring section and a diagonal cantilever section. The horizontal anchoring section is completely embedded inside the slope 001, and only its end is exposed on the slope 001. A first horizontal connecting plate is provided at the end of the horizontal anchoring section that is exposed on the slope 001, and a first horizontal connecting hole is opened on the first horizontal connecting plate. Similarly, the diagonal anchoring section is completely embedded inside the slope 001, and only its end is exposed on the slope 001. A first diagonal connecting plate is provided at the end of the diagonal anchoring section that is exposed on the slope 001, and a first diagonal connecting hole is opened on the diagonal connecting plate. The tail end of the horizontal cantilever section is provided with a corresponding second horizontal connecting plate, and a second horizontal connecting hole is opened on the second horizontal connecting plate. The tail end of the diagonal cantilever section is provided with a corresponding second diagonal connecting plate, and a second diagonal connecting hole is opened on the second diagonal connecting plate. When installing the cantilever support 110, the second horizontal connecting plate at the tail end of the horizontal cantilever section is connected to the first horizontal connecting plate by a connecting bolt, and the second diagonal connecting plate at the tail end of the diagonal cantilever section is connected to the first diagonal connecting plate by a connecting bolt, realizing the installation of the cantilever support 110 on the slope 001. This installation method uses a detachable connection method, which is convenient for subsequent disassembly and reuse.

[0058] Refer to Figure 5 、 Figure 6 In order to make the I-beam hinge bushing 113 firmly connected to the I-beam, in some embodiments, a limiting hole 1133 is provided on the I-beam hinge bushing 113. The limiting hole 1133 leads to the waist of the I-beam slot 1131, and a fastening member 1134 is used for connection in the limiting hole 1133.

[0059] Specifically, the limiting hole 1133 is horizontally opened in the middle of the I-beam hinge bushing 113 and communicates with the waist of the I-beam slot 1131. The inner wall of the limiting hole 1133 is provided with internal threads, and the fastening member 1134 is a fastening bolt. After the I-beam hinge bushing 113 is sleeved on the I-beam, the fastening member 1134 is rotated in the limiting hole 1133 to connect the I-beam and the I-beam hinge bushing 113.

[0060] In some embodiments, a plurality of support channel steels 115 are installed on the cantilever platform 100, and the bottom of the vertical pole 301 of the frame body 300 is supported in the support channel steels 115.

[0061] Specifically, the support channel steels 115 are arranged at intervals along the length direction of the horizontal I-beam 111. Each support channel steel 115 is connected to the horizontal I-beam 111 of each cantilever bracket 110. The 8# support channel steels 115 are arranged longitudinally on the upper part of the horizontal I-beam 111 of the cantilever platform 100. The openings of the support channel steels 115 face upward and are fixed to the horizontal I-beam 111 by U-shaped steel riding clips. The spacing of the support channel steels 115 is the same as the row spacing of the scaffolding vertical poles 301, ensuring that the scaffolding vertical poles 301 stand inside the channel steel and serve as the load-bearing members of the scaffolding while playing a role in anti-slip.

[0062] In the description of this specification, the description with reference to terms such as "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials, or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the embodiments of this application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described can be combined in a suitable manner in any one or more embodiments or examples. In addition, without contradiction, those skilled in the art can combine and combine the different embodiments or examples described in this specification and the features of different embodiments or examples.

[0063] The embodiments of the present application have been described in detail above in conjunction with the accompanying drawings. However, the present application is not limited to the above embodiments. Various changes can be made without departing from the spirit of the present application within the scope of knowledge possessed by those of ordinary skill in the art.

Claims

1. A construction scaffolding structure for high-steep slope protection project, characterized in that, including a cantilever platform, which is fixed on the slope; a first steel anchor pipe. For a slope with an inclination greater than 55°, the first steel anchor pipe is obliquely fixed on the slope so that the section of the first steel anchor pipe extending out of the slope inclines upward. For a slope with an inclination less than 55°, the first steel anchor pipe is vertically fixed on the slope; a framework, the vertical poles of the framework are supported on the cantilever platform, and the bottom of the vertical poles of the framework close to the slope is connected to the first steel anchor pipe.

2. The construction scaffolding structure for high and steep slope protection project according to claim 1, characterized in that: The construction scaffolding structure for high-steep slope protection project further includes a second steel anchor pipe, which is obliquely fixed on the slope, and the section of the second steel anchor pipe extending out of the slope inclines upward. The second steel anchor pipe is connected to the vertical pole of the nearest framework through a connecting piece.

3. The construction scaffolding structure for high-steep slope protection project according to claim 2, characterized in that: The depth of the first steel anchor pipe and the second steel anchor pipe anchored in the slope is greater than 2 meters.

4. The construction scaffolding structure for high and steep slope protection project according to claim 1, characterized in that: The construction scaffolding structure for high-steep slope protection project further includes a steel anchor rod, which is fixed on the slope, and the section of the steel anchor rod extending out of the slope bends upward. The steel anchor rod is located below the first steel anchor pipe, and the bottom end of the vertical pole of the framework close to the slope is sleeved on the bent section of the steel anchor rod.

5. The construction scaffolding structure for high and steep slope protection project according to claim 1, characterized in that: A bottom bar close to the slope is provided on the framework, and the bottom bar is connected to each of the first steel anchor pipes.

6. The construction scaffolding structure for high and steep slope protection project according to claim 1, wherein: One end of the cantilever platform far from the slope is connected to the slope through multiple stay cables.

7. The construction scaffolding structure for high and steep slope protection project according to claim 6, characterized in that: The cantilever platform includes multiple cantilever brackets, and the cantilever brackets are arranged side by side at intervals. The cantilever brackets are connected by longitudinal I-beams.

8. The construction scaffolding structure for high-steep slope protection project according to claim 7, characterized in that: The cantilever bracket includes a horizontal I-beam, a diagonal bracing I-beam, an I-beam articulated socket, and an I-beam reinforcing rod. The I-beam articulated socket is provided with an I-beam slot, and the I-beam articulated socket is provided with a rotating shaft seat. The end of the diagonal bracing I-beam is connected to the horizontal I-beam through the I-beam articulated socket. The middle parts of the horizontal I-beam and the diagonal bracing I-beam are both sleeved with the I-beam articulated socket, and the rotating shaft seats between the two I-beam sockets are connected by the I-beam reinforcing rod.

9. The construction scaffolding structure for high and steep slope protection project according to claim 8, characterized in that: The I-beam articulated socket is provided with a limiting hole, the limiting hole leads to the waist of the I-beam slot, and fasteners are used to be connected in the limiting hole.

10. The construction scaffolding structure for high and steep slope protection project according to claim 8, characterized in that: Multiple support channel steels are installed on the cantilever platform, and the bottom of the vertical pole of the framework is supported in the support channel steels.