Equipment foundation bolt mounting device

The corrugated tube device for foundation bolts allows precise alignment of equipment bolts, addressing misalignment issues and ensuring efficient installation without re-drilling, thus improving construction efficiency and foundation quality.

CN223105665UActive Publication Date: 2025-07-15CHINA MCC22 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422530569.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-10-18
Publication Date
2025-07-15
Estimated Expiration
2034-10-18

AI Technical Summary

Technical Problem

In the context of construction engineering, particularly in the metallurgical industry, there are issues with misaligned pre-buried foundation bolts for equipment, leading to incomplete installations, which cause delays and waste of resources, and can damage the concrete foundation quality.

Method used

A device for installing equipment foundation bolts includes a corrugated tube with adjustable features, equipped with a top and bottom cap, and a split hydraulic jack for fine-tuning the bolt position, allowing precise alignment before concrete pouring.

Benefits of technology

This solution ensures accurate bolt positioning, reducing the need for re-drilling and minimizing delays, thereby enhancing installation efficiency and maintaining foundation integrity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223105665U_ABST
    Figure CN223105665U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of foundation bolt construction in civil engineering, in particular to an equipment foundation bolt mounting device which comprises a corrugated pipe embedded in a primary structural layer together with a foundation bolt, an upper sealing cover with a hole in the middle is detachably mounted at the top of the corrugated pipe, and a lower sealing cover with a hole in the middle is arranged at the bottom of the corrugated pipe. An adjusting hole is formed in the corrugated pipe, and a separating ultrathin jack used for finely adjusting the foundation bolt is arranged in the adjusting hole in a matched mode. The positioning size of the foundation bolt of the forming foundation is measured in advance, the foundation bolt with construction errors is adjusted through the device, it is guaranteed that an equipment hole can be formed in the foundation bolt at a time, the hole re-milling construction procedure is reduced, the construction period is guaranteed, and the equipment installation efficiency is improved; according to the adjustable equipment foundation bolt mounting device, innovativeness and practicability are combined, an excellent solution is provided, and the adjustable equipment foundation bolt mounting device is suitable for large-scale equipment foundation bolt group construction in the engineering field.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of foundation bolt construction technology in civil engineering, in particular to an equipment foundation bolt installation device. Background Art

[0002] At present, the domestic metallurgical industry maintains a high-speed development trend. There is a situation where the metallurgical project construction period is tight, and the quality of equipment installation must be guaranteed at the same time. The equipment level has begun to move towards intelligence on the basis of large-scale and automation, and the equipment installation accuracy requirements are getting higher and higher, which requires the installation technology level of construction companies to improve accordingly.

[0003] However, the anchor bolts may have the problem of pre-embedded position offset, resulting in the equipment not being installed in place. Re-milling the holes will cause construction delays and waste of manpower and material resources, and will also damage the quality of the concrete foundation. Utility Model Content

[0004] In order to solve the above problems existing in the prior art, the utility model provides an equipment anchor bolt installation device.

[0005] The utility model provides an equipment anchor bolt installation device that adopts the following technical solution:

[0006] A device for installing equipment anchor bolts comprises a bellows pre-buried in a primary structural layer together with the anchor bolts, an upper cover with a hole in the middle being detachably mounted on the top of the bellows, a lower cover with a hole in the middle being arranged at the bottom of the bellows, an adjustment hole being formed in the bellows, and a separate ultra-thin jack for fine-tuning the anchor bolts being matched in the adjustment hole.

[0007] By adopting the above technical scheme, by measuring the positioning dimensions of the formed foundation anchor bolts in advance, the device is used to adjust the anchor bolts with construction errors, ensuring that the equipment holes can be installed on the anchor bolts at one time, reducing the re-milling construction process, ensuring the construction period, and improving the efficiency of equipment installation; the adjustable equipment anchor bolt installation device combines innovation and practicality, providing an excellent solution suitable for the construction of large-scale equipment foundation bolt groups in the engineering field.

[0008] Optionally, a primary structural layer protrudes from the top of the bellows, a secondary grouting layer covering and filling the bellows is provided on the top surface of the primary structural layer, and the equipment base is fixed to the top surface of the secondary grouting layer by nuts.

[0009] By adopting the above technical solution, the protrusions and grooves on the surface of the corrugated pipe are easy to be firmly connected with the secondary grouting layer.

[0010] Optionally, the bellows, the upper cover and the lower cover are all made of steel.

[0011] By adopting the above technical solution, it is convenient to obtain materials and fabricate the corrugated pipe, the upper cover and the lower cover.

[0012] Optionally, the upper cover is threadedly installed on the top of the corrugated pipe.

[0013] By adopting the above technical solution, the threaded connection facilitates the installation or disassembly of the upper cover.

[0014] Optionally, the lower cover is threadedly installed on the bottom of the corrugated pipe.

[0015] By adopting the above technical solution, the threaded connection facilitates the installation of the lower cover.

[0016] Optionally, a flame heating device for heating the root of the anchor bolt is fitted inside the adjustment hole.

[0017] By adopting the above technical solution, the fine adjustment of the anchor bolt is facilitated by the heating method.

[0018] In summary, the utility model includes at least one of the following beneficial technical effects:

[0019] 1. By measuring in advance the positioning dimensions of the formed basic anchor bolts and using this device to adjust the anchor bolts with construction errors, it is ensured that the equipment holes can be installed on the anchor bolts at one time, reducing the re-milling construction process, ensuring the construction period, and improving the efficiency of equipment installation;

[0020] 2. The protrusions and grooves on the surface of the corrugated pipe facilitate the firm connection with the secondary grouting layer;

[0021] 3. The threaded connection facilitates the installation or disassembly of the upper cover. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 is a schematic structural view of the equipment anchor bolt installation device according to an embodiment of the utility model Figure 1 .

[0023] Figure 2 is a schematic installation view of the corrugated pipe, the upper cover and the lower cover according to an embodiment of the utility model.

[0024] Figure 3 is a schematic structural view of the equipment anchor bolt installation device according to an embodiment of the utility model Figure 2

[0025] Description of the reference numerals: 1, anchor bolt; 2, corrugated pipe; 20, adjustment hole; 3, upper cover; 4, lower cover; 5, separating ultra-thin jack; 6, secondary grouting layer; 7, equipment base; 8, gasket; 9, nut. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0026] The following is combined with the attached Figure 1 - attachedFigure 3 A further detailed description of the present utility model will be given below.

[0027] An embodiment of the present utility model discloses a device for installing anchor bolts of equipment. Referring to Figure 1 , the device for installing anchor bolts of equipment is used to finely adjust the position of the anchor bolt 1 after the anchor bolt 1 is pre-buried. The upper part of the anchor bolt 1 is wrapped with adhesive tape. The installation device includes a corrugated pipe 2, which is a steel corrugated pipe. It is pre-buried in the concrete of the primary structural layer and its top protrudes 20 mm above the elevation of the primary structural surface. The corrugated pipe 2 is sleeved outside the rod part of the anchor bolt 1 and is coaxially arranged with the anchor bolt 1. An adjustment hole 20 is formed in the corrugated pipe 2, and the adjustment hole 20 provides an operating space for adjusting the positioning of the anchor bolt 1 before equipment installation.

[0028] Referring to Figure 1 and Figure 2 , a steel upper cover 3 is threadedly installed at the top of the corrugated pipe 2. The upper cover 3 is used to prevent concrete from entering the corrugated pipe 2 during concrete pouring due to improper operation, resulting in blockage of the adjustment hole 20. A steel lower cover 4 is threadedly installed at the bottom of the corrugated pipe 2. The lower cover 4 is used to prevent concrete from entering the corrugated pipe 2 due to the gravity of the height difference of the concrete itself during concrete pouring, resulting in blockage of the adjustment hole 20. Holes for the anchor bolt 1 to pass through are respectively formed at the central positions of the upper cover 3 and the lower cover 4.

[0029] Referring to Figure 3 , the corrugated pipe 2 is matched with a split ultra-thin jack 5. When it is necessary to adjust the anchor bolt 1, the construction worker first removes the upper cover 3, heats the root of the anchor bolt 1 with a flame heater, and then uses the split ultra-thin jack 5 in the adjustment hole 20 to adjust the position of the anchor bolt 1 from the root, so as to ensure that the equipment hole can be accurately installed on the anchor bolt 1 and improve the construction efficiency.

[0030] Referring to Figure 1 , a secondary grouting layer 6 with a thickness of 50 mm is constructed on the top of the primary structural layer. The secondary grouting layer 6 completely covers the corrugated pipe 2, and the adjustment hole 20 of the corrugated pipe 2 is simultaneously filled with slurry to fix the anchor bolt 1. An equipment base 7 is placed on the top of the secondary grouting layer 6. The equipment base 7 is installed on the anchor bolt 1, and then the gasket 8 and the nut 9 are installed on the top of the anchor bolt 1 to fix the equipment base 7.

[0031] The implementation principle of the equipment anchor bolt installation device in the embodiment of the present utility model is as follows: The construction workers first embed the anchor bolt 1 and the corrugated pipe 2 with the upper cover 3 and the lower cover 4 into the concrete of the primary structure layer. If the position of the anchor bolt 1 needs to be adjusted, the construction worker removes the upper cover 3, heats the root of the anchor bolt 1 with a flame, and uses the separating ultra-thin jack 5 to push the anchor bolt 1 to achieve the purpose of fine adjustment. Subsequently, the secondary grouting layer 6 is poured, the slurry fills the adjustment hole 20, and finally, the gasket 8 and the nut 9 are used to cooperate with the anchor bolt 1 to fix the equipment base 7.

[0032] By measuring in advance the positioning dimensions of the formed foundation anchor bolt 1 and using this device to adjust the anchor bolt 1 with construction errors, it is ensured that the equipment hole can be installed on the anchor bolt 1 at one time, reducing the construction process of re-milling the hole, ensuring the construction period, and improving the efficiency of equipment installation; The adjustable equipment anchor bolt installation device combines innovation and practicality, providing an excellent solution and is applicable to the construction of large equipment foundation bolt groups in the engineering field.

[0033] The above are all the preferred embodiments of the present utility model, and the protection scope of the present utility model is not limited thereby. Therefore, all equivalent changes made according to the structure, shape, and principle of the present utility model shall be covered within the protection scope of the present utility model.

Claims

1. An installation device for equipment anchor bolts, characterized in that: It includes a corrugated pipe (2) with the same anchor bolts (1) embedded in the primary structure layer. A top cover (3) with a hole in the middle is detachably installed at the top of the corrugated pipe (2), and a bottom cover (4) with a hole in the middle is arranged at the bottom of the corrugated pipe (2). An adjustment hole (20) is formed in the corrugated pipe (2), and a separating ultra-thin jack (5) for finely adjusting the anchor bolt (1) is fitted in the adjustment hole (20).

2. The device for installing the anchor bolts of the equipment according to claim 1, wherein: The top of the corrugated pipe (2) protrudes from the primary structure layer, and a secondary grouting layer (6) covering and filling the corrugated pipe (2) is arranged on the top surface of the primary structure layer. The equipment base (7) is fixed to the top surface of the secondary grouting layer (6) through a nut (9).

3. The device for installing the anchor bolts of the equipment according to claim 1, characterized in that: The corrugated pipe (2), the top cover (3) and the bottom cover (4) are all made of steel.

4. The device for installing anchor bolts of a foundation as claimed in claim 1, wherein: The top cover (3) is threadedly installed at the top of the corrugated pipe (2).

5. The device for installing the anchor bolts of the equipment according to claim 1, characterized in that: The bottom cover (4) is threadedly installed at the bottom of the corrugated pipe (2).

6. The device for installing anchor bolts of a device according to claim 1, wherein: A flame heating device for heating the root of the anchor bolt (1) is fitted in the adjustment hole (20).