Green steel structure fabricated building wall and stand column connecting structure

By using I-steel or square steel columns in prefabricated buildings and combining anchor tension and concrete connections, the problem of insolid connection of traditional prefabricated buildings is solved, and a higher connection strength and aesthetic effect is achieved, and fire-proof and hot-cold bridge avoidance functions are also available.

CN223119295UActive Publication Date: 2025-07-18XIANGWEI HAOFANGFANG ENTERPRISE MANAGEMENT (TONGXU COUNTY) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422386746.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2025-07-18
Estimated Expiration
2034-09-29

AI Technical Summary

Technical Problem

The connections of traditional prefabricated buildings are not firm and are prone to cracks, which affects the safety and durability of the building. The existing improvements include the use of anchor tension ribs with limited length and poor connection effect.

Method used

I-shaped steel or square steel is used as columns, and anchor tensioning ribs are installed on the sides of the surrounding side. The column and the wall are connected by anchor tensioning ribs and concrete to form a closed space. An outer decoration layer is set on the outside and a casting groove is opened at the wall to enhance the connection strength.

Benefits of technology

It improves the connection strength between the wall and the column, extends the service life, beautifies the appearance of the building, avoids cracks caused by insolid connections, and has the effect of fireproofing and hot and cold bridge avoidance of steel structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223119295U_ABST
    Figure CN223119295U_ABST
Patent Text Reader

Abstract

The utility model discloses a green steel structure assembly type building wall body and stand column connecting structure, and relates to the technical field of green assembly type building wall bodies, the green steel structure assembly type building wall body and stand column connecting structure comprises a stand column, a first wall body, a second wall body and a third wall body, the left side and the right side of the stand column are in butt joint with a first wall and a second wall respectively, the side, close to the indoor space, of the stand column is in butt joint with a third wall, the sides, close to the outdoor space, of the first wall and the second wall extend and are connected respectively, and the first wall, the second wall and the third wall define a closed space. The steel structure has the advantages that after the stand columns are made of I-shaped steel and square steel and concrete is poured, the steel structure does not need rust removal, fire retardant coating, a hot and cold bridge avoiding system and the like, the stand columns are wrapped by the concrete, the concrete is connected with the walls in a matched mode through the anchor tie bars and the pouring grooves, and the connection strength between the walls and the stand columns is greatly improved; and the problems of cracks and the like caused by infirm connection are effectively prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabricated building walls, in particular to a connecting structure between a green steel structure prefabricated building wall and a column. Background Art

[0002] In traditional prefabricated building walls, since the load-bearing columns are mostly concrete-cast columns with simple surface shapes, after pouring concrete later, the gripping force between the concrete and the load-bearing columns and the walls is small, and there are often problems such as insecure connection and easy cracking, which affect the overall safety and durability of the building. In the prior art, although there have been some improvement schemes, such as using anchor bars or reinforcing bars, etc., due to the requirements of assembly and installation construction, the length of the anchor bars is fixed, and the biting of the poured concrete is less, and there are still problems such as unsatisfactory connection effect. Content of the Utility Model

[0003] The purpose of the utility model is to provide a connecting structure between a green steel structure prefabricated building wall and a column in order to solve the above problems.

[0004] The utility model realizes the above purpose through the following technical solutions:

[0005] A connecting structure between a green steel structure prefabricated building wall and a column, comprising a column, a first wall, a second wall and a third wall. The column is an I-beam, and anchor bars are fixedly installed on the peripheral side surfaces of the I-beam. The first wall and the second wall are respectively butted on the left and right sides of the column, the third wall is butted on the side of the column close to the indoor side. The first wall and the second wall extend and connect with each other on the side close to the outdoor side, and the first wall, the second wall and the third wall enclose a closed space; the gaps between the column and the first wall, the second wall and the third wall are filled with concrete.

[0006] Preferably: an outer decorative layer is provided on the side surfaces of the first wall and the second wall close to the outdoor side, and a fastener is fixed at the butt joint seam position of the first wall and the second wall.

[0007] Preferably: the outer decorative layer includes an adhesive layer, a thermal insulation layer, a plastering layer and a decorative layer.

[0008] Preferably: the fastener is a decorative part.

[0009] Preferably: a first wall pouring groove is opened at the position of the first wall corresponding to the column, a second wall pouring groove is opened at the position of the second wall corresponding to the column, a third wall pouring groove is opened at the position of the third wall corresponding to the column, and the space formed by the first wall pouring groove, the second wall pouring groove and the third wall pouring groove is filled with concrete.

[0010] Preferably, anchor tie bars are also provided in the first wall casting groove, the second wall casting groove, and the third wall casting groove. One end of the anchor tie bar is embedded in the wall body, and the other end is exposed. The anchor tie bars in the first wall casting groove, the second wall casting groove, and the second wall casting groove do not extend out of the groove.

[0011] Preferably, the column is an I-beam or a square steel.

[0012] Compared with the prior art, the beneficial effects of the present utility model are as follows:

[0013] 1. By wrapping the load-bearing columns on the outer sides of the first wall and the second wall, the connection structure is protected from the external environment, extending its service life.

[0014] 2. By using an I-beam structure for the column, after pouring concrete, the concrete wraps the column and is connected to each wall through the cooperation of the anchor tie bars and each casting groove, greatly improving the connection strength between the wall and the column, and effectively preventing problems such as cracks caused by insecure connection.

[0015] 3. Fixing decorative parts at the joint positions on the outer sides of the first wall and the second wall not only beautifies the building appearance but also effectively covers the defects at the joints, improving the overall aesthetics.

[0016] 4. The steel structure has benefits such as not requiring rust removal, fireproof coatings, and hot and cold bridge avoidance systems. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions in the embodiments of the present utility model or the prior art, the following will briefly introduce the drawings required for use in the description of the embodiments or the prior art. Obviously, the following drawings are only some embodiments of the present utility model. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative efforts.

[0018] Figure 1 It is a top view structural schematic diagram of Embodiment 1 of the connection structure between the wall and the column of a green steel structure prefabricated building described in the present utility model.

[0019] Figure 2 It is a top view structural schematic diagram of Embodiment 2 of the connection structure between the wall and the column of a green steel structure prefabricated building described in the present utility model.

[0020] The reference numerals are explained as follows:

[0021] 1. Column; 2. First wall; 3. Second wall; 4. Third wall; 5. First wall casting groove; 6. Second wall casting groove; 7. Outer decorative layer; 8. Third wall casting groove; 9. Fastener. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0022] In the description of the present utility model, it should be understood that the orientation or positional relationship indicated by the terms "center", "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation to the present utility model. In addition, the terms "first", "second", etc. are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly specifying the quantity of the indicated technical features. Thus, the features defined with "first", "second", etc. may explicitly or implicitly include one or more of such features. In the description of the present utility model, unless otherwise specified, the meaning of "a plurality" is two or more.

[0023] In the description of the present utility model, it should be noted that unless otherwise clearly specified and defined, the terms "installation", "connection", and "coupling" should be understood in a broad sense. For example, it may be a fixed connection, a detachable connection, or an integral connection; it may be a mechanical connection or an electrical connection; it may be directly connected or indirectly connected through an intermediate medium, and it may be the communication inside two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood through specific circumstances.

[0024] The present utility model will be further described below with reference to the drawings:

[0025] Embodiment 1

[0026] As Figure 1 shown, a connection structure between a green steel structure prefabricated building wall and a column includes a column 1, a first wall 2, a second wall 3, and a third wall 4. The first wall 2 and the second wall 3 are respectively butted against the left and right sides of the column 1, the third wall 4 is butted against the side of the column 1 close to the indoor side, the sides of the first wall 2 and the second wall 3 close to the outdoor side are respectively extended and joined, and the first wall 2, the second wall 3, and the third wall 4 enclose a closed space; the gaps between the column 1 and the first wall 2, the second wall 3, and the third wall 4 are filled with concrete. The column 1 is an I-beam, and anchor bars are fixedly installed on the peripheral sides of the I-beam to facilitate the gripping force between the column 1 and the concrete, and the concrete increases the structural strength.

[0027] An exterior decorative layer 7 is provided on the side of the first wall 2 and the second wall 3 close to the outdoor side. The exterior decorative layer 7 includes an adhesive layer, a thermal insulation layer, a plastering layer, and a decorative layer. A fastener 9 is fixed at the butt joint position of the first wall 2 and the second wall 3. The fastener 9 is a decorative part, which protects the butt joint and makes the appearance more beautiful.

[0028] A first wall casting groove 5 is provided at the position of the first wall 2 corresponding to the column 1, a second wall casting groove 6 is provided at the position of the second wall 3 corresponding to the column 1, and a third wall casting groove 8 is provided at the position of the third wall 4 corresponding to the column 1. Concrete is cast in the space formed by the first wall casting groove 5, the second wall casting groove 6, and the third wall casting groove 8.

[0029] Anchoring bars are also provided in the first wall casting groove 5, the second wall casting groove 6, and the third wall casting groove 8. One end of the anchoring bar is embedded in the wall body and the other end is exposed. After casting the concrete, the connection with the wall body is ensured. The anchoring bars in the first wall casting groove 5, the second wall casting groove 6, and the second wall casting groove 6 do not extend out of the groove to avoid being affected during assembly.

[0030] Embodiment 2

[0031] As Figure 2 shown, the difference between this embodiment and Embodiment 1 is that the column 1 is a square steel.

[0032] The exterior decorative layer 7, the decorative part, the anchoring bar, and the I-beam are all general standard parts or parts known to those skilled in the art. Their structures and principles can be known to those skilled in the art through technical manuals or obtained through conventional experimental methods. Therefore, no more records will be made here.

[0033] The above shows and describes the basic principles, main features, and advantages of the present invention. Those skilled in the art of this industry should understand that the present invention is not limited by the above embodiments. What is described in the above embodiments and the specification only illustrates the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention will have various changes and improvements, and these changes and improvements all fall within the scope of the present invention claimed.

Claims

1. A connecting structure between a wall and a column of a green steel structure prefabricated building, comprising a column (1), a first wall (2), a second wall (3) and a third wall (4), characterized in that: Anchorage bars are fixedly installed on the four side surfaces around the column (1). The first wall (2) and the second wall (3) are respectively butted at the left and right positions of the column (1), and the third wall (4) is butted on the side of the column (1) close to the interior. The first wall (2) and the second wall (3) extend and connect to each other on the side close to the exterior. The first wall (2), the second wall (3) and the third wall (4) enclose a closed space; the gaps between the column (1) and the first wall (2), the second wall (3) and the third wall (4) are filled with concrete.

2. The connecting structure between the prefabricated building wall and the column according to claim 1, characterized in that: An exterior decoration layer (7) is provided on the side surfaces of the first wall (2) and the second wall (3) close to the exterior, and a fastener (9) is fixed at the butting joint position of the first wall (2) and the second wall (3).

3. The connecting structure between the prefabricated building wall and the column according to claim 2, characterized in that: The exterior decoration layer (7) includes an adhesive layer, a thermal insulation layer, a plastering layer and a decorative layer.

4. The connecting structure between the prefabricated building wall and the column according to claim 2, characterized in that: The fastener (9) is a decorative part.

5. The connecting structure between the prefabricated building wall and the column according to claim 1, characterized in that: A first wall casting groove (5) is formed at the position of the first wall (2) corresponding to the column (1), a second wall casting groove (6) is formed at the position of the second wall (3) corresponding to the column (1), and a third wall casting groove (8) is formed at the position of the third wall (4) corresponding to the column (1). The space formed by the first wall casting groove (5), the second wall casting groove (6) and the third wall casting groove (8) is filled with concrete.

6. The connecting structure between the prefabricated building wall and the column according to claim 5, characterized in that: Anchorage bars are also provided in the first wall casting groove (5), the second wall casting groove (6) and the third wall casting groove (8). One end of each anchorage bar is embedded in the wall and the other end is exposed. The anchorage bars in the first wall casting groove (5), the second wall casting groove (6) and the second wall casting groove (6) do not extend out of the groove.

7. The connecting structure between the prefabricated building wall and the column according to claim 1, characterized in that: The column (1) is an I-beam or a square steel.