Hybrid assembly type beam and floor formwork system structure
Through the mixed prefabricated beam and floor formwork architecture, and the use of pins and pins to connect the formwork, the installation difficulty and material cost of aluminum formwork in non-standard layer construction is solved, and the rapid and effective formwork setting and quality assurance is achieved.
Patent Information
- Application Number
- CN202422320911.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-23
- Publication Date
- 2025-07-18
- Estimated Expiration
- 2034-09-23
AI Technical Summary
The existing aluminum formwork is difficult to dismantle, transport and install during non-standard layer construction, resulting in slow construction speed, high material cost, and easy leaching of concrete slurry from the joints, affecting the quality of the project.
A hybrid prefabricated beam and floor formwork architecture is adopted, including a beam formwork system and a floor formwork system. Each formwork is connected through pins and pins to form a combination of standard and non-standard formwork to reduce the type of formwork and installation difficulty.
On the premise of ensuring the casting effect, the difficulty of formwork installation, disassembly and transfer installation is reduced, the cost of formwork materials is reduced, and the construction speed and project quality is improved.
Smart Images

Figure CN223119506U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of material fittings for formwork engineering in building construction, and more specifically to a hybrid prefabricated beam and floor formwork system structure. Background Art
[0002] Since the traditional aluminum formwork (metal formwork) began to be popularized and used in the standard floors of residential buildings in China in 2008, because it can better meet the quality requirements of the concrete structures of beams, slabs, walls and columns without plastering, and most of the node structures such as doors and windows that originally required secondary pouring can be poured at one time and meet the quality requirements without plastering, so up to now, aluminum formwork has been used for pouring in many standard floors above 25 floors.
[0003] Due to the requirement of using an all-aluminum structure, more than 300 strictly numbered modular aluminum formworks were initially introduced. The pre-assembly in the factory and the first assembly on the project each took more than 15 days. With gradual optimization and improvement, the number of modular categories of aluminum formworks has now been reduced to more than 200. Also, in the factory, computer software pre-assembly is used to replace on-site pre-assembly of aluminum formworks, and the first assembly time of aluminum formworks on the construction site has been reduced to about 7 days. However, until now, due to the use of an all-aluminum (metal) prefabricated formwork structure and an independent steel support and early removal and dot support structure, it is necessary to install, remove, and transport and install strictly according to the formwork number. In the construction of standard floors above the 25th floor, as long as the workers are not replaced, the construction speed and so on can be guaranteed; if the workers are replaced, it is only necessary to construct strictly according to the number. The impact on the construction speed is only in the 2 - 5 floors during the familiarization stage, and the construction speed can basically be guaranteed; but in the construction of non-standard floors such as basements and podium buildings, due to the changes in the structure, design dimensions, positions, etc. of each construction section, when the formwork is removed and turned over to the next construction section, in order to strictly turn over according to the design number and replace the newly added structural formwork, it is necessary for the technical personnel of the factory to closely cooperate with the on-site management personnel, piecework team leaders, piecework workers, etc. of the carpentry team to carry out the turnover construction better, that is, each turnover installation is equivalent to the first assembly. Moreover, due to the current common savage formwork removal, and the fact that the formwork removal, transportation, and installation workers generally belong to three different types of work in most cases and other comprehensive factors, the difficulty and cost of cleaning, packing according to the number, designing, managing, transporting, and installing after the formwork removal of the non-standard structural floor are high and difficult to reduce, and it is also very difficult to improve the installation speed. During each concrete pouring process, the concrete slurry is very easy to leak out from the joint gaps or the increasingly deep and large scratches caused by multiple formwork removals. Since it is difficult to clean the concrete slurry thoroughly during turnover use, the concrete slurry will gradually accumulate on the formwork surface, making the formwork thicker and larger. After 15 times of turnover use, the structural dimensions of most formworks will become larger and it is difficult to adjust them to the designed structural dimensions, resulting in more and more difficult formwork installation. At the same time, in order to save material costs, the formwork is generally not directly replaced, so more and more grinding and repair costs need to be paid to achieve the quality of plaster-free
[0004] How to improve the product structure, reduce the usage difficulty and usage cost, and at the same time ensure or even improve the project quality is the key research direction of each enterprise. Summary of the Invention
[0005] In view of the deficiencies of the prior art, the present application provides a hybrid prefabricated beam and floor formwork system structure, which can not only ensure the pouring effect, but also greatly reduce the modulus categories of standard beam and slab formwork on the premise of effectively using various non-standard wooden formwork settings. It can also significantly reduce the difficulty of formwork installation, disassembly and transfer installation, and can still quickly and effectively complete the setting of all beam and slab formwork system structures when the size structure of the beam and slab formwork changes greatly. Moreover, all standard formwork meets the use of the entire project, thereby greatly reducing the formwork structure material cost and costs such as packaging, design and management, and well promoting the development and progress of the industry.
[0006] A hybrid prefabricated beam and floor formwork system structure is arranged on the supporting vertical column system structure and is connected to the wall and column formwork system structure on the periphery, and includes a beam formwork system structure and a floor slab formwork system structure that are connected to each other; the beam formwork system structure and the floor slab formwork system structure are arranged at intervals.
[0007] Further, the beam formwork system structure is composed of a beam bottom formwork system and one or two beam side formwork systems connected to the beam bottom formwork system through corner L-shaped strips; the beam bottom formwork system is perpendicular to the beam side formwork system.
[0008] Still further, the beam bottom formwork system is composed of a beam bottom standard formwork structure composed of several sequentially connected beam bottom standard prefabricated formworks, and two beam bottom non-standard formworks respectively arranged at the front and rear ends of the standard formwork structure.
[0009] Preferably, the beam bottom non-standard formwork is composed of a first wooden board body, first L-shaped edge strips symmetrically arranged on the left and right sides of the back of the first wooden board body, and first L-shaped connectors symmetrically arranged on the front and rear sides of the back of the first wooden board body and located between the two first L-shaped edge strips; a plurality of pin holes are arranged on both the first L-shaped edge strips and the first L-shaped connectors; reinforcing pieces are respectively arranged at the two ends of the first L-shaped edge strips and the first L-shaped connectors.
[0010] The beam bottom non-standard formwork and the beam bottom standard prefabricated formwork are fixed together by pins and washers that simultaneously penetrate the pin holes on the first L-shaped connectors and the pin holes on the beam bottom standard prefabricated formwork.
[0011] Furthermore, the beam side formwork system is composed of several columns of beam side standard formwork structures composed of at least one beam side standard prefabricated formwork, beam side non-standard formworks arranged between any two columns of beam side standard formwork structures, and corner connection structures arranged above the beam side standard formwork structures and the beam side non-standard formworks; the corner connection structures are composed of several sequentially connected C-shaped grooves and non-standard L-shaped blocks arranged between any two adjacent C-shaped grooves.
[0012] Preferably, the non-standard formwork on the beam side consists of a second wooden board body, second L-shaped side strips symmetrically arranged on the left and right side edges of the back surface of the second wooden board body, and second L-shaped connectors symmetrically arranged on the upper and lower side edges of the back surface of the second wooden board body and located between the two second L-shaped side strips; a plurality of pin holes are provided on both the second L-shaped side strips and the second L-shaped connectors; reinforcing pieces are respectively provided at the two end portions of the second L-shaped side strips and the second L-shaped connectors.
[0013] The non-standard formwork on the beam side and the standard prefabricated formwork on the beam side are fixed together by pins and washers that simultaneously penetrate the pin holes on the second L-shaped side strips and the pin holes on the standard prefabricated formwork on the beam side.
[0014] Preferably, the C-shaped groove consists of an L-shaped back plate, two end L-shaped plates arranged in parallel at both ends of the L-shaped back plate, two connecting pieces respectively arranged on the upper end surface and the front end surface of the L-shaped back plate and fixed to the upper end surfaces and the front end surfaces of the two end L-shaped plates respectively, and a plurality of reinforcing L-shaped plates arranged on the L-shaped back plate and parallel to the end L-shaped plates; pin holes are provided on both the end L-shaped plates and the connecting pieces.
[0015] Preferably, the non-standard L-shaped block consists of an L-shaped wooden board, two L-shaped fixing pieces arranged at both ends of the L-shaped wooden board and fixed to the L-shaped wooden board by screws or screw assemblies respectively, two end connecting pieces respectively vertically arranged on the L-shaped fixing pieces and flush with the upper and front edges of the L-shaped wooden board respectively, and side reinforcing connecting pieces flush with both ends of the L-shaped wooden board and fixed to the L-shaped fixing pieces and the end connecting pieces; pin holes are provided on both the end connecting pieces and the side reinforcing connecting pieces.
[0016] The non-standard L-shaped block and the C-shaped groove are fixed together by pins and washers that simultaneously penetrate the pin slots on the end L-shaped plates and the pin slots on the side reinforcing connecting pieces.
[0017] Furthermore, the floor slab formwork system structure consists of several columns of floor slab standard formwork structures composed of at least one floor slab standard prefabricated formwork, a row of non-standard vertical formwork structures composed of at least one floor slab non-standard formwork arranged between any two columns of floor slab standard formwork structures, and a row of non-standard vertical formwork structures composed of at least one floor slab non-standard formwork arranged at the front end or the rear end of the floor slab standard formwork structure and the non-standard vertical formwork structure.
[0018] Preferably, the floor slab non-standard formwork consists of a third wooden board body, two reinforcing square tubes arranged on the long side edge of the back surface of the third wooden board body, a plurality of L-shaped hinges arranged in rows on the back surface of the third wooden board body and attached to the reinforcing square tubes, and a third L-shaped connector arranged on the short side edge of the back surface of the third wooden board body and located between the two reinforcing square tubes.
[0019] The reinforcing square pipe, the L-shaped hinge, and the third L-shaped connector are all provided with pin holes; two reinforcing pieces are respectively arranged at both ends of the third L-shaped connector.
[0020] The non-standard formwork of the floor slab and the standard prefabricated formwork of the floor slab are fixed together by pins and washers that simultaneously penetrate the pin holes on the L-shaped hinge, the pin holes on the reinforcing square pipe, and the pin holes on the standard prefabricated formwork of the floor slab.
[0021] Compared with the prior art, the embodiments of the present application have the following beneficial effects:
[0022] The present invention can not only ensure the pouring effect, but also greatly reduce the modulus categories of the standard beam and slab formwork on the premise of effectively using various non-standard wooden formworks. It can also greatly reduce the difficulty of formwork installation, disassembly, and transfer and reinstallation. Moreover, when the size and structure of the beam and slab formwork change greatly, it can still quickly and effectively complete the setting of all beam and slab formwork system structures, and all standard formworks meet the use requirements of the entire project. Thus, it greatly reduces the formwork structure material cost, as well as the costs of packing, design, management, etc., and promotes the development and progress of the industry well.
[0023] Some additional features of the present application can be described below. Through the inspection of the following description and the corresponding drawings, or the understanding of the production or operation of the embodiments, some additional features of the present application are obvious to those skilled in the art. The features disclosed in the present application can be realized and achieved through the practice or use of various methods, means, and combinations of the specific embodiments described below. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The drawings described herein are used to provide a further understanding of the present application, and constitute a part of the present application. The schematic embodiments of the present application and their descriptions are used to explain the present application, and do not constitute a limitation to the present application. In each figure, the same reference numerals represent the same components. Among them,
[0025] Figure 1 is a schematic structural diagram of the present invention.
[0026] Figure 2 is a bottom view of the present invention after removing the support vertical rod system structure.
[0027] Figure 3 is a perspective view of the beam formwork system structure of the present invention.
[0028] Figure 4 is a schematic structural diagram of the beam bottom formwork system of the present invention.
[0029] Figure 5 is a schematic structural diagram of the non-standard beam bottom formwork of the present invention.
[0030] Figure 6This is a schematic structural diagram of the side formwork system of the beam of the present invention.
[0031] Figure 7 This is a schematic structural diagram of the non-standard formwork of the beam side of the present invention.
[0032] Figure 8 This is a schematic structural diagram of the C-shaped groove of the present invention.
[0033] Figure 9 This is a schematic structural diagram of the non-standard L-shaped block of the present invention.
[0034] Figure 10 This is a schematic structural diagram of the floor slab formwork system structure of the present invention
[0035] Figure 11 This is a schematic structural diagram of the non-standard floor formwork of the present invention.
[0036] Explanation of reference numerals: 1000, support vertical rod system structure; 2000, beam formwork system structure; 2100, beam bottom formwork system; 2110, standard prefabricated beam bottom formwork; 2120, non-standard beam bottom formwork; 2121, first wooden board body; 2122, first L-shaped side strip; 2123, first L-shaped connector; 2200, beam side formwork system; 2210, standard prefabricated beam side formwork; 2220, non-standard beam side formwork; 2221, second wooden board body; 2222, second L-shaped side strip; 2223, second L-shaped connector; 2230, C-shaped groove; 2231, L-shaped back plate; 2232, end L plate; 2233, connecting piece; 2234, reinforcing L plate; 2240, non-standard L-shaped block; 2241, L-shaped wooden board; 2242, L-shaped fixing piece; 2243, end connecting piece; 2244, side reinforcement connecting piece; 2300, corner L strip; 3000, floor slab formwork system structure; 3010, standard prefabricated floor slab formwork; 3020, non-standard floor slab formwork; 3021, third wooden board body; 3022, L-shaped hinge; 3023, reinforcing square pipe; 3024, third L-shaped connector. Detailed implementation manners
[0037] In order to enable those skilled in the art to better understand the solution of this application, the technical solutions in the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings in the embodiments of this application. Obviously, the described embodiments are only a part of the embodiments of this application, rather than all the embodiments. Based on the embodiments in this application, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of this application.
[0038] It should be noted that if terms such as "first", "second", etc. are involved in the description, claims, and the above-mentioned drawings of this application, they are used to distinguish similar objects and do not necessarily describe a specific order or sequence. It should be understood that such data can be interchanged under appropriate circumstances for the embodiments of this application described herein. In addition, if terms such as "comprising", "having", and any variations thereof are involved, they are intended to cover non-exclusive inclusion. For example, a process, method, system, product, or device that comprises a series of steps or units does not necessarily limit to those steps or units clearly listed, but may include other steps or units not clearly listed or inherent to these processes, methods, products, or devices.
[0039] In this application, if terms such as "upper", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal", etc. are involved, the orientation or positional relationship indicated is based on the orientation or positional relationship shown in the drawings. These terms are mainly used to better describe this application and its embodiments, and are not used to limit that the indicated devices, elements, or components must have a specific orientation or be constructed and operated in a specific orientation.
[0040] Moreover, in addition to being able to represent an orientation or positional relationship, some of the above terms may also be used to represent other meanings. For example, the term "upper" may also be used to represent a certain attachment relationship or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.
[0041] In addition, in this application, if terms such as "installed", "set up", "provided with", "connected", "linked", "socketed", etc. are involved, they should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or there can also be internal communication between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0042] It should be noted that without conflict, the embodiments in this application and the features in the embodiments can be combined with each other. The following will detail this application with reference to the drawings and in combination with embodiments.
[0043] Embodiment 1
[0044] As Figure 1 , 2As shown in the figure, a hybrid prefabricated beam and floor formwork system structure is arranged on the support vertical rod system structure 1000 and is connected to the wall column formwork system structure at the periphery, and includes a beam formwork system structure 2000 and a floor slab formwork system structure 3000 that are connected to each other; the beam formwork system structure 2000 and the floor slab formwork system structure 3000 are arranged at intervals.
[0045] As Figure 3 shown in the figure, the beam formwork system structure 2000 is composed of a beam bottom formwork system 2100 and one or two beam side formwork systems 2200 connected to the beam bottom formwork system 2100 through corner L-shaped bars 2300; the beam bottom formwork system 2100 is perpendicular to the beam side formwork system 2200.
[0046] The corner L-shaped bar is the commonly used L-shaped angle steel in the art, and it is fixed to the adjacent structure through a pin and a washer. This structure is the prior art in the art, and those skilled in the art can complete its setting and use without creative labor, so it will not be elaborated here.
[0047] Generally, a beam is composed of a beam bottom formwork system and two beam side formwork systems arranged on both sides of it. However, when sunken pouring is required in positions such as bathrooms, one side of the beam bottom formwork system is connected to the beam side formwork system, and the other side is directly connected to the floor slab formwork system structure.
[0048] As Figure 4 shown in the figure, the beam bottom formwork system 2100 is composed of a beam bottom standard prefabricated formwork structure composed of several successively connected beam bottom standard prefabricated formworks 2110, and two beam bottom non-standard formworks 2120 with the same size respectively arranged at the front and rear ends of the standard formwork structure.
[0049] The beam bottom standard prefabricated formwork, the beam side standard prefabricated formwork, and the floor slab standard prefabricated formwork are all prior art. Generally, they are divided into aluminum formworks, steel frame formworks, high-strength steel formworks, plastic steel formworks, etc. Pin holes are arranged around their frames. Those skilled in the art can complete their setting and use without creative labor, so it will not be elaborated here.
[0050] Since the beam is mainly for support and load-bearing during actual use, two beam bottom non-standard formworks with the same size are respectively arranged at the front and rear of the standard formwork structure in this application. The main purposes are as follows: First, to make the overall force of the beam more uniform during pouring; Second, to make the forces borne by the two beam bottom non-standard formworks basically the same during pouring, so as to effectively avoid different deformations caused by different forces on them; Third, to make the overall force of the formed beam more uniform, and effectively avoid the situation of uneven force of the beam caused by deformation during pouring.
[0051] As Figure 5As shown in the figure, the non-standard formwork 2120 at the bottom of the beam is composed of a first wooden board main body 2121, first L-shaped side strips 2122 symmetrically arranged on the left and right side edges of the back of the first wooden board main body 2121, and first L-shaped connecting heads 2123 symmetrically arranged on the front and back side edges of the back of the first wooden board main body 2121 and located between the two first L-shaped side strips 2122; a number of pin holes are provided on both the first L-shaped side strips 2122 and the first L-shaped connecting heads 2123; a reinforcing piece is respectively provided at both ends of the first L-shaped side strips 2122 and the first L-shaped connecting heads 2123.
[0052] The non-standard formwork 2120 at the bottom of the beam and the standard prefabricated formwork 2110 at the bottom of the beam are fixed together by pins and washers that simultaneously penetrate the pin holes on the first L-shaped connecting heads 2123 and the pin holes on the standard prefabricated formwork 2110 at the bottom of the beam.
[0053] The non-standard formwork at the bottom of the beam and the corner L-bar are fixed together by pins and washers that simultaneously penetrate the pin holes on the first L-shaped side strips and the pin holes on the corner L-bar.
[0054] The first L-shaped side strip, the first L-shaped connecting head, the second L-shaped side strip, the second L-shaped connecting head, the L-shaped hinge, and the third L-shaped connecting head are respectively fixed on the first wooden board main body, the second wooden board main body, and the third wooden board main body by screws or screw assemblies. The setting method is a conventional means in the art, and those skilled in the art can complete its setting without creative labor, so it will not be elaborated here.
[0055] As Figure 6 shown in the figure, the beam side formwork system 2200 is composed of several columns of beam side standard formwork structures each consisting of at least one beam side standard prefabricated formwork 2210, beam side non-standard formworks 2220 arranged between any two columns of beam side standard formwork structures, and corner connection structures arranged above the beam side standard formwork structures and the beam side non-standard formworks 2220; the corner connection structures are composed of several sequentially connected C-shaped grooves 2230 and non-standard L-shaped blocks 2240 arranged between any two adjacent C-shaped grooves 2230.
[0056] As Figure 7 shown in the figure, the beam side non-standard formwork 2220 is composed of a second wooden board main body 2221, second L-shaped side strips 2222 symmetrically arranged on the left and right side edges of the back of the second wooden board main body 2221, and second L-shaped connecting heads 2223 symmetrically arranged on the upper and lower side edges of the back of the second wooden board main body 2221 and located between the two second L-shaped side strips 2222; a number of pin holes are provided on both the second L-shaped side strips 2222 and the second L-shaped connecting heads 2223; a reinforcing piece is respectively provided at both ends of the second L-shaped side strips 2222 and the second L-shaped connecting heads 2223.
[0057] The non-standard formwork 2220 on the side of the beam and the standard prefabricated formwork 2210 on the side of the beam are fixed together by a pin and a washer that simultaneously penetrate the pin holes on the second L-shaped side strip 2222 and the pin holes on the standard prefabricated formwork 2210 on the side of the beam.
[0058] As Figure 8 shown, the C-shaped groove 2230 is composed of an L-shaped back plate 2231, two mutually parallel end L-shaped plates 2232 provided at both ends of the L-shaped back plate 2231, two connecting pieces 2233 respectively provided on the upper end face and the front end face of the L-shaped back plate 2231 and fixed to the upper end faces and the front end faces of the two end L-shaped plates 2232, and a plurality of reinforcing L-shaped plates 2234 that are parallel to the end L-shaped plates 2232 and provided on the L-shaped back plate 2231; pin holes are provided on both the end L-shaped plates 2232 and the connecting pieces 2233.
[0059] The C-shaped groove is an existing technology in the art, and those skilled in the art can complete its setting and use without creative labor, so it will not be elaborated here.
[0060] As Figure 9 shown, the non-standard L-shaped block 2240 is composed of an L-shaped wooden board 2241, two L-shaped fixing pieces 2242 provided at both ends of the L-shaped wooden board 2241 and respectively fixed to the L-shaped wooden board 2241 by screws or screw assemblies, two end connecting pieces 2243 respectively vertically provided on the L-shaped fixing pieces 2242 and flush with the upper end and the front edge of the L-shaped wooden board 2241, and side reinforcing connecting pieces 2244 that are flush with both ends of the L-shaped wooden board 2241 and fixed together with the L-shaped fixing pieces 2242 and the end connecting pieces 2243; pin holes are provided on both the end connecting pieces 2243 and the side reinforcing connecting pieces 2244;
[0061] The non-standard L-shaped block 2240 and the C-shaped groove 2230 are fixed together by a pin and a washer that simultaneously penetrate the pin slots on the end L-shaped plate 2232 and the pin slots on the side reinforcing connecting piece 2244.
[0062] As Figure 10 shown, the floor slab formwork system structure 3000 is composed of a number of floor slab standard formwork structures each consisting of at least one floor slab standard prefabricated formwork 3010, a non-standard vertical formwork structure consisting of at least one floor slab non-standard formwork 3020 provided between any two columns of floor slab standard formwork structures, and a non-standard vertical formwork structure consisting of at least one floor slab non-standard formwork 3020 provided in a row at the front or rear of the floor slab standard formwork structure and the non-standard vertical formwork structure.
[0063] As Figure 11As shown, the non-standard floor slab formwork 3020 consists of a third wooden board main body 3021, two reinforcing square tubes 3023 arranged on the long edge of the back of the third wooden board main body 3021, several L-shaped hinges 3022 arranged in rows on the back of the third wooden board main body 3021 and attached to the reinforcing square tubes 3023, and a third L-shaped connector 3024 arranged on the short edge of the back of the third wooden board main body 3021 and located between the two reinforcing square tubes 3023;
[0064] In the non-standard floor slab formwork, the use of a reinforcing square tube in combination with an L-shaped hinge replaces the L-shaped edge strip. This not only effectively improves the support performance through the reinforcing square tube but also effectively reduces the overall weight through the L-shaped hinge.
[0065] When the width of the third wooden board main body exceeds 250 mm, a reinforcing square tube spanning its length needs to be provided in the middle of its back to improve the bearing capacity of the non-standard floor slab formwork.
[0066] The reinforcing square tubes 3023, L-shaped hinges 3022, and the third L-shaped connector 3024 are all provided with pin holes; both ends of the third L-shaped connector 3024 are respectively provided with a reinforcing piece;
[0067] The non-standard floor slab formwork 3020 and the standard prefabricated floor slab formwork 3010 are fixed together by pins and washers that simultaneously pass through the pin holes on the L-shaped hinges 3022, the pin holes on the reinforcing square tubes 3023, and the pin holes on the standard prefabricated floor slab formwork 3010.
[0068] The non-standard beam bottom formwork and the non-standard floor slab formwork are fixed together by pins and washers that simultaneously pass through the pin holes on the first L-shaped edge strip and the pin holes on the third L-shaped connector or the pin holes on the L-shaped hinges and the pin holes on the reinforcing square tubes. The non-standard beam bottom formwork and the standard prefabricated floor slab formwork are fixed together by pins and washers that simultaneously pass through the pin holes on the first L-shaped edge strip and the pin holes on the standard prefabricated floor slab formwork. During construction, an L-shaped edge strip can also be used to replace the combination of the reinforcing square tube and the L-shaped hinge, but it is necessary to ensure that the L-shaped edge strip has not undergone any deformation before use to ensure that the L-shaped edge strip can provide sufficient support force, thereby ensuring the safety and quality of the construction.
[0069] The above-mentioned various components are all connected and fixed by pins and washers. The pins and washers are prior art in this field and have been maturely used in this field. Those skilled in the art can complete the use of pins and washers without creative labor and will not be elaborated here.
[0070] In addition, to ensure the accuracy of the fit, the spacing between multiple pin holes at the same position on the same component is set to be a multiple of 50 mm, which not only ensures the fit effect between non-standard structures but also ensures the fit effect between non-standard structures and standard structures.
[0071] It should be noted that all the features disclosed in this specification, or all the steps in the disclosed methods or processes, except for mutually exclusive features and / or steps, can be combined in any way.
[0072] In addition, the above specific embodiments are exemplary. Those skilled in the art can come up with various solutions inspired by the disclosed content of the present invention, and these solutions also fall within the scope of the disclosure of the present invention and the protection scope of the present invention. Those skilled in the art should understand that the description of the present invention and its drawings are illustrative and do not constitute a limitation on the claims. The protection scope of the present invention is defined by the claims and their equivalents.
Claims
1. A hybrid prefabricated beam and floor formwork system structure is arranged on a support vertical rod system structure (1000) and is connected to a wall column formwork system structure at the periphery. It is characterized in that It includes a mutually connected beam formwork system structure (2000) and a floor slab formwork system structure (3000); the beam formwork system structure (2000) and the floor slab formwork system structure (3000) are arranged at intervals.
2. A hybrid prefabricated beam and floor formwork system structure according to claim 1, characterized in that, The beam formwork system structure (2000) is composed of a beam bottom formwork system (2100), and one or two beam side formwork systems (2200) connected to the beam bottom formwork system (2100) through corner L-shaped strips (2300); the beam bottom formwork system (2100) is perpendicular to the beam side formwork system (2200).
3. A hybrid prefabricated beam and floor formwork system structure according to claim 2, characterized in that, The beam bottom formwork system (2100) is composed of a beam bottom standard formwork structure formed by several successively connected beam bottom standard prefabricated formworks (2110), and two beam bottom non-standard formworks (2120) respectively arranged at the front and rear ends of the standard formwork structure.
4. A hybrid prefabricated beam and floor formwork system structure according to claim 3, characterized in that, The beam bottom non-standard formwork (2120) is composed of a first wooden board body (2121), first L-shaped side strips (2122) symmetrically arranged on the left and right side edges of the back of the first wooden board body (2121), and first L-shaped connectors (2123) symmetrically arranged on the front and rear side edges of the back of the first wooden board body (2121) and located between the two first L-shaped side strips (2122); a plurality of pin holes are provided on both the first L-shaped side strips (2122) and the first L-shaped connectors (2123); reinforcing pieces are respectively arranged at both ends of the first L-shaped side strips (2122) and the first L-shaped connectors (2123). The beam bottom non-standard formwork (2120) and the beam bottom standard prefabricated formwork (2110) are fixed together by pins and washers that simultaneously penetrate the pin holes on the first L-shaped connector (2123) and the pin holes on the beam bottom standard prefabricated formwork (2110).
5. A hybrid prefabricated beam and floor formwork system structure according to claim 4, characterized in that, The beam side formwork system (2200) is composed of several columns of beam side standard formwork structures formed by at least one beam side standard prefabricated formwork (2210), beam side non-standard formworks (2220) arranged between any two columns of beam side standard formwork structures, and a corner connection structure arranged above the beam side standard formwork structures and the beam side non-standard formworks (2220); the corner connection structure is composed of several successively connected C-shaped grooves (2230), and non-standard L-shaped blocks (2240) arranged between any two adjacent C-shaped grooves (2230).
6. A hybrid prefabricated beam and floor formwork system structure according to claim 5, characterized in that, The beam side non-standard formwork (2220) is composed of a second wooden board body (2221), second L-shaped side strips (2222) symmetrically arranged on the left and right side edges of the back of the second wooden board body (2221), and second L-shaped connectors (2223) symmetrically arranged on the upper and lower side edges of the back of the second wooden board body (2221) and located between the two second L-shaped side strips (2222); a plurality of pin holes are provided on both the second L-shaped side strips (2222) and the second L-shaped connectors (2223); reinforcing pieces are respectively arranged at both ends of the second L-shaped side strips (2222) and the second L-shaped connectors (2223). The non-standard formwork (2220) on the side of the beam and the standard prefabricated formwork (2210) on the side of the beam are fixed into one body by pins and washers that simultaneously penetrate the pin holes on the second L-shaped side strip (2222) and the pin holes on the standard prefabricated formwork (2210) on the side of the beam.
7. A hybrid prefabricated beam and floor formwork system structure according to claim 6, characterized in that, The C-shaped groove (2230) is composed of an L-shaped back plate (2231), two mutually parallel end L-shaped plates (2232) arranged at both ends of the L-shaped back plate (2231), two connecting pieces (2233) respectively arranged on the upper surface and the front surface of the L-shaped back plate (2231) and fixed to the upper surfaces and the front surfaces of the two end L-shaped plates (2232), and a number of reinforcing L-shaped plates (2234) that are parallel to the end L-shaped plates (2232) and arranged on the L-shaped back plate (2231); pin holes are provided on both the end L-shaped plates (2232) and the connecting pieces (2233).
8. A hybrid prefabricated beam and floor formwork system structure according to claim 7, characterized in that, The non-standard L-shaped block (2240) is composed of an L-shaped wooden board (2241), two L-shaped fixing pieces (2242) arranged at both ends of the L-shaped wooden board (2241) and fixed to the L-shaped wooden board (2241) by screws or screw assemblies respectively, two end connecting pieces (2243) vertically arranged on the L-shaped fixing pieces (2242) and flush with the upper and front edges of the L-shaped wooden board (2241) respectively, and side reinforcing connecting pieces (2244) flush with both ends of the L-shaped wooden board (2241) and fixed to the L-shaped fixing pieces (2242) and the end connecting pieces (2243) as a whole; pin holes are provided on both the end connecting pieces (2243) and the side reinforcing connecting pieces (2244); The non-standard L-shaped block (2240) and the C-shaped groove (2230) are fixed into one body by pins and washers that simultaneously penetrate the pin slots on the end L-shaped plates (2232) and the pin slots on the side reinforcing connecting pieces (2244).
9. A hybrid prefabricated beam and floor formwork system structure according to claim 8, characterized in that, The floor slab formwork system structure (3000) is composed of several columns of floor slab standard formwork structures each consisting of at least one floor slab standard prefabricated formwork (3010), a non-standard vertical formwork structure consisting of at least one floor slab non-standard formwork (3020) arranged in one column between any two columns of floor slab standard formwork structures, and a non-standard vertical formwork structure consisting of at least one floor slab non-standard formwork (3020) arranged in a row at the front or back of the floor slab standard formwork structure and the non-standard vertical formwork structure.
10. A hybrid prefabricated beam and floor formwork system structure according to claim 9, characterized in that, The floor slab non-standard formwork (3020) is composed of a third wooden board body (3021), two reinforcing square tubes (3023) arranged at the long edge of the back surface of the third wooden board body (3021), a number of L-shaped hinges (3022) arranged in rows on the back surface of the third wooden board body (3021) and attached to the reinforcing square tubes (3023), and a third L-shaped connecting head (3024) arranged at the short edge of the back surface of the third wooden board body (3021) and located between the two reinforcing square tubes (3023); The reinforcing square pipe (3023), the L-shaped hinge (3022) and the third L-shaped connector (3024) are all provided with pin holes; both ends of the third L-shaped connector (3024) are respectively provided with a reinforcing piece. The non-standard floor slab formwork (3020) and the standard prefabricated floor slab formwork (3010) are fixed into one body by pins and washers that simultaneously penetrate through the pin holes on the L-shaped hinge (3022), the pin holes on the reinforcing square pipe (3023) and the pin holes on the standard prefabricated floor slab formwork (3010).