Prefabricated stand pipe hoisting alignment fine adjustment structure
Through the combination of lifting devices and automatic telescopic devices, the precise docking of prefabricated risers is achieved, which solves the problems of difficulty, time and safety hazards in traditional lifting methods, and improves construction efficiency and accuracy.
Patent Information
- Application Number
- CN202422547338.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-22
- Publication Date
- 2025-07-25
- Estimated Expiration
- 2034-10-22
AI Technical Summary
The counter-opal operation and adjustment of traditional prefabricated riser lifting is difficult, time-consuming, large safety hazards and large error accumulation, especially in complex or large-scale projects.
The combination structure of lifting device, casing and riser fixing frame is adopted, combined with automatic telescopic device and sensor, and the riser fixing frame is stably supported on the pallet through the lifting device. The legs length adjustment and precise control of the automatic telescopic device are used to achieve fine adjustment and precise docking of the riser.
It improves the accuracy and efficiency of the lifting counterpart of the prefabricated riser, reduces operating time, reduces safety risks, avoids error accumulation, and ensures accurate connection between the riser and other structural components.
Smart Images

Figure CN223150113U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering and construction technology, in particular to a fine-tuning structure for hoisting and butting prefabricated risers. Background Technique
[0002] The prefabricated risers of a certain project's pipe shaft are for the air conditioning water system from the 3rd floor to the 29th floor above ground, and the prefabricated riser pipe shafts are distributed in the air conditioning machine rooms of the north and south core tubes. The prefabricated risers of this project are welded air conditioning water pipes with DN>100. The distribution positions of the pipe shafts and the pipe information are as follows:
[0003] After the prefabricated risers are in place, the shaft openings of the civil construction operation layer are closed and protected. If there is a situation of misalignment, fine-tuning work is carried out in the lower layer in a timely manner. The traditional hoisting and butting of prefabricated risers usually includes the following steps: First, use a crane or hoisting equipment to lift the riser to a position close to the predetermined position and carry out preliminary positioning. During the hoisting process, gradually adjust the position of the riser, and ensure that the riser butt joint is in the designed position through pads or adjustment devices. Then use a level and a vertical instrument to confirm the horizontal and verticality of the riser and carry out fine-tuning. When the riser butt joint is accurately in place, use a fixing device to firmly fix it to ensure its stability. Although the above-mentioned hoisting and butting operations of prefabricated risers are widely used in many projects, there are also some defects and challenges: 1. Difficult adjustment: There is more dependence on manual operation in the traditional method, resulting in low accuracy, especially in complex or large-scale projects. 2. Long butting operation time: The traditional butting operation may require a long time for adjustment and fixation, affecting the construction progress. Especially when multiple workers need to cooperate, it increases the operation complexity and time consumption; 3. Great potential safety hazards: There may be operation risks in the traditional hoisting process, especially during high-altitude operations, and workers need to adjust and fix at unstable positions; 4. Large error accumulation: In the process of multiple adjustments, there may be a problem of error accumulation, resulting in insufficient final docking accuracy and unable to achieve accurate docking in actual operation. Summary of the Utility Model
[0004] The purpose of the utility model is to provide a fine-tuning structure for hoisting and butting prefabricated risers, and solve the technical problems of difficult adjustment, long butting operation time, great potential safety hazards and large error accumulation in the traditional hoisting and butting operation of prefabricated risers.
[0005] To achieve the above purpose, the utility model adopts the following technical solutions.
[0006] A fine-tuning structure for hoisting and aligning prefabricated risers is provided at a shaft. The shaft is provided on a floor slab, and one side wall of the shaft is a wall, while the other side wall is a structural beam. The fine-tuning structure for hoisting and aligning prefabricated risers includes a hoisting device, a casing, and a riser fixing frame. The hoisting device is arranged above the shaft for hoisting the prefabricated riser. At a position below the hoisting device above the shaft, load-bearing brackets are arranged at intervals. The riser fixing frame is supported on the load-bearing brackets, and a set of unit frames is arranged inside the riser fixing frame. The prefabricated riser is correspondingly passed through a set of unit frames, and force-bearing attachment plates are arranged on the top of the unit frames on the peripheral side walls of the prefabricated riser. A support plate is arranged below the riser fixing frame in the shaft. One side edge of the support plate is connected to the wall, and the other side edge of the support plate is connected to the structural beam. A hole for passing the prefabricated riser is arranged on the support plate corresponding to the unit frame. The casing is installed in the hole, and the upper end of the casing extends beyond the upper surface of the support plate. The diameter of the casing is larger than the diameter of the prefabricated riser. Legs are arranged at intervals at the bottom of the riser fixing frame. The length of the legs is adjustable, and the legs support on the support plate.
[0007] Preferably, the load-bearing bracket includes a support rod. The support rod is in an inverted L shape, and a first end plate is arranged at the end of the horizontal side of the support rod. The first end plate is connected to the wall by bolts, and a second end plate is arranged at the bottom end of the vertical side of the support rod. The second end plate is connected to the top surface of the structural beam by bolts. A connecting rod is connected between adjacent support rods.
[0008] Preferably, the hoisting device includes a support frame and a chain hoist. There is a set of support frames, which are installed at intervals above the shaft. The support frame includes a horizontal rod and an inclined rod. The inclined rod is inclined on the floor slab, and the lower end of the inclined rod is fixedly connected to the floor slab. The horizontal rod is horizontally arranged above the shaft. One end of the horizontal rod is connected to the wall, and the other end of the horizontal rod is connected to the inclined rod. The chain hoist is installed on the horizontal rod.
[0009] Preferably, the riser fixing frame includes long crossbars and connecting short bars. There are two long crossbars, which are arranged in parallel at intervals, and the distance between the two long crossbars is not less than the diameter of the prefabricated riser. There is a set of connecting short bars, which are arranged at intervals in the transverse direction between the two long crossbars. The unit frame is enclosed by adjacent connecting short bars and long crossbars. The distance between two adjacent connecting short bars is not less than the diameter of the prefabricated riser. Connecting blocks are respectively arranged at intervals on the outer sides of the two long crossbars. The connecting blocks are connected to the load-bearing brackets by bolts.
[0010] Preferably, the length of the outrigger is adjustable and includes an outer sleeve, an inner inserting rod and a bottom plate; the inner inserting rod is connected to the bottom of the vertical pipe fixing frame, and perforations are provided on the inner inserting rod; the outer sleeve is sleeved on the outer side of the bottom of the inner inserting rod, and through holes are arranged on the outer sleeve at intervals in the vertical direction; the outer sleeve and the inner inserting rod are connected by bolts passing through the perforations and the corresponding through holes; the bottom plate is fixedly connected to the bottom of the outer sleeve, and the bottom plate is connected to the supporting plate.
[0011] Preferably, automatic telescopic devices are respectively arranged on the inner side wall of the sleeve in the front, back, left and right four directions of the prefabricated vertical pipe; displacement sensors are installed on each automatic telescopic device near the telescopic end.
[0012] Preferably, an anti-corrosion cushion block is provided between the force-bearing attachment plate and the unit frame.
[0013] Compared with the prior art, the utility model has the following characteristics and beneficial effects.
[0014] 1. In the utility model, the prefabricated vertical pipe is supported in the unit frame of the vertical pipe fixing frame through the force-bearing attachment plate, and the hoisting device stably supports the vertical pipe fixing frame on the supporting plate to ensure that the vertical pipe is in the correct position. By adjusting the length of the outrigger, the vertical pipe fixing frame is supported on the supporting plate, further ensuring the stability of the vertical pipe fixing frame; at the same time, with the help of the hoisting device, the vertical pipe is finely adjusted to accurately align the prefabricated vertical pipe in the unit frame, ensuring the accurate docking of the vertical pipe with other structural components.
[0015] 2. In the utility model, a plurality of hydraulic cylinders or air cylinders are installed inside the sleeve, sensors are arranged at the telescopic ends of the telescopic devices, and the position of the vertical pipe is monitored in real time through the telescopic of the automatic telescopic devices and the sensors to adjust the position of the vertical pipe in the front, back, left and right directions to ensure that it can be accurately docked to the predetermined position.
[0016] 3. During the hoisting process of the prefabricated vertical pipe, the adjustment system of the utility model realizes accurate docking and position adjustment through precise control and feedback mechanisms (such as sensors and control systems) to ensure the accurate docking of the vertical pipe with other pipes or structural components, and solves the technical problem of large error accumulation. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The following further describes the utility model in detail with reference to the drawings.
[0018] Figure 1 It is a schematic structural diagram of the prefabricated vertical pipe hoisting and alignment fine-tuning structure of the utility model arranged at the shaft.
[0019] Figure 2 It is a schematic structural diagram of the vertical pipe fixing frame supported on the load-bearing bracket in the utility model.
[0020] Figure 3This is a schematic diagram of the riser fixing bracket in the utility model.
[0021] Figure 4 This is a schematic diagram of the prefabricated riser arranged in the riser fixing bracket in the utility model.
[0022] Figure 5 This is a schematic diagram of the inner insertion rod inserted into the outer sleeve in the utility model.
[0023] Figure 6 This is a schematic diagram of the structure with an automatic telescopic device arranged between the prefabricated riser and the casing in the utility model.
[0024] Reference numerals: 1 - shaft, 2 - floor slab, 3 - wall, 4 - structural beam, 5 - casing, 6 - riser fixing bracket, 6.1 - long cross bar, 6.2 - connecting short bar, 6.3 - connecting block, 7 - prefabricated riser, 8 - load-bearing bracket, 8.1 - support rod, 8.2 - first end plate, 8.3 - second end plate, 8.4 - connecting rod, 9 - unit frame, 10 - force-bearing attachment plate, 11 - support plate, 12 - leg, 12.1 - outer sleeve, 12.2 - inner insertion rod, 12.3 - bottom plate, 13 - support frame, 13.1 - horizontal bar, 13.2 - diagonal bar, 14 - chain block, 15 - perforation, 16 - through hole, 17 - anti-corrosion cushion block, 18 - sling, 19 - automatic telescopic device. Detailed implementation manners
[0025] As Figures 1-6As shown in the figure, this prefabricated riser hoisting and alignment fine-tuning structure is arranged at shaft 1. The shaft 1 is arranged on the floor slab 2, and one side wall of the shaft 1 is the wall 3, and the other side wall of the shaft 1 is the structural beam 4. The structural beam 4 is arranged at the bottom of the floor slab 2. The prefabricated riser hoisting and alignment fine-tuning structure includes a hoisting device, a casing 5 and a riser fixing frame 6. It is characterized in that: the hoisting device is arranged above the shaft 1 for hoisting the prefabricated riser 7; at the position below the hoisting device above the shaft 1, load-bearing brackets 8 are arranged at intervals; the riser fixing frame 6 is supported on the load-bearing brackets 8, and a group of unit frames 9 are arranged in the riser fixing frame 6; the prefabricated riser 7 correspondingly passes through a group of unit frames 9, and force-bearing attachment plates 10 are arranged at the top of the unit frames 9 on the peripheral side walls of the prefabricated riser 7; the force-bearing attachment plates 10 are welded to the prefabricated riser 7; during hoisting, the force-bearing attachment plates 10 are pressed on the top of the unit frames 9 to prevent the prefabricated riser 7 from falling; in the shaft 1, a support plate 11 is arranged below the riser fixing frame 6; one side edge of the support plate 11 is connected to the wall 3, and the other side edge of the support plate 11 is connected to the structural beam 4; on the support plate 11, holes for passing the prefabricated riser 7 are arranged corresponding to the unit frames 9; the casing 5 is installed in the holes, and the upper end of the casing 5 extends beyond the upper surface of the support plate 11, and the diameter of the casing 5 is larger than the diameter of the prefabricated riser 7; the distance between the upper end of the casing 5 and the support plate 11 is not less than 200 mm; legs 12 are arranged at intervals at the bottom of the riser fixing frame 6; the length of the legs 12 is adjustable, and the legs 12 support on the support plate 11.
[0026] In this embodiment, after the construction of the prefabricated riser 7 is completed, 150-mm-thick post-cast concrete is poured in the shaft 1 at the height corresponding to the floor slab 2.
[0027] In this embodiment, the support plate 11 is made of a 3-mm-thick steel plate, and the support plate 11 also serves as a formwork for the post-cast concrete.
[0028] In this embodiment, the load-bearing bracket 8 includes a support rod 8.1. The support rod 8.1 is in an inverted L shape, and a first end plate 8.2 is arranged at the end of the horizontal side of the support rod 8.1. The first end plate 8.2 is connected to the wall 3 by bolts, and a second end plate 8.3 is arranged at the bottom end of the vertical side of the support rod 8.1. The second end plate 8.3 is connected to the top surface of the structural beam 4 by bolts. A connecting rod 8.4 is connected between adjacent support rods 8.1.
[0029] In this embodiment, the hoisting device includes a support frame 13 and a chain block 14; there is a group of support frames 13, which are installed at intervals above the shaft 1; the support frame 13 includes a horizontal rod 13.1 and an inclined rod 13.2; the inclined rod 13.2 is inclined on the floor slab 2, and the lower end of the inclined rod 13.2 is fixedly connected to the floor slab 2; the horizontal rod 13.1 is horizontally arranged above the shaft 1, one end of the horizontal rod 13.1 is connected to the wall 3, and the other end of the horizontal rod 13.1 is connected to the inclined rod 13.2; the chain block 14 is installed on the horizontal rod 13.1; sling ropes 18 are arranged at intervals on the vertical pipe fixing frame 6, and the chain block 14 is connected to the sling ropes 18.
[0030] In this embodiment, the vertical pipe fixing frame 6 includes a long cross bar 6.1 and connecting short bars 6.2; there are two long cross bars 6.1, which are arranged in parallel at intervals, and the distance between the two long cross bars 6.1 is not less than the diameter of the prefabricated vertical pipe 7; there is a group of connecting short bars 6.2, which are arranged at intervals in the transverse direction between the two long cross bars 6.1; the unit frame 9 is formed by enclosing the adjacent connecting short bars 6.2 and the long cross bar 6.1; the distance between two adjacent connecting short bars 6.2 is not less than the diameter of the prefabricated vertical pipe 7; connecting blocks 6.3 are respectively arranged at intervals on the outer sides of the two long cross bars 6.1; the connecting blocks 6.3 are connected to the load-bearing bracket 8 by bolts.
[0031] In this embodiment, the length of the support leg 12 is adjustable and includes an outer sleeve 12.1, an inner insertion rod 12.2 and a bottom plate 12.3; the inner insertion rod 12.2 is connected to the bottom of the vertical pipe fixing frame 6, and a perforation 15 is arranged on the inner insertion rod 12.2; the outer sleeve 12.1 is sleeved on the outer side of the bottom of the inner insertion rod 12.2, and through holes 16 are arranged at intervals along the vertical direction on the outer sleeve 12.1; the outer sleeve 12.1 and the inner insertion rod 12.2 are connected by bolts passing through the perforation 15 and the corresponding through holes 16; the bottom plate 12.3 is fixedly connected to the bottom of the outer sleeve 12.1, and the bottom plate 12.3 is connected to the support plate 11.
[0032] In this embodiment, an anti-corrosion cushion block 17 is provided between the force-bearing attachment plate 10 and the unit frame 9; the thickness of the anti-corrosion cushion block 17 is 30 mm.
[0033] In this embodiment, automatic telescopic devices 19 are respectively arranged on the inner side wall of the sleeve 5 in the front, back, left and right directions of the prefabricated vertical pipe 7; displacement sensors are installed on each automatic telescopic device 19 near the telescopic end.
[0034] In this embodiment, the automatic telescopic device 19 is a hydraulic cylinder or a pneumatic cylinder. The displacement sensor is electrically connected to the control system, and the signal of the displacement sensor is transmitted to the control system. The control system controls the telescopic movement of the automatic telescopic device 19 to precisely adjust the prefabricated riser, ensuring precise alignment. This also solves the potential operation risks that may exist in the traditional hoisting process, especially when working at heights, where workers need to make adjustments and fixations at unstable positions.
[0035] The above embodiments are not an exhaustive list of specific implementation manners, and there may be other embodiments. The purpose of the above embodiments is to illustrate the present invention, rather than to limit the protection scope of the present invention. All applications obtained by simple changes of the present invention fall within the protection scope of the present invention.
Claims
1. A prefabricated riser hoisting and alignment fine-tuning structure is provided at the shaft (1). The shaft (1) is provided on the floor slab (2), and one side wall of the shaft (1) is the wall (3), while the other side wall of the shaft (1) is the structural beam (4). The prefabricated riser hoisting and alignment fine-tuning structure includes a hoisting device, a casing (5) and a riser fixing frame (6). It is characterized in that: The hoisting device is arranged above the shaft (1) for hoisting the prefabricated riser (7); load-bearing brackets (8) are arranged at intervals below the hoisting device above the shaft (1); the riser fixing frame (6) is supported on the load-bearing brackets (8), and a group of unit frames (9) are arranged inside the riser fixing frame (6); the prefabricated riser (7) is correspondingly arranged through a group of unit frames (9), and force-bearing attachment plates (10) are arranged at the top of the unit frames (9) on the peripheral side walls of the prefabricated riser (7); a support plate (11) is arranged below the riser fixing frame (6) in the shaft (1); one side edge of the support plate (11) is connected to the wall body (3), and the other side edge of the support plate (11) is connected to the structural beam (4); holes for passing the prefabricated riser (7) are arranged on the support plate (11) corresponding to the unit frames (9); the sleeve (5) is installed in the holes, and the upper end of the sleeve (5) extends beyond the upper surface of the support plate (11), and the diameter of the sleeve (5) is larger than the diameter of the prefabricated riser (7); legs (12) are arranged at intervals at the bottom of the riser fixing frame (6); the lengths of the legs (12) are adjustable, and the legs (12) are supported on the support plate (11).
2. The prefabricated riser hoisting and alignment fine-tuning structure according to claim 1, wherein: The load-bearing bracket (8) includes a support rod (8.1); the support rod (8.1) is in an inverted L shape, and a first end plate (8.2) is arranged at the end of the horizontal side of the support rod (8.1); the first end plate (8.2) is connected to the wall body (3) by bolts, and a second end plate (8.3) is arranged at the bottom end of the vertical side of the support rod (8.1); the second end plate (8.3) is connected to the top surface of the structural beam (4) by bolts; a connecting rod (8.4) is connected between adjacent support rods (8.1).
3. The prefabricated riser hoisting and alignment fine-tuning structure according to claim 1, wherein: The hoisting device includes a support frame (13) and a chain hoist (14); there is a group of support frames (13), which are installed at intervals above the shaft (1); the support frame (13) includes a horizontal rod (13.1) and an inclined rod (13.2); the inclined rod (13.2) is inclined on the floor slab (2), and the lower end of the inclined rod (13.2) is fixedly connected to the floor slab (2); the horizontal rod (13.1) is horizontally arranged above the shaft (1), one end of the horizontal rod (13.1) is connected to the wall body (3), and the other end of the horizontal rod (13.1) is connected to the inclined rod (13.2); the chain hoist (14) is installed on the horizontal rod (13.1).
4. The prefabricated riser hoisting and alignment fine-tuning structure according to claim 1, wherein: The riser fixing bracket (6) includes a long cross bar (6.1) and connecting short bars (6.2); there are two long cross bars (6.1), which are arranged in parallel at intervals, and the distance between the two long cross bars (6.1) is not less than the diameter of the prefabricated riser (7); there is a group of connecting short bars (6.2), which are arranged at intervals in the transverse direction between the two long cross bars (6.1); the unit frame (9) is formed by enclosing adjacent connecting short bars (6.2) and long cross bars (6.1); the distance between two adjacent connecting short bars (6.2) is not less than the diameter of the prefabricated riser (7); connecting blocks (6.3) are respectively arranged at intervals on the outer sides of the two long cross bars (6.1); the connecting blocks (6.3) are bolted to the load-bearing bracket (8).
5. The prefabricated riser hoisting and alignment fine-tuning structure according to claim 1, characterized in that: The length of the leg (12) is adjustable and includes an outer sleeve (12.1), an inner insertion rod (12.2) and a bottom plate (12.3); the inner insertion rod (12.2) is connected to the bottom of the riser fixing bracket (6), and a through hole (15) is provided on the inner insertion rod (12.2); the outer sleeve (12.1) is sleeved on the outer side of the bottom of the inner insertion rod (12.2), and through holes (16) are arranged at intervals in the vertical direction on the outer sleeve (12.1); the outer sleeve (12.1) and the inner insertion rod (12.2) are bolted through bolts inserted into the through hole (15) and the corresponding through hole (16); the bottom plate (12.3) is fixedly connected to the bottom of the outer sleeve (12.1), and the bottom plate (12.3) is connected to the support plate (11).
6. The prefabricated riser hoisting and alignment fine-tuning structure according to claim 1, characterized in that: Automatic telescopic devices (19) are respectively arranged on the inner side wall of the sleeve (5) in the front, back, left and right directions of the prefabricated riser (7); displacement sensors are installed on each automatic telescopic device (19) near the telescopic end position.
7. The prefabricated riser hoisting and alignment fine-tuning structure according to claim 1, wherein: An anti-corrosion cushion block (17) is padded between the force-bearing attachment plate (10) and the unit frame (9).