Adjustable tie device for assisting installation of steel bridge cross beam
By using an adjustable pulling device in the arch-beam combination bridge, the gap problem caused by cross beam deformation is solved, and efficient gap adjustment between cross beams and small longitudinal beams is achieved, simplifying the operation process and reducing costs.
Patent Information
- Application Number
- CN202421716957.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-19
- Publication Date
- 2025-07-29
- Estimated Expiration
- 2034-07-19
AI Technical Summary
During the installation of the bridge deck system of the arch-beam combination bridge, the cross beam is prone to deformation when the length of the cross beam is large, resulting in inappropriate gaps between the small cross beams and the cross beams, affecting the welding quality and installation difficulty. The adjustment of the existing technology is cumbersome and laborious, and the existing equipment is prone to local deformation of the cross beams.
The adjustable pulling device is adopted, including the first clamp, the second clamp, the third clamp, the connecting piece and the basket bolt. By rotating the double-head nut, the gap between the cross beam and the small longitudinal beam is adjusted to achieve accurate adjustment of the gap between the cross beam and the small longitudinal beam, and reduce welding deformation.
The adjustment efficiency of cross beams and small longitudinal beams is improved, local deformation is reduced, operating procedures are simplified, labor costs are reduced, and welding quality is ensured.
Smart Images

Figure CN223163770U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of bridge construction equipment, and particularly relates to an adjustable tie device for assisting in the installation of steel bridge cross beams. Background Technique
[0002] With the development of bridge construction, more and more bridge types have emerged. The deck system of an arch-beam composite bridge generally consists of main longitudinal beams, end cross beams, cross beams, minor longitudinal beams, and orthotropic bridge decks, etc. The deck system of a common arch-beam composite bridge includes box steel beams for the main longitudinal beams and end cross beams, inverted T-shaped steel beams for the cross beams and minor longitudinal beams, and orthotropic steel plates for the bridge deck.
[0003] During the installation process of the deck system of an arch-beam composite bridge, when the length of the cross beam is relatively large, it is easy to form a small amount of deformation after the cross beam is hoisted and welded. Especially when the cross beam uses an inverted T-shaped steel beam, the top plate of the inverted T-shaped cross beam has no flange restriction, and the deformation is more obvious than that of the lower part. When installing the minor longitudinal beam between two cross beams after the cross beam is installed, there will be a situation where there is a gap or insufficient spacing between the minor longitudinal beam and the cross beam. The gap will increase the welding difficulty during the welding process of the minor longitudinal beam, and the welding quality cannot be guaranteed; insufficient spacing will make it difficult to install the minor longitudinal beam in place. In the prior art, the method of reducing the welding gap between steel bridge plates is to use flame repair or manually adjust with a wrench, etc. The problems with these methods are that the operation process is cumbersome and laborious, and it is difficult to fix the plates during welding after adjustment, resulting in an increase in the construction period and labor costs.
[0004] The Chinese utility model patent with the publication number CN216177972U discloses a lifting support device for steel box girder diaphragms. This device is mainly used for the support of steel box girder diaphragms. This support device is mainly clamped and fixed between the already welded and fixed diaphragm and the diaphragm to be fixed to achieve the support effect on the diaphragm to be fixed. During the installation process of the minor longitudinal beam between two cross beams, the single cross beam cannot be clamped too tightly, but the two cross beams need to be tied and tightened. The clamping part of the above patent is U-shaped, and the contact surface with the plate is small. When the two cross beams are tied and tightened, it is easy to cause local deformation of the cross beam and is not suitable for the auxiliary installation of steel bridge cross beams. Content of the Utility Model
[0005] The purpose of the utility model is to solve the deficiencies in the prior art and provide an adjustable tie device for assisting in the installation of steel bridge cross beams.
[0006] The specific technical solution adopted by the utility model is as follows:
[0007] The utility model provides an adjustable tie device for assisting in the installation of a steel bridge cross beam. The adjustable tie device includes a first clamp, a second clamp, and a third clamp with the same structure, as well as a first connecting piece, a first lock, a second connecting piece, a second lock, a third connecting piece, and a turnbuckle.
[0008] One end of the first connecting piece is fixedly connected to the first clamp, and the other end is fixedly connected to the first lock; one ends of the second connecting piece and the third connecting piece are respectively fixedly connected to the second clamp and the third clamp, and the other ends of the second connecting piece and the third connecting piece are both fixedly connected to the second lock; a turnbuckle is arranged between the first lock and the second lock; the turnbuckle includes screws at both ends and a double-headed nut between the screws; the screws are respectively fixedly connected to the first lock and the second lock.
[0009] The adjustable tie device is arranged between a first cross beam and a second cross beam that are parallelly arranged between two main longitudinal beams of a steel bridge. A small longitudinal beam to be installed needs to be vertically arranged between the first cross beam and the second cross beam; wherein the first clamp is clamped on the second cross beam, and the second clamp and the third clamp are both clamped on the first cross beam. By rotating the double-headed nut, the distance between the first clamp and the second clamp and the third clamp is adjusted, so as to adjust the gap between the first cross beam and the small longitudinal beam to be installed.
[0010] Preferably, the first clamp, the second clamp, and the third clamp are all welded into a whole by a rectangular steel plate and an L-shaped steel plate, and a card slot with a downward opening direction is formed between the rectangular steel plate and the L-shaped steel plate.
[0011] Preferably, the first connecting piece is made of round steel.
[0012] Preferably, the second connecting piece and the third connecting piece are both made of round steel.
[0013] Preferably, the two ends of the first connecting piece are respectively fixedly connected to the first clamp and the first lock by welding.
[0014] Preferably, the second connecting piece and the third connecting piece are both fixedly connected to the second lock by welding.
[0015] Preferably, the two ends of the small longitudinal beam to be installed are vertically fixed between the first cross beam and the second cross beam by spot welding.
[0016] Preferably, openings of the U-shaped ribs of the bridge deck roof plate are provided at the tops of the first cross beam and the second cross beam.
[0017] Further, the first clamp is clamped at the place where the second cross beam does not have the U-shaped rib opening.
[0018] Further, the second fixture and the third fixture are clamped to the first cross beam at the place where the U-shaped rib opening is not provided, and the distance between the second fixture and the third fixture is greater than the width of a U-shaped rib on the deck slab of the first cross beam.
[0019] The utility model has the following beneficial effects compared with the prior art:
[0020] (1) The adjustable tie device provided by the utility model can be arranged between the first cross beam and the second cross beam which are arranged in parallel between the two main longitudinal beams of the steel bridge. A turnbuckle is adopted in the adjustable tie device, and the distance between the two fixtures on both sides is adjusted by rotating the double-headed nut, so as to adjust the gap between the cross beam and the small longitudinal beam to be installed. After the gap is adjusted, it is convenient to carry out tie fixation, and the welding deformation between the cross beam and the small longitudinal beam is reduced.
[0021] (2) The adjustable tie device provided by the utility model adopts double-fixture tie for the cross beam to be adjusted, with high adjustment efficiency and more effectiveness; the fixture is in the form of a whole welded by a rectangular steel plate and an L-shaped steel plate, and the rectangular steel plate can increase the contact area with the cross beam and reduce the local deformation of the cross beam caused by the fixture. Description of the Drawings
[0022] Figure 1 is a schematic diagram of the overall adjustable tie device provided in this embodiment;
[0023] Figure 2 is a schematic diagram of the connection of the turnbuckle provided in this embodiment;
[0024] Figure 3 is a schematic diagram of the use of the adjustable tie device provided in this embodiment;
[0025] In the figure: the first fixture 1, the first connecting piece 2, the first lock 2-1, the turnbuckle 3, the screw rod 301, the double-headed nut 302, the second connecting piece 4, the second lock 4-1, the third connecting piece 5, the second fixture 6, the third fixture 7, the first cross beam 8-1, the second cross beam 8-2, the small longitudinal beam 9-1 to be installed, and the main longitudinal beam 10. Detailed Embodiment
[0026] In order to make the above-mentioned objects, features and advantages of the utility model more obvious and understandable, the following detailed description of the specific embodiment of the utility model will be given with reference to the drawings. Many specific details are set forth in the following description in order to fully understand the utility model. However, the utility model can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without departing from the connotation of the utility model. Therefore, the utility model is not limited by the specific embodiments disclosed below. The technical features in each embodiment of the utility model can be combined correspondingly without conflict.
[0027] In the description of the present utility model, it should be understood that the terms "first" and "second" are only used for the purpose of distinguishing descriptions, and cannot be understood as indicating or implying relative importance or implicitly specifying the quantity of the indicated technical features. Thus, the features defined with "first" and "second" may explicitly or implicitly include at least one of such features.
[0028] As Figure 1 shown, as a preferred embodiment of the specific implementation manner of the present utility model, this embodiment provides an adjustable tie device for assisting the installation of the cross beam of a steel bridge. The adjustable tie device includes a first clamp 1, a second clamp 6, a third clamp 7, a first connecting member 2, a first locking buckle 2-1, a second connecting member 4, a second locking buckle 4-1, a third connecting member 5, and a turnbuckle 3.
[0029] In this embodiment, the first clamp 1, the second clamp 6, and the third clamp 7 have the same structure. The first clamp 1, the second clamp 6, and the third clamp 7 are each formed by welding a rectangular steel plate and an L-shaped steel plate into a whole, and a card slot with a downward opening direction is formed between the rectangular steel plate and the L-shaped steel plate. The rectangular steel plate can increase the contact area with the cross beam and reduce the local deformation of the cross beam caused by the clamp.
[0030] In the device provided by the present utility model, one end of the first connecting member 2 is fixedly connected to the first clamp 1, and the other end is fixedly connected to the first locking buckle 2-1. One ends of the second connecting member 4 and the third connecting member 5 are respectively fixedly connected to the second clamp 6 and the third clamp 7, and the other ends of the second connecting member 4 and the third connecting member 5 are both fixedly connected to the second locking buckle 4-1.
[0031] In this embodiment, the first connecting member 2, the second connecting member 4, and the third connecting member 5 are all made of round steel. Those skilled in the art can select a suitable round steel model and length according to the actual working conditions. One end of the first connecting member 2 is fixedly connected to the first clamp 1 by welding, and the other end is also fixedly connected to the first locking buckle 2-1 by welding. One ends of the second connecting member 4 and the third connecting member 5 are respectively fixedly connected to the second clamp 6 and the third clamp 7 by welding, and the other ends are both fixedly connected to the second locking buckle 4-1 by welding.
[0032] A turnbuckle, also called a rigging screw or a wire tightener, is a connecting member that can adjust the tightness. As Figure 2 shown, in the device provided by the present utility model, the first locking buckle 2-1 and the second locking buckle 4-1 are connected by a turnbuckle 3. The turnbuckle 3 includes screw rods 301 at both ends and a double-headed nut 302 between the screw rods. The screw rods 301 are respectively fixedly connected to the first locking buckle 2-1 and the second locking buckle 4-1. By rotating the double-headed nut 302, the distance between the first clamp 1 and the second clamp 6, the third clamp 7 can be finely adjusted, so as to achieve the adjustment purpose.
[0033] The adjustable tie device provided by the utility model is used on a steel bridge, which is an arch-beam composite bridge, and involves a first cross beam 8-1, a second cross beam 8-2, a small longitudinal beam 9-1 to be installed, and a main longitudinal beam 10. The first cross beam 8-1 and the second cross beam 8-2 are installed between two main longitudinal beams 10, and the first cross beam 8-1 and the second cross beam 8-2 are arranged in parallel. A small longitudinal beam has been installed between the second cross beam 8-2 and the cross beam of the previous span. A small longitudinal beam 9-1 to be installed needs to be installed between the first cross beam 8-1 and the second cross beam 8-2.
[0034] As Figure 3 shown, openings of U-shaped ribs of the bridge deck top plate are provided at the tops of the first cross beam 8-1 and the second cross beam 8-2. The first fixture 1 is clamped on the second cross beam 8-2 and avoids the openings of the U-shaped ribs on the second cross beam 8-2. Both the second fixture 6 and the third fixture 7 are clamped on the first cross beam 8-1 and both avoid the openings of the U-shaped ribs on the first cross beam 8-1. The distance between the second fixture 6 and the third fixture 7 should be greater than the width of one U-shaped rib of the bridge deck top plate.
[0035] It should be noted that the lengths of the second connecting member 4 and the third connecting member 5 may not be equal. It is only necessary that the angle formed by the second connecting member and the third connecting member can make the second fixture and the third fixture avoid the opening of the U-shaped rib of the bridge deck top plate at the top of the first cross beam 8-1. The distance between the first fixture 1 and the second fixture 6 and the third fixture 7 is adjusted by rotating the double-headed nut 302, so as to adjust the gap between the first cross beam 8-1 and the small longitudinal beam 9-1 to be installed. After setting the above adjustable tie device, the two ends of the small longitudinal beam 9-1 to be installed are vertically fixed between the first cross beam 8-1 and the second cross beam 8-2 by spot welding.
[0036] The following provides the process of using the above adjustable tie device to assist in the installation of the steel bridge cross beam on the arch-beam composite bridge:
[0037] S1. Weld the first fixture 1, the first locking buckle 2-1 and the first connecting member 2 into a whole. Connect the first locking buckle 2-1 with one end of the flower basket bolt 3 by locking. Weld and fix one end of the second connecting member 4 and the third connecting member 5 to the second locking buckle 4-1, and weld the other ends to the second fixture 6 and the third fixture 7 respectively to form a whole. Connect the second locking buckle 4-1 with the other end of the flower basket bolt 3 by locking.
[0038] S2. Lift the small longitudinal beam 9-1 to the designated in-place position without releasing the hook.
[0039] S3. Avoid the opening of the U-shaped rib of the bridge deck top plate, and clamp the first fixture 1 on the top of the second cross beam 8-2. Avoid the opening of the U-shaped rib of the bridge deck top plate, and clamp the second fixture 6 and the third fixture 7 on the top of the first cross beam 8-1.
[0040] S4. Rotate the double-headed nut 302 on the swivel turnbuckle 3 to finely adjust the gap between the first crossbeam 8-1 and the small longitudinal beam 9-1 to be installed. After the fine adjustment is completed, spot-weld the small longitudinal beam 9-1 to be installed to the first crossbeam 8-1 and the second crossbeam 8-2.
[0041] S5. Weld the small longitudinal beam 9-1 to be installed, and remove the adjustable tie device after the welding is completed.
[0042] The above embodiments are only a preferred solution of the present invention, but they are not intended to limit the present invention. Those of ordinary skill in the relevant technical field can also make various changes and modifications without departing from the spirit and scope of the present invention. Therefore, all technical solutions obtained by means of equivalent replacement or equivalent transformation fall within the protection scope of the present invention.
Claims
1. An adjustable tie device for assisting in the installation of a steel bridge crossbeam, characterized in that, The adjustable tie device includes a first fixture (1), a second fixture (6), and a third fixture (7) with the same structure, as well as a first connecting member (2), a first lock (2-1), a second connecting member (4), a second lock (4-1), a third connecting member (5), and a turnbuckle (3). One end of the first connecting member (2) is fixedly connected to the first fixture (1), and the other end is fixedly connected to the first lock (2-1); one ends of the second connecting member (4) and the third connecting member (5) are respectively fixedly connected to the second fixture (6) and the third fixture (7), and the other ends of the second connecting member (4) and the third connecting member (5) are both fixedly connected to the second lock (4-1); a turnbuckle (3) is arranged between the first lock (2-1) and the second lock (4-1); the turnbuckle (3) includes screw rods (301) at both ends and a double-headed nut (302) between the screw rods; the screw rods (301) are respectively fixedly connected to the first lock (2-1) and the second lock (4-1). The adjustable tie device is arranged between a first cross beam (8-1) and a second cross beam (8-2) which are arranged in parallel between two main longitudinal beams (10) of a steel bridge, and a small longitudinal beam (9-1) to be installed needs to be vertically arranged between the first cross beam (8-1) and the second cross beam (8-2); wherein the first fixture (1) is clamped on the second cross beam (8-2), and the second fixture (6) and the third fixture (7) are both clamped on the first cross beam (8-1), and the distance between the first fixture (1) and the second fixture (6), the third fixture (7) is adjusted by rotating the double-headed nut (302), so as to adjust the gap between the first cross beam (8-1) and the small longitudinal beam (9-1) to be installed.
2. The adjustable tie device for assisting in the installation of the cross beam of the steel bridge according to claim 1, characterized in that, The first fixture (1), the second fixture (6), and the third fixture (7) are all welded into a whole by a rectangular steel plate and an L-shaped steel plate, and a clamping groove with a downward opening direction is formed between the rectangular steel plate and the L-shaped steel plate.
3. The adjustable tie device for assisting the installation of the cross beam of the steel bridge according to claim 1, characterized in that, The first connecting member (2) is made of round steel.
4. The adjustable tie device for assisting the installation of the cross beam of the steel bridge according to claim 1, wherein Both the second connecting member (4) and the third connecting member (5) are made of round steel.
5. The adjustable tie device for assisting the installation of the cross beam of the steel bridge according to claim 1, wherein, Both ends of the first connecting member (2) are fixedly connected to the first fixture (1) and the first lock (2-1) by welding.
6. The adjustable tie device for assisting in the installation of the steel bridge cross beam according to claim 1, characterized in that, Both the second connecting member (4) and the third connecting member (5) are fixedly connected to the second lock (4-1) by welding.
7. The adjustable tie device for assisting in the installation of the cross beam of a steel bridge according to claim 1, characterized in that, Both ends of the small longitudinal beam (9-1) to be installed are vertically fixed between the first cross beam (8-1) and the second cross beam (8-2) by spot welding.
8. The adjustable tie device for assisting the installation of the cross beam of a steel bridge according to claim 1, characterized in that, Openings of the U-shaped ribs of the bridge deck top plate are provided at the tops of the first cross beam (8-1) and the second cross beam (8-2).
9. The adjustable tie device for assisting the installation of the cross beam of the steel bridge according to claim 8, wherein, The first fixture (1) is clamped at the place where the second cross beam (8-2) does not have the opening of the U-shaped rib.
10. The adjustable tie device for assisting the installation of the cross beam of the steel bridge according to claim 8, characterized in that, The second fixture (6) and the third fixture (7) are clamped at the place where the first cross beam (8-1) does not have the opening of the U-shaped rib, and the distance between the second fixture (6) and the third fixture (7) is greater than the width of one U-shaped rib on the bridge deck top plate of the first cross beam (8-1).
Citation Information
Patent Citations
Lifting and supporting device for diaphragm plate of steel box girder
CN216177972U