Decoration material hoisting device
By designing a hoisting device including vertical short pipes, vertical long pipes, horizontal pipes and electric hoists, the problem of inconvenience of workers to carry strips is solved, efficient and safe strip installation is achieved, and the decoration progress is improved.
Patent Information
- Application Number
- CN202422403398.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-30
- Publication Date
- 2025-08-15
- Estimated Expiration
- 2034-09-30
AI Technical Summary
During the interior decoration process, it is inconvenient for workers to carry the strips to the high-level installation position, resulting in slow construction progress and the risk of the strips falling off.
A decoration material lifting device is designed, including a construction hanger composed of vertical short pipes, vertical long pipes, horizontal pipes, electric hoists and steel ropes. The electric hoists are used to drive the steel rope to lift the strips to a specified height for easy installation.
Through the lifting device, workers can easily lift the strips to the designated position, reducing labor intensity, improving the decoration progress and ensuring the stability and safety of the installation.
Smart Images

Figure CN223225652U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of interior decoration engineering, in particular to a decoration material hoisting device. Background Art
[0002] Decoration materials are materials used for home decoration. Decoration materials are divided into two parts: one part is outdoor materials, and the other part is indoor materials. Indoor materials are further divided into six types: stone, board, sheet, profile, wire and wall materials.
[0003] Usually during the home decoration process, some customers will choose to install strips on the wall to provide certain support for non-load-bearing walls and ensure the stability and safety of the indoor structure. However, the strips are relatively large overall. When installed at a high position on the wall, it is inconvenient for workers to carry them. Relying solely on manual handling and lifting operations can easily cause the strips to fall off and break, which slows down the progress of the decoration construction.
[0004] Therefore, the present application provides a decoration material hoisting device to solve the above problems. Utility Model Content
[0005] (1) Technical issues to be resolved
[0006] In view of the deficiencies of the prior art, the present invention provides a decoration material hoisting device, which aims to solve the problem in the background art that during the interior decoration process, workers need to carry the strips to the installation location and suffer inconvenience.
[0007] (2) Technical solution
[0008] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:
[0009] A decoration material hoisting device comprises two short vertical tubes and two long vertical tubes;
[0010] The two short vertical tubes and the two long vertical tubes are arranged in a front-to-back vertical array; a horizontal tube is provided between the adjacent short vertical tubes and the long vertical tubes, and the tubes are connected and fixed by means of the horizontal tube; a third splicing tube is provided at the upper portion between the two long vertical tubes, and the tubes are spliced and fixed together by means of the third splicing tube; a hook seat is provided on the third splicing tube; an electric hoist is provided between the two horizontal tubes; two positioning tubes are equidistantly arranged between the two horizontal tubes; a positioning plate is fixedly connected between the two positioning tubes; the base of the electric hoist is fixedly connected to the upper end of the positioning plate by bolts; a roller is provided on the hook seat; a steel rope is provided on the electric hoist; the steel rope is wound around the roller; and a hook is provided at the lower end of the steel rope. The short vertical tubes, reinforcing tubes, long vertical tubes, horizontal tubes, first splicing tubes, second splicing tubes, positioning tubes and third splicing tubes are all made of stainless steel, and the construction hanger is composed of the short vertical tubes, long vertical tubes, horizontal tubes and first splicing tubes respectively.
[0011] Preferably, universal wheels are fixedly mounted on the lower ends of the short vertical tube and the long vertical tube.
[0012] Preferably, a plurality of second splicing tubes are equidistantly arranged between the corresponding front and rear vertical short tubes and the vertical long tube; a first splicing tube is provided at both ends of the second splicing tube; and a reinforcing tube is provided between the two vertical short tubes.
[0013] Preferably, both ends of the reinforcing tube are detachably connected to the corresponding vertical short tubes through a cross fastener; both ends of the horizontal tube are detachably connected to the vertical short tubes and the vertical long tubes through a cross fastener; and both ends of the positioning tube are detachably connected to the corresponding horizontal tubes through a cross fastener.
[0014] Preferably, the second splicing tube close to the vertical long tube is detachably connected to the vertical long tube via a cross fastener; the second splicing tube close to the vertical short tube is detachably connected to the vertical short tube via a cross fastener.
[0015] Preferably, several of the second splicing tubes are detachably connected to the first splicing tube via a cross fastener. A positioning plate fixed between the two positioning tubes secures the electric hoist. A steel rope is wound around the hoist's wire roller. The internal wiring of the electric hoist utilizes existing technology. Power is supplied via external wiring, driving the steel rope to lift the slats hung on the hook to a specified height, facilitating installation by workers.
[0016] Preferably, the lower end of the third splicing pipe is fixedly connected to a fixing seat; and the hook on the hooking seat is hooked to the fixing seat.
[0017] Preferably, the electric hoist can drive the hook connected to the steel rope to lift the decoration materials.
[0018] (3) Beneficial effects
[0019] The beneficial effects of the present invention are as follows: The present invention provides a decoration material hoisting device, which has the following beneficial effects:
[0020] The material lifting device is a construction hanger composed of a short vertical tube, a reinforcing tube, a long vertical tube, a horizontal tube, a first splicing tube, a second splicing tube and a third splicing tube through a cross fastener. The electric hoist on the positioning plate cooperates with the steel rope and the roller on the hook seat, and uses the hook to lift the rope-covered slats to the specified position. Even when facing high-position installation, it can still be operated conveniently, which is convenient for workers to install the slats and improves the overall decoration progress.
[0021] The material lifting device is provided with universal wheels at the lower ends of the vertical short tube and the vertical long tube, so that the construction hanger can be moved to the designated lifting position at any time. It is convenient to use and reduces the labor intensity of the staff. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 This is a structural diagram of a decoration material hoisting device;
[0023] Figure 2 Schematic diagram of the structure of the positioning plate;
[0024] Figure 3 for Figure 1 A schematic diagram of the structure enlarged in the middle;
[0025] Figure 4 for Figure 2 Schematic diagram of the structure enlarged at point B.
[0026] [Description of Reference Numerals]
[0027] 1. Short vertical tube; 2. Reinforced tube; 3. Long vertical tube; 4. Horizontal tube; 5. First splicing tube; 6. Second splicing tube; 7. Positioning tube; 8. Positioning plate; 9. Electric hoist; 10. Steel rope; 11. Third splicing tube; 12. Fixed seat; 13. Hook seat; 14. Roller; 15. Hook; 16. Universal wheel. DETAILED DESCRIPTION
[0028] To make the purpose, technical solutions, and advantages of the embodiments of the present invention more clear, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the embodiments described are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts shall fall within the scope of protection of the present invention.
[0029] like Figures 1-4As shown: This embodiment provides a decoration material lifting device, including two vertical short tubes 1 and two vertical long tubes 3; the two vertical short tubes 1 and the two vertical long tubes 3 are arranged in a front-to-back vertical array; a horizontal tube 4 is provided between the front-to-back adjacent vertical short tubes 1 and the vertical long tubes 3, and they are connected and fixed with the help of the horizontal tube 4.
[0030] A third splicing pipe 11 is provided at the upper portion between the two vertical tubes 3 , and the two vertical tubes 3 are spliced and fixed into one body by means of the third splicing pipe 11 ; a hook seat 13 is provided on the third splicing pipe 11 ; an electric hoist 9 is provided between the two horizontal tubes 4 .
[0031] Two positioning tubes 7 are equidistantly arranged between the two horizontal tubes 4; a positioning plate 8 is fixedly connected between the two positioning tubes 7; the base of the electric hoist 9 is fixedly connected to the upper end of the positioning plate 8 by bolts; a roller 14 is provided on the hook seat 13; a steel rope 10 is provided on the electric hoist 9; the steel rope 10 is wound around the roller 14; and a hook 15 is provided at the lower end of the steel rope 10.
[0032] The short vertical tubes, reinforcing tubes, long vertical tubes, horizontal tubes, first splicing tubes, second splicing tubes, positioning tubes and third splicing tubes are all made of stainless steel, and the construction hanger is composed of the short vertical tubes, long vertical tubes, horizontal tubes and first splicing tubes respectively.
[0033] Among them, the positioning plate 8 fixed between the two positioning tubes 7 plays a role in fixing the electric hoist 9. The steel rope 10 is wound around the wire roller of the electric hoist 9. The internal circuit connection of the electric hoist 9 is an existing technology. When powered by external wiring, the steel rope 10 is driven to lift the slats hung on the hook 15 to a specified height, making it convenient for workers to install the slats.
[0034] Specifically, universal wheels 16 are fixedly mounted on the lower ends of the short vertical tube 1 and the long vertical tube 3. More specifically, by installing universal wheels 16 below the short vertical tube 1 and the long vertical tube 3 and having a locking structure, the entire construction hanger can be easily moved to the area to be installed when the hook 15 is lifting the slats, eliminating the need for workers to carry the slats back and forth, thereby reducing their workload.
[0035] In this embodiment, a plurality of second splicing tubes 6 are equidistantly arranged between the corresponding front and rear short vertical tubes 1 and the long vertical tubes 3 ; first splicing tubes 5 are provided at both ends of the second splicing tubes 6 ; and a reinforcing tube 2 is provided between the two short vertical tubes 1 .
[0036] It should be noted that the reinforcing pipe 2 and the second splicing pipe 6 both play a role in reinforcing the entire construction hanger, and can play a stabilizing role when the slats are hoisted.
[0037] The two ends of the reinforcing tube 2 are detachably connected to the corresponding vertical short tube 1 through a cross fastener; the two ends of the horizontal tube 4 are detachably connected to the vertical short tube 1 and the vertical long tube 3 through a cross fastener; the two ends of the positioning tube 7 are detachably connected to the corresponding horizontal tube 4 through a cross fastener.
[0038] The second splicing tube 6 close to the vertical long tube 3 is detachably connected to the vertical long tube 3 through a cross fastener; the second splicing tube 6 close to the vertical short tube 1 is detachably connected to the vertical short tube 1 through a cross fastener.
[0039] Several second splicing tubes 6 are detachably connected to the first splicing tube 5 via cross fasteners. A positioning plate fixed between the two positioning tubes secures the electric hoist. A steel rope is wound around the hoist's rollers. The hoist's internal wiring utilizes existing technology. Power is supplied via external wiring, driving the rope to lift the slats hung on the hook to a specified height, facilitating installation by workers.
[0040] It is worth mentioning that each pipe on the construction hanger is detachably connected with a cross fastener, rather than an integrated structure. It can be assembled directly in the decorated room, mainly to facilitate transportation after disassembly.
[0041] In this embodiment, the lower end of the third splicing pipe 11 is fixedly connected to a fixing seat 12; the hook on the hooking seat 13 is hooked to the fixing seat 12. The electric hoist 9 can drive the hook 15 connected to the steel rope 10 to lift the decoration materials.
[0042] When in use, first assemble the construction hanger consisting of the vertical short tube 1, the vertical long tube 3, the horizontal tube 4 and the first splicing tube 5, and then fix the reinforcing tube 2, the first splicing tube 5, the second splicing tube 6 and the positioning tube 7 on the construction hanger through the cross fasteners to provide reinforcement for the entire construction hanger, and pass the steel rope 10 on the electric hoist 9 around the roller 14 on the hook seat 13. The staff can move the lifted strips to the staff's position through the vertical short tube 1 and the universal wheel 16 under the vertical long tube 3, and lift the strips to the vicinity of the workers through the hook 15. The workers will pull the strips to the installation position and install them.
[0043] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments can still be modified, or some of the technical features thereof can be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the present invention.
Claims
1. A decoration material hoisting device, characterized in that: It comprises two short vertical tubes (1) and two long vertical tubes (3); The two short vertical tubes (1) and the two long vertical tubes are arranged in a front-to-back vertical array; A horizontal tube (4) is provided between the front and rear adjacent vertical short tubes (1) and the vertical long tubes (3), and the two tubes are connected and fixed by means of the horizontal tube (4); A third splicing tube (11) is provided at the upper portion between the two vertical tubes (3), and the two tubes are spliced and fixed into one body by means of the third splicing tube (11); The third splicing pipe (11) is provided with a hook seat (13); An electric hoist (9) is provided between the two transverse pipes (4); Two positioning tubes (7) are equidistantly arranged between the two transverse tubes (4); A positioning plate (8) is fixedly connected between the two positioning tubes (7); The base of the electric hoist (9) is fixedly connected to the upper end of the positioning plate (8) by bolts; The hook seat (13) is provided with a roller (14); The electric hoist (9) is provided with a steel rope (10); The steel rope (10) is wound around the roller (14); The lower end of the steel rope (10) is provided with a hook (15).
2. The decoration material hoisting device according to claim 1, characterized in that: Universal wheels (16) are fixedly mounted on the lower ends of the short vertical tube (1) and the long vertical tube (3).
3. The decoration material hoisting device according to claim 1, characterized in that: A plurality of second splicing tubes (6) are arranged at equal distances between the corresponding vertical short tubes (1) and the vertical long tubes (3); Both ends of the second splicing tube (6) are provided with a first splicing tube (5); A reinforcement tube (2) is provided between the two vertical short tubes (1).
4. The decoration material hoisting device according to claim 3, characterized in that: Both ends of the reinforcement tube (2) are detachably connected to the corresponding vertical short tube (1) via cross fasteners; The two ends of the horizontal tube (4) are detachably connected to the short vertical tube (1) and the long vertical tube (3) via cross fasteners; Both ends of the positioning tube (7) are detachably connected to the corresponding transverse tube (4) via cross fasteners.
5. The decoration material hoisting device according to claim 4, characterized in that: A second splicing pipe (6) close to the vertical pipe (3) is detachably connected to the vertical pipe (3) via a cross fastener; The second splicing tube (6) close to the vertical short tube (1) is detachably connected to the vertical short tube (1) via a cross fastener.
6. The decoration material hoisting device according to claim 5, characterized in that: A plurality of the second splicing tubes (6) are detachably connected to the first splicing tube (5) via a cross fastener.
7. The decoration material hoisting device according to claim 1, characterized in that: The lower end of the third splicing pipe (11) is fixedly connected to a fixing seat (12); The hook on the hooking seat (13) is hooked with the fixing seat (12).
8. The decoration material hoisting device according to claim 1, characterized in that: The electric hoist (9) can drive the hook (15) connected to the steel rope (10) to hoist the decoration materials.