Sluice pier
By using a cover plate structure composed of prefabricated layers and cast layer in the drain gate pier, the problem of space and safety hazards of the formwork support system is solved, and the installation of mechanical and electrical equipment and the construction of cast layer is achieved simultaneously, improving construction efficiency and safety.
Patent Information
- Application Number
- CN202422500890.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-15
- Publication Date
- 2025-08-19
- Estimated Expiration
- 2034-10-15
AI Technical Summary
The construction of the cover plate of the existing drainage gate piers requires the erecting of a formwork support system in the equipment installation chamber, which affects the installation progress of the electromechanical equipment, and there are safety hazards for dismantling the support system from high altitudes.
A cover plate structure consisting of a prefabricated layer and a cast layer is adopted. The prefabricated layer is spliced by multiple prefabricated plates and hoisted to the top of the pier. The load-bearing beam is pre-buried in the prefabricated plate. The cast layer cover is placed on the prefabricated plate. The connecting part is connected to the cast layer to avoid erecting a formwork support system in the equipment installation chamber.
It realizes the installation of electromechanical equipment and the construction of cast layers simultaneously, improves construction efficiency, avoids safety hazards during the demolition of the support system, and ensures construction progress and safety.
Smart Images

Figure CN223240638U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hydropower engineering sluice piers, in particular to a sluice pier. Background Art
[0002] In the field of water conservancy projects, especially in the design and construction of spillways, electromechanical equipment is often integrated inside the piers to operate the opening and closing of the gates. The protection of these electromechanical equipment is crucial to the safe operation of the entire water conservancy project. However, existing spillway piers are often designed as closed structures. For example, the Chinese patent document with publication number CN210507336U discloses a pier in which an inspection gate is suspended within an inspection gate slot. The electromechanical equipment is usually installed in an equipment installation chamber inside the pier and protected by a top cover plate. During the installation of equipment inside existing piers, it is often necessary to simultaneously construct the cover plate. However, the cover plate is generally a monolithic concrete structure that needs to be cast by setting up a formwork support system within the equipment installation chamber. In this way, the formwork support system will occupy the limited internal space of the pier, affecting the installation progress of the electromechanical equipment. In addition, the construction efficiency is low, which is not conducive to ensuring the smooth progress of the construction progress. In addition, the formwork support system needs to be dismantled, and the dismantling work usually needs to be carried out at high altitude, which not only affects construction efficiency but also poses a major safety hazard. The risks of working at height not only threaten the safety of construction workers, but also may cause damage to the electromechanical equipment inside the pier if components of the formwork support system fall, thereby affecting the safe operation of the entire water conservancy project. Utility Model Content
[0003] The technical problem to be solved by the utility model is to overcome the deficiencies of the existing technology and provide a sluice pier that can be constructed simultaneously with the installation of electromechanical equipment inside the pier, thereby improving construction efficiency, ensuring smooth progress of construction, and having a high degree of construction safety.
[0004] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0005] A sluice pier comprises a pier body, wherein an equipment installation chamber is provided in the pier body, an opening is provided at the top of the equipment installation chamber, a cover plate is provided at the top of the pier body to seal the opening of the equipment installation chamber, the cover plate comprises a prefabricated layer and a casting layer, the prefabricated layer comprises a plurality of prefabricated panels spliced in sequence, the prefabricated panels are erected on the pier body and span the top of the equipment installation chamber, the prefabricated panels are pre-embedded with load-bearing beams along the length direction, both ends of the load-bearing beams extend out of the prefabricated panels to form a connecting portion, the casting layer is covered on the prefabricated layer and supported on each load-bearing beam, and both sides of the casting layer are supported on the pier body, and the connecting portion is connected to the casting layer.
[0006] As a further improvement of the above technical solution: the load-bearing beam includes two load-bearing rods arranged in parallel, and a connecting rod connected between the two load-bearing rods, the bottom of the load-bearing rod is embedded in the prefabricated panel and extends along the length direction of the prefabricated panel, and the connecting portion is formed at the end of the load-bearing rod.
[0007] As a further improvement of the above technical solution: a plurality of first stiffening plates are provided on both sides of the load-bearing rod along the length direction.
[0008] As a further improvement of the above technical solution: a second stiffening plate and a third stiffening plate are provided on both sides of the connecting portion, the second stiffening plate is perpendicular to the load-bearing rod, and the third stiffening plate is perpendicular to the second stiffening plate.
[0009] As a further improvement of the above technical solution: the pier body is provided with a first limiting column on the end side of the connecting portion and a second limiting column on the peripheral side of the connecting portion.
[0010] As a further improvement of the above technical solution: the load-bearing beam is provided with a lifting lug.
[0011] As a further improvement of the above technical solution: the bottom end of the lifting ear is fixedly connected to the load-bearing beam and embedded in the prefabricated board, and the top of the lifting ear is formed with a lifting portion and embedded in the casting layer.
[0012] As a further improvement of the above technical solution: an inspection door is provided on the side of the pier body, and a lifting ring is provided on the bottom of the prefabricated plate.
[0013] As a further improvement of the above technical solution: steel bars are embedded in the prefabricated panels, and the load-bearing beams are fixedly connected to the steel bars in the prefabricated panels.
[0014] As a further improvement of the above technical solution: an upper steel mesh and a lower steel mesh are provided inside the prefabricated panel, the bottom of the load-bearing beam is in contact with the lower steel mesh, the load-bearing beam is passed through the upper steel mesh and fixedly connected to the upper steel mesh, and a plurality of tie bars are connected between the upper steel mesh and the lower steel mesh.
[0015] Compared with the prior art, the advantages of the present invention are:
[0016] The sluice pier disclosed in the utility model has a cover plate located on top of the pier body, comprising a prefabricated layer and a cast layer located on the prefabricated layer. The prefabricated layer can be divided into multiple prefabricated panels based on the shape of the pier body top, and each panel is prefabricated and numbered separately. After prefabrication, the panels are hoisted to the top of the pier body in sequence according to their numbers, so that each prefabricated panel spans the top of the equipment installation chamber and is placed on the pier body, providing a stable construction platform for the subsequent cast layer construction. After construction is completed, the cast layer will form an integral part with the prefabricated layer, eliminating the need to remove the prefabricated layer. During the construction of the entire cover plate, there is no need to set up a formwork support system in the equipment installation chamber, which does not occupy the space of the equipment installation chamber. The installation of the electromechanical equipment and the construction of the casting layer can be carried out simultaneously without affecting each other and the installation progress of the electromechanical equipment, thereby improving construction efficiency and ensuring the smooth progress of the construction. At the same time, it also avoids the support components from falling when the support system is removed, thereby damaging the electromechanical equipment or causing casualties, thereby improving construction safety. Each prefabricated board is embedded with a load-bearing beam along the length direction, and the two ends of the load-bearing beam extend out of the prefabricated board to form a connecting portion, which is connected to the casting layer, thereby improving the connection strength between the casting layer and the prefabricated layer after the construction is completed. In addition, during the prefabricated board hoisting process or the casting layer construction process, if the prefabricated board moves and its end separates from the pier body, the connecting portion can also be supported on the top of the pier body, thereby preventing the prefabricated board from falling and damaging the electromechanical equipment or causing casualties, thereby improving safety. The sluice pier disclosed by the utility model does not affect the installation of the electromechanical equipment in the equipment installation chamber during the cover plate construction process, thereby improving construction efficiency and construction safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the arrangement structure of the prefabricated plates of the sluice pier of the utility model.
[0018] Figure 2 yes Figure 1 Schematic diagram of the partial cross-sectional structure along the AA direction.
[0019] Figure 3 yes Figure 2 Schematic diagram of the enlarged structure of part B.
[0020] Figure 4 yes Figure 1 Schematic diagram of the top view of the A3 prefabricated panel.
[0021] Figure 5 yes Figure 4 Schematic diagram of the cross-sectional structure in the CC direction.
[0022] Figure 6 yes Figure 4 Schematic diagram of the cross-sectional structure in the DD direction.
[0023] Figure 7 yes Figure 5Schematic diagram of the cross-sectional structure in the EE direction.
[0024] Figure 8 It is a structural schematic diagram of a lifting lug of a sluice pier of the utility model.
[0025] Figure 9 It is a structural schematic diagram of the tie bars of the sluice pier of the utility model.
[0026] Figure 10 yes Figure 1 Schematic diagram of the structure of the lower layer of steel mesh of the A3 precast panel.
[0027] Figure 11 yes Figure 1 Schematic diagram of the top view of the A1 prefabricated panel.
[0028] Figure 12 yes Figure 1 Schematic diagram of the structure of the lower layer of steel mesh of the A1 precast panel.
[0029] Figure 13 yes Figure 1 Schematic diagram of the top view of the A2 prefabricated panel.
[0030] Figure 14 yes Figure 1 Schematic diagram of the structure of the lower steel mesh of the A2 precast panel.
[0031] Figure 15 It is a structural schematic diagram of the positioning component and the positioning load-bearing beam of the gate pier of the utility model.
[0032] The numbers in the figure represent: 1. Pier body; 11. First limiting column; 12. Second limiting column; 2. Equipment installation chamber; 3. Cover plate; 31. Prefabricated layer; 311. Prefabricated plate; 32. Casting layer; 4. Load-bearing beam; 40. Connection part; 401. Second stiffening plate; 402. Third stiffening plate; 41. Load-bearing rod; 411. First stiffening plate; 42. Connecting rod; 5. Lifting ear; 51. Lifting part; 6. Lifting ring; 7. Upper steel mesh; 8. Lower steel mesh; 9. Tie bar. DETAILED DESCRIPTION
[0033] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0034] In the description of the present invention, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0035] In this utility model, unless otherwise specified or limited, the terms "assemble," "connect," "connect," "fix," etc. should be understood in a broad sense. For example, they can refer to fixed connection, detachable connection, or integration; mechanical connection or electrical connection; direct connection or indirect connection through an intermediate medium; internal communication between two components or interaction between two components. For those skilled in the art, the specific meanings of the above terms in this utility model can be understood according to specific circumstances.
[0036] Figures 1 to 15 An embodiment of a sluice pier of the present invention is shown. The sluice pier of this embodiment includes a pier body 1. An equipment installation chamber 2 is provided in the pier body 1. An opening is provided on the top of the equipment installation chamber 2. A cover plate 3 is provided on the top of the pier body 1 to seal the opening of the equipment installation chamber 2. The cover plate 3 includes a prefabricated layer 31 and a casting layer 32. The prefabricated layer 31 includes a plurality of prefabricated panels 311 spliced in sequence. The prefabricated panels 311 are erected on the pier body 1 and span the top of the equipment installation chamber 2. The prefabricated panels 311 are pre-embedded with load-bearing beams 4 along the length direction. Both ends of the load-bearing beams 4 extend out of the prefabricated panels 311 to form a connecting portion 40. The casting layer 32 is covered on the prefabricated layer 31 and supported on each load-bearing beam 4. Both sides of the casting layer 32 are supported on the pier body 1. The connecting portion 40 is connected to the casting layer 32.
[0037] In the sluice pier of this embodiment, the cover plate 3 provided on the top of the pier body 1 includes a prefabricated layer 31 and a cast layer 32 provided on the prefabricated layer 31. The prefabricated layer 31 can be divided into multiple prefabricated panels 311 according to the shape of the top of the pier body 1. These panels are prefabricated and numbered separately. After prefabrication, they are hoisted to the top of the pier body 1 in sequence according to their numbers, so that each prefabricated panel 311 spans the top of the equipment installation chamber 2 and is erected on the pier body 1, providing a stable construction platform for the subsequent construction of the cast layer 32. After construction is completed, the cast layer 32 will form an integral part with the prefabricated layer 31, without the need to remove the prefabricated layer 31. During the construction of the entire cover plate 3, there is no need to set up a formwork support system in the equipment installation chamber 2, and the space of the equipment installation chamber 2 is not occupied. The installation of the electromechanical equipment and the construction of the casting layer 32 can be carried out simultaneously without affecting each other and the installation progress of the electromechanical equipment, thereby improving construction efficiency and ensuring the smooth progress of the construction progress. At the same time, it also avoids the support components from falling when the support system is dismantled, thereby damaging the electromechanical equipment or causing casualties, thereby improving construction safety; each prefabricated panel 311 is buried with a load-bearing beam 4 along the length direction, and both ends of the load-bearing beam 4 extend out of the prefabricated panel 311 to form a connecting portion 40, which is connected to the casting layer 32, which is conducive to improving the connection strength between the casting layer 32 and the prefabricated layer 31 after the construction is completed. In addition, during the hoisting process of the prefabricated panel 311 or the construction process of the casting layer 32, if the prefabricated panel 311 moves and its end is separated from the pier body 1, the connecting portion 40 can also be supported on the top of the pier body 1, which is conducive to preventing the prefabricated panel 311 from falling and damaging the electromechanical equipment or causing casualties, and has high safety. The sluice pier and the cover plate 3 of this embodiment will not affect the installation of the electromechanical equipment in the equipment installation chamber 2 during the construction process, and the construction efficiency and construction safety are high.
[0038] Furthermore, in this embodiment, the load-bearing beam 4 includes two load-bearing rods 41 arranged in parallel, and a connecting rod 42 connected between the two load-bearing rods 41 (see Figure 4 ), the bottom of the load-bearing rod 41 is embedded in the prefabricated plate 311 and extends along the length direction of the prefabricated plate 311, and the connecting portion 40 is formed at the end of the load-bearing rod 41 (see Figure 5 Specifically, multiple connecting rods 42 are provided and spaced along the length of the load-bearing rods 41. Connecting rods 42 are located within the prefabricated panel 311. This reduces the weight of the load-bearing beam 4 while maintaining its structural strength. Of course, in other embodiments, depending on the size of the prefabricated panel 311 and actual construction needs, a single or multiple load-bearing rods 41 may be provided, with connecting rods 42 connecting adjacent load-bearing rods 41. The details will not be repeated here.
[0039] As a preferred embodiment, the load-bearing rod 41 is an I-beam (see Figure 7 ), the connecting rod 42 is an angle steel (see Figure 5), the ends of the connecting rod 42 are respectively welded to the webs of the two load-bearing beams 4. I-beams and angle steel are easily available on site and have high structural strength. The flanges of the I-beams increase the contact area with the precast panels 311, improving the connection strength between them and the precast panels 311, thereby enhancing the ability of the load-bearing beams 4 and precast panels 311 to jointly bear the weight of the concrete cast layer 32.
[0040] Furthermore, in this embodiment, a plurality of first stiffening plates 411 are provided on both sides of the load-bearing rod 41 along the length direction (see Figure 2 、 Figure 5 and Figure 8 This can effectively enhance the rigidity and strength of the load-bearing rod 41, reduce the deflection and deformation of the load-bearing rod 41 when subjected to force, and help enhance stability during long-term use. Specifically, the side surfaces of the first stiffening plates 411 are welded to the web of the load-bearing rod 41, the top surfaces of the first stiffening plates 411 are welded to the upper flange of the load-bearing rod 41, and the bottom surfaces of the first stiffening plates 411 are welded to the lower flange of the load-bearing rod 41. Preferably, the first stiffening plates 411 on both sides of the load-bearing rod 41 are arranged symmetrically.
[0041] See Figure 2 、 Figure 3 、 Figure 5 and Figure 7 Furthermore, in this embodiment, a second stiffening plate 401 and a third stiffening plate 402 are provided on both sides of the connecting portion 40 (see Figure 7 ), the second stiffening plate 401 is perpendicular to the load-bearing rod 41, and the third stiffening plate 402 is perpendicular to the second stiffening plate 401 (see Figure 2 、 Figure 3 and Figure 5 ). The structural strength of the connection part 40 is enhanced, the connection area between the connection part 40 and the casting layer 32 is increased, and the connection strength between the load-bearing beam 4 and the casting layer 32 is improved. Specifically, a plurality of second stiffening plates 401 are spaced apart along the length direction of the connection part 40, the side surfaces of the second stiffening plates 401 are welded to the web of the load-bearing rod 41, the top surfaces of the second stiffening plates 401 are welded to the upper flange of the load-bearing rod 41, the bottom surfaces of the second stiffening plates 401 are welded to the lower flange of the load-bearing rod 41, the side surfaces of the third stiffening plates 402 are welded to the web of the load-bearing rod 41, and the two ends of the third stiffening plate 402 are respectively welded to the two adjacent second stiffening plates 401 located on the same connection part 40. Preferably, the second stiffening plates 401 on both sides of the connection part 40 are symmetrically arranged, and the third stiffening plates 402 on both sides of the connection part 40 are symmetrically arranged.
[0042] Furthermore, in this embodiment, the pier body 1 is provided with a first limiting column 11 at the end side of the connecting portion 40 and a second limiting column 12 at the peripheral side of the connecting portion 40 (see Figure 1 and Figure 15), the first limiting posts 11 and the second limiting posts 12 have a simple structure, which facilitates the accurate positioning of the precast panel 311 when it is hoisted onto the pier body 1. After the precast panel 311 is hoisted onto the pier body 1 and its position is determined, the first limiting posts 11 and the second limiting posts 12 limit the precast panel 311 to prevent it from shifting.
[0043] Furthermore, in this embodiment, the load-bearing beam 4 is provided with a lifting lug 5 (see Figure 9 ) to facilitate the lifting of prefabricated panels 311.
[0044] Furthermore, in this embodiment, the bottom end of the lifting lug 5 is fixedly connected to the load-bearing beam 4 and embedded in the precast plate 311, and the top of the lifting lug 5 is formed with a lifting portion 51 and embedded in the casting layer 32 (see Figure 2 The bottom end of the lifting lug 5 is embedded in the precast panel 311, further enhancing the structural strength of the precast panel 311 while also strengthening the connection between the lifting lug 5 and the load-bearing beam 4, thereby preventing the lifting lug 5 from falling off during the installation of the precast panel 311. The lifting portion 51 is embedded in the casting layer 32, thereby strengthening the connection between the precast layer 31 and the casting layer 32.
[0045] See Figure 2 、 Figure 4 、 Figure 5 、 Figure 11 and Figure 13 As a preferred embodiment, the lifting lugs 5 are provided on the load-bearing rods 41. The lifting lugs 5 are symmetrically provided on the front and rear sides of each load-bearing rod 41. The lifting lugs 5 are welded to the first stiffening plates 411 provided on the load-bearing rods 41. This is conducive to ensuring stability when hoisting the prefabricated panels 311.
[0046] Furthermore, in this embodiment, an inspection door (not shown) is provided on the side of the pier body 1, and a lifting ring 6 is provided at the bottom of the prefabricated plate 311 (see Figure 1 、 Figure 4 、 Figure 11 and Figure 13 ). It is convenient for maintenance personnel to maintain and replace the equipment in the equipment installation chamber 2.
[0047] See Figure 5 and Figure 6Furthermore, in this embodiment, steel bars are embedded in the precast panel 311, and the load-bearing beam 4 is fixedly connected to the steel bars in the precast panel 311. Specifically, an upper steel mesh 7 and a lower steel mesh 8 are provided inside the precast panel 311, and the bottom of the load-bearing beam 4 abuts against the lower steel mesh 8. The load-bearing beam 4 passes through the upper steel mesh 7 and is fixedly connected to the upper steel mesh 7. A plurality of tie bars 9 are connected between the upper steel mesh 7 and the lower steel mesh 8. The structural strength of the precast panel 311 is enhanced, and a more stable platform is provided for the construction of the casting layer 32. Preferably, a through hole is provided on the load-bearing rod 41 for the transverse steel bars of the upper steel mesh 7 to pass through, and the connection strength and integrity of the load-bearing rod 41 and the upper steel mesh 7 are higher.
[0048] The construction method of the sluice pier of this embodiment is as follows:
[0049] First, the pier body 1 is constructed. While the pier body 1 is being constructed, each precast panel 311 of the precast layer 31 is precast. After the pier body 1 is constructed, the electromechanical equipment is installed in the equipment installation chamber 2 inside the pier body 1. After the precast panels 311 are constructed, they are hoisted to the designated positions on the pier body 1 in sequence. After each precast panel 311 is hoisted into place, concrete is poured on the precast panel 311 to form a casting layer 32, so that the casting layer 32 covers the precast layer 31. After the construction of the casting layer 32 and the installation of the electromechanical equipment are completed, the construction of the sluice pier is completed. It should be noted that during the hoisting of the precast panels 311 and the construction of the casting layer 32, the installation of the electromechanical equipment is carried out simultaneously.
[0050] The construction process of the prefabricated panel 311 of this embodiment is as follows:
[0051] First, lay the lower steel mesh 8; then, fix two load-bearing rods 41 welded with the first stiffening plate 411, the second stiffening plate 401 and the third stiffening plate 402 on both sides of the upper surface of the lower steel mesh 8; then weld a plurality of connecting rods 42 between the two load-bearing rods 41; then lay the upper steel mesh 7, and fix the load-bearing rods 41 to the upper steel mesh 7; then weld the lifting lugs 5 on the load-bearing rods 41; then arrange the side formwork around the circumference of the upper steel mesh 7 and the lower steel mesh 8; after the side formwork is arranged, pour concrete to form the precast panel 311. It should be noted that after the concrete pouring is completed, the precast panel 311 needs to be cured, and the precast panel 311 can be hoisted to the top of the pier body 1 only after the curing is completed.
[0052] Although the present invention has been disclosed above with reference to preferred embodiments, this is not intended to limit the present invention. Any person skilled in the art can, without departing from the scope of the present invention, utilize the technical content disclosed above to make many possible changes and modifications to the present invention, or modify it into equivalent embodiments with equivalent variations. Therefore, any simple modifications, equivalent variations, and modifications to the above embodiments that do not depart from the content of the present invention and are based on the technical essence of the present invention shall fall within the scope of protection of the present invention.
Claims
1. A sluice pier, comprising a pier body (1), wherein an equipment installation chamber (2) is provided in the pier body (1), an opening is provided at the top of the equipment installation chamber (2), and a cover plate (3) is provided at the top of the pier body (1) to cover the opening of the equipment installation chamber (2), characterized in that: The cover plate (3) comprises a prefabricated layer (31) and a casting layer (32); the prefabricated layer (31) comprises a plurality of prefabricated panels (311) spliced in sequence; the prefabricated panels (311) are laid on the pier body (1) and span the top of the equipment installation chamber (2); the prefabricated panels (311) are pre-buried with load-bearing beams (4) along the length direction; both ends of the load-bearing beams (4) extend out of the prefabricated panels (311) to form connecting portions (40); the casting layer (32) is covered on the prefabricated layer (31) and supported on each load-bearing beam (4); and both sides of the casting layer (32) are supported on the pier body (1); and the connecting portion (40) is connected to the casting layer (32).
2. The sluice pier according to claim 1, characterized in that: The load-bearing beam (4) comprises two load-bearing rods (41) arranged in parallel, and a connecting rod (42) connected between the two load-bearing rods (41); the bottom of the load-bearing rod (41) is pre-buried in the prefabricated plate (311) and extends along the length direction of the prefabricated plate (311); and the connecting portion (40) is formed at the end of the load-bearing rod (41).
3. The sluice pier according to claim 2, characterized in that: A plurality of first stiffening plates (411) are provided on both sides of the load-bearing rod (41) along the length direction.
4. The sluice pier according to claim 2, characterized in that: A second stiffening plate (401) and a third stiffening plate (402) are provided on both sides of the connecting portion (40), the second stiffening plate (401) is perpendicular to the load-bearing rod (41), and the third stiffening plate (402) is perpendicular to the second stiffening plate (401).
5. The sluice pier according to claim 1, characterized in that: The pier body (1) is provided with a first limiting column (11) on the end side of the connecting portion (40), and a second limiting column (12) on the peripheral side of the connecting portion (40).
6. The sluice pier according to claim 1, characterized in that: The load-bearing beam (4) is provided with a lifting lug (5).
7. The sluice pier according to claim 6, characterized in that: The bottom end of the lifting lug (5) is fixedly connected to the load-bearing beam (4) and embedded in the prefabricated plate (311); the top of the lifting lug (5) is formed with a lifting portion (51) and embedded in the casting layer (32).
8. The sluice pier according to any one of claims 1 to 7, characterized in that: An inspection door is provided on the side of the pier body (1), and a lifting ring (6) is provided on the bottom of the prefabricated plate (311).
9. The sluice pier according to any one of claims 1 to 7, characterized in that: Steel bars are embedded in the prefabricated plate (311), and the load-bearing beam (4) is fixedly connected to the steel bars in the prefabricated plate (311).
10. The sluice pier according to claim 9, characterized in that: An upper steel mesh (7) and a lower steel mesh (8) are provided inside the prefabricated plate (311); the bottom of the load-bearing beam (4) abuts against the lower steel mesh (8); the load-bearing beam (4) is passed through the upper steel mesh (7) and fixedly connected to the upper steel mesh (7); and a plurality of tie bars (9) are connected between the upper steel mesh (7) and the lower steel mesh (8).
Citation Information
Patent Citations
Device for hanging bulkhead gate in bulkhead gate groove
CN210507336U