Detachable scaffold wall connecting piece

By pre-embedding sleeve bolt assemblies in the building wall and connecting them with L-shaped flat irons, a detachable scaffolding wall connection is formed, which solves the problems of material waste and leakage risks of traditional wall connections, and realizes the turnover of materials and the simplicity of construction.

CN223305390UActive Publication Date: 2025-09-05CHINA MCC5 GROUP CORP LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421749213.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2025-09-05
Estimated Expiration
2034-07-23

AI Technical Summary

Technical Problem

In the existing technology, traditional wall ties use large amounts of materials and cannot be recycled, resulting in unstable connections and the risk of leakage on the building's exterior walls.

Method used

The sleeve bolt assembly is embedded in the building wall and connected to the horizontal steel pipe through the L-shaped flat iron to form a detachable scaffolding wall connection component. The assembly can be used in a turnover manner.

Benefits of technology

It reduces material consumption, improves material utilization rate, connection reliability, reduces leakage risk, has low construction difficulty and low cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223305390U_ABST
    Figure CN223305390U_ABST
Patent Text Reader

Abstract

The utility model discloses a detachable scaffold wall connecting piece which comprises a transverse steel pipe connected with an outer scaffold vertical rod, a sleeve bolt assembly pre-buried in a building wall and L-shaped flat iron. The sleeve bolt assembly comprises a sleeve and a bolt and nut assembly. The sleeve comprises an end head and a pipe body, and a hexagon nut fixing groove is formed in the end head; the hexagon nut is arranged in the hexagon nut fixing groove. The vertical section of the L-shaped flat iron is provided with a bolt hole, and the transverse section of the L-shaped flat iron is fixedly connected with the transverse steel pipe. A bolt matched with the hexagon nut penetrates through the bolt hole, then penetrates through the open end of the pipe body and is fastened through the hexagon nut. Most components are recycled through a small number of pre-embedded and sleeve positioning bolt connection, the material consumption is greatly reduced, connection is reliable, and the leakage risk is small.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to a detachable scaffolding wall connecting piece. Background Art

[0002] Currently, building construction projects often require the erection of scaffolding outside buildings for on-site production and construction needs. To ensure the stability of the scaffolding and ensure safe on-site construction, wall ties must be calculated and installed according to the scaffolding plan. Currently, the most commonly used wall tie connection method involves pre-embedded vertical steel pipes in the main structure, which are then secured to the external scaffolding poles using horizontal steel pipes. Traditional wall ties use a large amount of material, are non-recyclable, hinder subsequent masonry and plastering work, and pose a high risk of leakage on the building's exterior walls.

[0003] Utility model patent publication number CN219365371U discloses a recyclable scaffolding wall connector assembly, comprising a horizontal tube, a sleeve, and through-wall bolts. While this solution eliminates the need for pre-embedded components within the main structure, the use of through-wall bolts creates a risk of wall leakage. Therefore, developing a removable scaffolding wall connector that is recyclable, provides reliable connections, and minimizes leakage risk is a pressing technical challenge. Utility Model Content

[0004] Due to the above-mentioned defects in the prior art, the utility model provides a detachable scaffolding wall connection part, which is connected by a small number of pre-embedded and sleeve-positioned bolts, and most of the components are recycled, which greatly reduces the material usage, and has a reliable connection and low leakage risk.

[0005] To achieve the above-mentioned object, the present invention provides a detachable scaffolding wall connecting member, comprising a transverse steel pipe connected to an outer scaffolding upright, characterized in that it also includes:

[0006] A sleeve bolt assembly embedded in a building wall comprises a sleeve and a bolt-nut assembly; the sleeve comprises an end and a tube body, the end being provided with a hexagonal nut fixing groove; the hexagonal nut being arranged in the hexagonal nut fixing groove;

[0007] An L-shaped flat iron, wherein bolt holes are provided on the vertical section and the horizontal section is fixedly connected to the horizontal steel pipe;

[0008] A bolt matched with the hexagonal nut passes through the bolt hole and then penetrates from the open end of the tube body and is fastened by the hexagonal nut.

[0009] The sleeve bolt assembly of the wall connecting piece is embedded in the wall through the formwork before the building wall is cast. After the building wall is cast, it can be used as a wall connecting piece by connecting it with the L-shaped flat iron. After the scaffolding is dismantled, the connecting bolts, flat iron and transverse steel pipe are recovered and reused.

[0010] Furthermore, the length of the end is 18.4 mm, and the length of the tube body is 65 mm.

[0011] Furthermore, the specifications of the hexagonal nuts and bolts are M14.

[0012] Furthermore, the sleeve is a 2mm thick PVC sleeve.

[0013] Furthermore, the thickness of the L-shaped flat iron is 5 mm.

[0014] Compared with the prior art, the above utility model has the following advantages or beneficial effects:

[0015] (1) The utility model only needs to embed a small-sized sleeve bolt assembly, which can be effectively connected with the structure to ensure the safety and stability of the frame, and has little impact on subsequent masonry, reducing the risk of leakage of the exterior wall;

[0016] (2) Most of the components of the utility model can be used in a reusable manner, thereby improving the utilization rate of materials;

[0017] (3) The utility model is easy to assemble, has low construction difficulty, simple operation and low cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The present invention and its features and advantages will become more apparent upon reading the detailed description of non-limiting embodiments with reference to the following drawings. Like reference numerals indicate like parts throughout the drawings. The drawings are not drawn to scale, with emphasis placed on illustrating the subject matter of the present invention.

[0019] Figure 1 This is a schematic diagram of the overall structure of a wall connecting member according to an embodiment of the present utility model;

[0020] Figure 2 This is a front view of a sleeve bolt assembly according to an embodiment of the present invention;

[0021] Figure 3 This is a left side view of a sleeve bolt assembly according to an embodiment of the present invention;

[0022] Figure 4 This is a right side view of a sleeve bolt assembly according to an embodiment of the present invention;

[0023] Figure 5 This is an axial cross-sectional view of a sleeve bolt assembly according to an embodiment of the present invention;

[0024] Among them, 1. horizontal steel pipe; 2. sleeve bolt assembly; 21. sleeve; 211. end; 212. pipe body; 22. hexagonal nut; 23. bolt; 3. L-shaped flat iron; 31. bolt hole; 4. building wall. DETAILED DESCRIPTION

[0025] The structure of the present invention will be further described below with reference to the accompanying drawings and specific embodiments, but they are not intended to limit the present invention.

[0026] The actions, steps, and the like in the apparatus and methods described in the claims, specifications, and drawings may be performed in any order unless otherwise specified, and as long as the output of a preceding process is not used in a subsequent process. The use of terms such as "first," "second," and "third" for convenience does not necessarily imply a requirement for execution in this order.

[0027] Example

[0028] See also Figures 1 to 5 This embodiment provides a detachable scaffolding wall connecting member, including a transverse steel pipe 1 connected to the outer scaffolding upright, a sleeve bolt assembly 2, and an L-shaped flat iron 3. The sleeve bolt assembly 2 is embedded in the building wall 4 and includes a sleeve 21 and a bolt and nut assembly; the sleeve 21 includes an end 211 and a tube body 212, and the end 211 is provided with a hexagonal nut fixing groove; the hexagonal nut 22 is arranged in the hexagonal nut fixing groove. A bolt hole 31 is provided on the vertical section of the L-shaped flat iron 3, and the transverse section is fixedly connected to the transverse steel pipe 1. The bolt 23 that matches the hexagonal nut 22 passes through the bolt hole 31, then penetrates from the open end of the tube body 212, and is fastened by the hexagonal nut 22.

[0029] The steps for using the wall connecting piece are as follows:

[0030] First, the wall connection piece is positioned and a hole is drilled in the building wall template at the corresponding position. The diameter of the hole is just enough to allow the bolt 23 to penetrate.

[0031] Next, the bolt 23 passes through the template opening and then enters from the open end of the tube body 212 , and is fastened by the hexagonal nut 22 , and the sleeve bolt assembly 2 is assembled on the template.

[0032] Next, pour concrete for the building wall 4. After the formwork is removed, remove the bolts 23, insert them through the bolt holes 31 in the L-shaped flat iron 3, and then through the open end of the tube 212, tightening them with hexagonal nuts 22. The transverse section of the L-shaped flat iron 3 is fixedly connected to the transverse steel tube 1, preferably by welding, but can also be connected by pipe clamps or other methods.

[0033] Finally, after the scaffolding is dismantled, the connecting bolts, flat irons and transverse steel pipes are recycled and reused.

[0034] The sleeve bolt assembly of the wall connecting piece is embedded in the wall through the formwork before the building wall is cast. After the building wall is cast, it can be used as a wall connecting piece by connecting it with the L-shaped flat iron. After the scaffolding is dismantled, the connecting bolts, flat iron and transverse steel pipe are recovered and reused.

[0035] As a preferred, feasible solution, the length of the end cap 211 is 18.4 mm, and the length of the tube body 212 is 65 mm. The hexagonal nut 22 and bolt 23 are M14 in size. The length of the sleeve determines the embedment depth. The specifications of the bolt and sleeve should be appropriately selected based on the load the embedded bolt needs to withstand.

[0036] As an implementable preferred technical solution, the sleeve 21 is a 2 mm thick PVC sleeve, which is easily available on site.

[0037] As an implementable preferred technical solution, the thickness of the L-shaped flat iron 3 is 5mm, which can be adjusted according to the load of the L-shaped flat iron and the principle of saving materials. When the load is large, a rib plate can be added between the two sections of the flat iron.

[0038] It can be seen that the wall connecting parts are effectively connected to the main body of the building to ensure the safety and stability of the frame; the assembly is simple, the cost is low, the embedded depth is adjustable, the impact on subsequent masonry is small, and the hidden danger of leakage of the exterior wall is reduced; the construction difficulty is small and the operation is simple; most components can be used in rotation to improve the utilization rate of materials.

[0039] In summary, the utility model provides a detachable scaffolding wall connection component, including a transverse steel pipe connected to the outer scaffolding upright, a sleeve bolt assembly embedded in the building wall, and an L-shaped flat iron. The sleeve bolt assembly includes a sleeve and a bolt and nut assembly; the sleeve includes an end and a tube body, and a hexagonal nut fixing groove is provided in the end head; the hexagonal nut is provided in the hexagonal nut fixing groove. Bolt holes are provided on the vertical section of the L-shaped flat iron, and the transverse section is fixedly connected to the transverse steel pipe. The bolt matching the hexagonal nut passes through the bolt hole, and then passes through the open end of the tube body and is tightened by the hexagonal nut. By connecting with a small amount of pre-embedded and sleeve-positioned bolts, most of the components are recycled, which greatly reduces the material consumption, and the connection is reliable and the risk of leakage is small.

[0040] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-mentioned disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solution of the present invention, or modify them into equivalent embodiments with equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention that do not depart from the content of the technical solution of the present invention are still within the scope of protection of the technical solution of the present invention.

Claims

1. A detachable scaffolding wall connecting member, comprising a transverse steel pipe (1) connected to an outer scaffolding upright, characterized in that: Also includes: A sleeve bolt assembly (2) embedded in a building wall comprises a sleeve (21) and a bolt and nut assembly; the sleeve (21) comprises an end (211) and a tube body (212); a hexagonal nut fixing groove is provided in the end (211); and a hexagonal nut (22) is provided in the hexagonal nut fixing groove; An L-shaped flat iron (3) with bolt holes (31) formed on its vertical section and a transverse section fixedly connected to the transverse steel pipe (1); A bolt (23) matched with the hexagonal nut (22) passes through the bolt hole (31) and then penetrates from the open end of the tube body (212) and is fastened by the hexagonal nut (22).

2. The detachable scaffolding wall connecting member according to claim 1, characterized in that: The length of the end head (211) is 18.4 mm, and the length of the tube body (212) is 65 mm.

3. The detachable scaffolding wall connecting member according to claim 2, characterized in that: The specifications of the hexagonal nut (22) and the bolt (23) are M14.

4. The detachable scaffolding wall connecting member according to claim 1, characterized in that: The sleeve (21) is a 2mm thick PVC sleeve.

5. The detachable scaffolding wall connecting member according to claim 1, characterized in that: The thickness of the L-shaped flat iron (3) is 5 mm.

Citation Information

Patent Citations

  • Recyclable scaffold wall connecting piece device

    CN219365371U