By connecting the pre-embedded bolts and connecting components to the I-beam cantilever beams of the cantilever scaffold as a whole, the problem of the stability of the cantilever scaffold being affected by individual tie rod connections is solved, thereby improving the overall stability and safety.
Patent Information
- Application Number
- CN202422601129.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-28
- Publication Date
- 2025-10-31
- Estimated Expiration
- 2034-10-28
AI Technical Summary
In existing cantilever scaffolding, the tie rods are connected separately between the I-beam cantilever and the wall. This results in instability due to the uncertainty of the wall position at the connection point and the load-bearing capacity of workers, which affects the overall stability, especially when one tie rod falls off.
The pre-embedded screw and connecting components are used. The pre-embedded screw and the I-beam cantilever rod are connected as a whole through the first connecting component and the second connecting component to ensure uniform force distribution, enhance anti-derailment ability, and further increase the firmness of the tie rod through the second connecting component.
This enhanced the overall stability of the cantilevered scaffolding, prevented tie rods from falling off, and improved safety and stability during construction.
Smart Images

Figure CN223497525U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of scaffolding technology, and in particular to a scaffolding for highway bridge construction. Background Technology
[0002] Scaffolding is a temporary structure used in construction, providing workers with a platform and support system so they can work safely at heights. Scaffolding used in highway and bridge construction can be categorized into cup-lock scaffolding, wheel-type scaffolding, frame scaffolding, folding scaffolding, tower scaffolding, cantilever scaffolding, hoist scaffolding, self-elevating scaffolding, suspended scaffolding, and mobile scaffolding. Cantilever scaffolding extends from a building or other structure, providing workers with a working platform close to the building's outer edge.
[0003] Existing cantilever scaffolding uses tie rods that are diagonally braced between the I-beam cantilever and the wall to increase the stability of the cantilever scaffolding. Each tie rod is individually connected to the wall. Due to the uncertainty of the wall position at the connection point and the load-bearing capacity of workers moving back and forth, if one tie rod falls off, it will affect the overall stability of the scaffolding. Therefore, there is a need to provide a scaffolding for highway bridge construction to solve the above problems. Utility Model Content
[0004] The purpose of this utility model is to provide a scaffold for highway bridge construction to solve the problem mentioned in the background art. In existing cantilever scaffolds, the tie rods are diagonally stretched between the I-beam cantilever and the wall to increase the stability of the cantilever scaffold. However, each tie rod is individually connected to the wall. Due to the uncertainty of the wall position at the connection point and the load-bearing capacity of workers walking back and forth, if one tie rod falls off, it will affect the overall stability of the scaffold.
[0005] To solve the above-mentioned technical problems, this utility model is achieved through the following technical solution:
[0006] This utility model relates to a scaffolding for highway bridge construction, comprising:
[0007] The cantilevered scaffolding includes pre-embedded screws and tie rods. One end of the pre-embedded screw is embedded in the wall, and one end of the tie rod is attached to the end of the pre-embedded screw located outside the wall.
[0008] The first connecting assembly includes a first connecting plate, a first U-shaped slot, a U-shaped support frame, a second U-shaped slot, a second connecting plate, a third U-shaped slot, and a first bolt. The first U-shaped slot is formed on both sides of the lower end of the first connecting plate. The first connecting plate is snapped onto one end of two pre-embedded screws through the first U-shaped slot. The U-shaped support frame is fixed on both sides of the upper end of the first connecting plate. The second U-shaped slot is formed on both sides of the side of the U-shaped support frame. The second connecting plate is fixed on both sides of one end of the pre-embedded screw. The third U-shaped slot is formed on one end of the second connecting plate. The first bolt is inserted into the second U-shaped slot and the third U-shaped slot.
[0009] Furthermore, the first connecting component also includes an opening, which is formed on the side of the U-shaped support frame and located between the two second U-shaped slots.
[0010] Furthermore, the cantilever scaffold also includes I-beam cantilever poles and support poles. One end of the I-beam cantilever pole is fixed to the wall, and multiple support poles are assembled into a support frame by clamps and fixed to the I-beam cantilever pole.
[0011] Furthermore, the cantilever scaffold also includes a U-shaped connector, which is welded to the end of the I-beam cantilever rod away from the wall, and the other end of the rod is hooked onto the U-shaped connector.
[0012] Furthermore, it also includes a second connector, which includes a first waist hole, a third connecting plate, and a second waist hole. The first waist hole is located at both ends of the first connecting plate, and the second waist hole is located at both ends of the third connecting plate.
[0013] Furthermore, the second connector also includes a second bolt and a third bolt. The second bolt is inserted into the first waist hole and the second waist hole at the upper end of the third connecting plate. One end of the third bolt is fixed to the end of the I-beam cantilever rod that is fixed to the wall, and the other end is inserted into the second waist hole at the lower end of the third connecting plate.
[0014] Compared with existing technologies, the advantages of this utility model are:
[0015] I. This utility model, through the first connecting component, installs the I-beam cantilever rod, embeds the pre-embedded screw rod into the wall, holds the first connecting plate, and from the first U-shaped slot, clamps the first connecting plate onto the pre-embedded screw rod above the outer end of the wall. At this time, the U-shaped support frame is located outside the second connecting plate at the outer end of the pre-embedded screw rod. The first bolt is inserted into the second U-shaped slot and the third U-shaped slot on the second connecting plate, and the first bolt is tightened. At this time, the two pre-embedded screw rods are connected into a whole through the first connecting component. This setting can make the two pre-embedded screw rods bear force evenly, and after being connected into a whole, the anti-detachment ability is enhanced.
[0016] II. In this utility model, by setting a second connecting component, the second bolt passes through the first waist hole and the second waist hole at the upper end of the third connecting plate, while the waist hole at the lower end of the third connecting plate is fitted onto the third bolt on the I-beam cantilever rod. The second bolt and the third bolt are tightened respectively. This setting connects the pre-embedded screw rod and the I-beam cantilever rod into a whole, further increasing the firmness of the tie rod. Attached Figure Description
[0017] To more clearly illustrate the technical solutions of the embodiments of this utility model, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0018] Figure 1 This is a schematic diagram of the overall structure of this utility model;
[0019] Figure 2 This is a schematic diagram showing the positions of the first connecting component and the second connecting component of this utility model;
[0020] Figure 3 This is a schematic diagram of the first connecting component of this utility model;
[0021] Figure 4 For the present utility model Figure 2 Enlarged view of point A in the middle;
[0022] Figure 5 For the present utility model Figure 2 Enlarged view of section B in the middle.
[0023] The attached diagram lists the components represented by each number as follows:
[0024] 10. I-beam cantilever pole; 11. Support rod; 12. U-shaped connector; 13. Embedded screw; 14. Tie rod; 20. First connecting plate; 21. First U-shaped slot; 22. U-shaped support frame; 23. Opening; 24. Second U-shaped slot; 25. Second connecting plate; 26. Third U-shaped slot; 27. First bolt; 30. First waist hole; 31. Third connecting plate; 32. Second waist hole; 33. Second bolt; 34. Third bolt. Detailed Implementation
[0025] To make the above-mentioned objectives, features and advantages of this utility model more apparent and understandable, the specific embodiments of this utility model will be described in detail below with reference to the accompanying drawings.
[0026] Many specific details are set forth in the following description in order to provide a full understanding of the present invention. However, the present invention may also be implemented in other ways different from those described herein. Those skilled in the art can make similar extensions without departing from the spirit of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0027] To make the objectives, technical solutions, and advantages of this utility model clearer, the embodiments of this utility model will be described in further detail below with reference to the accompanying drawings.
[0028] Please see Figure 1-3 As shown, this embodiment is a scaffold for highway bridge construction, comprising:
[0029] The cantilever scaffolding includes embedded screws 13 and tie rods 14. One end of the embedded screw 13 is embedded in the wall, and one end of the tie rod 14 is attached to the end of the embedded screw 13 located outside the wall.
[0030] The cantilever scaffold also includes I-beam cantilever poles 10 and support poles 11. One end of the I-beam cantilever pole 10 is fixed to the wall, and multiple support poles 11 are assembled into a support frame by clamps and fixed to the I-beam cantilever pole 10.
[0031] The cantilever scaffold also includes a U-shaped connector 12, which is welded to the end of the I-beam cantilever pole 10 away from the wall, and the other end of the tie rod 14 is attached to the U-shaped connector 12.
[0032] The I-beam cantilever pole 10 provides support, the support rod 11 forms a support frame and provides support, the U-shaped connector 12 and the pre-embedded screw 13 are used to connect the tie rod 14, and the tie rod 14 provides tension.
[0033] The first connecting assembly includes a first connecting plate 20, a first U-shaped slot 21, a U-shaped support frame 22, a second U-shaped slot 24, a second connecting plate 25, a third U-shaped slot 26, and a first bolt 27. The first U-shaped slot 21 is formed on both sides of the lower end of the first connecting plate 20. The first connecting plate 20 is snapped onto one end of two pre-embedded screws 13 through the first U-shaped slot 21. The U-shaped support frame 22 is fixed on both sides of the upper end of the first connecting plate 20. The second U-shaped slot 24 is formed on both sides of the side of the U-shaped support frame 22. The second connecting plate 25 is fixed on both sides of one end of the pre-embedded screws 13. The third U-shaped slot 26 is formed on one end of the second connecting plate 25. The first bolt 27 is inserted into the second U-shaped slot 24 and the third U-shaped slot 26.
[0034] The first connecting component also includes an opening 23, which is opened on the side of the U-shaped support frame 22 and located between the two second U-shaped slots 24;
[0035] The first connecting plate 20 serves a connecting function, the first U-shaped slot 21 facilitates the connection of the pre-embedded screw 13, the U-shaped support frame 22 serves a supporting function, the opening 23 is used to avoid the tie rod 14, the second connecting plate 25 serves a supporting function, and the second U-shaped slot 24 and the third U-shaped slot 26 cooperate with the first bolt 27 to serve a connecting function.
[0036] Working principle:
[0037] After installing the I-beam cantilever rod 10, embed the pre-embedded screw rod 13 into the wall. Holding the first connecting plate 20, from the first U-shaped slot 21, clamp the first connecting plate 20 onto the pre-embedded screw rod 13 above the outer end of the wall. At this time, the U-shaped support frame 22 is located outside the second connecting plate 25 at the outer end of the pre-embedded screw rod 13. Insert the first bolt 27 into the third U-shaped slot 26 on the second U-shaped slot 24 and the second connecting plate 25, and tighten the first bolt 27. At this time, the two pre-embedded screw rods 13 are connected into a whole through the first connecting assembly.
[0038] This step ensures that the two pre-embedded screws 13 are subjected to uniform force, and when connected as a whole, the anti-detachment ability is enhanced.
[0039] Please see Figure 3-5 This embodiment, based on the above embodiments, further includes:
[0040] The second connector includes a first waist hole 30, a third connecting plate 31, and a second waist hole 32. The first waist hole 30 is opened at both ends of the first connecting plate 20, and the second waist hole 32 is opened at both ends of the third connecting plate 31.
[0041] The second connector also includes a second bolt 33 and a third bolt 34. The second bolt 33 is inserted into the first waist hole 30 and the second waist hole 32 at the upper end of the third connecting plate 31. One end of the third bolt 34 is fixed to the end of the I-beam cantilever rod 10 fixed to the wall, and the other end is inserted into the second waist hole 32 at the lower end of the third connecting plate 31.
[0042] The first waist hole 30 and the second waist hole 32 are used to install the second bolt 33 and the third bolt 34. The third connecting plate 31 serves as a connection, and the second bolt 33 and the third bolt 34 serve as a fastener.
[0043] Working principle:
[0044] On the first connecting plate 20, the second bolt 33 is passed through the first waist hole 30 beforehand. After the first connecting assembly is installed, the second waist holes 32 at both ends of the third connecting plate 31 are fitted onto the second bolt 33 and the third bolt 34, and tightened respectively.
[0045] This step connects the pre-embedded screw 13 to the I-beam cantilever 10 as a whole, further increasing the strength of the tie rod 14.
[0046] In the description of this utility model, it should also be noted that, unless otherwise explicitly specified and limited, the terms "set," "install," "connect," and "link" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.
[0047] Finally, it should be noted that the above description is merely a preferred embodiment of this utility model and is not intended to limit the utility model. Although the utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the protection scope of this utility model.
Claims
1. A type of scaffolding for highway bridge construction, characterized in that, include: The cantilever scaffolding includes a pre-embedded screw (13) and a tie rod (14). One end of the pre-embedded screw (13) is embedded in the wall, and one end of the tie rod (14) is attached to the end of the pre-embedded screw (13) located outside the wall. The first connecting assembly includes a first connecting plate (20), a first U-shaped slot (21), a U-shaped support frame (22), a second U-shaped slot (24), a second connecting plate (25), a third U-shaped slot (26), and a first bolt (27). The first U-shaped slot (21) is opened on both sides of the lower end of the first connecting plate (20). The first connecting plate (20) is snapped onto one end of two pre-embedded screws (13) through the first U-shaped slot (21). The U-shaped support frame (22) is fixed on both sides of the upper end of the first connecting plate (20). The second U-shaped slot (24) is opened on both sides of the side of the U-shaped support frame (22). The second connecting plate (25) is fixed on both sides of one end of the pre-embedded screw (13). The third U-shaped slot (26) is opened on one end of the second connecting plate (25). The first bolt (27) is inserted into the second U-shaped slot (24) and the third U-shaped slot (26).
2. The scaffolding for highway bridge construction according to claim 1, characterized in that, The first connecting component also includes an opening (23), which is opened on the side of the U-shaped support frame (22) and located between two second U-shaped slots (24).
3. The scaffolding for highway bridge construction according to claim 1, characterized in that, The cantilever scaffold also includes an I-beam cantilever pole (10) and support poles (11). One end of the I-beam cantilever pole (10) is fixed to the wall, and multiple support poles (11) are assembled into a support frame by clamps and fixed to the I-beam cantilever pole (10).
4. The scaffolding for highway bridge construction according to claim 3, characterized in that, The cantilever scaffold also includes a U-shaped connector (12), which is welded to the end of the I-beam cantilever pole (10) away from the wall, and the other end of the tie rod (14) is attached to the U-shaped connector (12).
5. The scaffolding for highway bridge construction according to claim 1, characterized in that, It also includes a second connector, which includes a first waist hole (30), a third connecting plate (31), and a second waist hole (32). The first waist hole (30) is opened at both ends of the first connecting plate (20), and the second waist hole (32) is opened at both ends of the third connecting plate (31).
6. The scaffolding for highway bridge construction according to claim 5, characterized in that, The second connector also includes a second bolt (33) and a third bolt (34). The second bolt (33) is inserted into the first waist hole (30) and the second waist hole (32) at the upper end of the third connecting plate (31). One end of the third bolt (34) is fixed to the end of the I-beam cantilever rod (10) fixed to the wall, and the other end is inserted into the second waist hole (32) at the lower end of the third connecting plate (31).