Large module hoisting system

By introducing a balance beam and a hydraulic balancing device into the hoisting system, the problem of insufficient vertical docking accuracy in the hoisting of large modules was solved, achieving high-precision hoisting results and saving installation time and costs.

CN223659605UActive Publication Date: 2025-12-12SHANGHAI LIBERT ENG TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202520037269.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-08
Publication Date
2025-12-12
Estimated Expiration
2035-01-08

AI Technical Summary

Technical Problem

Existing technologies struggle to precisely control the vertical docking accuracy of large modules, especially when there is a deviation between the module's center of gravity and the theoretically calculated center of gravity. In such cases, the hoisting slings cannot meet the installation accuracy requirements, resulting in a significant deviation between the module's center of gravity and its geometric center. Conventional hoisting methods require repeated adjustments.

Method used

The lifting assembly includes first and second balance beams, main slings, synchronous lifting control components, and a hydraulic balancing device. By precisely controlling the tension and stroke at each lifting point, the horizontality and verticality of the module are ensured.

Benefits of technology

It enables precise hoisting of large modules, improves installation accuracy, reduces the time spent on repeated adjustments, and saves installation costs and time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223659605U_ABST
    Figure CN223659605U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of industrial module equipment, and discloses a large module lifting system which comprises a lifting appliance assembly, a first balance beam is arranged at the bottom end of the lifting appliance assembly, a main sling is arranged at the bottom of the first balance beam, and synchronous lifting control assemblies are arranged on all connecting points between the main sling and the first balance beam. A second balance beam is arranged at the bottom end of the synchronous lifting control assembly, six vertical slings are connected to the bottom of the second balance beam, turn buckles are fixedly connected to the bottom ends of the vertical slings, and the bottom ends of the turn buckles are connected with a hoisted large module. The first balance beam and the second balance beam are arranged, and the hydraulic balance device is arranged on the main sling, so that the pulling force and the stroke on each hoisting point can be accurately controlled, simultaneous stress of multiple hoisting points is met, the levelness and the perpendicularity of a hoisted large-scale module are guaranteed, and high practicability is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of industrial module equipment, and more particularly to a large module hoisting system. BACKGROUND

[0002] With the promotion of chemical plant modularization, the size and weight of the module are increasing, and the installation of the module is also challenged.

[0003] According to the current construction experience, the module installation methods are roughly divided into two kinds, one is to use SPMT hydraulic axis vehicle to transport to the installation position, and to be lifted into place. This method has certain requirements for the construction site and the installation position. One is to use hoisting machinery to hoist into place, and this form is more widely applicable.

[0004] At present, the vertical butt joint precision of large modules in the industry is difficult to control within a small range. The main reason is that the weight of the temporary reinforcement structure, paint, fire retardant paint and the like during the manufacturing process of the large module cannot be accurately estimated. There is a deviation between the actual center of gravity and the theoretically calculated center of gravity, and the length of the hoisting rigging cannot be accurately calculated. Whether the module is lifted into place by transportation or large machinery, the center of gravity of the module is the key.

[0005] For the hoisting into place which is more widely applicable, the greater the deviation between the center of gravity of the module and the geometric center of the module after the module is lifted, the greater the horizontal difference of each column. The conventional hoisting rigging cannot meet the installation precision requirements and needs to be adjusted repeatedly. CONTENT OF THE UTILITY MODEL

[0006] In order to solve the above problems, the present application provides a large module hoisting system.

[0007] The large module hoisting system provided by the present application adopts the following technical scheme:

[0008] A large module hoisting system, comprising a lifting assembly, a first balance beam is arranged at the bottom end of the lifting assembly, a main lifting cable is arranged at the bottom of the first balance beam, a synchronous lifting control assembly is arranged at each connection point between the main lifting cable and the first balance beam, a second balance beam is arranged at the bottom end of the synchronous lifting control assembly, six vertical lifting cables are connected to the bottom of the second balance beam, a basket bolt is fixedly connected to the bottom end of each vertical lifting cable, and the basket bolt is connected to a large module to be hoisted.

[0009] Further, the lifting assembly comprises a lifting hook and a ring-shaped lifting cable, the ring-shaped lifting cable is in the shape of a pyramid as a whole, the top end of the ring-shaped lifting cable is connected to the lifting hook, and the bottom section of the ring-shaped lifting cable is connected to the first balance beam.

[0010] Further, the first balance beam is a square frame arranged horizontally, and the top and bottom of the four corners are fixedly connected with first shackles.

[0011] Further, the second balance beam is a square frame arranged horizontally, and the bottom of the four corners and the center of the long side of the second balance beam are provided with second shackles, and the top of the vertical sling is connected with the second shackle.

[0012] Further, the long side size of the first balance beam is the same as the short side size of the second balance beam, and the vertical projection size of the second balance beam is approximately the same as the hoisted large module.

[0013] Further, the synchronous lifting control assembly comprises a SyncHoist hydraulic balance device and a controller, two ends of the SyncHoist hydraulic balance device are connected with the first shackle and the main sling respectively, and the controller is arranged at the center of the first balance beam.

[0014] In summary, the present application has at least one of the following beneficial technical effects:

[0015] The present application sets the first balance beam and the second balance beam, and sets the hydraulic balance device on the main sling, so as to accurately control the tension and stroke of each hoisting point, not only meet the force of multiple hoisting points at the same time, but also ensure the levelness and perpendicularity of the hoisted large module, and has high practicability. BRIEF DESCRIPTION OF DRAWINGS

[0016] Figure 1 It is a front view of the present application;

[0017] Figure 2 It is a side view of the present application.

[0018] Explanation of Markers in the Drawing:

[0019] 1, lifting assembly; 11, lifting hook; 12, ring sling; 2, first balance beam; 21, first shackle; 3, main sling; 4, synchronous lifting control assembly; 5, second balance beam; 51, second shackle; 6, vertical sling; 7, basket bolt. DETAILED DESCRIPTION

[0020] The technical solutions in the embodiments of the present application will be described clearly and completely below in combination with the drawings in the embodiments of the present application; obviously, the described embodiments are only part of the embodiments of the present application, not all the embodiments, and all other embodiments obtained by those skilled in the art without creative labor on the basis of the embodiments in the present application are within the scope of protection of the present application.

[0021] In the description of this application, it should be noted that the terms "upper," "lower," "inner," "outer," "top / bottom," etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this application. Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.

[0022] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installed," "equipped with," "sleeved / connected," "connected," etc., should be interpreted broadly. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be a connection within two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.

[0023] Example 1:

[0024] The present application will be further described in detail below with reference to the accompanying drawings.

[0025] This application discloses a large module hoisting system, including a hoisting assembly 1. A first balance beam 2 is provided at the bottom of the hoisting assembly 1. A main sling 3 is provided at the bottom of the first balance beam 2. A synchronous lifting control assembly 4 is provided at each connection point between the main sling 3 and the first balance beam 2. A second balance beam 5 is provided at the bottom of the synchronous lifting control assembly 4. Six vertical slings 6 are connected to the bottom of each of the second balance beams 5. Turnbuckles 7 are fixedly connected to the bottom of each of the vertical slings 6. The bottom of the turnbuckles 7 is connected to the large module being hoisted.

[0026] As a further preferred embodiment, the lifting device assembly 1 includes a hook 11 and an annular sling 12. The annular sling 12 is generally pyramid-shaped, with its top end connected to the hook 11 and its bottom end connected to the first balance beam 2.

[0027] As a further preferred embodiment, the first balance beam 2 is a horizontally arranged square frame, with first shackles 21 fixedly connected to the top and bottom of its four corners. The annular sling 12 and the synchronous lifting control assembly are both connected to the first shackles 21.

[0028] As a further preferred embodiment, the second balance beam 5 is a horizontally arranged square frame, and the bottom four corners and the center of the long side of the second balance beam 5 are provided with second shackles 51, and the top of the vertical sling 6 is connected to the second shackles 51.

[0029] As a further preferred embodiment of the present application, the long side dimension of the first balance beam 2 is the same as the short side dimension of the second balance beam 5, and the vertical projection dimension of the second balance beam 5 is approximate to the large module being hoisted.

[0030] As a further preferred embodiment of the present application, the synchronous hoisting control assembly 4 comprises a SyncHoist hydraulic balance device and a controller, two ends of the SyncHoist hydraulic balance device are connected with the first shackle 21 and the main sling 3 respectively, and the controller is arranged at the center position of the first balance beam 2.

[0031] The implementation principle of the large module hoisting system according to the embodiment of the present application is as follows: due to the integrity of module manufacturing, the center of gravity of the module is generally measured after the manufacturing is completed. At that time, the center of gravity cannot be changed, and the rigging can only be adjusted according to the actual center of gravity. Because the modules are manufactured in batches, the adaptability of the hoisting rigging is a big challenge. It is necessary to not only meet the force of multiple lifting points, but also ensure the levelness and perpendicularity of the module. As shown in the figure, the actual center of gravity of the module deviates from the geometric center by 753 mm in the length direction and by 211 mm in the width direction. After the module is lifted, the plumb line of the hook passes through the actual center of gravity, and the module as a whole is inclined. In view of the different direction deviations of multiple modules, the stroke of the hydraulic balance system is selected as the maximum value of 1200 mm according to the maximum rigging adjustment, and the rated lifting capacity of the hydraulic balance system is selected according to the maximum force of 130 tons. The SARS PIN precise positioning system is comprehensively selected and used, the maximum tension of a single oil cylinder is 200 tons, the full extension length is 4455 mm, the full retraction length is 2955 mm, and the stroke is 1500 mm. Adjustment is made at the positions of the four main slings, and the Hub adjustment system is placed at the position of the top balance beam. The effectiveness of the adjustment is ensured, and the number of SyncHoist Units used is reduced. At the same time, the system has the following advantages: the system is powered by electricity, the main power supply is 380V, and the auxiliary power supply is 220V, both of which are domestic industrial power supply and household power supply. The adjustment accuracy can reach 1mm, which meets the adjustment of the levelness and perpendicularity of the module, saves the installation time, and saves the customer 0.5-1 day in installation and docking. The operation is flexible, the four SyncHoist Units can be used vertically or obliquely, individually or simultaneously, manually or automatically, and individually or simultaneously. Wireless Wifi control can be performed, and the effective distance is 200m. At the same time, real-time visibility is provided, that is, through the interface of the remote controller, the cylinder stroke size, lifting height and load size of each SyncHoist Unit can be seen.

[0032] The above are preferred embodiments of the present application, which do not limit the protection scope of the present application, therefore: any equivalent changes made on the structure, shape, principle of the present application shall be covered within the protection scope of the present application.

Claims

1. A large modular hoisting system, characterized in that, The system includes a lifting device assembly (1), with a first balance beam (2) at the bottom of the lifting device assembly (1), a main sling (3) at the bottom of the first balance beam (2), a synchronous lifting control assembly (4) at each connection point between the main sling (3) and the first balance beam (2), a second balance beam (5) at the bottom of the synchronous lifting control assembly (4), and six vertical slings (6) at the bottom of each of the second balance beams (5). Each of the vertical slings (6) is fixedly connected to a turnbuckle (7) at the bottom, and the bottom of the turnbuckle (7) is connected to the large module being lifted.

2. The large modular hoisting system according to claim 1, characterized in that: The lifting device assembly (1) includes a hook (11) and a ring sling (12). The ring sling (12) is pyramid-shaped. The top of the ring sling (12) is connected to the hook (11), and its bottom section is connected to the first balance beam (2).

3. A large modular hoisting system according to claim 2, characterized in that: The first balance beam (2) is a horizontally set square frame, and the top and bottom of its four corners are fixedly connected with the first shackle (21). The ring sling (12) and the synchronous lifting control component (4) are both connected to the first shackle (21).

4. A large modular hoisting system according to claim 3, characterized in that: The second balance beam (5) is a horizontally arranged square frame. The bottom four corners and the center of the long side of the second balance beam (5) are provided with second shackles (51). The top of the vertical sling (6) is connected to the second shackles (51).

5. A large modular hoisting system according to claim 4, characterized in that: The long side dimension of the first balance beam (2) is the same as the short side dimension of the second balance beam (5), and the vertical projection dimension of the second balance beam (5) is approximately the same as that of the large module being hoisted.

6. A large modular hoisting system according to claim 5, characterized in that: The synchronous lifting control component (4) includes a SyncHoist hydraulic balancing device and a controller. The two ends of the SyncHoist hydraulic balancing device are respectively connected to the first shackle (21) and the main sling (3). The controller is located at the center of the first balance beam (2).

Citation Information

Cited By

  • A large module general lifting tool and lifting method

    CN122355145A