Safety protection device for blasting construction of reconstructed and extended highway slope
By designing and upgrading the safety protection device for blasting construction on highway slopes, and utilizing a combination of support rods and ground-inserting rods, the problems of vibration and flying rock hazards during slope blasting were solved, achieving precise protection and stability maintenance of the slope.
Patent Information
- Application Number
- CN202423178502.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-23
- Publication Date
- 2025-12-16
- Estimated Expiration
- 2034-12-23
AI Technical Summary
Existing technologies are insufficient to precisely control vibration, flyrock, and dust hazards during slope blasting, and they can cause significant damage to rock mass stability, thus affecting the construction safety of slopes.
A safety protection device for blasting construction on the slope of a highway reconstruction and expansion project was designed, including a first support rod, a second support rod, a protective net, a first ground insertion rod, and a second ground insertion rod. The protective area is expanded by adjusting the distance between the support rods, and the stability and strength of the device are improved by rotating the second rotating rod to insert the ground insertion rod horizontally into the ground.
It achieves precise protection of slope blasting, reduces vibration and rockfall hazards, protects the stability of the rock mass, and improves the safety and flexibility of construction.
Smart Images

Figure CN223678338U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of slope blasting protection, in particular to a reconstruction and expansion highway slope blasting construction safety protection device. BACKGROUND
[0002] China is in the stage of high-speed development of infrastructure construction, and the transportation industry is developing rapidly. Many highway rock slopes exist, and the demand for slope rock mass excavation engineering is very large every year. In the process of highway slope excavation, blasting is the most frequently used and effective rock breaking method.
[0003] Traditional blasting technology can obtain regular excavation contour surface by optimizing blasting parameters, but how to accurately control the surrounding forming, reduce the vibration, flying stone and dust disasters caused by blasting, and reduce the damage of blasting to the rock mass and protect the stability of the slope has always been the focus of many blasting experts and field engineers.
[0004] Therefore, a reconstruction and expansion highway slope blasting construction safety protection device is proposed. UTILITY MODEL CONTENT
[0005] The utility model discloses a reconstruction and expansion highway slope blasting construction safety protection device, which solves the problems in the above background technology and achieves the above purpose. The utility model provides the following technical scheme: a reconstruction and expansion highway slope blasting construction safety protection device, which comprises a first supporting rod, a second supporting rod and a first ground insertion rod.
[0006] Preferably, the width of the drill bit is greater than the width of the first ground insertion rod, and the two sides of one end of the first ground insertion rod are slidingly installed in the inner wall of the drill bit.
[0007] Preferably, the bottom end of the compression spring is connected to the top end of the first ground insertion rod, and the second ground insertion rod and the lead screw are connected through thread engagement.
[0008] Preferably, the first supporting rod and the second supporting rod are each provided with two rotating shafts, and the rotating shafts are provided with a fixing ring on one side.
[0009] Preferably, the inner sleeve of the fixed ring is provided with a first ground insertion rod, one end of the first ground insertion rod is provided with a knocking plate, and the inner part of the knocking plate is provided with a rotating nut.
[0010] Preferably, the bottom end of the rotating nut extends into the first ground insertion rod, and the bottom end of the rotating nut is connected with one end of the second rotating rod.
[0011] Preferably, the outer side of the second rotating rod is provided with a gear, and the gear provided on the outer side of the second rotating rod is meshed and connected with the gear at one end of the lead screw.
[0012] Preferably, the outer side of the first rotating rod in the inner part of the second supporting rod is provided with a reinforcing rib, and the bottom end of the reinforcing rib is provided with a plurality of connecting rods at equal distances.
[0013] Preferably, the bottom end of the connecting rod is connected with the top end of the protective net, one end of the protective net penetrates into the inner part of the second supporting rod, and the one end of the protective net extends into the inner part of the first supporting rod and is connected with the first rotating rod.
[0014] Compared with the prior art, the utility model provides a kind of improved and expanded highway side slope blasting construction safety protection device, with the following beneficial effects:
[0015] By being provided with first supporting rod, protective net, second supporting rod, first ground insertion rod and second ground insertion rod, the distance between first supporting rod and second supporting rod can be expanded, so as to expand the protective area of the protective net for side slope blasting, and the size of the protective surface can be self-adaptively adjusted according to the site construction area, thereby improving the flexibility of the protective device in use.After determining the protective area, the first ground insertion rod is vertically inserted into the ground to fix the entire protective device.In order to avoid the impact force generated during blasting from affecting the stability of the first ground insertion rod, after the first ground insertion rod is inserted into the ground, the second ground insertion rod installed in the first ground insertion rod can be extended out and inserted horizontally into the ground by rotating the second rotating rod, thereby improving the stability of the first ground insertion rod in the ground and avoiding the situation that the first ground insertion rod is shaken out by the shock wave generated during blasting, so that the protective net cancels the protection of the side slope, and the installation strength of the side slope blasting protection device is improved. BRIEF DESCRIPTION OF DRAWINGS
[0016] Figure 1 It is a schematic diagram of the main structure of the utility model;
[0017] Figure 2 It is a schematic diagram of the installation structure of the utility model;
[0018] Figure 3 It is a schematic diagram of the enlarged structure of the A place of the utility model;
[0019] Figure 4 It is a schematic diagram of the enlarged structure of the B place of the utility model.
[0020] Figure: 1, the first support rod; 2, the reinforcing bar; 3, the protective net; 4, the second support rod; 5, the first ground insertion rod; 6, the fixed ring; 7, the knock plate; 8, the rotating nut; 9, the rotating shaft; 10, the drill bit; 11, the first rotating rod; 12, the second ground insertion rod; 13, the screw rod; 14, the second rotating rod; 15, the perforation; 16, the compression spring; 17, the reset spring; 18, the connecting rod. DETAILED DESCRIPTION
[0021] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the protection scope of the utility model.
[0022] Embodiment 1: the first support rod 1 and the second support rod 4 are internally provided with the first rotating rod 11, the outer side of the two ends of the first rotating rod 11 in the second support rod 4 is provided with the reset spring 17, the outer side of the first rotating rod 11 in the second support rod 4 is provided with the protective net 3, one end of the first ground insertion rod 5 is provided with the drill bit 10, the inside of the drill bit 10 is provided with the compression spring 16, the two sides in the first ground insertion rod 5 are provided with the screw rod 13, the outer side of the screw rod 13 is provided with the second ground insertion rod 12, the outer side of the first ground insertion rod 5 is provided with the perforation 15, and the inside of the first ground insertion rod 5 is provided with the second rotating rod 14.
[0023] Specifically, as Figure 1 , Figure 2 , Figure 3 and Figure 4As shown, the first support rod 1 and the second support rod 4 are movably provided with the protective nets 3, and the second support rod 4 is sleeved with a large number of protective nets 3, so that the distance between the first support rod 1 and the second support rod 4 can be pulled to expand the protective area of the protective nets 3 to the slope blasting, the size of the protective surface can be self-adaptively adjusted according to the construction area, and the flexibility of the protective device in use is improved. As shown in the first support rod 1 and the second support rod 4 are provided with the first ground insertion rod 5, so that after the protective area is determined, the first ground insertion rod 5 can be vertically inserted into the ground to fix the whole protective device. In order to avoid the impact force generated during blasting from affecting the stability of the first ground insertion rod 5, a plurality of second ground insertion rods 12 are movably arranged in the first ground insertion rod 5, so that after the first ground insertion rod 5 is inserted into the ground, the second ground insertion rods 12 arranged in the first ground insertion rod 5 can be extended out and inserted into the ground transversely by rotating the second rotating rod 14, the stability of the first ground insertion rod 5 in the ground is improved, and the situation that the impact wave generated during blasting shakes out the first ground insertion rod 5 to cancel the protection of the slope by the protective nets 3 is avoided, and the installation strength of the slope blasting protection device is improved.
[0024] The width of the drill bit 10 is greater than the width of the first ground insertion rod 5, the two sides of one end of the first ground insertion rod 5 are slidably arranged in the inner wall of the drill bit 10, the bottom end of the rotating nut 8 extends into the first ground insertion rod 5, the bottom end of the rotating nut 8 is connected with one end of the second rotating rod 14, the outer side of the second rotating rod 14 is provided with a gear, the gear on the outer side of the second rotating rod 14 is meshed and connected with the gear on one end of the lead screw 13, the bottom end of the compression spring 16 is connected with the top end of the first ground insertion rod 5, the second ground insertion rod 12 is threadedly connected with the lead screw 13, one end of the first ground insertion rod 5 is provided with the knocking plate 7, and the inside of the knocking plate 7 is provided with the rotating nut 8.
[0025] Specifically, as shown in Figure 1 , Figure 2 and Figure 4 , since the width of the drill bit 10 is greater than the width of the first ground insertion rod 5, when the first ground insertion rod 5 is inserted into the ground, the drill bit 10 arranged at one end of the first ground insertion rod 5 can provide a channel for the first ground insertion rod 5, so that the situation that the perforations 15 on the outer side of the first ground insertion rod 5 are blocked by the soil is avoided, and the second ground insertion rod 12 can be stably extended out of the first ground insertion rod 5. The rotation of the rotating nut 8 can drive the rotation of the second rotating rod 14, the rotation of the second rotating rod 14 can drive the rotation of the lead screw 13, and the rotation of the lead screw 13 can drive the movement of the second ground insertion rod 12 along the installation direction of the lead screw 13.
[0026] The outer side of the first supporting rod 1 and the second supporting rod 4 is provided with two rotating shafts 9, one side of the rotating shaft 9 is provided with a fixed ring 6, the inside of the fixed ring 6 is provided with a first ground insertion rod 5, the outer side of the first rotating rod 11 in the second supporting rod 4 is provided with a reinforcing rib 2, a plurality of connecting rods 18 are equidistantly arranged at the bottom end of the reinforcing rib 2, the bottom end of the connecting rod 18 is connected with the top end of the protective net 3, one end of the protective net 3 penetrates into the second supporting rod 4, and the other end of the protective net 3 extends into the first supporting rod 1 and is connected with the first rotating rod 11.
[0027] Specifically, as shown in Figure 1 、 Figure 2 and Figure 3 , since the two ends of the first rotating rod 11 in the second supporting rod 4 are provided with reset springs 17, the first rotating rod 11 in the second supporting rod 4 can be automatically rotated through the rotation of the reset spring 17 when the protective device is stored, so that the protective net 3 extending out of the second supporting rod 4 is stored in the second supporting rod 4. At the same time, when installed and used, the protective net 3 can be prevented from being in a tight state through the action of the reset spring 17. When blasting, the protective net 3 with certain ductility can better protect the flying stones with impact force and avoid the breaking of the protective net 3 due to strong impact force. The reinforcing rib 2 and the connecting rod 18 can provide better support and protection for the protective net 3 as a whole.
[0028] Working principle: when used, the protective area of the protective net 3 on the slope blasting can be expanded by pulling the distance between the first supporting rod 1 and the second supporting rod 4, the size of the protective surface can be self-adaptively adjusted according to the on-site construction area, and the flexibility of the protective device when used is improved. Since one side of the first supporting rod 1 and the second supporting rod 4 is provided with the first ground insertion rod 5, after the protective area is determined, the first ground insertion rod 5 can be vertically inserted into the ground to fix the whole protective device. In order to avoid the impact force generated during blasting affecting the stability of the first ground insertion rod 5, a plurality of second ground insertion rods 12 are movably arranged in the first ground insertion rod 5. Therefore, after the first ground insertion rod 5 is inserted into the ground, the second ground insertion rod 12 arranged in the first ground insertion rod 5 can be extended out and inserted into the ground transversely by rotating the second rotating rod 14, thereby improving the stability of the first ground insertion rod 5 in the ground.
[0029] It is apparent for a person skilled in the art that the present application is not restricted to the details of the above exemplary embodiments, but that it can be implemented in other concrete forms without departing from the spirit or the essential characteristics of the present application. Therefore, the embodiments should be considered as exemplary only, and not limiting, the scope of the present application being defined by the appended claims rather than the above description, and all changes coming within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference signs in the claims should not be construed as limiting the claims concerned.
Claims
1. A safety protection device for highway slope blasting construction, comprising a first support rod (1), a second support rod (4) and a first ground insertion rod (5), characterized in that: The inside of the first support rod (1) and the second support rod (4) is provided with a first rotating rod (11), the outside of both ends of the first rotating rod (11) in the second support rod (4) is provided with a reset spring (17), the outside of the first rotating rod (11) in the second support rod (4) is provided with a protective net (3), one end of the first ground insertion rod (5) is provided with a drill bit (10), the inside of the drill bit (10) is provided with a compression spring (16), both sides of the inside of the first ground insertion rod (5) is provided with a lead screw (13), the outside of the lead screw (13) is provided with a second ground insertion rod (12), the outside of the first ground insertion rod (5) is provided with a through hole (15), and the inside of the first ground insertion rod (5) is provided with a second rotating rod (14).
2. The safety protection device for reconstruction and extension of highway slope blasting construction according to claim 1, characterized in that: The width of the drill bit (10) is greater than the width of the first ground insertion rod (5), and both sides of one end of the first ground insertion rod (5) are slidingly installed on the inner walls of the drill bit (10).
3. The safety protection device for reconstruction and extension of highway slope blasting construction according to claim 1, characterized in that: The bottom end of the compression spring (16) is connected with the top end of the first ground insertion rod (5), and the second ground insertion rod (12) and the lead screw (13) are connected through thread engagement.
4. The safety protection device for reconstruction and extension of highway slope blasting construction according to claim 1, characterized in that: The outside of the first support rod (1) and the second support rod (4) is provided with two rotating shafts (9), and one side of the rotating shaft (9) is provided with a fixed ring (6).
5. The safety protection device for reconstruction and extension of highway slope blasting construction according to claim 4, characterized in that: The inside of the fixed ring (6) is provided with the first ground insertion rod (5), one end of the first ground insertion rod (5) is provided with a knocking plate (7), and the inside of the knocking plate (7) is provided with a rotating nut (8).
6. The safety protection device for reconstruction and extension of highway slope blasting construction according to claim 5, characterized in that: The bottom end of the rotating nut (8) extends into the inside of the first ground insertion rod (5), and the bottom end of the rotating nut (8) is connected with one end of the second rotating rod (14).
7. The safety protection device for reconstruction and extension of highway slope blasting construction according to claim 6, characterized in that: The outside of the second rotating rod (14) is provided with a gear, and the gear on the outside of the second rotating rod (14) is engaged with the gear on one end of the lead screw (13).
8. The safety protection device for reconstruction and extension of highway slope blasting construction according to claim 1, characterized in that: The outside of the first rotating rod (11) in the second support rod (4) is provided with a reinforcing rib (2), and the bottom end of the reinforcing rib (2) is provided with a plurality of connecting rods (18) at equal distances.
9. The safety protection device for reconstruction and extension of highway slope blasting construction according to claim 8, characterized in that: The bottom end of the connecting rod (18) is connected with the top end of the protective net (3), one end of the protective net (3) penetrates into the inside of the second support rod (4), and the one end of the protective net (3) extends into the inside of the first support rod (1) and is connected with the first rotating rod (11).