Special tool for hanging scattered tubes of boiler in thermal power plant

The special tool for hanging boiler tubes in thermal power plants, which combines steel wire ropes and fixed pulleys, solves the problems of low hoisting efficiency and inconsistent installation in existing technologies, and realizes rapid hoisting and safe and efficient installation of the tubes.

CN223852040UActive Publication Date: 2026-01-30CHINA POWER CONSTR HUBEI ELECTRIC POWER CONSTR CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520631062.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-07
Publication Date
2026-01-30
Estimated Expiration
2035-04-07

AI Technical Summary

Technical Problem

In the construction of existing thermal power plant boilers, the process of hoisting and installing the diffuser tubes consumes a lot of manpower and resources. The installation locations are not uniform, the installation efficiency is low, and it is difficult to adapt to the installation requirements of multiple sets or long diffuser tubes and changes in direction.

Method used

Design a special tool for hanging boiler tubes in thermal power plants. It adopts a combination of steel wire rope and fixed pulley. The lifting lug is rotatably connected to the base. The tubes are quickly hung and positioned by operating the cable. Multiple tubes can be hung at the same time, and the position of the lifting lug can be flexibly adjusted.

Benefits of technology

It improved hoisting efficiency, reduced the frequency of tower crane use, lowered the amount of machinery required and the risks of working at height, and improved construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223852040U_ABST
    Figure CN223852040U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of hanging tools, in particular to a special tool for hanging scattered tubes of a boiler in a thermal power plant, which comprises a steel wire rope serving as a track and a fixed pulley hung on the steel wire rope, the fixed pulley frame is arranged on the pedestal, the pedestal is movably connected with a lifting lug, and the lifting lug can rotate relative to the pedestal by pulling the lifting lug; a plurality of first through holes are formed in the pedestals and used for connecting the adjacent pedestals. Through the combination of the steel wire rope and the fixed pulley, an operator can easily move the lifting lug on the platform through the cable, so that the scattered pipes can be quickly hung and placed in place, the use frequency of a tower crane is reduced, and the hoisting efficiency is improved. According to the tool, the positions of the lifting lugs can be flexibly adjusted according to the installation positions of the scattered pipes and the hanging pipes, the tool is suitable for various installation scenes, the pedestals can be connected with one another, and simultaneous hanging of multiple sets of scattered pipes and hanging of long scattered pipes can be achieved. When the mounting direction of the scattered pipe is changed, the relative position of the lifting lug and the fixed pulley can be adjusted, so that the tool can meet different mounting requirements.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to a hanging tool technical field, more specifically, especially relates to a special tool for hanging boiler pipe in power plant. BACKGROUND

[0002] In the boiler construction of power plant, the tower crane is usually used to hoist the smoke shaft and the pipe. However, the current hoisting method has many problems: the hooking and unhooking speed of single hanging pipe is slow, and a large amount of manpower and material resources are consumed; the installation position of hanging pipe is not uniform, and the installation efficiency is low.

[0003] The patent with publication number CN221876389U discloses a special tool for hanging boiler pipe in power plant. A steel wire rope is fixed at the position close to the installation of hanging pipe as a track, a fixed pulley runs on the steel wire rope, and the rope hole of the steel plate is used to fasten the cable. The operator pulls the cable on the platform and runs back and forth to position. The special tool is pulled to the platform on the boiler steel frame platform, and the construction personnel hang the pipe and the hanging pipe on the lug with the snap ring and the steel wire rope. However, when multiple groups of pipes need to be installed simultaneously or when a long pipe needs to be installed, the above-mentioned tool is no longer applicable. When the installation direction of the pipe changes, the relative position of the lug and the fixed pulley cannot be changed, so the above-mentioned tool is also not applicable. SUMMARY

[0004] The utility model aims at providing a special tool for hanging boiler pipe in power plant to overcome the above-mentioned shortcomings.

[0005] A special tool for hanging boiler pipe in power plant, comprising a fixed pulley suspended on a steel wire rope as a track; the fixed pulley is arranged on a pedestal, and a lug is movably connected to the pedestal, and pulling the lug can make the lug rotate relative to the pedestal.

[0006] A plurality of first through holes are formed in the pedestal for connecting adjacent pedestals.

[0007] Further, the pedestal comprises a bottom plate and a vertical plate for arranging the fixed pulley, and the vertical plate is fixedly connected to the upper end surface of the bottom plate.

[0008] Further, a second through hole is formed in the center of the bottom plate, the lug penetrates through the second through hole and can rotate in the second through hole.

[0009] Further, four first through holes are formed in the bottom plate, and each first through hole is located at the periphery of the second through hole.

[0010] Further, the first through hole of two adjacent pedestals is penetrated by a connecting rope for connecting the two adjacent pedestals.

[0011] Further, the lug comprises a rotary connecting piece, a flat plate and a vertical plate which are integrally arranged; the lower end surface of the rotary connecting piece is fixed to the center of the flat plate, and the lower end surface of the flat plate is fixed with the vertical plate;

[0012] The rotary connecting piece penetrates the second through hole, and the top end of the rotary connecting piece is provided with a baffle which abuts against the upper end surface of the bottom plate.

[0013] Further, the vertical plate is provided with a lifting hole.

[0014] Further, the vertical plate is also provided with a rope penetrating hole.

[0015] Compared with the prior art, the utility model has the beneficial effects that:

[0016] The special tool for boiler pipe hanging of thermal power plant can flexibly adjust the position of the lug according to the installation position of the pipe and the hanging pipe, is suitable for various installation scenes, the pedestals can be connected with each other, and the simultaneous hanging of multiple pipes and the hanging of a long pipe can be realized.

[0017] The special tool for boiler pipe hanging of thermal power plant can flexibly adjust the position of the lug according to the installation position of the pipe and the hanging pipe, is suitable for various installation scenes, the pedestals can be connected with each other, and the simultaneous hanging of multiple pipes and the hanging of a long pipe can be realized.

[0018] The special tool for boiler pipe hanging of thermal power plant can reduce the use of the tower crane, reduce the investment of the mechanical shift, reduce the risk of aerial work, and improve the safety of construction. BRIEF DESCRIPTION OF DRAWINGS

[0019] The drawings are used to provide a further understanding of the utility model, and constitute a part of the specification, are used together with the embodiments of the utility model to explain the utility model, and do not constitute the limitation to the utility model. In the drawings:

[0020] Figure 1 It is the whole structure schematic view of the special tool for boiler pipe hanging of thermal power plant in the embodiment.

[0021] Figure 2 It is the schematic view of the pedestal in the embodiment.

[0022] Figure 3 It is the schematic view of the lug in the embodiment.

[0023] Figure 4 is the schematic diagram of two groups of boiler pipe hanging special tools for power plant connected for use in the embodiment.

[0024] In the figure: 1, the fixed pulley;

[0025] 2, pedestal; 21, bottom plate; 211, first through hole; 212, second through hole; 22, vertical plate;

[0026] 3, lifting lug; 31, rotary connecting piece; 311, baffle; 32, flat plate; 33, vertical plate; 331, lifting hole; 332, rope hole;

[0027] 4, connecting rope. DETAILED DESCRIPTION

[0028] The technical solutions in the embodiments of the present application will be described clearly and completely below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of the present application.

[0029] As shown in the figure, Figures 1-3 The present embodiment provides a boiler pipe hanging special tool for power plant, which comprises a fixed pulley 1 suspended on a steel wire rope as a track, the fixed pulley 1 is erected on a pedestal 2, the pedestal 2 is movably connected with a lifting lug 3, and pulling the lifting lug 3 can make the lifting lug 3 rotate relative to the pedestal 2.

[0030] In the present embodiment, as shown in the figure, Figure 1 and Figure 2 The pedestal 2 comprises a bottom plate 21 and two vertical plates 22 for erecting the fixed pulley 1, the vertical plates 22 are fixedly connected to the upper end face of the bottom plate 21, and the fixed pulley 1 is rotatably connected between the two vertical plates 22.

[0031] In the pedestal 2, a plurality of first through holes 211 are formed in the bottom plate 21 for connecting adjacent pedestals 2. A second through hole 212 is formed in the center of the bottom plate 21, the lifting lug 3 penetrates through the second through hole 212 and can rotate in the second through hole 212.

[0032] Specifically, the bottom plate 21 is provided with four first through holes 211, and each first through hole 211 is located at the periphery of the second through hole 212, i.e. the four first through holes 211 are located at the four side sides of the second through hole 212.

[0033] The first through holes 211 of the two adjacent pedestals 2 are penetrated by the connecting rope 4, as shown in the figure, Figure 4As shown, two adjacent pedestals 2 can be connected. In this way, two groups of tools provided by the embodiment can be used to simultaneously perform the hanging of the scattered pipes. In actual applications, if multiple groups of scattered pipes are to be hung, the multiple groups of tools can be connected by using the connecting rope 4, and the fixed pulleys 1 of the tools can be simultaneously moved along the steel wire rope to perform the hanging of the scattered pipes. The connecting rope 4 can be a steel wire rope or a wire rope.

[0034] As shown in the embodiment, Figure 1 and Figure 3 The lug 3 includes a rotating connecting piece 31, a flat plate 32, and a vertical plate 33, which are integrally arranged. The lower end surface of the rotating connecting piece 31 is fixed to the center of the flat plate 32, and the lower end surface of the flat plate 32 is fixed with the vertical plate 33. The rotating connecting piece 31 penetrates the second through hole 212 of the pedestal 2, and the top end of the rotating connecting piece 31 is provided with a baffle 311, which is circular and abuts against the upper end surface of the bottom plate 21.

[0035] The vertical plate 33 is provided with a hanging hole 331, and the vertical plate 33 is also provided with a rope passing hole 332.

[0036] The working principle of the special tool for the hanging of the scattered pipes of the boiler of the thermal power plant provided by the embodiment is as follows: a steel wire rope penetrating from the left side of the furnace to the right side of the furnace is fixed as a track near the installation position of the hanging pipe. The fixed pulley 1 is installed on the steel wire rope and can move back and forth along the steel wire rope.

[0037] The lug 3 is rotationally connected to the pedestal 2 and is hung on the steel wire rope through the fixed pulley 1, and the rope passing hole 332 is arranged on the lug 3. The operator connects the rope passing hole 332 of the lug 3 through the cable on the platform, pulls the cable to move the lug 3 along the steel wire rope, and thus realizes the hanging and positioning of the scattered pipes or the hanging pipe. Since the lug 3 is rotationally connected to the pedestal, when the cable pulling direction is changed by rotating the cable, the lug 3 can be rotated relative to the pedestal 2 to reach the required angle of the hanging and positioning of the scattered pipes or the hanging pipe.

[0038] Multiple pedestals 2 can be connected by using the connecting rope 4 to simultaneously perform the hanging of multiple groups of scattered pipes, and thus the simultaneous hanging and positioning of multiple groups of scattered pipes are realized.

[0039] The special tool for the hanging of the scattered pipes of the boiler of the thermal power plant provided by the embodiment can easily move the lug 2 through the cable on the platform by using the combination of the steel wire rope and the fixed pulley, and thus the quick hanging and positioning of the scattered pipes are realized, the frequency of using the tower crane is reduced, and the hoisting efficiency is improved.

[0040] The special tool for boiler pipe hanging in a thermal power plant provided by the embodiment can flexibly adjust the position of the lifting lug 2 according to the installation position of the pipe and the hanging pipe, is suitable for various installation scenes, the various pedestals can be connected with each other, and the simultaneous hanging of multiple groups of pipes and the hanging of a long pipe can be realized. When the installation direction of the pipe changes, the relative position of the lifting lug 3 and the fixed pulley 1 can be adjusted, so that the tool can adapt to different installation requirements.

[0041] The special tool for boiler pipe hanging in a thermal power plant provided by the embodiment can reduce the use of the tower crane, reduce the investment of the mechanical shift, simultaneously reduce the risk of the air operation, and improve the safety of the construction.

[0042] Finally, it should be noted that: the above only for the preferred embodiments of the utility model, and does not limit the utility model, although the utility model has been described in detail with reference to the foregoing embodiments, for the person skilled in the art, it still can modify the technical scheme recorded in the foregoing each embodiment, or equivalent replacement to part of technical features. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model should be included in the protection scope of the utility model.

Claims

1. A tool for hanging a boiler pipe in a thermal power plant, characterized in that, The utility model provides a steel wire rope suspension pulley (1) as track, the pulley (1) is erected on pedestal (2), the pedestal (2) is movably connected with lifting lug (3), and pulling the lifting lug (3) can make the lifting lug (3) rotate relative to the pedestal (2). The pedestal (2) is provided with a plurality of first through holes (211) for connecting adjacent pedestals (2).

2. The tool for hanging a boiler pipe in a thermal power plant according to claim 1, characterized in that, The pedestal (2) comprises a bottom plate (21) and a vertical plate (22) for erecting the pulley (1), and the vertical plate (22) is fixedly connected to the upper end surface of the bottom plate (21).

3. The tool according to claim 2, characterized in that, The bottom plate (21) is provided with a second through hole (212) in the center, the lifting lug (3) penetrates the second through hole (212) and can rotate in the second through hole (212).

4. The tool according to claim 3, characterized in that, The bottom plate (21) is provided with four first through holes (211), and each first through hole (211) is located at the periphery of the second through hole (212).

5. The tool according to claim 4, characterized in that, The first through holes (211) of two adjacent pedestals (2) are penetrated by a connecting rope (4) for connecting the two adjacent pedestals (2).

6. The tool according to claim 5, characterized in that, The lifting lug (3) comprises a rotating connecting piece (31), a flat plate (32) and a vertical plate (33) arranged integrally, the lower end surface of the rotating connecting piece (31) is fixedly connected to the center of the flat plate (32), and the lower end surface of the flat plate (32) is fixedly connected with the vertical plate (33). The rotating connecting piece (31) penetrates the second through hole (212), the top end of the rotating connecting piece (31) is provided with a baffle (311), and the baffle (311) abuts against the upper end surface of the bottom plate (21).

7. The tool according to claim 6, characterized in that, The vertical plate (33) is provided with a lifting hole (331).

8. The tool according to claim 7, characterized in that, The vertical plate (33) is also provided with a rope penetrating hole (332).

Citation Information

Patent Citations

  • Special tool for hanging scattered tubes of boiler in thermal power plant

    CN221876389U