Curtain wall air assembly platform suitable for super high-rise building
By designing an aerial assembly platform for curtain walls suitable for super high-rise buildings, and utilizing the coordination of translational structures, deflection components, and telescopic components, the installation plate is automatically adjusted to be parallel to the building, solving the problems of construction complexity and danger in existing technologies, and improving construction safety and efficiency.
Patent Information
- Application Number
- CN202520881237.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-05-07
- Publication Date
- 2026-02-06
- Estimated Expiration
- 2035-05-07
AI Technical Summary
Existing glass curtain wall installation devices are complex to operate in super high-rise buildings. Construction workers need to make significant adjustments to the curtain wall's position in mid-air, which increases the risk of construction and reduces efficiency.
An aerial assembly platform for curtain walls of super high-rise buildings was designed. Through the cooperation of translation structure, deflection component and telescopic component, the installation plate is automatically adjusted to be parallel to the building, reducing the range of operations and dangers for construction workers.
It simplifies the operation process for construction workers, shortens the distance between construction workers and the curtain wall, and improves construction safety and efficiency.
Smart Images

Figure CN223880792U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to glass curtain wall construction lifting appliance technical field, specifically is curtain wall air assembly platform suitable for super high -rise building. BACKGROUND
[0002] Air construction platform refers to the equipment for high altitude operation, usually by platform, support structure and control system composition, is widely used in engineering construction, maintenance, cleaning etc. field, guarantees the safety of operating personnel, when selecting and using air construction platform, need to strictly abide by the operation procedure, ensure the safety and stability of equipment.
[0003] At present, the air construction platform device used in glass curtain wall installation usually adopts fixed installation mode, when the glass curtain wall is in the process of building, meets the distance beyond the range of air construction platform device, needs to use hoisting structure, hoists the construction platform on the outside of building, the relevant technical personnel need to take the building process on the glass curtain wall on the air construction platform, when installing big curtain wall, the construction personnel need to adjust the curtain wall direction on the air construction platform, the whole range of action is big, and the operation is complex, reduces the building efficiency of glass curtain wall, and the operation range is big, which increases the danger in the construction process. UTILITY MODEL CONTENTS
[0004] The utility model aims at providing curtain wall air assembly platform suitable for super high -rise building to solve the problems in the above background technology.
[0005] To achieve the above object, the utility model provides the following technical scheme:
[0006] Curtain wall air assembly platform suitable for super high -rise building, including: installation platform, the fixed setting of support plate is set up on the installation platform, the mobile piece is set up on the support plate, the mobile piece is connected with the installation platform through the translation structure, the translation structure can drive the mobile piece relative to the installation platform and slide;
[0007] The installation plate is set up on the mobile piece, the installation plate is connected with the mobile piece through the support assembly, the support assembly includes the deflection piece and the telescopic piece, the deflection piece is connected with the deflection assembly arranged on the support plate, the telescopic piece is connected with the telescopic assembly arranged on the support plate, in the process that the mobile piece slides relative to the installation platform, the deflection assembly can drive the deflection piece to rotate ninety degrees, and simultaneously the telescopic assembly can drive the telescopic piece to slide relative to the deflection piece, thereby pushing the installation plate to turn to keep perpendicular to the installation platform, thereby facilitating the installation of subsequent curtain wall.
[0008] The curtain wall aerial assembly platform suitable for super high-rise buildings comprises a support plate, a moving piece and a deflection piece, and the moving piece comprises a moving plate, a threaded sleeve is arranged on the moving plate, two groups of the threaded sleeves are symmetrically arranged along the length direction of the moving plate, the two groups of the threaded sleeves are respectively threadedly connected with two groups of lead screws, and a placing groove is arranged on the side of the moving plate away from the lead screws, and two groups of the placing grooves are symmetrically arranged along the length direction of the moving plate.
[0009] The curtain wall aerial assembly platform suitable for super high-rise buildings comprises a support plate, a moving piece and a deflection piece, and the moving piece comprises a moving plate, a threaded sleeve is arranged on the moving plate, two groups of the threaded sleeves are symmetrically arranged along the length direction of the moving plate, the two groups of the threaded sleeves are respectively threadedly connected with two groups of lead screws, and a placing groove is arranged on the side of the moving plate away from the lead screws, and two groups of the placing grooves are symmetrically arranged along the length direction of the moving plate.
[0010] The curtain wall aerial assembly platform suitable for super high-rise buildings comprises a support plate, a moving piece and a deflection piece, and the moving piece comprises a moving plate, a threaded sleeve is arranged on the moving plate, two groups of the threaded sleeves are symmetrically arranged along the length direction of the moving plate, the two groups of the threaded sleeves are respectively threadedly connected with two groups of lead screws, and a placing groove is arranged on the side of the moving plate away from the lead screws, and two groups of the placing grooves are symmetrically arranged along the length direction of the moving plate.
[0011] The curtain wall aerial assembly platform suitable for super high-rise buildings comprises a support plate, a moving piece and a deflection piece, and the moving piece comprises a moving plate, a threaded sleeve is arranged on the moving plate, two groups of the threaded sleeves are symmetrically arranged along the length direction of the moving plate, the two groups of the threaded sleeves are respectively threadedly connected with two groups of lead screws, and a placing groove is arranged on the side of the moving plate away from the lead screws, and two groups of the placing grooves are symmetrically arranged along the length direction of the moving plate.
[0012] The curtain wall aerial assembly platform suitable for super high-rise buildings comprises a support plate, a moving piece and a deflection piece, and the moving piece comprises a moving plate, a threaded sleeve is arranged on the moving plate, two groups of the threaded sleeves are symmetrically arranged along the length direction of the moving plate, the two groups of the threaded sleeves are respectively threadedly connected with two groups of lead screws, and a placing groove is arranged on the side of the moving plate away from the lead screws, and two groups of the placing grooves are symmetrically arranged along the length direction of the moving plate.
[0013] The curtain wall aerial assembly platform suitable for super high-rise buildings comprises a support plate, a moving piece and a deflection piece, and the moving piece comprises a moving plate, a threaded sleeve is arranged on the moving plate, two groups of the threaded sleeves are symmetrically arranged along the length direction of the moving plate, the two groups of the threaded sleeves are respectively threadedly connected with two groups of lead screws, and a placing groove is arranged on the side of the moving plate away from the lead screws, and two groups of the placing grooves are symmetrically arranged along the length direction of the moving plate.
[0014] The curtain wall air assembling platform suitable for super high-rise building as described above: the driving structure comprises a first driving rod fixedly arranged on the support plate, a rotating cylinder is sleeved on the first driving rod, the rotating cylinder is rotatably installed on the support plate, and a protruding column is formed on the inner wall of the rotating cylinder and is slidably arranged in a composite groove formed in the first driving rod.
[0015] Compared with the prior art, the curtain wall air assembling platform suitable for super high-rise building has the advantages that:
[0016] By setting the translation structure and the supporting assembly, in the process that the translation structure pushes the moving plate to move close to the building, the supporting assembly is driven to act by the mutual cooperation between the deflection assembly and the telescopic assembly, and then the installation plate is automatically adjusted to be parallel to the inside of the building, so that the adjustment operation of the construction personnel during installation is reduced, the construction personnel can be conveniently installed, the working distance between the construction personnel and the curtain wall is shortened, the operation range of the whole installation process is small, and the operation safety of the construction personnel during installation of the curtain wall is improved. BRIEF DESCRIPTION OF DRAWINGS
[0017] Figure 1 It is a structural schematic view of the curtain wall air assembling platform suitable for super high-rise building.
[0018] Figure 2 It is a structural schematic view of the installation plate in the curtain wall air assembling platform suitable for super high-rise building.
[0019] Figure 3 It is a structural schematic view of the connection between the back of the installation plate and the moving plate in the curtain wall air assembling platform suitable for super high-rise building.
[0020] Figure 4 It is a structural schematic view of the translation structure in the curtain wall air assembling platform suitable for super high-rise building.
[0021] Figure 5 It is a structural schematic view of the supporting assembly in the curtain wall air assembling platform suitable for super high-rise building.
[0022] Figure 6 It is a structural schematic view of the deflection assembly in the curtain wall air assembling platform suitable for super high-rise building.
[0023] Figure 7 It is a structural schematic view of the driving structure in the curtain wall air assembling platform suitable for super high-rise building.
[0024] Figure 8 It is a structural schematic view of the telescopic assembly in the curtain wall air assembling platform suitable for super high-rise building.
[0025] In the figure: 1, installation platform; 2, support plate; 3, mounting plate; 301, suction cup; 302, sliding groove; 4, screw rod; 5, first driving rod; 501, first vertical groove; 502, spiral groove; 503, second vertical groove; 6, second driving rod; 601, first limiting groove; 602, rotating groove; 603, second limiting groove; 7, moving plate; 701, placing groove; 8, first bevel gear set; 9, belt; 10, threaded sleeve; 11, workpiece; 12, telescopic rod; 13, deflection cylinder; 14, mounting rod; 15, sleeve cylinder; 1501, protrusion; 16, connecting rod; 17, rotating rod; 18, linkage belt; 1801, connecting piece; 19, pulley; 20, rotating cylinder; 21, second bevel gear set. DETAILED DESCRIPTION
[0026] Various exemplary embodiments, features, and aspects of the present application will be described in detail below with reference to the accompanying drawings. The same reference numbers in the drawings represent the same elements or similar elements. Although various aspects of the embodiments are illustrated in the drawings, the drawings are not necessarily drawn to scale unless specifically indicated.
[0027] The word "exemplary" is used herein to mean "serving as an example, instance, or illustration." Any implementation described herein as "exemplary" is not necessarily to be construed as preferred or advantageous over other implementations.
[0028] In addition, for the purpose of convenience and brevity, detailed descriptions of well-known functions and structures incorporated in the application will be omitted when they are considered to make the subject matter of the application obscure. It will be appreciated that those skilled in the art will be able to devise various arrangements that, although not explicitly described herein, embody the essential characteristics of the application.
[0029] Please refer to Figures 1-8 In the embodiment of the utility model, the curtain wall air assembling platform suitable for super high-rise building comprises:
[0030] The installation platform 1 is fixedly provided with a support plate 2, the support plate 2 is provided with a moving part, the moving part is connected with the installation platform 1 through a translation structure, and the translation structure can drive the moving part to slide relative to the installation platform 1.
[0031] Specifically, the installation platform 1 is connected with a hoisting structure arranged at the top of the building (not shown in the figure), and the height between the installation platform 1 and the ground can be changed by using the hoisting structure, so that the construction personnel can conveniently install the curtain wall at different heights of the building.
[0032] Please refer to Figure 1The open guardrail is provided around the mounting platform 1, and the open guardrail can provide certain safety protection for the construction personnel standing on the mounting platform 1, and the opening of the guardrail faces and is close to the building, so that the construction personnel can conveniently install the curtain wall.
[0033] The translation structure comprises a screw rod 4 rotatably mounted on the support plate 2, and two groups of the screw rod 4 are symmetrically arranged along the length direction of the support plate 2, the two groups of the screw rod 4 are connected through a belt 9, and particularly, one group of the screw rod 4 is fixedly connected with the output shaft of the motor fixedly mounted on the support plate 2;
[0034] The moving part comprises a moving plate 7, a threaded sleeve 10 is arranged on the moving plate 7, two groups of the threaded sleeve 10 are symmetrically arranged along the length direction of the moving plate 7, the two groups of the threaded sleeve 10 are respectively threadedly connected with the two groups of the screw rod 4, and a placing groove 701 is formed on the side, away from the screw rod 4, of the moving plate 7, and two groups of the placing groove 701 are symmetrically arranged along the length direction of the moving plate 7;
[0035] In detail, in the initial state, the moving plate 7 is away from the opening of the guardrail, in the process of installing the curtain wall, the motor is started, and then the output shaft of the motor drives the screw rod 4 to continuously rotate in the same direction, in this process, the two groups of the screw rod 4 are synchronously rotated due to the connection of the belt 9, so as to drive the moving plate 7 to move close to the opening of the guardrail, until the moving plate 7 reaches the stroke end of the screw rod 4, the motor stops working, at this time, the moving plate 7 is close to the opening of the guardrail, and the curtain wall on the moving plate 7 is as close to the building as possible, so as to shorten the distance between the construction personnel and the building, facilitate the construction personnel to install the curtain wall, and reduce the danger of the construction personnel in the high place to install the curtain wall.
[0036] Further, referring to Figures 1-5 , the moving part is provided with a mounting plate 3, the mounting plate 3 is connected with the moving part through a support assembly, the support assembly comprises a deflection piece and an extension piece, the deflection piece is connected with a deflection assembly arranged on the support plate 2, the extension piece is connected with an extension assembly arranged on the support plate 2, in the process that the moving part slides relative to the mounting platform 1, the deflection assembly can drive the deflection piece to rotate by ninety degrees, and the extension assembly can drive the extension piece to slide relative to the deflection piece, so as to push the mounting plate 3 to be perpendicular to the mounting platform 1, thereby facilitating the subsequent installation of the curtain wall.
[0037] In detail, referring to Figure 1 , Figure 2The one side of the mounting plate 3 away from the moving plate 7 is fixedly provided with a plurality of suction cups 301, the plurality of suction cups 301 are uniformly distributed on the surface of the mounting plate 3, and the plurality of suction cups 301 are controlled by the same control system and cooperatively adsorb and release the curtain.
[0038] In the initial state, the mounting plate 3 is parallel to the moving plate 7, before the curtain is installed, the curtain is placed on the mounting plate 3, and the control system can adsorb the curtain on the mounting plate 3, so that the subsequent construction personnel can perform the installation operation.
[0039] Further, referring to Figure 4 The mounting plate 3 is rotationally connected with a mounting rod 14 fixedly arranged on the moving plate 7, the mounting rod 14 is close to the guardrail opening, under the cooperation of the supporting assembly, the mounting plate 3 can be deflected by 90 degrees with the mounting rod 14 as the center, so that the mounting plate 3 can be perpendicular to the moving plate 7, at this time, the mounting plate 3 is parallel to the side surface of the building, which can facilitate the construction personnel to install the curtain on the surface of the building.
[0040] The deflection piece includes a deflection cylinder 13 rotationally arranged on the moving plate 7, the deflection cylinder 13 is symmetrically arranged along the length direction of the moving plate 7, and the rotation centers of the two groups of deflection cylinders 13 are fixed;
[0041] The telescopic piece includes a telescopic rod 12, the telescopic rod 12 is arranged in two groups, the two groups of telescopic rods 12 are respectively slidably arranged in the deflection cylinder 13, the two groups of telescopic rods 12 are fixedly connected through a connecting rod 16, and one end of each group of telescopic rods 12 away from the deflection cylinder 13 is hingedly connected with a workpiece 11, the workpiece 11 is slidably arranged in a sliding groove 302 arranged on the mounting plate 3;
[0042] Specifically, in the initial state, the deflection cylinder 13 is arranged in the placing groove 701 and is parallel to the moving plate 7, at this time, the telescopic rod 12 is retracted into the deflection cylinder 13, and the workpiece 11 is located at the stroke end of the sliding groove 302 close to the mounting rod 14, at this time, the mounting plate 3 is parallel to the moving plate 7, which can ensure the stability of the curtain placed on the mounting plate 3 and followed by the mounting plate 3 during movement.
[0043] The deflection assembly includes a second driving rod 6 fixedly arranged on the supporting plate 2, a sleeve 15 is arranged on the second driving rod 6, the sleeve 15 is rotationally connected with a fixed piece fixedly arranged on the moving plate 7, the sleeve 15 is connected with the rotation shaft of one of the deflection cylinders 13 through a first bevel gear set 8, the inside of the sleeve 15 is formed with a protrusion 1501, and the protrusion 1501 is slidably arranged in a fitting groove arranged on the outer wall of the second driving rod 6;
[0044] The first bevel gear set 8 comprises a first bevel gear coaxially fixed with the sleeve 15 and a second bevel gear coaxially fixed with the rotation shaft of the deflection cylinder 13.
[0045] Specifically, please refer to Figures 2-6 The fitting groove comprises a rotating groove 602 provided on the second driving rod 6, the first limiting groove 601 and the second limiting groove 603 are respectively connected to the first end and the second end of the rotating groove 602, and the second limiting groove 603 is away from the mounting rod 14. The spiral angle of the rotating groove 602 is less than ninety degrees.
[0046] In the initial state, the protrusion 1501 is combined with the second limiting groove 603 away from the stroke end of the spiral groove 602. As described above, in the process that the lead screw 4 cooperates with the threaded sleeve 10 to drive the moving plate 7 to move towards the opening of the railing, the mounting plate 3 synchronously moves with the moving plate 7. In this process, the protrusion 1501 slides in the second limiting groove 603. After the protrusion 1501 is combined with the rotating groove 602, the contact and extrusion of the rotating groove 602 on the protrusion 1501 can force the sleeve 15 to rotate clockwise (combined with Figure 5 、 Figure 6 description), then the first bevel gear and the second bevel gear enter the meshing transmission state, which can drive the deflection cylinder 13 to deflect clockwise around the rotation shaft. At the same time, the telescopic assembly can drive the telescopic rod 12 to extend outwardly from the deflection cylinder 13. The two cooperate with each other to drive the mounting plate 3 to deflect around the mounting rod 14 towards the building until the protrusion 1501 is separated from the rotating groove 602 and combined with the first limiting groove 601. At this time, the deflection cylinder 13 cooperates with the telescopic rod 12 to push the mounting plate 3 to a state perpendicular to the mounting plate 3. Then the moving plate 7 continues to move, the sleeve 15 slides in the first limiting groove 601, which can lock the positions of the sleeve 15 and the deflection cylinder 13. Until the moving plate 7 moves to the end of the lead screw 4, the mounting plate 3 always maintains the perpendicular state, so that the construction personnel can install the curtain wall.
[0047] In detail, please refer to Figures 1-8 The telescopic assembly comprises a belt wheel 19 rotationally installed on another group of the deflection cylinder 13 and a rotation rod 17 connected with the driving structure provided on the support plate 2. A linkage belt 18 is provided between the rotation rod 17 and the belt wheel 19. One group of running ends of the linkage belt 18 is fixedly provided with a connecting piece 1801, and the connecting piece 1801 is fixedly connected with the telescopic rod 12.
[0048] The driving structure comprises a first driving rod 5 fixedly arranged on the support plate 2, a rotating cylinder 20 sleeved on the first driving rod 5, the rotating cylinder 20 being rotatably arranged on the support plate 2, and a protruding column formed on the inner wall of the rotating cylinder 20 being slidably arranged in a composite groove formed in the first driving rod 5;
[0049] Please refer to Figure 7 The composite groove comprises a first vertical groove 501, a spiral groove 502, and a second vertical groove 503, the second vertical groove 503 being away from the mounting rod 14, and the rotating cylinder 20 being connected with the rotating rod 17 through a second bevel gear set 21, the second bevel gear set 21 comprising a third bevel gear and a fourth bevel gear, the third bevel gear being coaxially fixed with the rotating cylinder 20, and the fourth bevel gear being coaxially fixed with the rotating rod 17.
[0050] In combination with the above, in the initial state, the protruding column formed on the inner wall of the rotating cylinder 20 is located at the stroke end of the second vertical groove 503 away from the spiral groove 502, when the protrusion 1501 is combined with the rotating groove 502, the protruding column is combined with the spiral groove 502 at the same time, in the process of combination of the protruding column with the spiral groove 502, the contact extrusion of the spiral groove 502 on the protruding column can force the rotating cylinder 20 to rotate counterclockwise for several turns (in combination with Figure 5 、 Figure 7 ), and then, under the cooperation of the second bevel gear set 21, the rotating cylinder 20 can drive the rotating rod 17 to rotate counterclockwise, thereby driving the linkage belt 18 to rotate counterclockwise, in this process, the connecting piece 1801 can drive the telescopic rod 12 to extend to the outside of the deflection cylinder 13, thereby making the workpiece 11 slide in the sliding groove 302, until the protrusion 1501 is combined with the first limiting groove 601, the protruding column is combined with the first vertical groove 501, at this time, the position of the telescopic rod 12 is limited, at this time, under the cooperation of the deflection cylinder 13 and the telescopic rod 12, the vertical state of the mounting plate 3 is fixed, and then, when the mounting plate 3 is moved to the end of the lead screw 4 following the movement of the moving plate 7, the construction personnel hold the curtain wall, and after the control system releases the adsorption state of the suction cup 301, the curtain wall can be installed, in the whole process, the action range of the construction personnel is small, and in the installation process, it is not necessary to manually greatly adjust the position of the curtain wall, thereby improving the construction safety of the construction personnel.
[0051] It is apparent for a person skilled in the art that the present application is not limited to the details of the above-described exemplary embodiments, but that it can be implemented in other concrete forms without departing from the spirit or the essential characteristics of the present application. Therefore, the embodiments should be considered as exemplary and non-limiting, the scope of the present application being defined by the claims appended hereto rather than by the above description, and all the changes which fall within the meaning and the scope of the equivalent elements of the claims are intended to be embraced therein. Any reference signs in the claims should not be construed as limiting the claims to the figures in which the reference signs are used.
[0052] Furthermore, it should be understood that although the present specification describes exemplary embodiments, not every embodiment contains only one independent technical solution, and the present specification is described in this way only for the sake of clarity, and a person skilled in the art should consider the specification as a whole, and the technical solutions in each embodiment can also be appropriately combined to form other embodiments that a person skilled in the art can understand.
Claims
1. A curtain wall air assembly platform suitable for super high-rise buildings, characterized in that, The utility model provides a kind of curtain wall installation device, including: Mounting platform (1), the support plate (2) is fixedly arranged on the mounting platform (1), the moving piece is arranged on the support plate (2), the moving piece is connected with the mounting platform (1) by translation structure, the translation structure can drive the moving piece to slide relative to the mounting platform (1); The mounting plate (3) is arranged on the moving piece, the mounting plate (3) is connected with the moving piece by support assembly, the support assembly includes deflection piece and telescopic piece, the deflection piece is connected with the deflection assembly arranged on the support plate (2), the telescopic piece is connected with the telescopic assembly arranged on the support plate (2), in the process that the moving piece slides relative to the mounting platform (1), the deflection assembly can drive deflection piece to rotate ninety degrees, simultaneously the telescopic assembly can drive the telescopic piece to slide relative to the deflection piece, to push the mounting plate (3) to turn to keep perpendicular with the mounting platform (1), to facilitate subsequent installation of curtain wall.
2. The curtain wall assembly platform for use in super high-rise buildings according to claim 1, characterized in that, The translation structure includes screw rod (4) rotatably mounted on the support plate (2), the screw rod (4) is symmetrically provided with two groups along the length direction of the support plate (2), two groups of the screw rod (4) are connected by belt (9).
3. The curtain wall assembly platform for use in super high-rise buildings according to claim 2, characterized in that, The moving piece includes moving plate (7), the threaded sleeve (10) is arranged on the moving plate (7), the threaded sleeve (10) is symmetrically provided with two groups along the length direction of the moving plate (7), two groups of the threaded sleeve (10) are respectively connected with two groups of the screw rod (4) in screw thread, and the side, away from the screw rod (4), of the moving plate (7) is provided with placing groove (701), the placing groove (701) is symmetrically provided with two groups along the length direction of the moving plate (7).
4. The curtain wall assembly platform for use in super high-rise buildings according to claim 3, characterized in that, The deflection piece includes deflection cylinder (13) rotatably mounted on the moving plate (7), the deflection cylinder (13) is symmetrically provided with two groups along the length direction of the moving plate (7), and the rotation centers of two groups of the deflection cylinder (13) are fixed.
5. The curtain wall assembly platform for use in super high-rise buildings according to claim 4, characterized in that, The telescopic piece includes telescopic rod (12), the telescopic rod (12) is provided with two groups, two groups of the telescopic rod (12) are respectively slidably arranged in the deflection cylinder (13), and two groups of the telescopic rod (12) are fixedly connected by connecting rod (16), and the end, away from the deflection cylinder (13), of each group of the telescopic rod (12) is hingedly connected with the workpiece (11), and the workpiece (11) is slidably arranged in the sliding slot (302) formed in the mounting plate (3).
6. The curtain wall assembly platform for use in super high-rise buildings according to claim 4, characterized in that, The deflection assembly includes second driving rod (6) fixedly arranged on the support plate (2), the sleeve joint cylinder (15) is sleeved on the second driving rod (6), the sleeve joint cylinder (15) is rotatably connected with the fixed piece fixedly arranged on the moving plate (7), and the sleeve joint cylinder (15) is connected with the rotation shaft of one of the deflection cylinder (13) through the first bevel gear set (8), the inside of the sleeve joint cylinder (15) is formed with the protrusion (1501), and the protrusion (1501) is slidably arranged in the fitting groove formed in the outer wall of the second driving rod (6).
7. The curtain wall assembly platform for use in super high-rise building according to claim 5, wherein, Said telescopic assembly includes a belt wheel (19) rotatably installed on another set of said deflection cylinders (13) and a rotating rod (17), said rotating rod (17) is connected with a driving structure arranged on said support plate (2), and a linkage belt (18) is arranged between said rotating rod (17) and said belt wheel (19), one set of running ends of said linkage belt (18) is fixedly provided with a connecting piece (1801), said connecting piece (1801) is fixedly connected with said telescopic rod (12).
8. The curtain wall assembly platform for use in super high-rise buildings according to claim 7, characterized in that, Said driving structure includes a first driving rod (5) fixedly arranged on said support plate (2), said first driving rod (5) is sleeved with a rotating cylinder (20), said rotating cylinder (20) is rotatably installed on said support plate (2), and a protruding column is formed on the inner wall of said rotating cylinder (20), said protruding column is slidably arranged in a composite groove formed on said first driving rod (5).