Pile grouting operation platform device for bored pile
By designing a drilling pile grouting operation platform device, and using steel casing and side flaps to fix the guide pipe, the problems of low safety and low efficiency in traditional drilling pile construction have been solved, and safety and efficiency have been improved.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2026-03-20
AI Technical Summary
In traditional bored pile construction, the borehole protection is simple, which poses safety risks and has low construction efficiency.
A drilling pile grouting operation platform device is designed, including a steel casing, an operation platform, a side flap, and a hinge flap. By placing the operation platform horizontally above the steel casing and using the side flap and hinge flap to fix the guide pipe, a stable grouting operation platform is formed, which improves safety and construction efficiency.
It improved construction safety and efficiency, reduced construction risks, and increased construction efficiency.
Smart Images

Figure CN224016730U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of drilling pile filling related equipment, specifically to a drilling pile filling operation platform device. BACKGROUND
[0002] At present, pile foundation construction is mainly divided into two kinds of precast pile and bored pile. The precast pile is generally small in diameter and short in length, and is mainly used for foundation treatment. The bored pile is generally large in diameter and long in length, and is often used as a structural foundation. The bored pile refers to the pile formed by forming a pile hole in the ground through mechanical drilling, steel pipe soil extrusion or manpower excavation, and placing a steel reinforcement cage and pouring concrete in the hole.
[0003] The bored pile forming method mainly has dry operation hole forming and mud wall hole forming. Generally, the guide pipe method is used for pouring. When pouring, a simple construction platform is set up at the hole opening to provide a work site. In the traditional drilling pile pouring process, the hole opening protection is relatively simple, and there is a great safety risk. During the operation process of the construction personnel, due to the site limitation, the construction efficiency is low. UTILITY MODEL CONTENT
[0004] The utility model provides a drilling pile filling operation platform device to solve the problems in the background art.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical scheme: a drilling pile filling operation platform device, including a steel casing and a guide pipe placed in the inner cavity of the steel casing and with the end part penetrating out of the inner cavity of the steel casing, the top of the steel casing is provided with an operation platform, both sides of the operation platform are provided with a side turnover plate for being placed on the ground, the top of the operation platform is formed with a mounting groove, the inner walls of both sides of the mounting groove are hinged with symmetrically arranged hinge turnover plates, one side of the two hinge turnover plates close to each other is formed with an arc-shaped groove, and the two hinge turnover plates provided with the arc-shaped grooves are used to clamp and fix the guide pipe.
[0006] Further, the mounting groove is a square groove.
[0007] Further, the side turnover plate is a reinforced mesh turnover plate.
[0008] Further, the side turnover plate is rotatably arranged on the side surface of the operation platform.
[0009] Further, the operation platform includes an operation steel plate and an I-steel, the top center of the operation steel plate is provided with a mounting groove, and the bottom of the operation steel plate is fixedly connected with an I-steel along the outer peripheral direction thereof.
[0010] Further, at least two strip grooves are arranged on both sides of the top of the operation steel plate.
[0011] Compared with the prior art, the drilling pile pouring operation platform device has the following beneficial effects: the drilling pile pouring operation platform device is horizontally placed above the steel casing, cooperates with the side turnover plates on the two sides, can cover the steel casing, forms a pouring operation table, greatly improves the safety of the construction personnel during construction, and can also improve the construction efficiency. BRIEF DESCRIPTION OF DRAWINGS
[0012] Figure 1 It is a structural schematic view of the utility model;
[0013] Figure 2 It is a structural schematic view of the utility model when the hinge turnover plate is opened;
[0014] Figure 3 It is a top view structural schematic view of the utility model;
[0015] Figure 4 It is a structural schematic view of the operation platform of the utility model;
[0016] Figure 5 It is a structural schematic view of the hinge turnover edge of the utility model.
[0017] In the drawing: 1, steel casing; 2, guide pipe; 3, operation platform; 4, installation groove; 5, hinge turnover plate; 6, arc-shaped groove; 7, side turnover plate; 8, operation steel plate; 9, I-shaped steel; 10, strip groove. DETAILED DESCRIPTION
[0018] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the protection scope of the utility model.
[0019] Please refer to Figures 1-5 The utility model discloses a drilling pile pouring operation platform device, including steel casing 1 and the guide pipe 2 of being placed in the inner chamber of steel casing 1 and the end part of being worn out the inner chamber of steel casing 1, the top of steel casing 1 is placed with operation platform 3, the both sides of operation platform 3 are equipped with the side turnover plate 7 for being placed on the ground, the top of operation platform 3 forms and is equipped with installation groove 4, the both sides inner wall of installation groove 4 are hinged with the hinge turnover plate 5 of being set up symmetrically, the side of two hinge turnover plate 5 is formed with arc-shaped groove 6, and two hinge turnover plate 5 with arc-shaped groove 6 are used to clamp and fix guide pipe 2.
[0020] Specifically, the installation groove 4 is a square groove.
[0021] In the embodiment, the cooperation of the two hinge flaps 5 can close the mounting groove 4.
[0022] The inner wall bottom end of the mounting groove 4 can be fixed with a carrier plate, which is used to support the hinge flaps 5 when the hinge flaps 5 close the mounting groove 4, so as to prevent the hinge flaps 5 from continuing to rotate downward when closing the mounting groove 4.
[0023] Of course, the hinge flaps 5 can also be hingedly connected to the inner wall of the mounting groove 4 through a fixed-angle hinge, such as a one-hundred-and-eighty-degree hinge, so as to avoid the end of the hinge flaps 5 opening the arc-shaped slot 6 from continuing to rotate downward when the hinge flaps 5 close the mounting groove 4.
[0024] Specifically, the side flap 7 is a steel mesh flap.
[0025] The side flap 7 is rotatably arranged on the side of the operation platform 3.
[0026] In the embodiment, the steel mesh flap is made of 22 mm steel bars and 14 mm steel bars, and when the side flap 7 is unfolded, the steel casing 1 is fully covered to form a pouring operation platform, so that the safety of the construction personnel is greatly improved, and the construction efficiency is also improved.
[0027] Specifically, the operation platform 3 comprises an operation steel plate 8 and an I-shaped steel 9, the top center of the operation steel plate 8 is provided with the mounting groove 4, and the bottom of the operation steel plate 8 is fixedly connected with the I-shaped steel 9 along the outer peripheral direction thereof.
[0028] At least two strip grooves 10 are formed on both sides of the top of the operation steel plate 8.
[0029] In the embodiment, the operation steel plate 8 is made of an 8 mm steel plate, the I-shaped steel 9 is provided with four I16 I-shaped steels, and the I-shaped steels 9 are arranged in a square ring shape and are welded at the bottom end of the operation steel plate 8.
[0030] The strip grooves 10 on both sides of the operation steel plate 8 in the mounting groove 4 can reduce the weight of the operation steel plate 8 without affecting the protection function of the operation steel plate 8.
[0031] In use, the operation platform 3 is placed on the top of the steel casing 1, and the two sides thereof are placed on the solid ground, the hinge flaps 5 are in a closed state, the side flaps 7 are opened, and the concrete pouring height needs to be pulled out one or more sections of the guide pipe 2, at which time the hinge flaps 5 are opened, and the guide pipe 2 is lifted.
[0032] In summary, the drilling pile pouring operation platform device, the operation platform 3 is horizontally placed above the steel casing 1, and the two side flaps 7 on both sides thereof can fully cover the steel casing 1 to form a pouring operation platform, so that the safety of the construction personnel is greatly improved, and the construction efficiency is also improved.
[0033] While the embodiments of the present application have been illustrated and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the spirit and scope of the application, which is defined by the appended claims and their equivalents.
Claims
1. A drilling pile grouting operation platform device, comprising a steel casing (1) and a guide pipe (2) placed inside the steel casing (1) and having its end extending out of the steel casing (1), characterized in that: The top of the steel casing (1) is provided with a working platform (3), and the two sides of the working platform (3) are provided with side flaps (7) for placing on the ground. The top of the working platform (3) is formed with an installation groove (4), and the inner walls of the two sides of the installation groove (4) are hinged with symmetrically arranged hinge flaps (5). The two hinge flaps (5) that are close to each other are formed with an arc groove (6). The two hinge flaps (5) with arc grooves (6) are used to lock and fix the guide tube (2).
2. The drilling pile grouting operation platform device according to claim 1, characterized in that: The mounting slot (4) is a square slot.
3. The drilling pile grouting operation platform device according to claim 1, characterized in that: The side flap (7) is a steel mesh flap.
4. The drilling pile grouting operation platform device according to claim 3, characterized in that: The side flap (7) is rotatably mounted on the side of the work platform (3).
5. The drilling pile grouting operation platform device according to claim 1, characterized in that: The working platform (3) includes a working steel plate (8) and an I-beam (9). An installation groove (4) is opened at the top center of the working steel plate (8), and an I-beam (9) is fixedly connected to the bottom of the working steel plate (8) along its outer periphery.
6. The drilling pile grouting operation platform device according to claim 5, characterized in that: The top of the working steel plate (8) is provided with at least two grooves (10) on both sides of the mounting groove (4).