Tower crane bracket steel beam foundation device based on pier body
By designing the tower crane bracket steel beam foundation device for the bridge pier, the problem of tower crane installation in cross-river environments was solved, enabling stable and rapid tower crane construction and improving the efficiency and safety of bridge construction.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-25
- Publication Date
- 2026-03-24
AI Technical Summary
Under the constraints of cross-river and surrounding environment, tower crane installation is difficult. High river water levels result in a lack of dry and stable environment for the tower crane foundation, affecting the normal operation of the tower crane and slowing down the bridge construction speed.
Design a tower crane corbel steel beam foundation device based on bridge pier body, including pier body, steel beam foundation frame, steel bars, pier body supporting steel corbel and connecting components, forming a stable structure through welding and threaded connection, adapting to bridge pier structure and improving the stability of construction environment.
It enables rapid and stable installation of tower cranes in complex environments, reduces construction difficulty, improves construction efficiency and quality, and reduces costs.
Smart Images

Figure CN224031735U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to tower machine foundation technical field, especially a tower machine bracket steel beam foundation device based on bridge pier body. BACKGROUND
[0002] In construction engineering, tower crane is a common hoisting equipment for lifting and carrying heavy objects. The stability of tower crane is crucial to ensure construction safety, so the foundation design of tower crane is particularly important. In bridge construction, due to the special structure of bridge pier, the traditional concrete foundation may not meet the requirements. Therefore, a specially designed foundation device is needed to adapt to the special structure of bridge pier.
[0003] Through retrieval, the patent with publication number CN207987956U discloses a bridge-mounted tower crane foundation, which comprises a No. 1 bridge pier pile cap and a No. 2 bridge pier pile cap. The No. 1 bridge pier pile cap is provided with a No. 1 main bridge tower body on the upper side, and a No. 1 bridge pier group pile is arranged on the lower side of the No. 1 bridge pier pile cap. The No. 1 bridge pier pile cap is provided with a No. 2 bridge pier pile cap on one side, and the No. 2 bridge pier pile cap is provided with a No. 2 main bridge tower body on the upper side. The No. 2 bridge pier pile cap is provided with a No. 2 bridge pier group pile on the lower side. The No. 1 bridge pier pile cap and the No. 2 bridge pier pile cap are connected through a base plate. The base plate is provided with a support column at the bottom. The support column is connected with the No. 1 bridge pier pile cap and the No. 2 bridge pier pile cap through a metal fixed plate. A tower crane foundation pile cap is cast on the base plate. The outer surface of the tower crane foundation pile cap is provided with an anti-weathering layer. The base plate is made of stainless steel plate, which facilitates the casting of the tower crane foundation pile cap and effectively prevents water from corroding the bottom of the tower crane foundation pile cap.
[0004] Based on the above retrieval and combining with the prior art, it is found that
[0005] Although the above-mentioned patent sets an anti-weathering layer, it is difficult to install the tower crane under the condition of crossing a river and surrounding environmental restrictions. The common water level of the river is higher than the top surface of the bridge pier pile cap. The tower crane foundation lacks a dry and stable environment, which cannot ensure the normal operation of the tower crane, resulting in slow bridge construction speed. Therefore, there are certain limitations. UTILITY MODEL CONTENTS
[0006] In order to solve the above technical problems, the utility model provides a tower crane bracket steel beam foundation device based on bridge pier body, which can keep the construction environment dry and avoid water impact, speed up the construction speed, and improve the construction quality and efficiency.
[0007] The technical solution for achieving the utility model discloses the following: a tower crane bracket steel beam foundation device based on a pier body, which comprises a pier body and a steel beam foundation frame, a plurality of groups of steel bars are fixedly installed in the interiors of the pair of pier bodies, a pier body support steel bracket is fixedly welded at the end of each group of steel bars, the steel beam foundation frame is fixedly connected with the pier body support steel bracket, and a connecting assembly is further included;
[0008] The connecting assembly comprises a steel plate one fixedly installed on the surface of the steel beam foundation frame.
[0009] Preferably, a plurality of groups of stiffening ribs are fixedly installed between the steel beam foundation frame and the pier body support steel bracket, and a stiffening inclined brace is fixedly installed in the interior of the steel beam foundation frame.
[0010] Preferably, a plurality of support steels one are fixedly installed on the surface of the steel plate one, a steel plate three is fixedly installed at the top of each support steel one, and a steel plate two is arranged on the surface of the steel plate three.
[0011] Preferably, a threaded rod is slidably penetrated between each steel plate two and steel plate three, and a pair of nuts are threadedly connected to the two ends of the threaded rod.
[0012] Preferably, a tower crane standard section is fixedly installed on the surface of the steel plate two, and a plurality of support steels two are fixedly installed between the surface of the steel plate two and the bottom of the tower crane standard section.
[0013] Compared with the prior art, the utility model has the following advantages:
[0014] Firstly, the utility model is suitable for arc-shaped close-range piers and meets the optimal position arrangement of a tower crane, and the foundation has high adaptability, high turnover rate, fast processing, efficient installation, stable and safe support and reliability.
[0015] Secondly, the utility model is designed with four brackets, a steel beam is prefabricated and hoisted into position, and then is welded on site, a plurality of trapezoidal stiffening plates are arranged at the welding position to strengthen the welding position, increase the length of the welding seam, reduce the difficulty of tower crane arrangement and foundation construction, save costs, and accelerate the engineering progress.
[0016] The utility model solves the problem that, under the restriction of existing cross-river and surrounding environment conditions, the installation of a tower crane is difficult, the normal operation of the tower crane cannot be ensured because the river water level is higher than the top surface of a pier cap and the tower crane foundation lacks a dry and stable environment, and the bridge construction speed is slow. BRIEF DESCRIPTION OF DRAWINGS
[0017] The utility model will be further explained in combination with the drawings and embodiments:
[0018] Figure 1 is a schematic diagram of an overall three-dimensional structure provided by the utility model;
[0019] Figure 2 is the overall overhead structure schematic view provided by the utility model;
[0020] Figure 3 is the plane structure schematic view provided by the utility model;
[0021] Figure 4 is the local structure schematic view provided by the utility model;
[0022] Figure 5 is the pier body steel hanger structure schematic view provided by the utility model.
[0023] Mark explanation:
[0024] 1, pier body; 2, steel beam foundation frame; 3, tower crane standard section; 4, stiffening rib; 5, connecting assembly; 6, pier body support steel hanger; 7, stiffening diagonal brace; 8, reinforcing bar; 9, support steel; 10, threaded rod; 11, nut; 12, steel plate one; 13, steel plate two; 14, steel plate three; 15, support steel two. Specific implementation
[0025] The utility model will be described in detail below, and the technical scheme in the embodiment of the utility model is clearly and completely described. Obviously, the described embodiment is only a part of the embodiment of the utility model, not all. Based on the embodiment in the utility model, all other embodiments obtained by the ordinary skill in the art without creative labor belong to the scope of the utility model protection.
[0026] The utility model improves and provides a tower crane hanger steel beam foundation device based on pier body, and the technical scheme of the utility model is:
[0027] As shown in Figures 1-5 A tower crane hanger steel beam foundation device based on pier body, comprising a pier body 1 and a steel beam foundation frame 2, a plurality of reinforcing bars 8 are fixedly installed in the inside of a pair of pier bodies 1, a pier body support steel hanger 6 is commonly fixedly welded at one end of each group of reinforcing bars 8, the steel beam foundation frame 2 is fixedly connected with the pier body support steel hanger 6, the impact resistance and the carrying capacity of the device are strengthened by welding and assembling reinforcing bars 8 and pier body support steel hangers 6, which is beneficial to the device to maintain a relatively stable construction environment, and further comprising a connecting assembly 5.
[0028] The connecting assembly 5 comprises a steel plate one 12 fixedly installed on the surface of the steel beam foundation frame 2, and a plurality of steel plates are installed to provide a stable foundation for the installation of the tower crane standard section 3 in the later period.
[0029] Further, a plurality of stiffening ribs 4 are fixedly installed between the steel beam foundation frame 2 and the pier body supporting steel corbel 6, and a stiffening diagonal brace 7 is fixedly installed in the steel beam foundation frame 2, so that the device components are stably and firmly connected, the device is stable, safe and reliable, and the difficulty of tower crane arrangement and foundation construction is reduced.
[0030] Further, a plurality of support steels 9 are fixedly installed on the surface of the steel plate 12, the top of each support steel 9 is fixedly installed with a steel plate 14, and the surface of the steel plate 14 is provided with a steel plate 13, so that the plurality of steel plates are combined and the support steels are installed in the steel plates, the connecting component 5 is well played, and the ideal working state is achieved.
[0031] As a further scheme of the utility model, a threaded rod 10 is slidably penetrated between each steel plate 13 and the steel plate 14, and a pair of nuts 11 are threadedly connected to both ends of the threaded rod 10, so that the threaded rod 10 can be repeatedly used after being disassembled and assembled, and the construction cost is saved.
[0032] Further, a tower crane standard section 3 is fixedly installed on the surface of the steel plate 13, and a plurality of support steels 15 are fixedly installed between the surface of the steel plate 13 and the bottom of the tower crane standard section 3, so that the tower crane standard section 3 provides necessary support and connection in the operation of the tower crane, improves the safety and reliability of the tower crane, reduces the maintenance cost, and facilitates installation and disassembly.
[0033] Specific working method is: first, select appropriate position between the pier body 1, weld a plurality of reinforcing steels 8 and the pier body supporting steel corbel 6, then fixedly install four pier body supporting steel corbels 6 with the pier body 1, second, place the steel beam foundation frame 2 between the pier body supporting steel corbel 6, and the steel beam foundation frame 2 is fixedly welded with the stiffening rib 4 at four ends, ensure the stability, then fixedly weld the stiffening diagonal brace 7 between the steel beam foundation frame 2, improve the firmness of the device, finally, install a plurality of steel plates on the surface of the steel beam foundation frame 2, fix the steel plates by the threaded rod 10 and the nut 11, and install support steels to improve the carrying capacity of the device, and fixedly install the tower crane standard section 3 on the foundation frame, avoid the delay of construction period caused by water flow problem, and keep the construction environment dry.
[0034] The technical means disclosed by the utility model scheme is not limited to the technical means disclosed by the above technical means, and also includes technical solutions composed of equivalent replacement of the above technical features. The matters not covered by the utility model belong to the common knowledge of those skilled in the art.
Claims
1. A tower crane corbel steel beam foundation device based on a bridge pier, comprising a pier body (1) and a steel beam foundation frame (2), characterized in that: Multiple sets of reinforcing bars (8) are fixedly installed inside each pair of pier bodies (1). One end of each set of reinforcing bars (8) is fixedly welded to a pier body supporting steel bracket (6). The steel beam foundation frame (2) is fixedly connected to the pier body supporting steel bracket (6). The connecting component (5) includes a steel plate (12) fixedly installed on the surface of the steel beam foundation frame (2).
2. The tower crane corbel steel beam foundation device based on bridge pier body according to claim 1, characterized in that: Multiple sets of stiffening ribs (4) are fixedly installed between the steel beam foundation frame (2) and the pier support steel corbel (6), and stiffening diagonal braces (7) are fixedly installed inside the steel beam foundation frame (2).
3. The tower crane corbel steel beam foundation device based on bridge pier body according to claim 1, characterized in that: Multiple supporting steel plates (9) are fixedly installed on the surface of the steel plate (12), and a steel plate (14) is fixedly installed on the top of each supporting steel plate (9). A steel plate (13) is provided on the surface of the steel plate (14).
4. The tower crane corbel steel beam foundation device based on bridge pier body according to claim 3, characterized in that: A threaded rod (10) slides through each of the steel plates 2 (13) and 3 (14), and a pair of nuts (11) are threadedly connected to both ends of the threaded rod (10).
5. The tower crane corbel steel beam foundation device based on bridge pier body according to claim 3, characterized in that: The surface of the steel plate 2 (13) is fixedly installed with a tower crane standard section (3), and multiple supporting steel plates 2 (15) are fixedly installed between the surface of the steel plate 2 (13) and the bottom of the tower crane standard section (3).