Directly-supplied electric boiler prizing and installing integrated unit
By designing a skid-mounted integrated unit for direct-supply electric boilers, the problems of low on-site installation efficiency, high error rate, and difficulty in customization of electric boilers have been solved. This has enabled efficient and customized multi-boiler linkage and intelligent monitoring, improving construction efficiency and reliability.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- HEBEI GECHENG SHENGHONG ELECTRIC CO LTD
- Filing Date
- 2025-08-07
- Publication Date
- 2026-07-17
AI Technical Summary
Existing electric boilers suffer from low on-site installation efficiency, high error rate, difficulty in customization, and difficulty in achieving multi-boiler linkage and intelligent monitoring.
Design a skid-mounted integrated unit for direct-supply electric boilers, including control components, electric boiler components, and water supply components. The unit is professionally designed and debugged in the factory beforehand. Once the unit arrives on site, it only needs to be simply connected to the water lines and cables to be used. It supports the linkage of multiple boilers and intelligent monitoring.
Significantly shortens on-site construction time, reduces construction error rate, meets customer customization needs, and improves installation efficiency and fault tolerance.
Smart Images

Figure CN224517026U_ABST
Abstract
Claims
1. A direct supply electric boiler skid integrated unit, comprising a control assembly, an electric boiler assembly and a water replenishment assembly, the control assembly is used to provide power for the electric boiler assembly and the water replenishment assembly while coordinating and controlling the operation of the electric boiler assembly and the water replenishment assembly, characterized in that, The control components include a power cabinet (1) and a main control cabinet (2). The power cabinet (1) provides power to the electric boiler assembly and the water supply assembly, and the main control cabinet (2) coordinates and controls the operation between the electric boiler assembly and the water supply assembly.
2. A direct-fired electric boiler skid-integrated unit according to claim 1, characterized in that, The electric boiler assembly includes an electric boiler body (3), a circulating pump (4), a water inlet pipe (5), and a water return pipe (6). The output end of the electric boiler body (3) is connected to the input end of the circulating pump (4). The output end of the circulating pump (4) is provided with a water inlet pipe (5), and the input end of the electric boiler body (3) is provided with a water return pipe (6). A valve is provided at the inlet and outlet of the circulating pump (4).
3. A direct supply electric boiler skid integrated unit according to claim 2, characterized in that, The water replenishment assembly includes a water replenishment pipe (7), a water softener (8), a water replenishment tank (9), and a water replenishment pump (10). The input end of the water replenishment tank (9) is connected to the output end of the water softener (8), the input end of the water replenishment pump (10) is connected to the output end of the water replenishment tank (9), the output end of the water replenishment pump (10) is connected to the input end of the water replenishment pipe (7), and the output end of the water replenishment pipe (7) is connected to the side wall of the return water pipe (6). The inlet and outlet of the water replenishment pump (10) are respectively equipped with valve No.
2.
4. A direct supply electric boiler skid integrated unit according to claim 2, characterized in that, The number of circulating pumps (4) is two.
5. A direct-fired electric boiler skid-integrated unit according to claim 3, wherein, The number of water replenishment pumps (10) is two sets.