A gas mixing control device

By designing a gas mixing control device, precise mixing and control of argon and nitrogen are achieved, solving the problems of stopper head and nozzle blockage and molten steel quality during continuous casting, ensuring stable molten steel flow, reducing bubbles and slag entrapment, and improving steel quality.

CN224950032UActive Publication Date: 2026-11-10VESUVIUS ADVANCED CERAMICS (CHINA) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522577652.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-04
Publication Date
2026-11-10
Estimated Expiration
2035-12-04

AI Technical Summary

Technical Problem

In the continuous casting process, improper control of argon flow can easily lead to blockage of the stopper head and nozzle, or the formation of bubbles and slag in the molten steel, affecting the quality of the steel.

Method used

A gas mixing control device was designed to achieve precise mixing and control of argon and nitrogen through argon and nitrogen gas transmission pipelines, mixing pipelines and controllers, ensuring accurate flow regulation, reducing aluminum oxide accumulation and stabilizing molten steel flow.

Benefits of technology

It effectively reduces the accumulation of aluminum oxide at the stopper head and nozzle, ensuring stable molten steel flow, reducing the occurrence of bubbles and slag entrapment, and improving steel quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224950032U_ABST
    Figure CN224950032U_ABST
Patent Text Reader

Abstract

This invention provides a gas mixing control device, comprising a controller, an argon gas supply pipeline, a nitrogen gas supply pipeline, and a mixing pipeline. A first calibration pipeline section includes a first calibration sub-pipeline and a first transmission sub-pipeline. A first calibration flow meter is installed on the first calibration sub-pipeline, and a first flow meter is installed on the first automatic gas supply sub-pipeline. A first calibration flow meter is installed on the second calibration sub-pipeline, and a second flow meter is installed on the second automatic gas supply sub-pipeline. By connecting the various components to the pipelines, argon and nitrogen are thoroughly mixed. The mixed gas is then input into the stopper rod and nozzle, reducing the accumulation of alumina at the stopper rod head and nozzle, ensuring stable steel flow, and simultaneously reducing the formation of bubbles and slag in the molten steel, thereby enhancing the quality of the steel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of gas mixing technology, and in particular to a gas mixing control device. Background Technology

[0002] With increasingly stringent requirements for billet quality during continuous casting, traditional control devices prevent alumina from adhering to the stopper head and nozzle, thus avoiding blockage. These devices typically inject argon gas into the stopper head or nozzle. However, improper argon flow control can lead to blockages; too low a flow rate can still cause blockages, while too high a flow rate can allow argon bubbles to enter the molten steel, resulting in slag entrapment, bubbles, and other defects, thereby reducing the quality of the steel product. Utility Model Content

[0003] This invention provides a gas mixing control device that reduces the accumulation of aluminum oxide at the stopper head and nozzle. While ensuring stable molten steel flow, it can also reduce the formation of bubbles and slag in the molten steel, thereby enhancing the quality of the steel.

[0004] According to one aspect of the present invention, a gas mixing control device is provided, comprising: The system includes a controller, an argon gas delivery pipeline, a nitrogen gas delivery pipeline, and a mixing pipeline; the argon gas delivery pipeline includes a first inlet pipeline section, a first calibration pipeline section, a first manual / automatic pipeline section, and a first outlet pipeline section; the nitrogen gas delivery pipeline includes a second inlet pipeline section, a second calibration pipeline section, a second manual / automatic pipeline section, and a second outlet pipeline section. The first calibration pipeline section includes a first calibration sub-pipeline and a first transmission sub-pipeline; the first manual / automatic pipeline section includes a first manual gas supply sub-pipeline and a first automatic gas supply sub-pipeline; the first end of the first inlet pipeline section is used to input argon gas, the second end of the first inlet pipeline section is connected to the inlet of a first solenoid valve, the first outlet and the second outlet of the first solenoid valve are respectively connected to the first end of the first calibration sub-pipeline and the first end of the first transmission sub-pipeline; the second end of the first calibration sub-pipeline and the second end of the first transmission sub-pipeline are connected to the first end of the first manual gas supply sub-pipeline and the first end of the first automatic gas supply sub-pipeline, and the second end of the first manual gas supply sub-pipeline and the second end of the first automatic gas supply sub-pipeline are both connected to the first end of the first outlet pipeline section; a second solenoid valve is provided on the first manual gas supply sub-pipeline, and a third solenoid valve is provided on the first automatic gas supply sub-pipeline; The second calibration pipeline section includes a second calibration sub-pipeline and a second transmission sub-pipeline; the second manual / automatic pipeline section includes a second manual gas supply sub-pipeline and a second automatic gas supply sub-pipeline; the first end of the second inlet pipeline section is used to input nitrogen gas, and the second end of the second inlet pipeline section is connected to the inlet of the fourth solenoid valve; the third outlet and the fourth outlet of the fourth solenoid valve are respectively connected to the first end of the second calibration sub-pipeline and the first end of the second transmission sub-pipeline; the second end of the second calibration sub-pipeline and the second end of the second transmission sub-pipeline are connected to the first end of the second manual gas supply sub-pipeline and the first end of the second automatic gas supply sub-pipeline; the second end of the second manual gas supply sub-pipeline and the second end of the second automatic gas supply sub-pipeline are both connected to the first end of the second outlet pipeline section; a fifth solenoid valve is provided on the second manual gas supply sub-pipeline, and a sixth solenoid valve is provided on the second automatic gas supply sub-pipeline; The second end of the first outlet pipe section and the second outlet pipe section are both connected to the first end of the mixing pipe, and the second end of the mixing pipe is used to output a mixture of argon and nitrogen. A first calibration flow meter is installed on the first calibration sub-pipeline, and the first calibration flow meter is used to measure the first flow rate of argon gas in the first calibration sub-pipeline; a first flow meter is installed on the first automatic gas delivery sub-pipeline, and the first flow meter is used to adjust and measure the second flow rate of argon gas in the first automatic gas delivery sub-pipeline; the measurement accuracy of the first calibration flow meter is higher than the measurement accuracy of the first flow meter; a first manual flow meter is installed on the first manual gas delivery sub-pipeline, and the first manual flow meter is used to adjust and measure the third flow rate of argon gas in the first manual gas delivery sub-pipeline; A second calibration flow meter is installed on the second calibration sub-pipeline, and the second calibration flow meter is used to measure the fourth flow rate of nitrogen in the second calibration sub-pipeline; a second flow meter is installed on the second automatic gas delivery sub-pipeline, and the second flow meter is used to adjust and measure the fifth flow rate of nitrogen in the second automatic gas delivery sub-pipeline; the measurement accuracy of the second calibration flow meter is higher than that of the second flow meter; a second manual flow meter is installed on the second manual gas delivery sub-pipeline, and the second manual flow meter is used to adjust and measure the sixth flow rate of nitrogen in the second manual gas delivery sub-pipeline; The controller is connected to the first solenoid valve, the second solenoid valve, the third solenoid valve, the fourth solenoid valve, the fifth solenoid valve, the sixth solenoid valve, the first calibration flow meter, the second calibration flow meter, the first flow meter, the second flow meter, the first manual flow meter, and the second manual flow meter, respectively. The controller is used to control the conduction state of the first solenoid valve, the second solenoid valve, the third solenoid valve, the fourth solenoid valve, the fifth solenoid valve, and the sixth solenoid valve, and is also used to collect the first flow rate, the second flow rate, the third flow rate, the fourth flow rate, the fifth flow rate, and the sixth flow rate, and to control the working state of the first flow meter and the second flow meter.

[0005] Optionally, the gas mixing control device also includes: Verify the selection button; The controller is used to output a first control signal to the first solenoid valve, the second solenoid valve, the fourth solenoid valve and the fifth solenoid valve when it detects that the verification selection button is pressed; The first solenoid valve is used to connect the inlet and the first outlet after receiving the first control signal, and to close the inlet and the second outlet, so that the first intake pipe section is connected to the first verification sub-pipeline and the first intake pipe section is disconnected from the first transmission sub-pipeline. The third solenoid valve is used to connect the second end of the first verification sub-pipeline and the first end of the first automatic gas supply sub-pipeline after receiving the first control signal, so that the first automatic gas supply sub-pipeline and the first verification sub-pipeline are connected. The fourth solenoid valve is used to connect the inlet and the third outlet after receiving the first control signal, and to close the inlet and the fourth outlet, so that the first intake pipe section is connected to the first verification sub-pipeline, and the second intake pipe section is disconnected from the second transmission sub-pipeline. The sixth solenoid valve is used to connect the second end of the second verification sub-pipeline and the first end of the second automatic gas supply sub-pipeline after receiving the first control signal, so that the second automatic gas supply sub-pipeline and the second verification sub-pipeline are connected.

[0006] Optionally, the gas mixing control device also includes: Verification pass indicator and verification fail indicator; The controller is also used to collect the first flow rate, the second flow rate, the fourth flow rate, and the fifth flow rate, and then output a second control signal to the verification pass indicator or a third control signal to the verification fail indicator; the second control signal is used to control the verification pass indicator to light up, and the third control signal is used to control the verification fail indicator to light up.

[0007] Optionally, the gas mixing control device also includes: First flow rate adjustment button and second flow rate adjustment button; The controller is used to obtain the input signal of the first flow adjustment button, and then output a fourth control signal to the first flow meter; and to obtain the input signal of the second flow adjustment button, and then output a fifth control signal to the second flow meter. The first flow meter is used to adjust the argon flow rate of the first automatic gas supply sub-pipeline according to the fourth control signal, and the second flow meter is used to adjust the nitrogen flow rate of the second automatic gas supply sub-pipeline according to the fifth control signal.

[0008] Optionally, the gas mixing control device also includes: Manual / automatic air supply selection knob; The controller is used to detect the position of the manual / automatic air delivery selection knob and output a sixth control signal to the second solenoid valve and the fifth solenoid valve or a seventh control signal to the third solenoid valve and the sixth solenoid valve; The second solenoid valve is opened when the sixth control signal is received, and the third solenoid valve is opened when the seventh control signal is received; The fifth solenoid valve is opened when the sixth control signal is received, and the sixth solenoid valve is opened when the seventh control signal is received.

[0009] Optionally, the gas mixing control device also includes: Local control buttons and remote control buttons; The controller is configured to detect the state of each button when the local control button is pressed, and output control signals according to the state of each button. When the remote control button is pressed, the controller acquires the control command from the remote control terminal and outputs control signals according to the control command from the remote control terminal.

[0010] Optionally, a first pressure regulating valve and a first filter are provided on the first intake pipe section, and the first pressure regulating valve and the first filter are connected to the controller; The controller is used to control the operating status of the first pressure regulating valve and the first filter; The second intake pipe section is equipped with a second pressure regulating valve and a second filter, which are connected to the controller. The controller is used to control the operating status of the second pressure regulating valve and the second filter; A first check valve is installed on the first air outlet pipe section, and the first check valve is connected to the controller.

[0011] A second check valve is installed on the second air outlet pipe section, and the second check valve is connected to the controller.

[0012] A first valve is provided at the first end of the first intake pipe section, a second valve is provided at the first end of the second intake pipe section, and a third valve is provided at the second end of the mixing pipe.

[0013] Optionally, the mixing pipeline section is equipped with a static mixer for mixing argon and nitrogen.

[0014] The mixing pipeline is also equipped with a back pressure sensor, which is used to detect the pressure of the gas in the mixing pipeline.

[0015] Optionally, the gas mixing control device also includes: Display and vortex cooling pipe; The controller is used to control the display to show the gas flow rate, gas pressure, and alarm status of the argon gas delivery pipeline, the nitrogen gas delivery pipeline, and the mixing pipeline.

[0016] The controller is used to control the vortex cooling pipe to reduce the temperature inside the device.

[0017] Optionally, the first solenoid valve, the second solenoid valve, the third solenoid valve, the fourth solenoid valve, the fifth solenoid valve, and the sixth solenoid valve are all in the normally open state.

[0018] The gas mixing control device of this utility model embodiment includes a controller, an argon gas supply pipeline, a nitrogen gas supply pipeline, and a mixing pipeline; a first calibration pipeline section includes a first calibration sub-pipeline and a first transmission sub-pipeline; a first manual / automatic pipeline section includes a first manual gas supply sub-pipeline and a first automatic gas supply sub-pipeline; a second calibration pipeline section includes a second calibration sub-pipeline and a second transmission sub-pipeline; a second manual / automatic pipeline section includes a second manual gas supply sub-pipeline and a second automatic gas supply sub-pipeline; a first calibration flow meter is installed on the first calibration sub-pipeline, and a first flow meter is installed on the first automatic gas supply sub-pipeline; a second calibration flow meter is installed on the second calibration sub-pipeline, and a second flow meter is installed on the second automatic gas supply sub-pipeline; the controller controls the conduction status of a first, second, third, fourth, fifth, and sixth solenoid valve, and is also used to collect the first, second, third, fourth, fifth, and sixth flow rates and control the working status of the first and second flow meters. By connecting each component to the pipeline, argon and nitrogen are fully mixed. Since nitrogen dissolves in molten steel, introducing a mixture of argon and nitrogen into the stopper rod and nozzle reduces alumina buildup at the stopper rod head and nozzle, ensuring stable steel flow. This also reduces the formation of bubbles and slag in the molten steel, thus improving steel quality. By calibrating the first flowmeter using a first calibration flowmeter and the second flowmeter using a second calibration flowmeter, it is ensured that the first flowmeter can accurately regulate the argon flow rate and the second flowmeter can accurately regulate the nitrogen flow rate. A manual gas delivery sub-pipeline is also included; if the automatic delivery sub-pipeline malfunctions, the gas flow rate can be adjusted manually to ensure the argon and nitrogen are mixed in the correct proportions, further reducing bubble and slag formation in the molten steel.

[0019] It should be understood that the description in this section is not intended to identify key or essential features of the embodiments of this utility model, nor is it intended to limit the scope of this utility model. Other features of this utility model will become readily apparent from the following description. Attached Figure Description

[0020] To more clearly illustrate the technical solutions in the embodiments of this utility model, the drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0021] Figure 1 This is a schematic diagram of the structure of a gas mixing control device provided in an embodiment of the present invention; Figure 2This is a schematic diagram of the structure of another gas mixing control device provided in this embodiment of the present invention.

[0022] Figure reference numerals: 10-Controller, 20-Argon gas delivery pipeline, 30-Nitrogen gas delivery pipeline, 40-Mixing pipeline, 21-First inlet pipeline section, 22-First calibration pipeline section, 23-First manual / automatic pipeline section, 24-First outlet pipeline section, 31-Second inlet pipeline section, 32-Second calibration pipeline section, 33-Second manual / automatic pipeline section, 34-Second outlet pipeline section, 221-First calibration sub-pipeline, 222- First transmission sub-pipeline, 231-First manual gas supply sub-pipeline, 232-First automatic gas supply sub-pipeline, 321-Second verification sub-pipeline, 322-Second transmission sub-pipeline, 331-Second manual gas supply sub-pipeline, 332-Second automatic gas supply sub-pipeline, 51-First solenoid valve, 52-Second solenoid valve, 53-Third solenoid valve, 54-Fourth solenoid valve, 55-Fifth solenoid valve, 56-Sixth solenoid valve, 61-First Calibrate flow meter, 71-First flow meter, 81-First manual flow meter, 62-Second calibration flow meter, 72-Second flow meter, 82-Second manual flow meter, 511-First outlet, 512-Second outlet, 541-Third outlet; 542-Fourth outlet, 91-First pressure regulating valve, 101-First filter, 92-Second pressure regulating valve, 102-Second filter, 111-First check valve, 112-Second check valve, 120-Static mixer, 201-First valve, 202-Second valve, 203-Third valve, 300-Calibration selection button, 301-Calibration pass indicator light, 302-Calibration fail indicator light, 401-First flow adjustment button, 402-Second flow adjustment button, 500-Manual / automatic air supply selection knob, 601-Local control button, 602-Remote control button, 700-Display. Detailed Implementation

[0023] To enable those skilled in the art to better understand the present invention, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort should fall within the protection scope of the present invention.

[0024] It should be noted that the terms "first," "second," etc., in the specification, claims, and accompanying drawings of this utility model are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate so that the embodiments of the utility model described herein can be implemented in orders other than those illustrated or described herein. Furthermore, the terms "comprising" and "having," and any variations thereof, are intended to cover non-exclusive inclusion; for example, a process, method, system, product, or apparatus that comprises a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units not explicitly listed or inherent to such processes, methods, products, or apparatus.

[0025] This utility model provides a gas mixing control device. Figure 1 This is a schematic diagram of a gas mixing control device provided in an embodiment of the present invention, with reference to... Figure 1 The gas mixing control device includes: a controller 10, an argon gas supply pipeline 20, a nitrogen gas supply pipeline 30, and a mixing pipeline 40; the argon gas supply pipeline 20 includes a first inlet pipeline section 21, a first calibration pipeline section 22, a first manual / automatic pipeline section 23, and a first outlet pipeline section 24; the nitrogen gas supply pipeline 30 includes a second inlet pipeline section 31, a second calibration pipeline section 32, a second manual / automatic pipeline section 33, and a second outlet pipeline section 34.

[0026] The first calibration pipeline section 22 includes a first calibration sub-pipeline 221 and a first transmission sub-pipeline 222; the first manual / automatic pipeline section 23 includes a first manual gas supply sub-pipeline 231 and a first automatic gas supply sub-pipeline 232; the first end of the first inlet pipeline section 21 is used to input argon gas, the second end of the first inlet pipeline section 21 is connected to the inlet of the first solenoid valve 51, and the first outlet 511 and the second outlet 512 of the first solenoid valve 51 are respectively connected to the first end of the first calibration sub-pipeline 221 and the first transmission sub-pipeline 222. The first end; the second end of the first verification sub-pipeline 221 and the second end of the first transmission sub-pipeline 222 are connected to the first end of the first manual gas supply sub-pipeline 231 and the first end of the first automatic gas supply sub-pipeline 232. The second ends of the first manual gas supply sub-pipeline 231 and the second ends of the first automatic gas supply sub-pipeline 232 are both connected to the first end of the first gas outlet pipe section 24. A second solenoid valve 52 is provided on the first manual gas supply sub-pipeline 231, and a third solenoid valve 53 is provided on the first automatic gas supply sub-pipeline 232. The second calibration pipeline section 32 includes a second calibration sub-pipeline 321 and a second transmission sub-pipeline 322; the second manual / automatic pipeline section 33 includes a second manual gas supply sub-pipeline 331 and a second automatic gas supply sub-pipeline 332; the first end of the second inlet pipeline section 31 is used to input nitrogen gas, and the second end of the second inlet pipeline section 31 is connected to the inlet of the fourth solenoid valve 54; the third outlet 541 and the fourth outlet 542 of the fourth solenoid valve 54 are respectively connected to the first end of the second calibration sub-pipeline 321 and the second transmission sub-pipeline 322. The first end; the second end of the second verification sub-pipeline 321 and the second end of the second transmission sub-pipeline 322 are connected to the first end of the second manual gas supply sub-pipeline 331 and the first end of the second automatic gas supply sub-pipeline 332. The second end of the second manual gas supply sub-pipeline 331 and the second end of the second automatic gas supply sub-pipeline 332 are both connected to the first end of the second gas outlet pipe section 34. A fifth solenoid valve 55 is provided on the second manual gas supply sub-pipeline 331 and a sixth solenoid valve 56 is provided on the second automatic gas supply sub-pipeline 332.

[0027] The second end of the first outlet pipe section 24 and the second outlet pipe section 34 are both connected to the first end of the mixing pipe 40. The second end of the mixing pipe 40 is used to output a mixture of argon and nitrogen.

[0028] A first calibration flow meter 61 is installed on the first calibration sub-pipeline 221. The first calibration flow meter 61 is used to measure the first flow rate of argon gas in the first calibration sub-pipeline 221. A first flow meter 71 is installed on the first automatic gas supply sub-pipeline 232. The first flow meter 71 is used to adjust and measure the second flow rate of argon gas in the first automatic gas supply sub-pipeline 232. The measurement accuracy of the first calibration flow meter 61 is higher than that of the first flow meter 71. A first manual gas supply sub-pipeline 231 is installed on the first manual gas supply sub-pipeline 231. The first manual flow meter 81 is used to adjust and measure the third flow rate of argon gas in the first manual gas supply sub-pipeline 231.

[0029] A second calibration flow meter 62 is installed on the second calibration sub-pipeline 321. The second calibration flow meter 62 is used to measure the fourth flow rate of nitrogen in the second calibration sub-pipeline 321. A second flow meter 72 is installed on the second automatic gas supply sub-pipeline 332. The second flow meter 72 is used to adjust and measure the fifth flow rate of nitrogen in the second automatic gas supply sub-pipeline 332. The measurement accuracy of the second calibration flow meter 62 is higher than that of the second flow meter 72. A second manual gas supply sub-pipeline 331 is installed on the second manual gas supply sub-pipeline 331. The second manual flow meter 82 is used to adjust and measure the sixth flow rate of nitrogen in the second manual gas supply sub-pipeline 331.

[0030] The controller 10 is connected to the first solenoid valve 51, the second solenoid valve 52, the third solenoid valve 53, the fourth solenoid valve 54, the fifth solenoid valve 55, the sixth solenoid valve 56, the first calibration flow meter 61, the second calibration flow meter 62, the first flow meter 71, the second flow meter 72, the first manual flow meter 81, and the second manual flow meter 82, respectively. The controller 10 is used to control the conduction status of the first solenoid valve 51, the second solenoid valve 52, the third solenoid valve 53, the fourth solenoid valve 54, the fifth solenoid valve 55, and the sixth solenoid valve 56, and is also used to collect the first flow rate, the second flow rate, the third flow rate, the fourth flow rate, the fifth flow rate, and the sixth flow rate, and to control the working status of the first flow meter 71 and the second flow meter 72.

[0031] Specifically, controller 10 controls various components in the device. Controller 10 can be a PLC. The opening and closing of the first solenoid valve 51, second solenoid valve 52, third solenoid valve 53, fourth solenoid valve 54, fifth solenoid valve 55, and sixth solenoid valve 56 can be controlled by relays. Controlling the opening and closing of different solenoid valves can connect different pipelines and control the flow direction of argon and nitrogen. The gas mixing control device also includes a power supply and a circuit breaker. The power supply provides power to the device and is a 24V DC power supply. The circuit breaker protects components such as controller 10, first flow meter 71, and second flow meter 72.

[0032] The first calibration flowmeter 61 is used to calibrate the measurement accuracy of the first flowmeter 71, ensuring that the first flowmeter 71 accurately regulates the argon flow rate. The first flowmeter 71 can be a Bronkhorst high-precision flowmeter or a BROOKS high-precision flowmeter. The measurement accuracy of the first calibration flowmeter 61 is greater than that of the first flowmeter 71. The second calibration flowmeter 62 is used to calibrate the measurement accuracy of the second flowmeter 72, ensuring that the second flowmeter 72 accurately regulates the nitrogen flow rate. The second flowmeter 72 can be a Siemens CPU 1511 or a BROOKS high-precision flowmeter. The measurement accuracy of the second calibration flowmeter 62 is greater than that of the second flowmeter 72.

[0033] When the first calibration flowmeter 61 calibrates the measurement accuracy of the first flowmeter 71, the inlet and outlet 511 of the first solenoid valve 51 are connected, the third solenoid valve 53 is in the open state, and the second solenoid valve 52 is in the closed state. At this time, the first air inlet pipe section 21 is connected to the first calibration pipe section 22, and the first calibration pipe section 22 is connected to the first automatic gas supply sub-pipeline 232. Argon gas is input into the first air inlet pipe section 21, and the flow measurement value of the first calibration flowmeter 61 is compared with the flow measurement value of the first flowmeter 71 to verify the measurement accuracy of the first flowmeter 71.

[0034] When the second calibration flow meter 62 verifies the measurement accuracy of the second flow meter 72, the inlet of the fourth solenoid valve 54 and the third outlet 541 are connected, the sixth solenoid valve 56 is in the open state, and the fifth solenoid valve 55 is in the closed state. At this time, the second air inlet pipe section 31 is connected to the second calibration pipe section 32, and the second calibration pipe section 32 is connected to the second automatic gas supply sub-pipeline 332. Nitrogen gas is input into the second air inlet pipe section 31, and the flow measurement value of the second calibration flow meter 62 is compared with the flow measurement value of the second flow meter 72 to verify the measurement accuracy of the second flow meter 72.

[0035] When the flow rates of argon and nitrogen are manually adjusted, the inlet and second outlet 512 of the first solenoid valve 51 are open, the inlet and fourth outlet 542 of the fourth solenoid valve 54 are open, and the second solenoid valve 52 and the fifth solenoid valve 55 are both open. At this time, the first inlet pipe section 21 and the first transmission sub-pipeline 222 are open, and the first transmission sub-pipeline 222 and the first manual gas supply sub-pipeline 231 are open; the second inlet pipe section 31 and the second transmission sub-pipeline 322 are open, and the second transmission sub-pipeline 322 and the second manual gas supply sub-pipeline 331 are open. The flow rate of argon is manually adjusted by the first manual flow meter 81, and the flow rate of nitrogen is manually adjusted by the second manual flow meter 82. Argon flows into the mixing pipe 40 through the first outlet pipe section 24, and nitrogen flows into the mixing pipe 40 through the second outlet pipe section 34. After the argon and nitrogen are mixed, they are output through the mixing pipe 40.

[0036] When the flow rates of argon and nitrogen are automatically adjusted, the inlet and second outlet 512 of the first solenoid valve 51 are open, the inlet and fourth outlet 542 of the fourth solenoid valve 54 are open, and the third solenoid valve 53 and the sixth solenoid valve 56 are both open. At this time, the first inlet pipe section 21 and the first transmission sub-pipeline 222 are open, as are the first automatic gas supply sub-pipeline 232; the second inlet pipe section 31 and the second transmission sub-pipeline 322 are open, as are the second transmission sub-pipeline 322 and the second automatic gas supply sub-pipeline 332. The flow rate of argon is automatically adjusted by the first flow meter 71, and the flow rate of nitrogen is automatically adjusted by the second flow meter 72. Argon flows into the mixing pipe 40 through the first outlet pipe section 24, and nitrogen flows into the mixing pipe 40 through the second outlet pipe section 34. After mixing, the argon and nitrogen are output through the mixing pipe 40. When the device is working normally, the flow rates of argon and nitrogen will be automatically adjusted.

[0037] The second end of the first vent pipe section 24 and the second end of the second vent pipe section 34 are both connected to the first end of the mixing pipe 40. The second end of the mixing pipe 40 is used to output a mixture of argon and nitrogen to the stopper rod and the nozzle, reducing the accumulation of aluminum oxide on the stopper rod head and the nozzle, ensuring stable steel flow, reducing liquid level fluctuations, and lowering the risk of blockage and bubble generation.

[0038] The gas mixing control device of this utility model embodiment includes a controller 10, an argon gas supply pipeline 20, a nitrogen gas supply pipeline 30, and a mixing pipeline 40; the first calibration pipeline section 22 includes a first calibration sub-pipeline 221 and a first transmission sub-pipeline 222; the first manual / automatic pipeline section 23 includes a first manual gas supply sub-pipeline 231 and a first automatic gas supply sub-pipeline 232; the second calibration pipeline section 32 includes a second calibration sub-pipeline 321 and a second transmission sub-pipeline 322; the second manual / automatic pipeline section 33 includes a second manual gas supply sub-pipeline 331 and a second automatic gas supply sub-pipeline 332; the first calibration sub-pipeline 221 is provided with... A first calibration flow meter 61 is installed on the first automatic gas supply sub-pipeline 232; a second calibration flow meter 62 is installed on the second calibration sub-pipeline 321; a second automatic gas supply sub-pipeline 232 is also equipped with a second flow meter 72. The controller 10 controls the conduction status of the first solenoid valve 51, the second solenoid valve 52, the third solenoid valve 53, the fourth solenoid valve 54, the fifth solenoid valve 55, and the sixth solenoid valve 56. It is also used to collect the first, second, third, fourth, fifth, and sixth flow rates and to control the operating status of the first flow meter 71 and the second flow meter 72. By connecting the various components to the pipelines, argon and nitrogen are thoroughly mixed, and the resulting argon-nitrogen mixture is input into the stopper rod and the nozzle. Since nitrogen dissolves in molten steel, introducing a mixture of argon and nitrogen into the stopper rod and nozzle reduces the accumulation of alumina at the stopper rod head and nozzle. This ensures stable steel flow while minimizing the formation of bubbles and slag in the molten steel, thus enhancing steel quality. By calibrating the measurement accuracy of the first flowmeter 71 using a first calibration flowmeter 61 and the measurement accuracy of the second flowmeter 72 using a second calibration flowmeter 62, it can be ensured that the first flowmeter 71 can accurately regulate the argon flow rate and the second flowmeter 72 can accurately regulate the nitrogen flow rate. A manual gas delivery sub-pipeline is also included. If the automatic delivery sub-pipeline malfunctions, the gas flow rate can be adjusted manually to ensure that argon and nitrogen are mixed in the correct proportions, further reducing the formation of bubbles and slag in the molten steel.

[0039] Figure 2 This is a schematic diagram of another gas mixing control device provided in this embodiment of the present invention, for reference. Figure 1 and Figure 2 Optionally, the gas mixing control device also includes: Verification selection button 300.

[0040] When the controller 10 detects that the verification selection button 300 is pressed, it outputs a first control signal to the first solenoid valve 51, the third solenoid valve 53, the fourth solenoid valve 54 and the sixth solenoid valve 56.

[0041] The first solenoid valve 51 is used to connect the inlet and the first outlet 511 after receiving the first control signal, and to close the inlet and the second outlet 512, so that the first intake pipe section 21 is connected to the first verification sub-pipeline 221 and disconnected from the first transmission sub-pipeline 222.

[0042] The third solenoid valve 53 is used to connect the second end of the first verification sub-pipeline 221 and the first end of the first automatic gas supply sub-pipeline 232 after receiving the first control signal, so that the first automatic gas supply sub-pipeline 232 and the first verification sub-pipeline 221 are connected.

[0043] The fourth solenoid valve 54 is used to connect the inlet and the third outlet 541 and close the inlet and the fourth outlet 542 after receiving the first control signal, so that the second intake pipe section 31 is connected to the second verification sub-pipeline 321 and disconnected from the second transmission sub-pipeline 322.

[0044] The sixth solenoid valve 56 is used to connect the second end of the second verification sub-pipeline 321 and the first end of the second automatic gas supply sub-pipeline 332 after receiving the first control signal, so that the second automatic gas supply sub-pipeline 332 and the second verification sub-pipeline 321 are connected.

[0045] Specifically, the first control signal is a signal that controls the opening of the first solenoid valve 51 and the fourth solenoid valve 54. For example, when both the first solenoid valve 51 and the fourth solenoid valve 54 are normally open solenoid valves, the first control signal is a signal that controls the first solenoid valve 51 and the fourth solenoid valve 54 to not be energized. After receiving the first control signal, the first solenoid valve 51 opens, connecting the first air inlet pipe section 21 with the first calibration sub-pipeline 221. After receiving the first control signal, the third solenoid valve 53 opens, connecting the first automatic gas supply sub-pipeline 232 with the first calibration sub-pipeline 221, and inputting argon gas into the first air inlet pipe section 21. The argon gas passes through the first calibration flow meter 61 and the first flow meter 71, and the measurement accuracy of the first flow meter 71 is verified by the first calibration flow meter 61.

[0046] After receiving the first control signal, the fourth solenoid valve 54 opens, connecting the second air intake pipe section 31 with the second calibration sub-pipeline 321. After receiving the first control signal, the sixth solenoid valve 56 opens, connecting the first automatic gas supply sub-pipeline 232 with the first calibration sub-pipeline 221, and inputting nitrogen into the second air intake pipe section 31. The nitrogen passes through the second calibration flow meter 62 and the second flow meter 72, and the measurement accuracy of the second flow meter 72 is verified by the second calibration flow meter 62.

[0047] At this time, the second solenoid valve 52 and the fifth solenoid valve 55 are in the closed state. The first solenoid valve 51, the second solenoid valve 52, the third solenoid valve 53, the fourth solenoid valve 54, the fifth solenoid valve 55 and the sixth solenoid valve 56 are all closed when energized and opened when de-energized.

[0048] For example, the flow rate of the first flow meter 71 can be adjusted, and the flow rate value of the first calibration flow meter 61 can be compared with the low, middle, and high points of the range of the first flow meter 71 to verify the measurement accuracy of the first flow meter 71. Verification is performed once at each of the low, middle, and high points of the range of the first flow meter 71. If the error between the flow rate value of the first calibration flow meter 61 and the flow rate measurement value of the first flow meter 71 in all three verifications is greater than or equal to -1% and less than or equal to 1%, it indicates that the measurement accuracy of the first flow meter 71 is qualified. The low point is 20% of the range of the first flow meter 71, the middle point is 50% of the range of the first flow meter 71, and the high point is 80% of the range of the first flow meter 71.

[0049] The flow rate of the second flow meter 72 can be adjusted, and the flow rate value of the second calibration flow meter 62 can be compared with the low, middle, and high points of the second flow meter 72's range to verify the measurement accuracy of the first flow meter 72. Verification is performed once at each of the low, middle, and high points of the second flow meter 72's range. If the error between the flow rate value of the second calibration flow meter 62 and the flow rate measurement value of the second flow meter 72 in all three verifications is greater than or equal to -1% and less than or equal to 1%, it indicates that the measurement accuracy of the second flow meter 72 is qualified. The low point is 20% of the second flow meter 72's range, the middle point is 50% of the second flow meter 72's range, and the high point is 80% of the second flow meter 72's range.

[0050] Optionally, the gas mixing control device also includes: The verification pass indicator 301 and the verification fail indicator 302.

[0051] The controller 10 is also used to collect the first flow rate, the second flow rate, the fourth flow rate, and the fifth flow rate, and then output a second control signal to the verification pass indicator 301 or a third control signal to the verification fail indicator 302; the second control signal is used to control the verification pass indicator 301 to light up, and the third control signal is used to control the verification fail indicator 302 to light up.

[0052] Specifically, the calibration pass indicator 301 and calibration fail indicator 302 visually indicate whether the measurement accuracy of the first flow meter 71 and the second flow meter 72 in the device is qualified. When the calibration pass indicator 301 is lit, it indicates that the measurement accuracy of the first flow meter 71 and the second flow meter 72 is qualified. When the calibration fail indicator 302 is lit, it indicates that the measurement accuracy of the first flow meter 71 and the second flow meter 72 is unqualified. This allows the operator to know the status of the first flow meter 71 and the second flow meter 72 in a timely manner, thereby improving the accuracy of the device.

[0053] Optionally, the gas mixing control device also includes: First flow rate adjustment button 401 and second flow rate adjustment button 402.

[0054] After receiving the input signal from the first flow adjustment button 401, the controller 10 outputs a fourth control signal to the first flow meter 71, and after receiving the input signal from the second flow adjustment button 402, outputs a fifth control signal to the second flow meter 72.

[0055] The first flow meter 71 is used to adjust the argon flow rate of the first automatic gas supply sub-pipeline 232 according to the fourth control signal, and the second flow meter 72 is used to adjust the nitrogen flow rate of the second automatic gas supply sub-pipeline 332 according to the fifth control signal.

[0056] Specifically, the fourth control signal includes signals to increase and decrease the argon flow rate, and the fifth control signal includes signals to increase and decrease the nitrogen flow rate. The first flow meter 71 increases or decreases the argon flow rate of the first automatic gas delivery sub-pipeline 232 according to the fourth control signal, and the second flow meter 72 increases or decreases the nitrogen flow rate of the second automatic gas delivery sub-pipeline 332 according to the fifth control signal, ensuring precise control of the argon and nitrogen flow rates so that the ratio of the nitrogen flow rate to the argon flow rate is always less than or equal to 50%. The device also includes a first flow rate setting button and a second flow rate setting button. The argon flow rate can only be adjusted when both the first flow rate adjustment button 401 and the first flow rate setting button are pressed simultaneously, and the nitrogen flow rate can only be adjusted when both the second flow rate adjustment button 402 and the second flow rate setting button are pressed simultaneously. After receiving the control signal, the controller 10 first adjusts the argon flow rate and then adjusts the nitrogen flow rate. The ratio of nitrogen flow rate to argon flow rate is always less than or equal to 50% to reduce alumina accumulation at the stopper head and nozzle, ensure stable molten steel flow, minimize surface fluctuations, and prevent slag entrapment. For example, the argon flow rate is set to 15 NL / min using the first flow rate adjustment button, and after 10 seconds, the nitrogen flow rate is set to less than or equal to 7.5 NL / min using the second flow rate adjustment button.

[0057] Optionally, the gas mixing control device also includes: Manual / automatic air supply selection knob 500.

[0058] The controller 10 is used to detect the position of the manual / automatic air supply selection knob 500 and output a sixth control signal to the second solenoid valve 52 and the fifth solenoid valve 55 or a seventh control signal to the third solenoid valve 53 and the sixth solenoid valve 56.

[0059] The second solenoid valve 52 is opened when the sixth control signal is received, and the third solenoid valve 53 is opened when the seventh control signal is received.

[0060] The fifth solenoid valve 55 is opened when a sixth control signal is received, and the sixth solenoid valve 56 is opened when a seventh control signal is received.

[0061] Specifically, the sixth control signal is a signal to open the second solenoid valve 52 and the fifth solenoid valve 55. For example, when the second solenoid valve 52 and the fifth solenoid valve 55 are normally open solenoid valves, the sixth control signal is a signal to de-energize the second solenoid valve 52 and the fifth solenoid valve 55. The seventh control signal is a signal to open the third solenoid valve 53 and the sixth solenoid valve 56. For example, when the third solenoid valve 53 and the sixth solenoid valve 56 are normally open solenoid valves, the seventh control signal is a signal to de-energize the third solenoid valve 53 and the sixth solenoid valve 56.

[0062] The manual / automatic gas supply selection knob 500 has two positions: manual and automatic. When the manual / automatic gas supply selection knob 500 is in the manual position, the second solenoid valve 52 and the fifth solenoid valve 55 open upon receiving the sixth control signal. The inlet and second outlet 512 of the first solenoid valve 51 are connected, the inlet and fourth outlet 542 of the fourth solenoid valve 54 are connected, the first air intake pipe section 21 and the first transmission sub-pipeline 222 are connected, and the first transmission sub-pipeline 222 and the first manual gas supply sub-pipeline 231 are connected. The second air intake pipe section 31 and the second transmission sub-pipeline 322 are connected, and the second transmission sub-pipeline 322 and the second manual gas supply sub-pipeline 331 are connected. At this time, the flow rate of argon needs to be adjusted by the first manual flow meter 81, and the flow rate of nitrogen needs to be adjusted by the second manual flow meter 82. Argon flows into the mixing pipeline 40 through the first outlet pipeline section 24, and nitrogen flows into the mixing pipeline 40 through the second outlet pipeline section 34. After the argon and nitrogen are mixed, they are output through the mixing pipeline 40.

[0063] When the manual / automatic gas supply selection knob 500 is in the automatic gas supply position, the third solenoid valve 53 and the sixth solenoid valve 56 open upon receiving the seventh control signal. The inlet and second outlet 512 of the first solenoid valve 51 are connected, the inlet and fourth outlet 542 of the fourth solenoid valve 54 are connected, the first inlet pipe section 21 and the first transmission sub-pipeline 222 are connected, and the first transmission sub-pipeline 222 and the first automatic gas supply sub-pipeline 232 are connected; the second inlet pipe section 31 and the second transmission sub-pipeline 322 are connected, and the second transmission sub-pipeline 322 and the second automatic gas supply sub-pipeline 332 are connected. At this time, the flow rate of argon is automatically adjusted by the first flow meter 71, and the flow rate of nitrogen is automatically adjusted by the second flow meter 72. Argon flows into the mixing pipe 40 through the first outlet pipe section 24, and nitrogen flows into the mixing pipe 40 through the second outlet pipe section 34. After the argon and nitrogen are mixed, they are output through the mixing pipe 40. The device includes both manual and automatic gas supply modes, which ensures that in the event of a malfunction or power outage, the flow rates of nitrogen and argon can be manually adjusted, thereby improving the reliability of the device.

[0064] It should be noted that manual / automatic gas delivery selection knobs (500) can be set for both the argon and nitrogen gas delivery lines. The argon gas delivery line can be selected to use either the first manual delivery sub-line or the first automatic delivery sub-line, as needed. Similarly, the nitrogen gas delivery line can be selected to use either the second manual delivery sub-line or the second automatic delivery sub-line, as needed.

[0065] Optionally, the gas mixing control device also includes: a local control button 601 and a remote control button 602.

[0066] The controller 10 is used to detect the state of each button when the local control button 601 is pressed, and output control signals according to the state of each button. When the remote control button 602 is pressed, the controller 10 obtains the control command from the remote control terminal and outputs control signals according to the control command from the remote control terminal.

[0067] Specifically, when the local control button 601 is pressed, the controller 10 detects the status of each button, such as the verification selection button 300, the first flow rate adjustment button 401, the second flow rate adjustment button 402, and the manual / automatic air supply selection knob 500, and outputs control signals according to the status of each button to control each component to work.

[0068] When the remote control button 602 is pressed, the controller 10 first obtains the control command from the remote control terminal, and outputs control signals according to the control command to control the operation of each component. The device includes a local control button 601 and a remote control button 602, which can be compatible with the usage requirements of different scales and scenarios, further improving the reliability and flexibility of the device.

[0069] Optionally, a first pressure regulating valve 91 and a first filter 101 are provided on the first air intake pipe section 21, and the first pressure regulating valve 91 and the first filter 101 are connected to the controller 10.

[0070] The controller 10 is used to control the working status of the first pressure regulating valve 91 and the first filter 101.

[0071] The second intake pipe section 31 is equipped with a second pressure regulating valve 92 and a second filter 102, which are connected to the controller 10.

[0072] The controller 10 is used to control the working status of the second pressure regulating valve 92 and the second filter 102.

[0073] A first check valve 111 is installed on the first air outlet pipe section 24, and the first check valve 111 is connected to the controller 10.

[0074] A second check valve 112 is installed on the second air outlet pipe section 34, and the second check valve 112 is connected to the controller 10.

[0075] The first end of the first intake pipe section 21 is provided with a first valve 201, the first end of the second intake pipe section 31 is provided with a second valve 202, and the second end of the mixing pipe 40 is provided with a third valve 203.

[0076] Specifically, the first pressure regulating valve 91 and the first filter 101 are used to regulate the pressure of argon in the first intake pipe section 21 and filter argon. The second pressure regulating valve 92 and the second filter 102 are used to regulate the pressure of nitrogen in the second intake pipe section 31 and filter nitrogen. The pressure of both the filtered argon and the filtered nitrogen is adjusted to 3 bar.

[0077] The first check valve 111 is used to prevent argon backflow, and the second check valve 112 is used to prevent nitrogen backflow. This prevents damage to the first flow meter 71 and the second flow meter 72 due to argon and nitrogen backflow, and extends the service life of the device.

[0078] The first valve 201 controls the input of argon gas to the first end of the first intake pipe section 21, the second valve 202 controls the input of nitrogen gas to the first end of the second intake pipe section 31, and the third valve 203 controls the output of a mixture of argon and nitrogen gas to the second end of the mixing pipe 40.

[0079] Optionally, the mixing pipeline section is equipped with a static mixer 120, which is used to mix argon and nitrogen.

[0080] A back pressure sensor 130 is also provided on the mixing pipeline 40, which is used to detect the pressure of the gas in the mixing pipeline 60.

[0081] Specifically, the static mixer ensures that argon and nitrogen are fully mixed before being injected into the stopper rod, reducing the accumulation of alumina at the stopper rod head and nozzle, ensuring stable molten steel flow, and reducing fluctuations in the molten steel level. The back pressure sensor 130 is used to detect the gas pressure in the mixing pipeline 60, ensuring that the mixing pipeline 40 is leak-free.

[0082] Optionally, the gas mixing control device also includes: Display 700 and vortex cooling pipe; The controller 10 is used to control the display to show the gas flow rate, gas pressure and alarm status of the argon gas pipeline 20, the nitrogen gas pipeline 30 and the mixing pipeline 40.

[0083] The controller 10 is used to control the vortex cooling tube to reduce the temperature inside the device.

[0084] Specifically, the gas flow and pressure values ​​include the flow and pressure values ​​of argon in argon delivery line 20, nitrogen in nitrogen delivery line 30, and the flow and pressure values ​​of the argon and nitrogen mixture in mixing line 40. The controller 10 automatically alarms when an abnormal situation occurs in the device and displays the alarm status on a TP700 HMI display. Abnormal situations include a nitrogen flow rate to argon flow rate ratio greater than 50% and gas pressure values ​​in argon delivery line 20, nitrogen delivery line 30, and mixing line 40 being less than -0.5 bar or greater than 3 bar. Alarm statuses include flow alarms and pressure alarms, improving the safety of the device.

[0085] Eddy current cooling tubes are used to reduce the temperature inside the device, ensuring that the internal components are within the normal operating temperature range, and further improving the safety of the device.

[0086] Optionally, the first solenoid valve 51, the second solenoid valve 52, the third solenoid valve 53, the fourth solenoid valve 54, the fifth solenoid valve 55, and the sixth solenoid valve 56 are all in the normally open state.

[0087] Specifically, the first solenoid valve 51, the second solenoid valve 52, the third solenoid valve 53, the fourth solenoid valve 54, the fifth solenoid valve 55, and the sixth solenoid valve 56 are all in the normally open state, that is, the first solenoid valve 51, the second solenoid valve 52, the third solenoid valve 53, the fourth solenoid valve 54, the fifth solenoid valve 55, and the sixth solenoid valve 56 are all in the normally de-energized state. This allows the device to adjust the flow rate of argon and nitrogen gas using the first manual flow meter 81 and the second manual flow meter 82 when the first flow meter 71 or the second flow meter 72 malfunctions or when the device is powered off, ensuring that the device can operate normally in the event of a malfunction.

[0088] It should be understood that the various forms of the process shown above can be used, with steps reordered, added, or deleted. For example, the steps described in this utility model can be executed in parallel, sequentially, or in different orders, as long as the desired result of the technical solution of this utility model can be achieved, and this is not limited herein.

[0089] The specific embodiments described above do not constitute a limitation on the scope of protection of this utility model. Those skilled in the art should understand that various modifications, combinations, sub-combinations, and substitutions can be made according to design requirements and other factors. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of this utility model should be included within the scope of protection of this utility model.

Claims

1. A gas mixing control device, characterized in that, include: The system includes a controller, an argon gas delivery pipeline, a nitrogen gas delivery pipeline, and a mixing pipeline; the argon gas delivery pipeline includes a first inlet pipeline section, a first calibration pipeline section, a first manual / automatic pipeline section, and a first outlet pipeline section; the nitrogen gas delivery pipeline includes a second inlet pipeline section, a second calibration pipeline section, a second manual / automatic pipeline section, and a second outlet pipeline section. The first calibration pipeline section includes a first calibration sub-pipeline and a first transmission sub-pipeline; the first manual / automatic pipeline section includes a first manual gas supply sub-pipeline and a first automatic gas supply sub-pipeline; the first end of the first inlet pipeline section is used to input argon gas, the second end of the first inlet pipeline section is connected to the inlet of a first solenoid valve, the first outlet and the second outlet of the first solenoid valve are respectively connected to the first end of the first calibration sub-pipeline and the first end of the first transmission sub-pipeline; the second end of the first calibration sub-pipeline and the second end of the first transmission sub-pipeline are connected to the first end of the first manual gas supply sub-pipeline and the first end of the first automatic gas supply sub-pipeline, and the second end of the first manual gas supply sub-pipeline and the second end of the first automatic gas supply sub-pipeline are both connected to the first end of the first outlet pipeline section; a second solenoid valve is provided on the first manual gas supply sub-pipeline, and a third solenoid valve is provided on the first automatic gas supply sub-pipeline; The second calibration pipeline section includes a second calibration sub-pipeline and a second transmission sub-pipeline; the second manual / automatic pipeline section includes a second manual gas supply sub-pipeline and a second automatic gas supply sub-pipeline; the first end of the second inlet pipeline section is used to input nitrogen gas, and the second end of the second inlet pipeline section is connected to the inlet of the fourth solenoid valve; the third outlet and the fourth outlet of the fourth solenoid valve are respectively connected to the first end of the second calibration sub-pipeline and the first end of the second transmission sub-pipeline; the second end of the second calibration sub-pipeline and the second end of the second transmission sub-pipeline are connected to the first end of the second manual gas supply sub-pipeline and the first end of the second automatic gas supply sub-pipeline; the second end of the second manual gas supply sub-pipeline and the second end of the second automatic gas supply sub-pipeline are both connected to the first end of the second outlet pipeline section; a fifth solenoid valve is provided on the second manual gas supply sub-pipeline, and a sixth solenoid valve is provided on the second automatic gas supply sub-pipeline; The second end of the first outlet pipe section and the second outlet pipe section are both connected to the first end of the mixing pipe, and the second end of the mixing pipe is used to output a mixture of argon and nitrogen. A first calibration flow meter is installed on the first calibration sub-pipeline, and the first calibration flow meter is used to measure the first flow rate of argon gas in the first calibration sub-pipeline; a first flow meter is installed on the first automatic gas delivery sub-pipeline, and the first flow meter is used to adjust and measure the second flow rate of argon gas in the first automatic gas delivery sub-pipeline; the measurement accuracy of the first calibration flow meter is higher than the measurement accuracy of the first flow meter; a first manual flow meter is installed on the first manual gas delivery sub-pipeline, and the first manual flow meter is used to adjust and measure the third flow rate of argon gas in the first manual gas delivery sub-pipeline; A second calibration flow meter is installed on the second calibration sub-pipeline, and the second calibration flow meter is used to measure the fourth flow rate of nitrogen in the second calibration sub-pipeline; a second flow meter is installed on the second automatic gas delivery sub-pipeline, and the second flow meter is used to adjust and measure the fifth flow rate of nitrogen in the second automatic gas delivery sub-pipeline; the measurement accuracy of the second calibration flow meter is higher than that of the second flow meter; a second manual flow meter is installed on the second manual gas delivery sub-pipeline, and the second manual flow meter is used to adjust and measure the sixth flow rate of nitrogen in the second manual gas delivery sub-pipeline; The controller is connected to the first solenoid valve, the second solenoid valve, the third solenoid valve, the fourth solenoid valve, the fifth solenoid valve, the sixth solenoid valve, the first calibration flow meter, the second calibration flow meter, the first flow meter, the second flow meter, the first manual flow meter, and the second manual flow meter, respectively. The controller is used to control the conduction state of the first solenoid valve, the second solenoid valve, the third solenoid valve, the fourth solenoid valve, the fifth solenoid valve, and the sixth solenoid valve, and is also used to collect the first flow rate, the second flow rate, the third flow rate, the fourth flow rate, the fifth flow rate, and the sixth flow rate, and to control the working state of the first flow meter and the second flow meter.

2. The gas mixing control device according to claim 1, characterized in that, Also includes: Verify the selection button; When the controller detects that the verification selection button is pressed, it outputs a first control signal to the first solenoid valve, the third solenoid valve, the fourth solenoid valve, and the sixth solenoid valve. The first solenoid valve is used to connect the inlet and the first outlet after receiving the first control signal, and to close the inlet and the second outlet, so that the first intake pipe section is connected to the first verification sub-pipeline and the first intake pipe section is disconnected from the first transmission sub-pipeline. The third solenoid valve is used to connect the second end of the first verification sub-pipeline and the first end of the first automatic gas supply sub-pipeline after receiving the first control signal, so that the first automatic gas supply sub-pipeline and the first verification sub-pipeline are connected. The fourth solenoid valve is used to connect the inlet and the third outlet after receiving the first control signal, and to close the inlet and the fourth outlet, so that the second intake pipe section is connected to the second verification sub-pipeline, and the second intake pipe section is disconnected from the second transmission sub-pipeline. The sixth solenoid valve is used to connect the second end of the second verification sub-pipeline and the first end of the second automatic gas supply sub-pipeline after receiving the first control signal, so that the second automatic gas supply sub-pipeline and the second verification sub-pipeline are connected.

3. The gas mixing control device according to claim 2, characterized in that, Also includes: Verification pass indicator and verification fail indicator; The controller is also used to collect the first flow rate, the second flow rate, the fourth flow rate, and the fifth flow rate, and then output a second control signal to the verification pass indicator or a third control signal to the verification fail indicator; the second control signal is used to control the verification pass indicator to light up, and the third control signal is used to control the verification fail indicator to light up.

4. The gas mixing control device according to claim 1, characterized in that, Also includes: First flow rate adjustment button and second flow rate adjustment button; The controller is used to obtain the input signal of the first flow adjustment button, and then output a fourth control signal to the first flow meter; and to obtain the input signal of the second flow adjustment button, and then output a fifth control signal to the second flow meter. The first flow meter is used to adjust the argon flow rate of the first automatic gas supply sub-pipeline according to the fourth control signal, and the second flow meter is used to adjust the nitrogen flow rate of the second automatic gas supply sub-pipeline according to the fifth control signal.

5. The gas mixing control device according to claim 1, characterized in that, Also includes: Manual / automatic air supply selection knob; The controller is used to detect the position of the manual / automatic air delivery selection knob and output a sixth control signal to the second solenoid valve and the fifth solenoid valve or a seventh control signal to the third solenoid valve and the sixth solenoid valve; The second solenoid valve is opened when the sixth control signal is received, and the third solenoid valve is opened when the seventh control signal is received; The fifth solenoid valve is opened when the sixth control signal is received, and the sixth solenoid valve is opened when the seventh control signal is received.

6. The gas mixing control device according to any one of claims 2-5, characterized in that, Also includes: Local control buttons and remote control buttons; The controller is configured to detect the state of each button when the local control button is pressed, and output control signals according to the state of each button. When the remote control button is pressed, the controller acquires the control command from the remote control terminal and outputs control signals according to the control command from the remote control terminal.

7. The gas mixing control device according to claim 1, characterized in that: The first intake pipe section is equipped with a first pressure regulating valve and a first filter, and the first pressure regulating valve and the first filter are connected to the controller; The controller is used to control the operating status of the first pressure regulating valve and the first filter; The second intake pipe section is equipped with a second pressure regulating valve and a second filter, which are connected to the controller. The controller is used to control the operating status of the second pressure regulating valve and the second filter; A first check valve is installed on the first outlet pipe section, and the first check valve is connected to the controller; A second check valve is installed on the second outlet pipe section, and the second check valve is connected to the controller; A first valve is provided at the first end of the first intake pipe section, a second valve is provided at the first end of the second intake pipe section, and a third valve is provided at the second end of the mixing pipe.

8. The gas mixing control device according to claim 1, characterized in that: The mixing pipeline section is equipped with a static mixer, which is used to mix argon and nitrogen. The mixing pipeline is also equipped with a back pressure sensor, which is used to detect the pressure of the gas in the mixing pipeline.

9. The gas mixing control device according to claim 1, characterized in that, Also includes: Display and vortex cooling pipe; The controller is used to control the display to show the gas flow rate, gas pressure, and alarm status of the argon gas delivery pipeline, the nitrogen gas delivery pipeline, and the mixing pipeline; The controller is used to control the vortex cooling pipe to reduce the temperature inside the device.

10. The gas mixing control device according to claim 1, characterized in that: The first solenoid valve, the second solenoid valve, the third solenoid valve, the fourth solenoid valve, the fifth solenoid valve, and the sixth solenoid valve are all in the normally open state.