A waste heat recovery device for horizontal buried pipe gangue slag pile
By horizontally burying multiple heat exchange modules and air supply pipes in the gangue slag pile, combined with a circulation system, the problems of difficult and costly waste heat recovery from the gangue slag pile are solved, achieving efficient and stable waste heat recovery and utilization.
Patent Information
- Application Number
- CN202522665223.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-16
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-12-16
AI Technical Summary
In existing technologies, it is difficult and costly to recover waste heat from gangue piles, and traditional ground source heat pumps are difficult and costly to drill, making it difficult to effectively utilize the waste heat resources of gangue piles.
Multiple heat exchange modules are installed using a horizontal buried pipe method. Combined with a gas supply pipe and a circulation system, the horizontal burial of heat exchange modules and gas supply pipes reduces drilling difficulty and improves heat exchange efficiency. Gas supply is used to enhance gangue oxidation and increase temperature.
It reduces drilling difficulty and cost, improves waste heat recovery efficiency, adapts to uneven site conditions, and features an independent control module to ensure system stability and heat exchange effect.
Smart Images

Figure CN224957218U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of energy recovery technology, and in particular to a waste heat recovery device for horizontal buried pipe gangue slag piles. Background Technology
[0002] In my country, coal mining and washing processes generate a large amount of gangue. The naturally accumulated gangue piles, due to the oxidation of the gangue, have very high internal temperatures and are prone to spontaneous combustion, generating significant amounts of heat. These gangue piles contain enormous waste heat resources. However, because gangue piles are mainly composed of crushed gangue fragments, drilling is extremely difficult. Traditional ground-source heat pump methods, such as drilling vertical holes and arranging U-shaped heat exchange tubes, are impractical. Furthermore, drilling into gangue piles (mountains) is extremely costly, making it difficult to extract waste heat from these piles using traditional ground-source heat pump methods. Utility Model Content
[0003] The purpose of this utility model is to provide a waste heat recovery device for horizontal buried pipe gangue slag piles, which solves the technical problems of difficult and costly waste heat recovery from gangue slag piles in the prior art. The various technical effects of the preferred technical solutions provided by this utility model are detailed below.
[0004] To achieve the above objectives, the present invention provides the following technical solution: This utility model provides a horizontal buried pipe waste heat recovery device for gangue slag piles, including a heat exchange module, a heat exchange water supply pipe, a heat exchange return water pipe, a circulation section, an air supply pipe, and an air supply section. The heat exchange module is horizontally buried in the gangue slag pile. There are multiple heat exchange modules, and each heat exchange module is connected to the heat exchange water supply pipe and the heat exchange return water pipe. The heat exchange water supply pipe and the heat exchange return water pipe are both connected to the circulation section. The air supply pipe is provided with an air outlet and is arranged in the gangue slag pile near the heat exchange module. The air supply pipe is connected to the air supply section.
[0005] Preferably, the circulation section includes a water distributor and a water collector, the heat exchange water supply pipe is connected to the water distributor, the heat exchange return water pipe is connected to the water collector, and the water distributor and the water collector are connected to an external heat pump unit.
[0006] Preferably, the air supply unit includes a connecting pipeline and an air compressor, and there are multiple air supply pipes, all of which are connected to the connecting pipeline, which is connected to the air compressor.
[0007] Preferably, the gas supply pipe is located below the heat exchange module.
[0008] Preferably, the air supply pipe is provided with air outlet holes evenly distributed on it.
[0009] Preferably, the heat exchange module is horizontally positioned.
[0010] Preferably, the heat exchange module is a pipe frame made of steel pipes, and the heat exchange module is laid flat or placed on its side in the gangue slag pile.
[0011] It also includes a manhole, and the circulation unit and the gas supply unit are disposed in the manhole.
[0012] The application employs the above technical solution and has at least the following beneficial effects: A horizontally buried waste heat recovery device for gangue slag piles includes heat exchange modules, heat exchange water supply pipes, heat exchange water return pipes, a circulation section, an air supply pipe, and an air supply unit. The heat exchange modules are horizontally buried in the gangue slag pile. This horizontal arrangement, combined with pre-buried installation, greatly reduces the difficulty of vertical drilling and lowers costs. There are multiple heat exchange modules, each connected to both the heat exchange water supply and return pipes. The heat exchange modules are relatively independent, better adapting to the uneven site conditions of the gangue pile and preventing overall damage to the heat exchange system due to uneven weight distribution of gangue during stacking. Each heat exchange module can be independently controlled; a problem with a single module can be directly disconnected from the system without affecting the overall heat exchange. The heat exchange water supply and return pipes are both connected to the circulation section. The air supply pipe has an air outlet and is located in the gangue slag pile near the heat exchange modules, connected to the air supply unit. By supplying air to the heat exchanger's heat exchange area through the air supply section, the oxidation of gangue is enhanced, the temperature of the heat exchange area is increased, and the heat exchange efficiency is improved.
[0013] It should be understood that the above general description and the following detailed description are exemplary and explanatory only, and do not limit this application. Attached Figure Description
[0014] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0015] Figure 1 This is a top view schematic diagram of the waste heat recovery device for horizontal buried pipe gangue slag pile provided in this embodiment of the utility model; Figure 2 This is a side view of the heat exchange module laid out in a flat configuration according to an embodiment of the present invention. Figure 3 This is a side view of the heat exchange module provided in this embodiment of the utility model.
[0016] In the diagram: 1. Heat exchange module; 2. Heat exchange water supply pipe; 3. Heat exchange return water pipe; 4. Air supply pipe; 5. Gangue slag pile; 6. Water distributor; 7. Water collector; 8. Connecting pipeline; 9. Air compressor; 10. Inspection well. Detailed Implementation
[0017] To make the objectives, technical solutions, and advantages of this utility model clearer, the technical solutions of this utility model will be described in detail below. Obviously, the described embodiments are only a part of the embodiments of this utility model, and not all of them. Based on the embodiments of this utility model, all other implementation methods obtained by those skilled in the art without creative effort are within the scope of protection of this utility model.
[0018] A specific embodiment of this utility model provides a waste heat recovery device for a horizontally buried pipe gangue slag pile, as shown in the attached figure. Figure 1 - Appendix Figure 3 As shown, it mainly includes a heat exchange module 1, a heat exchange water supply pipe 2, a heat exchange return water pipe 3, a circulation section, an air supply pipe 4, and an air supply section. The heat exchange module 1 is horizontally buried in the gangue slag pile 5. There are multiple heat exchange modules 1, and each heat exchange module 1 is connected to the heat exchange water supply pipe 2 and the heat exchange return water pipe 3. The heat exchange water supply pipe 2 and the heat exchange return water pipe 3 are both connected to the circulation section. The air supply pipe 4 is provided with an air outlet. The air supply pipe 4 is arranged in the gangue slag pile 5 near the heat exchange module 1 and is connected to the air supply section.
[0019] In this device, heat exchange module 1, as the core component, is responsible for heat exchange and transfer. Heat exchange supply pipe 2 and heat exchange return pipe 3 are connected to heat exchange module 1, forming a closed circulation system that ensures the heat exchange medium circulates within the device, effectively recovering and transferring residual heat from the gangue pile. The circulation section, together with heat exchange supply pipe 2 and heat exchange return pipe 3, forms a circulation loop, further enhancing the stability and efficiency of this circulation system and making the heat recovery process smoother. Heat exchange module 1 is horizontally buried... The design, placed within the gangue slag pile 5, significantly reduces the difficulty compared to traditional vertical drilling. Furthermore, multiple heat exchange modules 1 are used, each mounted on the heat exchange water supply pipe 2 and the heat exchange water return pipe 3, ensuring independence between them. This better adapts to the uneven terrain of the gangue pile, preventing damage to the entire heat exchange system due to uneven weight distribution during storage. Each heat exchange module 1 can be independently controlled; a problem with a single module can be removed from the system without affecting the overall heat exchange. The air supply pipe 4 and air supply unit are designed to replenish gas into the device when necessary, enhancing gangue oxidation, increasing the temperature of the heat exchange area, and improving heat exchange efficiency.
[0020] To ensure the independence of each heat exchange module 1, each heat exchange module 1 can be paired with a set of heat exchange water supply pipe 2 and heat exchange water return pipe 3. In actual installation, when a heat exchange module 1 needs to be installed, the corresponding heat exchange water supply pipe 2 and heat exchange water return pipe 3 can be installed on the circulation section. Alternatively, one set of heat exchange water supply pipe 2 and heat exchange water return pipe 3 can be used to correspond to multiple heat exchange modules 1. Multiple branch pipes can be installed on the heat exchange water supply pipe 2 and heat exchange water return pipe 3, each with a valve. This valve can be used to control whether the heat exchange module 1 on that branch pipe is activated, and it can also be removed as needed.
[0021] In a specific embodiment of this application, the circulation section includes a water distributor 6 and a water collector 7. The heat exchange water supply pipe 2 is connected to the water distributor 6, the heat exchange return water pipe 3 is connected to the water collector 7, and the water distributor 6 and the water collector 7 are connected to an external heat pump unit.
[0022] The water distributor 6 is used to evenly distribute circulating water to the corresponding heat exchange water supply pipes 2, ensuring that each heat exchange module 1 on the corresponding branch of the heat exchange water supply pipe 2 receives a stable water flow supply, thereby ensuring the consistency of heat exchange effect. The water collector 7 is responsible for collecting the circulating water flowing back from each branch of the heat exchange return water pipe 3, converging it and then sending it back to the circulation system for subsequent heat supply. Through reasonable pipe connection and layout, the water distributor 6 and the water collector 7, together with the heat exchange water supply pipe 2, the heat exchange return water pipe 3 and the heat exchange module 1, constitute a complete and efficient circulation system, effectively realizing the recovery and utilization of waste heat from the gangue slag pile.
[0023] In some embodiments, the air supply unit includes a connecting pipe 8 and an air compressor 9. There are multiple air supply pipes 4, all of which are connected to the connecting pipe 8, and the connecting pipe 8 is connected to the air compressor 9.
[0024] One end of the connecting pipe 8 is connected to the air outlet of the air compressor 9, and the other end extends to a suitable position in the circulation system according to actual needs and is connected to the corresponding air supply pipe 4. The air compressor 9 is used to generate compressed air with a certain pressure. The compressed air is delivered to the air supply pipe 4 through the connecting pipe 8, and the gas is sent into the gangue slag pile 5 through the air supply pipe 4 to provide oxygen for gangue oxidation, thereby increasing the temperature of the corresponding area and enhancing the heat exchange effect.
[0025] The heat exchange modules 1 and the air supply pipes 4 should be evenly distributed according to the actual or expected size of the gangue slag pile 5 to ensure the overall heat exchange effect. Therefore, multiple air supply pipes 4 can be laid side-by-side below the heat exchange modules 1.
[0026] In some embodiments, the air supply pipe 4 is arranged below the heat exchange module 1.
[0027] This arrangement of the air supply pipe 4 ensures that the gas supplied from the air supply pipe 4 is evenly diffused to the bottom area of the gangue slag pile 5, allowing the bottom of the gangue slag pile 5 to also receive sufficient oxygen, thereby improving the oxidation effect in this area and further enhancing the heat exchange efficiency of the heat exchange module 1. Furthermore, this arrangement will not interfere with the normal operation of the heat exchange module 1, ensuring the stability and reliability of the entire waste heat recovery device.
[0028] Specifically, air outlets are evenly distributed on the air supply pipe 4. The diameter and spacing of the air outlets are set according to actual needs to ensure that compressed air is released evenly and stably from the air outlets. This design allows compressed air to be distributed more widely and evenly inside the gangue slag pile, further improving the uniformity and efficiency of gangue oxidation, thereby better enhancing the heat exchange effect of the entire waste heat recovery device.
[0029] In some embodiments, the heat exchange module 1 is horizontally arranged. There is no need to drill holes in the waste rock pile; it can be arranged horizontally before the waste rock is dumped and stockpiled, or it can be horizontally arranged by excavation on-site.
[0030] Specifically, in this application, heat exchange module 1 is a pipe frame assembled from steel pipes. This pipe frame is constructed by welding multiple steel pipes together, and its shape and size are flexibly designed according to the actual waste heat recovery requirements and the scale of the gangue slag pile. Steel pipes have excellent thermal conductivity, efficiently transferring waste heat from the gangue slag pile to the subsequent heat exchange medium, thus achieving waste heat recovery and utilization. Moreover, this assembled pipe frame structure is stable, able to withstand a certain pressure from the gangue slag pile, and is not prone to deformation or damage, ensuring the stability and reliability of the entire waste heat recovery device during long-term operation. Multiple steel pipes can be arranged side-by-side in the pipe frame, with steel pipe connections at both ends, creating an interconnected pipe space within the pipe frame.
[0031] The heat exchange module 1 is laid flat or upright in the gangue slag pile 5, as shown in the attached diagram. Figure 1 and attached Figure 2 As shown, the heat exchange module 1 can have a larger contact area with the gangue pile 5 in the horizontal direction, thereby more fully absorbing the waste heat emitted by the gangue pile; the side-mounted configuration is shown in the attached figure. Figure 3 As shown, the heat exchange module 1 can be flexibly embedded inside the gangue slag pile according to its shape and terrain characteristics, achieving waste heat recovery in the vertical direction within a limited space. Whether laid flat or installed on its side, the heat exchange module 1 can quickly transfer the absorbed waste heat to the connected heat exchange medium due to its excellent thermal conductivity. Then, through subsequent heat exchange processes, the waste heat is converted into usable energy, realizing the effective recovery and reuse of resources.
[0032] In some embodiments, an inspection well is also included, and a circulation section and a gas supply section are disposed within the inspection well 10.
[0033] The installation of inspection well 10 not only facilitates daily inspection and maintenance of the circulation and gas supply parts, ensuring their normal operation, but also effectively protects these critical components from external environmental erosion and damage.
[0034] In this utility model, the terms "one embodiment," "some embodiments," "example," "specific example," and "some examples," etc., refer to specific features, structures, materials, or characteristics described in connection with that embodiment or example, which are included in at least one embodiment or example of this utility model. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples. Furthermore, without contradiction, those skilled in the art can combine and integrate the different embodiments or examples described in this specification, as well as the features of different embodiments or examples.
[0035] The above description is merely a specific embodiment of this utility model, but the protection scope of this utility model is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in this utility model should be included within the protection scope of this utility model. Therefore, the protection scope of this utility model should be determined by the protection scope of the claims.
Claims
1. A horizontal buried pipe gangue residue stack waste heat recovery device, characterized in that, The device includes a heat exchange module, a heat exchange water supply pipe, a heat exchange return water pipe, a circulation section, an air supply pipe, and an air supply unit. The heat exchange module is horizontally buried in the gangue slag pile. There are multiple heat exchange modules, and each heat exchange module is connected to the heat exchange water supply pipe and the heat exchange return water pipe. The heat exchange water supply pipe and the heat exchange return water pipe are both connected to the circulation section. The air supply pipe is provided with an air outlet and is arranged in the gangue slag pile near the heat exchange module. The air supply pipe is connected to the air supply unit.
2. The horizontal buried pipe gangue stack waste heat recovery device according to claim 1, characterized in that, The circulation section includes a water distributor and a water collector. The heat exchange water supply pipe is connected to the water distributor, and the heat exchange return water pipe is connected to the water collector. The water distributor and the water collector are connected to an external heat pump unit.
3. The horizontal buried pipe gangue stack waste heat recovery device according to claim 1, characterized in that, The air supply unit includes a connecting pipeline and an air compressor. There are multiple air supply pipes, all of which are connected to the connecting pipeline, and the connecting pipeline is connected to the air compressor.
4. The horizontal buried pipe gangue stack waste heat recovery device according to claim 1, characterized in that, The gas supply pipe is located below the heat exchange module.
5. The horizontal buried pipe gangue stack waste heat recovery device according to claim 1, characterized in that, The air supply pipe has evenly distributed air outlet holes.
6. The horizontal buried pipe gangue stack waste heat recovery device according to claim 1, characterized in that, The heat exchange module is set horizontally.
7. The horizontal buried pipe gangue stack waste heat recovery device according to claim 6, characterized in that, The heat exchange module is a pipe frame made of steel pipes, and the heat exchange module is laid flat or placed on its side in the gangue slag pile.