A support structure for permanent structures

By combining temporary support piles with bridge pier foundations through an integrated composite support structure, the problems of resource waste and construction period extension of traditional support structures are solved, and the effects of permanent load bearing and green construction are achieved.

CN224982198UActive Publication Date: 2026-11-17JIANG SU SHUN LI LENG WAN XING GANG SHI YE YOU XIAN GONG SI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522729237.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-23
Publication Date
2026-11-17
Estimated Expiration
2035-12-23

AI Technical Summary

Technical Problem

In traditional bridge engineering, the construction and dismantling of temporary support structures consume a lot of resources, prolong the construction period, generate noise and construction waste, and waste their performance by failing to participate in the load-bearing of the permanent structure.

Method used

An integrated composite support structure is designed, which combines cast-in-place reinforced concrete support piles and cap beams with the pier cap, and forms a permanent pier foundation through an anchoring mechanism. The anchoring mechanism is used to achieve a firm connection between the support piles and the cap, forming an overall composite structure.

Benefits of technology

It enables the full life-cycle utilization of temporary support structures, saving costs, shortening the construction period, improving project safety and load-bearing capacity, and meeting the requirements of green construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224982198U_ABST
    Figure CN224982198U_ABST
Patent Text Reader

Abstract

This utility model discloses a support structure for permanent structures, relating to the fields of geotechnical engineering and building engineering technology. It includes: cast-in-place reinforced concrete support piles surrounding the foundation pit and a reinforced concrete capping beam connected to the top of all the support piles. The support piles and capping beam together constitute a temporary support system during the foundation pit excavation stage. The temporary support system is integrated with the post-cast pier cap through an integrated connection structure to form a permanent pier foundation load-bearing structure. This utility model transforms the temporary foundation pit support structure into a permanent pier foundation structure, completely avoiding the demolition and abandonment of the support structure, realizing the full life-cycle utilization of materials, saving costs, and meeting the requirements of green construction. By firmly combining the support piles, capping beam, and pier cap into a single composite structure, it greatly improves the vertical bearing capacity, horizontal thrust resistance, and overall stiffness of the pier foundation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the fields of geotechnical engineering and building engineering, and in particular to a support structure for permanent structures. Background Technology

[0002] In bridge construction, bridge pier foundations are usually constructed in the form of deep foundation pits. Currently, the general construction process is as follows: first, temporary support structures such as steel sheet piles and bored piles are constructed; then, the foundation pit is excavated; next, the bridge pier cap and pier body are constructed at the bottom of the pit; and finally, the foundation pit is backfilled and the temporary support structures are removed.

[0003] This traditional temporary support model has many drawbacks: First, the construction and dismantling of the support structure requires a large investment of manpower, material resources, and financial resources, resulting in serious waste of resources and increased economic costs; second, the dismantling process of the support structure prolongs the overall construction period; third, the dismantling process generates construction waste, noise, and vibration, which does not conform to the concept of green and environmentally friendly construction; and finally, the performance of the temporary support structure itself is wasted, failing to contribute to the performance of the permanent structure.

[0004] Therefore, developing an integrated structure that combines temporary support structures with permanent bridge pier foundations has significant economic and environmental value. Utility Model Content

[0005] In view of the shortcomings of the existing technology, this utility model aims to provide a composite support structure that is integrated with the permanent structure. It can provide reliable support force during the construction phase and can also directly participate in long-term stress as part of the permanent structure, thereby achieving the goals of saving materials, simplifying procedures, shortening the construction period, and improving the safety of the project.

[0006] To achieve the above objectives, this utility model provides a support structure for permanent structures. The utility model provides the following technical solution, including: The cast-in-place reinforced concrete support piles surrounding the foundation pit and the reinforced concrete capping beam connected to the top of the support piles together constitute a temporary support system during the foundation pit excavation stage. The temporary support system is combined with the post-cast pier cap through an integrated connection structure to form a permanent pier foundation load-bearing structure. The integrated connection structure includes an anchoring mechanism that anchors the main reinforcement bars of the support piles into the pier cap.

[0007] Furthermore, the support piles are arranged in a closed loop or rectangle to form a cylindrical support body.

[0008] Furthermore, the anchoring mechanism includes a foundation connecting plate pre-embedded inside the support pile. The foundation connecting plate is a rectangular steel plate or an arc-shaped steel plate, and its shape and curvature are consistent with the inner wall curvature of the support pile. The foundation connecting plate is provided with a number of holes for concrete flow. The foundation connecting plate is also provided with a number of vertical shear connectors. The side of the foundation connection plate is also provided with several horizontal shear connectors. One end of each horizontal shear connector extends into the pile body of the support pile, and the other end is vertically and fixedly connected to the side of the foundation connection plate.

[0009] Furthermore, the vertical shear connector and the horizontal shear connector are steel shear keys, which are channel steel, I-beams or H-beams arranged along the entire length.

[0010] Furthermore, the anchoring mechanism is provided in several sets at intervals along the vertical direction of the support pile.

[0011] Furthermore, the top elevation of the cap beam is lower than the top elevation of the pier, so that the side portion of the cap beam is embedded in the pier, forming a mortise and tenon joint structure. A pier column and a cap beam are provided above the pier.

[0012] Furthermore, the bottom of the support pile is provided with a rigid base plate protruding into the pit, and the rigid base plate, together with the support pile, the cap beam and the pile cap, constitute a closed box foundation.

[0013] Furthermore, the support piles are diaphragm walls or bored piles.

[0014] Compared with the prior art, the beneficial effects achieved by this utility model are: This utility model transforms temporary foundation pit support structures into permanent bridge pier foundation structures, completely avoiding the demolition and abandonment of support structures, realizing the full life cycle utilization of materials, saving costs, and meeting the requirements of green construction. Through various structural measures such as main reinforcement bars of pile body, foundation connecting plate, vertical and horizontal shear connectors, mortise and tenon cap beams, and box-type bottom plates, the support piles, cap beams, and pier caps are firmly combined into an integral composite structure, which greatly improves the vertical bearing capacity, horizontal thrust resistance, and overall stiffness of the bridge pier foundation.

[0015] This utility model eliminates the need for dismantling the support structure, simplifies the construction process, and significantly shortens the construction period. At the same time, the support piles and cap beams can serve as permanent external forms for the pier cap construction, improving construction convenience. In addition, the cylindrical support body and box foundation formed by this utility model provide excellent soil restraint and foundation bearing capacity, making it particularly suitable for soft soil foundations, deep foundation pits, and bridge piers that bear large horizontal loads. Attached Figure Description

[0016] The accompanying drawings are provided to further understand the present invention and form part of the specification. They are used together with the embodiments of the present invention to explain the present invention and do not constitute a limitation thereof.

[0017] Figure 1 This is a schematic diagram of the overall structure of this utility model; Figure 2 This is a cross-sectional view of the present invention; Figure 3 This is a schematic diagram of the installation structure of the main reinforcement bars of the pile body according to this utility model; Figure 4 This is a schematic diagram of the installation structure of the anchoring mechanism in this utility model.

[0018] In the diagram: 1. Support pile; 2. Cap beam; 3. Pier cap; 4. Main reinforcement of pile body; 5. Pier column; 6. Cap beam; 7. Rigid base plate; 10. Foundation connection plate; 101. Hole; 102. Vertical shear connector; 103. Horizontal shear connector. Detailed Implementation

[0019] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0020] like Figures 1 to 4 As shown, the construction and formation process of a support structure for permanent structures according to this utility model is as follows: First, at the pier design location, a certain operating space is set out along the outline of the pier cap 3 to determine the circular layout line of the support pile 1. The cast-in-place reinforced concrete support pile 1 is constructed using the underground continuous wall process. When binding the steel cage of the underground continuous wall, the anchoring mechanism is installed simultaneously and the main reinforcement 4 of the pile body is set. During the fabrication of the steel cage for the diaphragm wall, the top of the longitudinal main reinforcement bars, i.e., the main reinforcement bars 4 of the pile body, is reserved with a length exceeding the designed pile top elevation. The length of the reserved anchorage section must meet the anchorage requirements of the bridge design code. The anchorage method of the main reinforcement bars 4 at the top is to use welded anchor plates to enhance its anchorage reliability in the concrete of the pile cap 3. The main reinforcement bars 4 of the pile body are evenly arranged along the perimeter of the diaphragm wall. In addition to meeting the stress requirements of the foundation pit support stage, their vertical spacing and quantity must also be checked and configured according to the standards of permanent structural components. The anchoring mechanism includes a foundation connecting plate 10, which can be a rectangular steel plate according to the shape of the diaphragm wall, with its curvature consistent with the inner wall of the wall. Holes 101 for concrete flow are pre-drilled in the foundation connecting plate 10, and then a continuous steel section such as a channel steel is vertically welded to its front as a vertical shear connector 102, and the same type of steel section is vertically welded to its side as a horizontal shear connector 103. The other end of the horizontal shear connector 103 is embedded inside the reinforcement cage of the diaphragm wall. At the same time, the installation position of the foundation connecting plate 10 is coordinated with the arrangement of the main reinforcement 4 of the pile body to ensure that both have sufficient concrete cover thickness in the post-cast pile cap 3. This anchoring mechanism, together with the main reinforcement 4 of the pile body, is set in multiple sets at intervals along the vertical of the diaphragm wall to form a complete force transmission system.

[0021] After all the underground continuous wall sections are constructed, a reinforced concrete capping beam 2 is constructed on top of the wall to connect the sections into a whole. Then, the foundation pit is excavated. At this time, the system composed of the underground continuous wall and the capping beam 2 serves as a temporary support system to ensure the safety of the foundation pit.

[0022] In traditional designs, the diaphragm wall is a purely temporary structure, designed solely to meet the strength and deformation requirements during the excavation of the foundation pit. The reinforcement configuration also serves only temporary conditions. After the foundation pit is excavated, when constructing the pier cap 3, a certain gap is usually maintained between the pier cap 3 and the diaphragm wall, or only a simple isolation layer is set up. The two are completely separated in structure. After the pier cap 3 and the pier body are constructed and the foundation pit is backfilled, this expensive diaphragm wall is permanently abandoned in the soil. It cannot participate in the permanent load-bearing of the bridge structure, and its huge material properties and early investment are completely wasted, resulting in a huge consumption of resources.

[0023] To address the aforementioned problems, this utility model, from its initial design, treats the underground continuous wall as an important component of the permanent bridge pier foundation. During the binding of its reinforcing cage, a specially designed anchoring mechanism for permanent integration is simultaneously installed, achieving a fundamental functional transformation through this design. Construction phase: The underground continuous wall and capping beam 2 serve as the support system for the foundation pit, playing a temporary retaining and water-stopping function; Permanent Stage: Through the anchoring mechanism, the post-cast foundation 3 concrete is tightly interlocked with the diaphragm wall through the hole 101, and the huge horizontal forces such as vehicle braking force and seismic force borne by the foundation 3 are reliably transferred to the diaphragm wall through the vertical shear connector 102; the horizontal shear connector 103 ensures a firm connection between the foundation connection plate 10 and the diaphragm wall itself, preventing them from separating; the anchoring of the main reinforcement of the wall effectively transfers the vertical force. Finally, the diaphragm wall transforms from a temporary retaining wall into a foundation load-bearing structure, forming a composite foundation with greater depth and stronger rigidity together with the foundation 3.

[0024] In this preferred embodiment, after the foundation pit is excavated to the design elevation, a rigid base plate 7 protruding inward from the bottom of the pit is constructed to connect with the bottom of the diaphragm wall, forming the base plate of the box foundation. Subsequently, the steel mesh of the foundation cap 3 can be tied to ensure that the main reinforcement 4 of the diaphragm wall piles, as well as all vertical shear connectors 102 and horizontal shear connectors 103, are reliably anchored and embedded in the foundation cap 3. Note that the top elevation of the cap beam 2 should be lower than the design top elevation of the foundation cap 3. Finally, the formwork of the foundation cap 3 is erected, and the concrete of the foundation cap 3 is poured in one go.

[0025] This utility model uses underground continuous walls as support piles, which have excellent water-stopping performance and can provide a drier working and use environment for foundation pit excavation and subsequent permanent structures. In addition, the formed cylindrical support body and box foundation provide excellent soil restraint and foundation bearing capacity, and are especially suitable for soft soil foundations, deep foundation pits and bridge piers that bear large horizontal loads, with good waterproof performance.

[0026] After the concrete sets, the underground continuous wall and the cap beam 2 are combined with the pier cap 3 through a strong anchoring mechanism and mortise and tenon structure to form a permanent and integral pier foundation structure; the top of the cap beam 2 is wrapped by the concrete of the pier cap 3, forming a mortise and tenon joint; various shear connectors and the main reinforcement of the wall body realize the effective transmission of force; the rigid base plate 7 and the superstructure together form a high-rigidity box foundation, and the pier columns 5 and cap beam 6 can be constructed normally on the pier cap 3 in the future.

[0027] Through the above method, this utility model successfully integrates the foundation pit support structure with the permanent foundation of the bridge pier, combining the safety of temporary support with the durability and high load-bearing capacity of permanent structure.

[0028] The parts not covered in this utility model are the same as or can be implemented using existing technologies.

[0029] Finally, it should be noted that the above description is merely a preferred embodiment of this utility model and is not intended to limit the utility model. Although the utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the protection scope of this utility model.

Claims

1. A support structure for a permanent structure, comprising cast-in-situ reinforced concrete support piles (1) arranged around a foundation pit and reinforced concrete corbel beams (2) connected to the top ends of the support piles (1), characterized in that: The support piles (1) and the cap beam (2) together constitute a temporary support system for the foundation pit excavation stage; the temporary support system is combined with the post-cast pier cap (3) through an integrated connection structure to form a permanent pier foundation load-bearing structure; the integrated connection structure includes an anchoring mechanism that anchors the main reinforcement (4) of the support pile (1) into the pier cap (3).

2. The support structure for permanent structures according to claim 1, characterized in that: The support piles (1) are arranged in a closed ring or rectangle to form a cylindrical support body.

3. A support structure for permanent structures according to claim 1, characterized in that: The anchoring mechanism includes a foundation connecting plate (10) pre-embedded inside the support pile (1), and the foundation connecting plate (10) has a plurality of holes (101) for concrete flow; the foundation connecting plate (10) is vertically provided with a plurality of vertical shear connectors (102). The side of the foundation connection plate (10) is also provided with several horizontal shear connectors (103). One end of the horizontal shear connector (103) extends into the pile body of the support pile (1), and the other end is vertically and fixedly connected to the side of the foundation connection plate (10).

4. A support structure for permanent structures according to claim 3, characterized in that: The vertical shear connector (102) and the horizontal shear connector (103) are steel shear keys, which are channel steel, I-beams or H-beams arranged along the entire length.

5. A support structure for permanent structures according to claim 3, characterized in that: The anchoring mechanism is arranged in several groups at intervals along the vertical direction of the support pile (1).

6. A support structure for permanent structures according to claim 1, characterized in that: The top elevation of the crown beam (2) is lower than the top elevation of the pier (3), so that the side part of the crown beam (2) is embedded in the pier (3) to form a tenon and mortise fixed structure. The pier (3) is provided with a pier column (5) and a cap beam (6).

7. A support structure for permanent structures according to claim 1, characterized in that: The bottom of the support pile (1) is provided with a rigid base plate (7) protruding into the pit. The rigid base plate (7), the support pile (1), the cap beam (2) and the pile cap (3) together form a closed box foundation.

8. A support structure for permanent structures according to claim 1, characterized in that: The support pile (1) is a diaphragm wall.