An adjustable subway electromechanical pipeline installation device
The adjustable subway electromechanical pipeline installation device, with its modular design and threaded drive, solves the problems of high procurement costs and construction delays caused by the fixed length of traditional devices. It enables flexible splicing and layered arrangement of electrical pipelines, thereby improving construction efficiency.
Patent Information
- Application Number
- CN202522350254.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-05
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-11-05
AI Technical Summary
Traditional subway electromechanical pipeline installation devices are single structures with fixed lengths, which cannot be flexibly adjusted. This leads to the need for custom-made special supports, increasing procurement costs and construction delays. Furthermore, they are difficult to meet the requirements for layered layout and are prone to pipeline interference.
The modular adjustable subway electromechanical pipeline installation device uses a combination of base mechanism, fixed bearing, locking component and fixing ring to achieve splicing and height adjustment of multiple devices, and uses threaded drive and interference fit to achieve flexible installation of electrical pipelines.
It enables flexible splicing and height adjustment based on the actual length of electrical pipelines, avoiding positional deviations and construction delays, meeting the hierarchical layout specifications of subway electromechanical pipelines, and reducing inventory pressure and construction costs.
Smart Images

Figure CN224983607U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of subway electromechanical installation technology, and more specifically, to an adjustable subway electromechanical pipeline installation device. Background Technology
[0002] With the rapid development of subway transportation networks, the installation environment of its electromechanical system pipelines is becoming increasingly complex. The internal space of the subway is compact and various types of pipelines are densely arranged, requiring strict adherence to the layered specifications of air-cooled, electrical, and underwater systems. At the same time, it is necessary to cope with the high-frequency vibrations generated by train operation. However, traditional subway electromechanical pipeline installation devices are mostly single structures with fixed lengths, which cannot be flexibly adjusted according to the actual length of electrical pipelines in different areas. Custom-made special brackets are required, which not only increases procurement costs and inventory pressure, but also often leads to construction delays due to mismatched specifications. Existing publication number CN220706597U discloses a pipeline installation bracket for subway electromechanical equipment, including an "H"-shaped frame. An upper pipe bracket is rotatably connected to the "H"-shaped frame, and a lower pipe bracket is rotatably connected to the upper pipe bracket. Two sliding rods are slidably connected to the inner wall of the "H"-shaped frame. Side rods are fixedly connected to both sides of the upper pipe bracket. Each sliding rod has a groove, and a slider is slidably connected to the inner wall of the groove. The slider has an upper alignment hole. The side rods and the inner wall of the upper pipe bracket both have lower alignment holes that match the slider. The "H"-shaped frame, fixed frame, upper pipe bracket, lower pipe bracket, and side rods form a component capable of supporting and mounting two pipelines with different directions and relatively large vertical diameters. This avoids the limitations of existing brackets, which offer only a single support angle for pipelines and cannot simultaneously support pipelines perpendicular to each other when they pass through intersecting pipelines. The inventors discovered the following problems with the existing technology during the development of this utility model: Traditional electrical conduit installation devices are mostly single-component fixed-length structures that lack modular design for splicing, making it impossible to adjust the length of the electrical conduit according to the actual length. They require custom-made special brackets for conduits of different lengths, and construction delays can occur due to mismatch between the on-site conduit length and the bracket specifications. In terms of height adjustment, traditional installation devices are mostly fixed-height installations, which are difficult to meet the hierarchical layout specifications of subway electromechanical conduits and are prone to conduit interference problems. Therefore, an adjustable subway electromechanical pipeline installation device is proposed to address the above problems. Utility Model Content
[0003] In order to overcome the above-mentioned defects of the prior art, the present invention provides an adjustable subway electromechanical pipeline installation device to solve the problems mentioned in the background art.
[0004] To achieve the above objectives, this utility model provides the following technical solution: an adjustable subway electromechanical pipeline installation device, comprising a base mechanism, a fixed bearing, a locking component, and a fixing ring. The fixed bearing is installed above the base mechanism, and the locking component is installed above the fixed bearing. The fixing ring is installed above the locking component. The base mechanism includes a base plate, an adjustment component, and an installation component. The adjustment component is installed above the base plate, and the installation component is provided on the side of the adjustment component.
[0005] Preferably, the base plate includes a plate body, a connecting hole plate, and a mounting post, wherein the connecting hole plate is installed on the side of the plate body, and the mounting post is installed on the side of the plate body away from the connecting hole plate.
[0006] Preferably, the adjusting assembly includes a fixing nut, a first threaded rod, and a fixing rod, wherein the fixing nut is mounted on the outer diameter surface of the first threaded rod, and the fixing rod is mounted above the first threaded rod.
[0007] Preferably, the mounting assembly includes a fixing bolt, a first anti-loosening washer, and a second anti-loosening washer, wherein the first anti-loosening washer is mounted on the outer diameter surface of the fixing bolt, and the second anti-loosening washer is disposed below the first anti-loosening washer.
[0008] Preferably, the locking assembly includes a locking nut, a brake washer, and a second threaded rod, wherein the brake washer is disposed on the outer diameter surface of the second threaded rod, and the locking nut is disposed above the brake washer.
[0009] Preferably, the fixing ring includes a first half-ring, a second half-ring, and an adjusting bolt, with the second half-ring disposed above the first half-ring and the adjusting bolt mounted on the side of the second half-ring.
[0010] Preferably, the second threaded rod and the locking nut are connected by threads, and the second threaded rod and the brake washer are in clearance fit. The brake washer has an annular structure and its inner radius is slightly larger than the outer radius of the second threaded rod.
[0011] Preferably, the base mechanism and the fixed bearing are interference fits, and the fixed bearing and the locking assembly are interference fits, and the locking assembly and the fixing ring are connected by welding.
[0012] The technical effects and advantages of this utility model are as follows: 1. Compared with the existing technology, this adjustable subway electromechanical pipeline installation device realizes the modular splicing function of multiple devices through the connecting hole plate set on the side of the base plate and the single-sided mounting column. Before construction, the workers can first align and splice the connecting hole plates and mounting columns of multiple installation devices according to the actual length of the electrical pipeline, such as long pipelines in subway station platforms and short pipelines in tunnel sections. During installation, it is necessary to ensure that the base plates of multiple devices are kept on the same horizontal line to avoid the overall positional displacement of the installation device after splicing.
[0013] 2. Compared with the existing technology, this adjustable subway electromechanical pipeline installation device uses a screw drive as the core of the adjustment component. Through the coordinated action of the first screw rod, the fixing nut and the fixing rod, the installation height of the electrical pipeline can be controlled. When the staff adjusts, they only need to loosen the fixing nut on the outer diameter of the first screw rod first, rotate the first screw rod clockwise or counterclockwise according to the site requirements, and tighten the fixing nut again after the height is suitable to lock the position. Attached Figure Description
[0014] Figure 1 This is a three-dimensional structural diagram of the present invention.
[0015] Figure 2 This is a three-dimensional structural diagram of the base plate of this utility model.
[0016] Figure 3 For the present utility model Figure 1 A schematic diagram of the structure at point A.
[0017] Figure 4 For the present utility model Figure 1 A schematic diagram of the structure at point B.
[0018] The attached figures are labeled as follows: 1. Base mechanism; 2. Fixed bearing; 3. Locking assembly; 4. Fixing ring; 5. Base plate; 6. Adjusting assembly; 7. Mounting assembly; 8. Plate; 9. Connecting hole plate; 10. Mounting column; 11. Fixing nut; 12. First threaded rod; 13. Fixing rod; 14. Fixing bolt; 15. First anti-loosening washer; 16. Second anti-loosening washer; 17. Locking nut; 18. Brake washer; 19. Second threaded rod; 20. First half ring; 21. Second half ring; 22. Adjusting bolt. Detailed Implementation
[0019] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0020] Example 1 As attached Figures 1 to 4 An adjustable subway electromechanical pipeline installation device is shown, including a base mechanism 1, a fixed bearing 2, a locking assembly 3 and a fixing ring 4. The fixed bearing 2 is installed on the top of the base mechanism 1, the locking assembly 13 is installed on the top of the fixed bearing 2, and the fixing ring 4 is installed on the top of the locking assembly 3. The base mechanism 1 includes a base plate 5, an adjustment assembly 6 and an installation assembly 7. The adjustment assembly 6 is installed on the top of the base plate 5, and the installation assembly 7 is provided on the side of the adjustment assembly 6.
[0021] Specifically: When the device adopts a layered modular structure design, the base mechanism 1 serves as the overall load-bearing foundation. The fixed bearing 2 enables the rotation adjustment function of the fixed ring 4, so that the opening direction of the fixed ring 4 is not affected by the rotation of the base mechanism 1 due to height adjustment. The locking component 3 is used to fix the position after rotation or height adjustment. The fixed ring 4 directly achieves the clamping and fixing of the electrical conduit. At the same time, the base plate 5 of the base mechanism 1 serves as the load-bearing base. The adjustment component 6 can adjust the height of the electrical conduit. The installation component 7 connects the installation device to the building structure, forming a three-level functional division of basic load-bearing, functional adjustment and external fixing.
[0022] Example 2 Based on Example 1, the solution in Example 1 will be further described in detail below with reference to the specific working method, such as... Figures 1 to 4 As shown below, see details: In a preferred embodiment, the base plate 5 includes a plate body 8, a connecting hole plate 9, and a mounting column 10. The connecting hole plate 9 is installed on the side of the plate body 8, and the mounting column 10 is installed on the side of the plate body 8 away from the connecting hole plate 9. The base plate 5 uses the plate body 8 as the core supporting body. Through the lateral expansion structural layout, the connecting hole plate 9 and the mounting column 10 are provided on the side of the plate body 8 for connecting the base plates 5. Workers can splice multiple installation mechanisms according to the length of the construction electrical conduit, thereby adjusting the length of the installation device for the electrical conduit.
[0023] In a preferred embodiment, the adjusting assembly 6 includes a fixing nut 11, a first threaded rod 12, and a fixing rod 13. The fixing nut 11 is installed on the outer diameter surface of the first threaded rod 12, and the fixing rod 13 is installed above the first threaded rod 12. The adjusting assembly 6 achieves height adjustment through the principle of threaded transmission. The first threaded rod 12 is the core transmission component, and the thread on its outer diameter surface engages with the fixing nut 11. By turning the first threaded rod 12 itself, its height protruding from the plate 8 is adjusted. When the first threaded rod 12 is turned clockwise, the first threaded rod 12 descends, and when it is turned counterclockwise, the first threaded rod 12 rises. The fixing rod 13 connected to the top of the first threaded rod 12 connects and fixes the adjusting assembly 6 and the fixing bearing 2, transmitting the lifting action to the locking assembly 3 and the fixing ring 4 above. The fixing nut 11 can be fixed by turning the first threaded rod 12.
[0024] In a preferred embodiment, the mounting assembly 7 includes a fixing bolt 14, a first anti-loosening washer 15, and a second anti-loosening washer 16. The first anti-loosening washer 15 is mounted on the outer diameter surface of the fixing bolt 14, and the second anti-loosening washer 16 is disposed below the first anti-loosening washer 15. The mounting assembly 7 adopts a composite fixing structure of fixing bolt 14 and double anti-loosening washers. The fixing bolt 14 is used as the core connecting component. The connection between the base mechanism 1 and the building base is realized by the bolt passing through the connecting hole plate 9 and engaging with the threaded hole of the building structure. At the same time, the first anti-loosening washer 15 and the second anti-loosening washer 16 are sequentially mounted on the outer diameter surface of the fixing bolt 14. The friction between the two washers and the pressure between the washer and the bolt head on the plate 8 form a double anti-loosening effect to counteract the high-frequency vibration generated by the operation of the subway train.
[0025] In a preferred embodiment, the locking assembly 3 includes a locking nut 17, a brake washer 18, and a second threaded rod 19. The brake washer 18 is disposed on the outer diameter surface of the second threaded rod 19, and the locking nut 17 is disposed above the brake washer 18. The locking assembly 3 uses the second threaded rod 19 as an axial bearing member. The annular structure of the brake washer 18 is sleeved on the outer diameter surface of the second threaded rod 19 to provide buffering and anti-loosening transition. Then, by utilizing the thread engagement between the locking nut 17 and the second threaded rod 19, the locking nut 17 is tightened to fit tightly against the brake washer 18. Through the axial pressure of the nut, the second threaded rod 19 is fixed on the fixed bearing 2, so that it will not slip relative to the bearing.
[0026] In a preferred embodiment, the fixing ring 4 includes a first half-ring 20, a second half-ring 21, and an adjusting bolt 22. The second half-ring 21 is positioned above the first half-ring 20, and the adjusting bolt 22 is mounted on the side of the second half-ring 21. The fixing ring 4 adopts an openable double half-ring structure. The first half-ring 20 and the second half-ring 21 form an openable annular cavity for wrapping the pipeline. By setting the adjusting bolt 22 on the side of the second half-ring 21, the opening degree of the double half-ring is controlled by the axial thrust of the bolt. When the adjusting bolt 22 is tightened clockwise, the distance between the double half-rings decreases, and the clamping force on the pipeline increases. When rotated counterclockwise, the distance increases, allowing the pipeline to be removed or replaced, achieving non-disassembly installation.
[0027] In a preferred embodiment, the second threaded rod 19 and the locking nut 17 are connected by threads, the second threaded rod 19 and the brake washer 18 are in clearance fit, the brake washer 18 is annular and its inner radius is slightly larger than the outer radius of the second threaded rod 19.
[0028] In a preferred embodiment, the base mechanism 1 and the fixed bearing 2 are interference fits, the fixed bearing 2 and the locking assembly 3 are interference fits, and the locking assembly 3 and the fixing ring 4 are connected by welding.
[0029] The working process of this utility model is as follows: First, when the operator installs the electrical conduit, the length of the electrical conduit must be determined. Then, according to the length of the electrical conduit, multiple installation devices are connected and assembled through the connecting hole plate 9 and the installation column 10. Then, the plate body 8 of the base plate 5 of the fixed base mechanism 1 is attached to the building installation surface. The fixing bolts 14 in the installation component 7 are passed through the first anti-loosening washer 15, the second anti-loosening washer 16 and the installation hole of the plate body 8 in sequence, and screwed into the preset threaded hole of the building structure, ensuring that the base mechanism 1 is firmly attached to the building base.
[0030] Next, adjust the pipeline installation height by adjusting component 6. First, loosen the fixing nut 11 on the outer diameter surface of the first threaded rod 12. Rotate the first threaded rod 12 clockwise or counterclockwise as needed. After the height is suitable, tighten the fixing nut 11 to lock the first threaded rod 12. At this time, the fixing rod 13 above the first threaded rod 12 will transmit the height position to the fixed bearing 2 connected to it.
[0031] Then adjust the pipeline installation direction. Since the fixed bearing 2 can rotate, after the direction is determined, push the interference fit locking component 3 above it, which will cause the brake washer 18 inside the locking component 3 to rotate on the outer diameter surface of the second threaded rod 19. Then tighten the locking nut 17 on the second threaded rod 19 so that the locking nut 17 and the brake washer 18 fit tightly together, and fix the second threaded rod 19 on the fixed bearing 2 to prevent relative slippage.
[0032] Finally, the electrical conduit is installed. Since the locking component 3 and the fixing ring 4 are connected by welding, the first half ring 20 and the second half ring 21 of the fixing ring 4 are opened, and the electrical conduit is placed into the annular cavity formed by the two. Then, the adjusting bolt 22 on the side of the second half ring 21 is turned clockwise to reduce the distance between the two half rings and increase the clamping force. If the conduit needs to be replaced, the adjusting bolt 22 is turned counterclockwise to expand the distance, realizing non-disassembly installation. Finally, the electrical conduit is fixed. The above is the working principle of this adjustable subway electromechanical conduit installation device.
Claims
1. An adjustable subway electromechanical pipeline installation device, comprising a base mechanism (1), a fixed bearing (2), a locking assembly (3), and a fixing ring (4), characterized in that: A fixed bearing (2) is installed above the base mechanism (1), and a locking component (3) is installed above the fixed bearing (2). A fixing ring (4) is installed above the locking component (3). The base mechanism (1) includes a base plate (5), an adjustment component (6), and a mounting component (7). The adjustment component (6) is installed above the base plate (5), and the mounting component (7) is provided on the side of the adjustment component (6).
2. An adjustable subway electromechanical pipe installation device according to claim 1, characterized in that: The base plate (5) includes a plate body (8), a connecting hole plate (9) and a mounting post (10), and the connecting hole plate (9) is installed on the side of the plate body (8), and the mounting post (10) is installed on the side of the plate body (8) away from the connecting hole plate (9).
3. An adjustable subway mechanical and electrical conduit mounting device according to claim 1, characterized in that: The adjustment assembly (6) includes a fixing nut (11), a first threaded rod (12) and a fixing rod (13), and the fixing nut (11) is installed on the outer diameter surface of the first threaded rod (12), and the fixing rod (13) is installed above the first threaded rod (12).
4. An adjustable subway electro-mechanical conduit mounting device according to claim 1, wherein: The mounting assembly (7) includes a fixing bolt (14), a first anti-loosening washer (15) and a second anti-loosening washer (16), and the first anti-loosening washer (15) is mounted on the outer diameter surface of the fixing bolt (14), and the second anti-loosening washer (16) is provided below the first anti-loosening washer (15).
5. An adjustable subway electro-mechanical conduit mounting device as claimed in claim 1, wherein: The locking assembly (3) includes a locking nut (17), a brake washer (18), and a second threaded rod (19), wherein the outer diameter surface of the second threaded rod (19) is provided with a brake washer (18), and the locking nut (17) is provided above the brake washer (18).
6. An adjustable subway electro-mechanical conduit mounting device as claimed in claim 1, wherein: The fixing ring (4) includes a first half ring (20), a second half ring (21) and an adjusting bolt (22), and the second half ring (21) is provided above the first half ring (20), and the adjusting bolt (22) is installed on the side of the second half ring (21).
7. An adjustable subway electromechanical pipeline installation device according to claim 5, characterized in that: The second threaded rod (19) and the locking nut (17) are connected by threads, and the second threaded rod (19) and the brake washer (18) are in clearance fit. The brake washer (18) is an annular structure and its inner radius is slightly larger than the outer radius of the second threaded rod (19).
8. The adjustable subway electromechanical pipeline installation device according to claim 1, characterized in that: The base mechanism (1) and the fixed bearing (2) are interference fits, and the fixed bearing (2) and the locking assembly (3) are interference fits. The locking assembly (3) and the fixed ring (4) are connected by welding.