Rescue device for roadway collapse incidents in underground coal mines and rescue method therefor

The rescue device employs a guided drilling mechanism with an electromagnetic ranging radar and inflatable membrane duct to bypass debris piles in coal mine collapses, addressing the inefficiencies of traditional methods and ensuring rapid rescue passage construction.

GB2645531APending Publication Date: 2026-11-11CHINA UNIV OF MINING & TECH
View PDF 12 Cites 0 Cited by

Patent Information

Application Number
GB2026007306
Authority / Receiving Office
GB · GB
Patent Type
Applications
Current Assignee / Owner
Priority Date
2025-01-10
Filing Date
2025-11-01
Publication Date
2026-11-11

AI Technical Summary

Technical Problem

Existing rescue methods for roadway collapse incidents in underground coal mines are time-consuming and labor-intensive, failing to account for the structural integrity above the debris and often result in substantial loss of life and property due to the lack of a rapid rescue tunnel establishment.

Method used

A rescue device comprising a guided drilling mechanism with an electromagnetic ranging radar, a transmission and coupling mechanism, and a rescue passage mechanism, which uses high-level directional drilling to bypass the debris pile by forming a temporary support with an air-ribbed inflatable membrane duct, enabling rapid rescue passage construction.

Benefits of technology

The device significantly reduces excavation workload and time, enhancing rescue efficiency and success rates while minimizing loss of life and property by providing a flexible and reliable rescue passage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

A rescue device for roadway collapse incidents in underground coal mines and a rescue method therefor are disclosed, wherein the rescue device comprises a guided drilling mechanism 1, a transmission and coupling mechanism 2, and a rescue passage mechanism 3. The method involves detecting a slope gradient of a collapsed debris pile 4 to determine an initial drilling angle, advancing a central directional drill along a slope of the collapsed debris pile, conducting real-time monitoring using an electromagnetic ranging radar 1-5 and, upon detecting a significant electrical signal anomaly, adjusting the drilling angle to a near-horizontal orientation. The central guide drill 1-1 is then advanced through the collapsed debris and, upon the electromagnetic ranging radar detecting a significant electrical signal anomaly, adjusting the drilling angle to an inclination direction opposite to the initial drilling angle. The borehole diameter is enlarged using a reamer 1-3 and an air-ribbed inflatable membrane duct 3-1 inserted into the borehole before a coating operation is performed using membrane spraying assemblies 1-4.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field The present invention relates to a rescue device for roadway collapse incidents in underground coal mines and a rescue method therefor, falling within the technical field of underground coal mine drilling rescue. Background Technology The occurrence of geological dynamic disasters in coal mines frequently results in the collapse of roadways and excavation spaces. Existing rescue methods typically rely on manual labor or excavators to directly clear the collapsed debris or involve extensive, large-scale excavation while simultaneously installing immediate support within the excavated space. However, those methods do not account for the structural integrity of the space situated above the collapsed debris, nor do they explore the option of establishing a new rescue tunnel to bypass the accident zone. Consequently, these approaches entail massive engineering workloads and are highly time-consuming, making it difficult to complete rescue operations within the critical "golden hour" and resulting in substantial loss of life and property. Summary of the Invention To address the problems existing in the aforementioned prior art, the present invention provides a rescue device and a rescue method for roadway collapse incidents in underground coal mines. This rescue device and method facilitate rescue operations following a roadway collapse, enhance rescue efficiency and success rates, and minimize loss of life and property. To achieve the above-mentioned purpose, the present invention provides a rescue device for roadway collapse incidents in underground coal mines, comprising a guided drilling mechanism, a transmission and coupling mechanism, and a rescue passage mechanism, wherein the guided drilling mechanism comprises a central pilot drill, a drill rod, a reaming drill, and film-spraying assemblies; an electromagnetic ranging radar is mounted on the central pilot drill; the reaming drill is connected to the central pilot drill via the drill rod; a diameter of the reaming drill is greater than a diameter of the central pilot drill, reaming cutters are arranged at equal intervals along a circumference of an outer wall thereof, and the film-spraying assemblies are installed between adjacent reaming cutters; the transmission and coupling mechanism comprises a transmission connecting rod and a spherical joint structure, wherein the spherical joint structure comprises a housing support, a cage is positioned between the housing support and an inner raceway, transmission steel balls are installed within the cage, and the transmission steel balls engage in a rolling fit with the housing support and the inner raceway, and an end portion of the transmission connecting rod is connected to the reaming drill, while another end portion is connected to the inner raceway; and the rescue passage mechanism comprises an air-ribbed inflatable membrane duct; one end portion of the air-ribbed inflatable membrane duct communicates with the guided drilling mechanism via the transmission coupling mechanism, the air-ribbed inflatable membrane duct is provided with a fluid supply channel and air supply channels; both the fluid supply channel and the air supply channels extend continuously through the transmission coupling mechanism and the guided drilling mechanism, serving respectively to supply spraying slurry and air to the membrane spraying assembly and the air-ribbed inflatable membrane duct. Further, the air-ribbed inflatable membrane duct is provided with flexible reinforcing ribs, and the flexible reinforcing ribs are arranged in close contact with a surface of the air-ribbed inflatable membrane duct. Further, the film-spraying assemblies comprise mounting bases, support frames, pressurization chambers, liquid inlet pipes, and spray heads; the mounting bases are fixed to a body of the reaming drill; the support frames are arranged on the mounting bases; the pressurization chambers and the liquid inlet pipes are sealingly installed within the support frames; the spray heads are mounted on exposed upper end portions of the support frames; the pressurization chambers serve to connect the spray heads with one end portion of the liquid inlet pipes; and another end portion of the liquid inlet pipes communicate with the liquid supply channel. A rescue method for roadway collapse incidents in underground coal mines by utilizing the rescue device as mentioned above, comprising following steps: Sl-detecting a slope gradient of a collapsed debris pile by an inclinometer, and determining an initial drilling angle for the central pilot drill based on measurement results; S2-sequentially installing the guide drilling mechanism, the transmission coupling mechanism, and the rescue passage mechanism in a front-to-rear order; and activating the central pilot drill to drill along a slope of the collapsed debris pile at the initial drilling angle determined in the SI; S3-continuously transmitting, by an electromagnetic ranging radar, electromagnetic wave signals ahead of the drill and receiving reflected signals in real time during a drilling process, wherein when the central pilot drill approaches a first inflection point of the collapsed debris pile, and the electromagnetic ranging radar detects that reflected signals exhibit a distinct electrical difference, the central pilot drill automatically adjusts a drilling angle thereof to a near-horizontal orientation; S4-continually drilling, by the central pilot drill, along an upper horizontal section of the collapsed debris pile until approaching a second inflection point, wherein when the electromagnetic ranging radar once again detects reflected signals exhibiting a distinct electrical difference, the central pilot drill automatically adjusting the drilling angle thereof to an inclination opposite to the initial drilling angle; S5-entering, by the reaming drill, a pre-drilled borehole along a same trajectory under guidance of the central pilot drill, and wherein through rotation and feeding actions of the reaming drill, the reaming cutters continuously cutting the rock, gradually enlarges a borehole diameter, thereby enabling the air-ribbed inflatable membrane duct to subsequently advance into an enlarged borehole, simultaneously, the membrane spraying assemblies spray the collapsed debris pile within a drilling cavity, as well as a surface of a caved arch situated above, thereby forming a sprayed flexible membrane that provides temporary support; S6-after the guided drilling mechanism has bypassed the collapsed debris pile and reached a rescue location, the film-spraying assemblies ceasing spraying, inflating and deploying the air-ribbed inflatable membrane duct via the air supply channels, thereby causing the flexible reinforcing ribs to gradually fit snugly against the air-ribbed inflatable membrane duct; and S7-deataching the guided drilling mechanism and the transmission coupling mechanism, and enabling a trapped personnel to evacuate from the load-bearing air-ribbed inflatable membrane duct to the outside. Further, the reaming drill enlarges the hole diameter to no less than 600 mm; the sprayed flexible films formed by the film-spraying assemblies have a tensile strength of no less than 30 MPa, a thickness of no less than 5 mm, and an initial setting time of no more than 60 seconds. Based on the unique spatial characteristics formed above a collapsed debris pile, this invention employs high-level directional drilling to bypass the debris, thereby reducing the volume of excavation work required. The film-spraying assemblies provide comprehensive temporary support to the rescue space prior to the construction of the actual rescue passage. The rescue passage itself utilizes an air-ribbed inflatable membrane tube structure, enabling the rapid formation of a rescue channel immediately upon the completion of drilling within the rescue space. By leveraging the unique high-level spatial features of the collapsed debris pile—specifically by establishing the rescue passage above the debris—the system effectively bypasses the collapsed zone. This approach significantly reduces the time required for breaking through rock to carve out a passage and lowers the engineering workload associated with structural support. The system offers the advantages of a flexible and reliable passage, efficient and rapid construction, and simplified support procedures; it facilitates rescue operations following tunnel collapses, thereby enhancing rescue efficiency and success rates while minimizing loss of life and property. Brief Description of the Drawings Figure 1 is a schematic structural diagram of the present invention. Figure 2 is a schematic structural diagram of a guided drilling mechanism of the present invention. Figure 3 is a schematic structural diagram of a film-spraying assembly of the present invention. Figure 4 is a schematic structural diagram of a transmission coupling mechanism of the present invention. Figure 5 is a schematic structural diagram of a cooperative arrangement between a rescue passage mechanism and a transmission coupling mechanism of the present invention. Figure 6 is a schematic structural diagram of the rescue passage mechanism of the present invention. Figure 7 is a flowchart of the working process of the method of the present invention. The markups in the drawings are indicated as follows: 1-guided drilling mechanism; 1-1-central pilot drill; 1-2-drill rod; 1-3-reaming drill; 1-4-film-spraying assembly; 1-41-mounting base; 1-42-support frame; 1-43-pressurization chamber; 1-44-liquid inlet pipe; 1-45-spray head; 1-5-electromagnetic ranging radar; 1-6-reaming cutter; 2-transmission and coupling mechanism; 2-1-transmission connecting rod; 2-2-housing support; 2-3-inner raceway; 2-4-cage; 2-5-transmission steel ball; 3-rescue passage mechanism; 3-1-air-ribbed inflatable membrane duct; 3-11-fluid supply channel; 3-12-air supply channel; 3-13-flexible reinforcing rib; 4-collapsed debris pile; 5-natural caving arch structure; 6-first inflection point; 7-second inflection point; and 8-rescue location. Specific Embodiments The present invention is further described below with reference to the accompanying drawings. As shown in figure 1, a rescue device for use in coal mine underground roadway collapse incidents comprises a guided drilling mechanism 1, a transmission and coupling mechanism 2, and a rescue passage mechanism 3. As shown in figures 1 and 2, the aforementioned guided drilling mechanism 1 includes a central pilot drill 1-1, a drill rod 1-2, a reaming drill 1-3, and film-spraying assemblies 1-4. An electromagnetic ranging radar 1-5 is mounted on the central pilot drill 1-1, which is capable of transmitting and receiving electromagnetic wave signals while drilling, and performing the function of identifying the interface—characterized by distinct electrical property differences—between the collapsed debris pile 4 and the natural caving arch structure 5. The underlying principle is that of electromagnetic wave reflection ranging: as electromagnetic waves propagate through a medium, they undergo reflection upon encountering an interface where electrical properties differ. The reflected waves are subsequently received by the radar; by analyzing characteristics such as the waveform and variations in amplitude intensity of the received electromagnetic waves, the distance between the radar's current position and the boundary interface can be determined. The collapsed debris pile 4 comprises fragmented rock blocks with large voids, whereas the surrounding rock of the natural caving arch structure 5 is relatively intact and dense; consequently, a distinct density difference exists at the interface between the two, resulting in markedly different propagation and reflection signals for the electromagnetic waves. The reaming drill 1-3 is connected to the central pilot drill 1-1 via the drill rod 1-2; the reaming drill 1-3 has a larger diameter than that of the central pilot drill 1-1, and multiple reaming cutters 1-6 are mounted at equal intervals along the circumference of its outer wall, with multiple film-spraying assemblies 1-4 installed between adjacent reaming cutters 1-6. As shown in Figure 3, the thin-film spraying assemblies 1-4 comprise mounting bases 1-41, support frames 1-42, pressurization chambers 1-43, liquid inlet pipes 1-44, and spray heads 1-45. The mounting bases 1-41 are fixed to the main body of the reaming drill 1-3. The support frames 1-42 are arranged on the mounting bases 1-41, and the pressurization chambers 1-43 and the liquid inlet pipes 1-44 are hermetically installed within the support frames 1-42. The spray heads 1-45 are mounted on the exposed upper end portions of the support frames 1-42. The pressurization chambers 1-43 serve to connect the spray heads 1-45 with end portions of the liquid inlet pipes 1-44, while another end portions of the liquid inlet pipes 1-44 communicate with the liquid supply channel 3-11. The function of the pressurization chambers 1-43 are to increase the pressure of the spraying liquid, thereby ensuring that the liquid is ejected at a high velocity and enhancing the spraying coverage capability. As shown in figure 4, the transmission and coupling mechanism 2 comprises a transmission connecting rod 2-1 and a ball joint assembly. The ball joint assembly includes a housing support 2-2; a retainer 2-4 is positioned between the housing support 2-2 and an inner raceway 2-3, and transmission steel balls 2-5 are installed within the retainer 2-4. These transmission steel balls 2-5 engage in a rolling fit with the housing support 2-2 and the inner raceway 2-3. One end of the transmission link 2-1 is connected to the hole-enlarging drill 1-3, while the other end is connected to the inner raceway 2-3. As shown in Figures 2 through 6, the rescue passage mechanism 3 comprises an air-ribbed inflatable membrane duct 3-1, one end of which is connected to the guided drilling mechanism 1 via a transmission coupling mechanism 2. The air-ribbed inflatable membrane duct 3-1 is internally provided with a fluid supply channel 3-11 and an air supply channel 3-12; both the fluid supply channel 3-11 and the air supply channel 3-12 extend continuously through the transmission coupling mechanism 2 and the guided drilling mechanism 1, serving respectively to supply spraying slurry to the membrane spraying assembly 1-4 and air to the air-ribbed inflatable membrane duct 3-1. To further enhance the load-bearing strength of the air-ribbed inflatable membrane duct 3-1, flexible reinforcing ribs 3-13 are provided on said air-ribbed inflatable membrane duct 3-1, wherein the flexible reinforcing ribs 3-13 are positioned in close contact with the surface of the air-ribbed inflatable membrane duct 3-1. As shown in Figure 7, a rescue method utilizing a rescue device for mine roadway collapse incidents comprises the following steps: Sl-detecting a slope gradient of a collapsed debris pile 4 by an inclinometer, and determining an initial drilling angle for the central pilot drill 1-1 based on measurement results; 52- sequentially installing the guide drilling mechanism 1, the transmission coupling mechanism 2, and the rescue passage mechanism 3 in a front-to-rear order; and activating the central pilot drill 1-1 to drill along a slope of the collapsed debris pile 4 at the initial drilling angle determined in the SI; S3-entering, by the reaming drill 1-3, a pre-drilled borehole along a same trajectory under guidance of the central pilot drill 1-1, and wherein through rotation and feeding actions of the reaming drill 1-3, the reaming cutters 1-6 continuously cutting the rock, gradually enlarges a borehole diameter, thereby enabling the air-ribbed inflatable membrane duct 3-1 to subsequently advance into an enlarged borehole, simultaneously, the membrane spraying assemblies 1-4 spray the collapsed debris pile 4 within a drilling cavity, as well as a surface of a caved arch situated above, thereby forming a sprayed flexible membrane that provides temporary support S4-continuously transmitting, by an electromagnetic ranging radar 1-5, electromagnetic wave signals ahead of the drill and receiving reflected signals in real time during a drilling process; when the central pilot drill 1-1 approaches a first inflection point 6 of the collapsed debris pile 4, and the electromagnetic ranging radar 1-5 detects that reflected signals exhibit a distinct electrical difference, the central pilot drill 1-1 automatically adjusts a drilling angle thereof to a near-horizontal orientation; S5-continually drilling, by the central pilot drill 1-1, along an upper horizontal section of the collapsed debris pile 4 until approaching a second inflection point 7; when the electromagnetic ranging radar 1-5 once again detects reflected signals exhibiting a distinct electrical difference, the central pilot drill 1-1 automatically adjusting the drilling angle thereof to an inclination opposite to the initial drilling angle; S6-after the guided drilling mechanism 1 has bypassed the collapsed debris pile (4) and reached a rescue location 8, the film-spraying assemblies 1-4 ceasing spraying, inflating and deploying the air-ribbed inflatable membrane duct 3-1 via the air supply channels 3-12, thereby causing the flexible reinforcing ribs 3-13 to gradually fit snugly against the air-ribbed inflatable membrane duct 3-1; and S7-deataching the guided drilling mechanism 1 and the transmission coupling mechanism 2, and enabling trapped personnel to evacuate from the load-bearing air-ribbed inflatable membrane duct 3-1 to the outside.. As shown in Figure 2, to ensure that personnel can pass through the rescue passage mechanism unimpeded, the hole-enlarging drill 1-3 expands the hole diameter to no less than 600 mm; furthermore, to ensure the safety of the rescue passage mechanism, the sprayed flexible film formed by the film-spraying assembly 1-4 possesses a tensile strength of no less than 30 MPa, a thickness of no less than 5 mm, and an initial setting time of no more than 60 seconds.

Claims

1. A rescue device for roadway collapse incidents in underground coal mines, comprising a guided drilling mechanism (1), a transmission and coupling mechanism (2), and a rescue passage mechanism (3), whereinthe guided drilling mechanism (1) comprises a central pilot drill (1-1), a drill rod (1-2), a reaming drill (1-3), and film-spraying assemblies (1-4); an electromagnetic ranging radar (1-5) is mounted on the central pilot drill (1-1); the reaming drill (1-3) is connected to the central pilot drill (1-1) via the drill rod (1-2), a diameter of the reaming drill (1-3) is greater than a diameter of the central pilot drill (1-1), reaming cutters (1-6) are arranged at equal intervals along a circumference of an outer wall thereof, and the film-spraying assemblies (1-4) are installed between adjacent reaming cutters (1-6);the transmission and coupling mechanism (2) comprises a transmission connecting rod (2-1) and a spherical joint structure, wherein the spherical joint structure comprises a housing support (2-2), wherein a cage (2-4) is positioned between the housing support (2-2) and an inner raceway (2-3), and wherein transmission steel balls (2-5) are installed within the cage (2-4), and the transmission steel balls (2-5) engage in a rolling fit with the housing support (2-2) and the inner raceway (2-3), and an end portion of the transmission connecting rod (2-1) is connected to the reaming drill (1-3), while another end portion is connected to the inner raceway (2-3); andthe rescue passage mechanism (3) comprises an air-ribbed inflatable membrane duct (3-1); one end portion of the air-ribbed inflatable membrane duct (3-1) communicates with the guided drilling mechanism (1) via the transmission coupling mechanism (2), wherein the air-ribbed inflatable membrane duct (3-1) is provided with a fluid supply channel (3-11) and air supply channels (3-12); both the fluid supply channel (3-11) and the air supply channels (3-12) extend continuously through the transmission coupling mechanism (2) and the guided drilling mechanism (1), serving respectively to supply spraying slurry and air to the membrane spraying assembly (1-4) and the air-ribbed inflatable membrane duct (3-1).

2. The rescue device for roadway collapse incidents in underground coal mines according to claim 1, wherein the air-ribbed inflatable membrane duct (3-1) is provided with flexible reinforcing ribs (3-13), and the flexible reinforcing ribs (3-13) are arranged in close contact with a surface of the air-ribbed inflatable membrane duct (3-1).

3. The rescue device for roadway collapse incidents in underground coal mines according to claim 1, wherein the film-spraying assemblies (1-4) comprise mounting bases (1-41), support frames (1-42), pressurization chambers (1-43),liquid inlet pipes (1-44), and spray heads (1-45); the mounting bases (1-41) are fixed to a body of the reaming drill (1-3); the support frames (1-42) are arranged on the mounting bases (1-41), the pressurization chambers (1-43) and the liquid inlet pipes (1-44) are sealingly installed within the support frames (1-42), the spray heads (1-45) are mounted on exposed upper end portions of the support frames (1-42), the pressurization chambers (1-43) serve to connect the spray heads (1-45) with end portions of the liquid inlet pipes (1-44); and another end portions of the liquid inlet pipes (1-44) communicate with the liquid supply channel (3-11).

4. A rescue method for roadway collapse incidents in underground coal mines by utilizing the rescue device according to any one of the claims 1-3, comprising following steps:SI- detecting a slope gradient of a collapsed debris pile (4) by an inclinometer, and determining an initial drilling angle for the central pilot drill (1-1) based on measurement results;S2- sequentially installing the guide drilling mechanism (1), the transmission coupling mechanism (2), and the rescue passage mechanism (3) in a front-to-rear order; and activating the central pilot drill (1-1) to drill along a slope of the collapsed debris pile (4) at the initial drilling angle determined in the SI;S3-continuously transmitting, by an electromagnetic ranging radar (1-5), electromagnetic wave signals ahead of the drill and receiving reflected signals in real time during a drilling process; when the central pilot drill (1-1) approaches a first inflection point (6) of the collapsed debris pile (4), and the electromagnetic ranging radar (1-5) detects that reflected signals exhibit a distinct electrical difference, the central pilot drill (1-1) automatically adjusts a drilling angle thereof to a near-horizontal orientation;S4-continually drilling, by the central pilot drill (1-1), along an upper horizontal section of the collapsed debris pile (4) until approaching a second inflection point (7); when the electromagnetic ranging radar (1-5) once again detects reflected signals exhibiting a distinct electrical difference, the central pilot drill (1-1) automatically adjusting the drilling angle thereof to an inclination opposite to the initial drilling angle;S5- entering, by the reaming drill (1-3), a pre-drilled borehole along a same trajectory under guidance of the central pilot drill (1-1), and wherein through rotation and feeding actions of the reaming drill (1-3), the reaming cutters (1-6) continuously cutting the rock, gradually enlarges a borehole diameter, thereby enabling the air-ribbed inflatable membrane duct (3-1) to subsequently advance into an enlarged borehole, simultaneously, the membrane spraying assemblies(1-4) spray the collapsed debris pile (4) within a drilling cavity, as well as a surface of a caved arch situated above, thereby forming a sprayed flexible membrane that provides temporary support;S6-afterthe guided drilling mechanism (1) has bypassed the collapsed debris pile (4) and reached a rescue location (8), the film-spraying assemblies (1-4) ceasing spraying, inflating and deploying the air-ribbed inflatable membrane duct (3-1) via the air supply channels (3-12), thereby causing the flexible reinforcing ribs (3-13) to gradually fit snugly against the air-ribbed inflatable membrane duct (3-1); andS7-deataching the guided drilling mechanism (1) and the transmission coupling mechanism (2), and enabling trapped personnel to evacuate from the load-bearing air-ribbed inflatable membrane duct (3-1) to the outside.

5. The rescue method for roadway collapse incidents in underground coal mines according to claim 4, wherein the reaming drill (1-3) enlarges the hole diameter to no less than 600 mm; the sprayed flexible film formed by the film spraying assembly (1-4) has a tensile strength of no less than 30 MPa, a thickness of no less than 5 mm, and an initial setting time of no more than 60 seconds.PATENT COOERATH» TREATY PCTInternational Search Report (PCT Article 18 and Rules 43 and 44)Applicant's or agent's file reference PCT008 FOR FURTHER ACTION: See Form PCT / ISA / 220 as well as, where applicable, item 5 below. International application No. PCT / CN2025 / 131972 International filing date(day / month / year) November 1, 2025 (Earliest)Prioruty Date(day / month / year) January 10,2025 Applicant CHINA UNIVERSITY OF MINING AND TECHNOLOGYThis international search report has been prepared by this International Searching Authority and is transmitted to the applicant according to Article 18. A copy is being transmitted to the International Bureau.Ulis search report has 5 pages in total.□It is also accompanied by a copy of each prior art document cited in this report.

1. Basis of the reporta. With regard to the language, the international search was carried out on the basis of:■the international application in the language in which it was filed.Oa translation of the international application into which is the language of a translation furnished for the purposes of internationalsearch (Rules 12.3(a) and 23.1(b)).b. OThis international search report has been established taking into account the rectification of an obvious mistake authorized by or notified to this Authority under Rule 91 (Rule 43.66^ (2a)).c.Dwith regard to any nucleotide and / or amino acid sequence disclosed in the international application (as it appears in Box No. I)2. OCertain claims were found unsearchable, as it appears in Box No. II3. OUnity of invention is lacking4. With regard to title of the invention■The text is approved as submitted by the applicant.□The text has been established by this Authority to read as follows:

5. With regard to Abstract□The text is approved as submitted by the applicant.■The text has been established, according to Rule 38.2 (b), by this Authority as it appears in Box No. IV. The applicant may, within one month from the date of mailing of this international search report, submit comments to this Authority.

6. With regard to drawingsa. The figure of the drawings to be published with the abstract is Figure No. 1■as suggested by the applicant.□as selected by this Authority, because the applicant failed to suggest a figure.□as selected by this Authority, because this figure better characterizes the invention. b.Onone of the figures is to be published with the abstract.International application No.PCT / CN2025 / 131972Box No. IV Abstract (followed item 5 on page 1)A rescue device for roadway collapse incidents in underground coal mines and a rescue method therefor are disclosed, wherein the rescue device comprises a guided drilling mechanism (1), a transmission and coupling mechanism (2), and a rescue passage mechanism (3); and the rescue method involves: Sl-detecting a slope gradient of a collapsed debris pile (4) to determine an initial drilling angle; S2-advancing a central directional drill along a slope of the collapsed debris pile; S3-conducting real-time monitoring using an electromagnetic ranging radar (1-5) and, upon detecting a significant electrical signal anomaly, adjusting the drilling angle to a near-horizontal orientation; S4-continuing to advance the central guide drill (1-1) through the collapsed debris (4) and, upon the electromagnetic ranging radar (1-5) detecting a significant electrical signal anomaly, adjusting the drilling angle to an inclination direction opposite to the initial drilling angle; S5-enlarging the borehole diameter using a reamer (1-3), inserting an air-ribbed inflatable membrane duct (3-1) into the enlarged borehole, and performing a coating operation by using membrane spraying assemblies (1-4); S6-maneuvering the guided drilling mechanism (1) around the collapsed debris pile (4) to reach a rescue location (8), whereupon the membrane spraying assemblies (1-4) cease spraying and the air-ribbed inflatable membrane duct (3-1) is inflated and deployed; and S7-evacuating the trapped personnel through the interior of the air-ribbed inflatable membrane duct (3-1). This method enhances both the efficiency and success rate of rescue operations following roadway collapse accidents in underground coal mines.International application No.PCT / CN2025 / 131972A. CLASSIFICATION OF SUBJECT MATTER E21F11 / 00(2006.01)i According to International Patent Classification (IPC) or to both national classification and IPC R FIELDS SEARCHED Minimum documentation searched (classification system followed by classification symbols): IPC:E21F Documentation searched other than minimum documentation to the extent that such documents are included in the fields searched Electronic data base consulted during the international search (name of data base and, where practicable, search terms used): CJFD, CNTXT, ENTXT ENTXTC, A / EN. Thin Inflatable Ba& l ubc_ S]urrv Lifesaving, Rescue, Reaming, Bladder, Shotcreting, Shotcrete hole, Shotcrete nozzle, Gas / Air, Spherical joint, Escape, Passageway, Universal, Support, Grouting, Drilling, Drill bit, slurry, air+, bag+, succor+, ream+, spheric+, drill+, serum+, grout+, hol+, univers+, resc+, gas+, ser a+, support+, lifesav+ C. RELEVANT DOCUMENTS Category* Citation of document, with indication, where appropriate, of the relevant passages Relevant to claim No. PX CN 119754841 A (China University of Alining and Technology) April 4, 2025 (2025-04-04) Description: Paragraphs 19-42, Figures 1-7 1-5 A CN 116025410 A (China University of Mining and Technology ) April 28, 2023 (2023-04-28) Description: Paragraphs 86-164, Figures 1-10 1-5 A CN 117307036 A (CCRI Xi'an Research Institute (Group) Co., Ltd.) December 29, 2023 (2023-12-29) Full Text 1-5 A CN 222184830 LT (Tianjin Fire Research Institute of the Ministry of Emergency Management) December 17, 2024 (2024-12-17) Full Text 1-5 A CN 204175189 U (Beijing Jiayouxincheng Industry and Trade Co., Ltd.) February 25, 2015 (2015-02-25) Full Text 1-5 A CN 113482651 A (China Coal Geology Group Co., Ltd.) October 8, 2021 (2021-10-08) Full Text 1-5 lie other documents are listed in the subsequent pages in column C ■ see attachment of the same patent familInternational application No.PCT / CN2019088909*Special categories of cited documents:"A" document defining the general state of the art which is not considered to*T" later document published after the international filing date or priority date and not in conflict with the application but cited to understand the principle or theoiybe of particular relevance "E” earlier application or patent but published on or after the international filing date "L" document which may throw doubts on priority claim(s) or which is cited to establish the publication date of another citation or other special reason (as specified) *O" document referring to an oral disclosure, use, exhibition or other means "P" document published prior to the international filing date but later than the priority date claimed underlying the invention "X" document of particular relevance; the claimed invention cannot be considered novel or cannot be considered to involve an inventive step when the document is taken alone "Y” document of particular relevance; the claimed invention cannot be considered to involve an inventive step when the document is combined with one or more other such documents, such combination being obvious to a person skilled in the art document member of the same patent family Date of the actual completion of the international search: December 30 2025 Date of mailing of the international search report: January 27, 2026 Name and mailing address of the ISA / CN: National Intellectual Property Administration, PRC (ISA / CN) No. 6, Xitucheng Lu, Jimenqiao Haidian District, Beijing City, 100088 Authorized officer: HE Cunfang Telephone No.: (+86) 027-59182107

Citation Information

Patent Citations

  • Drilling obstacle removing device for mine rescue

    CN113482651A

  • Rapid rescue device and rescue method

    CN116025410A

  • Underground large-diameter drilling equipment and construction method

    CN117307036A

  • Rescue device and rescue method for collapse accident of underground roadway of coal mine

    CN119754841A

  • Spiral eccentric expanded-base drill bit

    CN204175189U