Simulation method for construction plan and simulation system

The simulation method and system address power supply challenges by determining optimal power methods for electric working machines, ensuring efficient and cost-effective power distribution at construction sites.

JP2024132446APending Publication Date: 2024-10-01KOMATSU LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023043206
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-17
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

Existing methods for powering electric working machines at construction sites face challenges such as insufficient power supply when multiple machines are operated, and installing temporary power sources incurs high costs.

Method used

A simulation method and system that simulates construction plans using electric working machines, acquiring construction and machine data to determine the total power required, and selects optimal power supply methods like temporary power sources, portable storage batteries, portable generators, or battery exchanges based on cost and timing.

Benefits of technology

Determines an appropriate power supply method for electric working machines at construction sites, optimizing power distribution and reducing installation costs by predicting the need for temporary power sources and timing power supply effectively.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024132446000001_ABST
    Figure 2024132446000001_ABST
Patent Text Reader

Abstract

To provide a simulation method for a construction plan for determining an appropriate power supply system according to a construction site, and a simulation system.SOLUTION: A simulation method is a method for simulating a construction plan using a plurality of electric work machines at a construction site. The simulation method comprises: acquiring construction amount data indicating a construction amount at the construction site; acquiring work machine data including the power consumption of each of the plurality of electric work machines; calculating a total amount of power required by the plurality of electric work machines at the construction site based on the construction amount data and the work machine data; and determining a power supply system from a plurality of different types of power supply systems for charging the plurality of electric work machines based on the total amount of power required.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a simulation method and a simulation system for a construction plan. [Background technology]

[0002] In recent years, electric work machines have come to be used at construction sites. In order to efficiently perform work at construction sites using the electric work machine, it is desirable to charge the electric work machine at the construction site. For this reason, for example, Patent Document 1 describes a method in which a charged towed vehicle, which has been charged at a charging facility, is towed to the construction site by a transport vehicle, and the towed vehicle supplies power to the electric work machine. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2016-084633 A Summary of the Invention [Problem to be solved by the invention]

[0004] However, when a large number of electric work machines are operated at a construction site, sufficient power supply equipment is required. Therefore, there is a possibility that power shortages may occur when power is supplied from a towed vehicle as described above. In addition, when a temporary power source connected to a power grid is newly installed at a construction site, a large cost is incurred. Therefore, an appropriate power supply method for electric work machines according to the construction site is required. An object of the present disclosure is to provide a simulation method and a simulation system for a construction plan for determining an appropriate power supply method according to a construction site. [Means for solving the problem]

[0005] A simulation method according to one aspect of the present disclosure is a method for simulating a construction plan using a plurality of electric work machines at a construction site, the simulation method includes acquiring construction volume data indicating a construction volume at the construction site, acquiring work machine data including the power consumption of each of the plurality of electric work machines, calculating a total amount of power required by the plurality of electric work machines at the construction site based on the construction volume data and the work machine data, and determining a power supply method from a plurality of different types of power supply methods for charging the plurality of electric work machines based on the total amount of power required.

[0006] A simulation system according to another aspect of the present disclosure is a simulation system for a construction plan using a plurality of electric work machines at a construction site. The simulation system includes a first data acquisition unit, a second data acquisition unit, a power calculation unit, and a power supply determination unit. The first data acquisition unit acquires construction amount data indicating a construction amount at the construction site. The second data acquisition unit acquires work machine data including the power consumption of each of the plurality of electric work machines. The power calculation unit calculates the total amount of power required by the plurality of electric work machines at the construction site based on the construction amount data and the work machine data. The power supply determination unit determines the power supply method from a plurality of different types of power supply methods for charging the plurality of electric work machines based on the total amount of power required. Effect of the Invention

[0007] According to the present disclosure, the power supply method is determined based on the total amount of power required by a plurality of electric work machines at a construction site, making it possible to determine an appropriate power supply method for the construction site. [Brief description of the drawings]

[0008] [Figure 1] 1 is a diagram illustrating a configuration of a simulation system according to an embodiment. [Diagram 2] FIG. 1 is a diagram illustrating an example of a construction site and a work machine. [Diagram 3] 11 is a flowchart showing a process of simulating a construction plan. [Figure 4] FIG. 2 is a diagram showing an example of the current topography and the designed topography of a construction site. [Diagram 5] FIG. 13 is a diagram showing an example of a setting screen for a construction plan simulation. [Figure 6] FIG. 4 is a diagram showing an example of operation status data indicating a predicted operation status of a work machine. [Figure 7] FIG. 1 is a diagram showing a power supply method using a "temporary power source." [Figure 8] FIG. 1 is a diagram showing a power supply method using a “portable storage battery.” [Figure 9] FIG. 1 is a diagram showing a power supply method using a “portable generator.” [Figure 10] FIG. 1 is a diagram showing a power supply method by "battery exchange". DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0009] Hereinafter, an embodiment will be described with reference to the drawings. Fig. 1 is a diagram showing a configuration of a simulation system 1 according to an embodiment. As shown in Fig. 2, the simulation system 1 performs a simulation of a construction plan using a plurality of work machines M1-M3 at a construction site 100.

[0010] The work machines M1-M3 perform work at the construction site 100. The work machines M1-M3 include construction machines capable of pushing or excavating soil and / or transport vehicles capable of transporting soil. The construction machines include, for example, excavators and / or bulldozers. The transport vehicles include dump trucks. The construction machines may be wheel loaders or motor graders. The work machines M1-M3 are an example of multiple electric work machines. The number of multiple electric work machines is not limited to three. The number of multiple electric work machines may be more than three or less than three.

[0011] As shown in FIG. 1, the simulation system 1 includes a server computer 2. The server computer 2 includes a processor 11, a storage device 12, and a communication device 13. The processor 11 is, for example, a CPU (Central Processing Unit) and executes processing for simulating a construction plan. The storage device 12 includes a non-volatile memory such as a ROM (Read Only Memory) or a flash memory, and a volatile memory such as a RAM (Random Access Memory). The storage device 12 may include an auxiliary storage device such as an HDD (Hard Disc Drive) or an SSD (Solid State Drive). The storage device 12 stores programs and data for simulating a construction plan. The processor 11 executes processing for simulating a construction plan according to the programs and data.

[0012] The communication device 13 communicates with devices external to the server computer 2. The communication device 13 is connected to an external client computer 3 via a communication network 9 such as the Internet. The configuration of the client computer 3 is the same as that of the server computer 2. The client computer 3 is connected to an input device 4 and an output device 5.

[0013] The input device 4 can be operated by a user. The input device 4 generates input data in response to an operation by the user. The input data generated by the input device 4 is transmitted from the client computer 3 to the server computer 2. The input device 4 includes, for example, a touch screen. The input device 4 may include a keyboard. The input device 4 may include a pointing device such as a mouse. The output device 5 is, for example, a display, and displays an image in response to an output signal from the client computer 3. The output device 5 may alternatively be a printer.

[0014] Next, a process of simulating a construction plan executed by the processor 11 will be described. As shown in Fig. 1, the processor 11 includes a first data acquisition unit 14, a second data acquisition unit 15, a simulation unit 16, a power calculation unit 17, a power supply determination unit 18, and an output control unit 19. The first data acquisition unit 14, the second data acquisition unit 15, the simulation unit 16, the power calculation unit 17, the power supply determination unit 18, and the output control unit 19 are each realized by the processor 11. Fig. 3 is a flowchart showing the process of simulating a construction plan.

[0015] 3, in step S101, the first data acquisition unit 14 acquires construction volume data. The construction volume data indicates a construction volume at a construction site 100. The construction volume data is transmitted from the client computer 3 to the server computer 2. For example, the construction volume data includes current topography data and designed topography data.

[0016] As shown in Fig. 4, the current terrain data indicates the current terrain 101 of the construction site 100. The current terrain data is three-dimensional terrain data that indicates the shape of the current terrain 101. The current terrain data is acquired, for example, by a camera mounted on an unmanned aerial vehicle. Alternatively, the current terrain data may be acquired by a stereo camera mounted on a work machine at the construction site 100, or a measuring device such as a LIDAR (Light Detection And Ranging) device.

[0017] The designed terrain data shows the designed terrain 102 of the construction site 100. The designed terrain data is three-dimensional terrain data that shows the shape of the designed terrain 102. The designed terrain data is created, for example, by a construction company. As shown in Fig. 4, the designed terrain 102 includes a plurality of work areas 103, 104 that are partitioned from each other. The work areas 103, 104 show areas where work is performed by a work machine.

[0018] The work areas 103, 104 include a first area 103 and a second area 104. The design terrain 102 may include three or more areas that are partitioned from each other. For example, the first area 103 is a cut area, which will be described later. The cut area indicates the area in the construction site 100 where excavation of earth and sand is carried out. For example, the second area 104 is a banking area. The banking area indicates the area in the construction site 100 where banking is carried out.

[0019] In step S102, the second data acquisition unit 15 acquires work machine data. The work machine data indicates the work machines assigned to each of the work areas 103, 104 of the construction site 100. FIG. 5 is a diagram showing an example of a setting screen 20 for a simulation of a construction plan. The output control unit 19 generates an output signal for displaying the setting screen 20 on the output device 5, and transmits it to the client computer 3. The output device 5 displays the setting screen 20 in response to the output signal from the server computer 2. The operator of the client computer 3 uses the input device 4 to input settings for the simulation of the construction plan on the setting screen 20.

[0020] As shown in Fig. 5, the setting screen 20 includes a work type area list 21, a work machine list 22, and an allocation list 23. The work type area list 21 shows a list of work areas 103, 104 included in the construction site 100. For example, as shown in Fig. 5, the work type area list 21 includes a "cutting area A" and a "filling area B." The operator selects a work area to which a work machine is to be allocated from the work type area list 21.

[0021] The work machine list 22 shows a list of work machines that can be assigned to each work area. The work machine list 22 includes the identification number (ID), model number, and construction capacity of the work machine. The identification number is a unique number assigned to each work machine. The model number indicates the type of work machine. The construction capacity indicates the amount of work per unit time. For example, the construction capacity of a shovel may be the loading amount, the cutting amount, or the filling amount per unit time. Alternatively, the construction capacity of a shovel may be determined based on the capacity of the bucket. The construction capacity of a bulldozer may be the pushing amount or the filling amount per unit time. The construction capacity of a bulldozer may be determined based on the size of the blade. The construction capacity of a dump truck may be the transport amount per unit time.

[0022] On the setting screen 20, the operator determines which work machines to assign to each work area from among the work machines included in the work machine list 22. The assignment list 23 shows a list of the work machines assigned to each work area. The operator specifies the construction details to be performed by the work machines assigned to each work area. The construction details indicate the details of the work to be performed by the work machines, such as "excavation" or "banking".

[0023] For example, as shown in FIG. 5, shovel A with ID "101" and shovel B with ID "102" are assigned to cut earth area A, and the construction content of these shovels A and B is set to "excavation."

[0024] 4, the operator can set a travel route 30 for the dump truck at the construction site 100. For example, the operator designates a start point 31, a target point 32, and a route 33 connecting the start point 31 and the target point 32 on a screen showing the construction site 100. The contents set on the setting screen 20 as described above are transmitted from the client computer 3 to the server computer 2 as work machine data.

[0025] In step S103, the simulation unit 16 performs a simulation of the construction plan based on the construction volume data and the work machine data. The simulation result of the construction plan includes the predicted operation status of the work machine. The simulation unit 16 calculates the construction volume from the construction volume data. For example, the simulation unit 16 calculates the construction volume from the difference between the current topography 101 and the design topography 102. The construction volume is indicated, for example, by the volume of soil. The simulation unit 16 calculates the predicted operation status of the work machine based on the construction volume and the work machine data.

[0026] FIG. 6 is a diagram showing an example of operation status data 40 indicating the predicted operation status of a work machine. As shown in FIG. 6, the operation status data 40 indicates the predicted operation status of a work machine assigned to each work area. The operation status data 40 includes the operation time 41 of each work machine in one day. The operation time 41 is shown, for example, in a graph. The operation status data 40 includes the operation rate 42 of each work machine. The operation rate 42 indicates, for example, the proportion of the time that each work machine is actually operating out of the operation time of each work machine in one day. The operation status data 40 includes the construction volume 43 of each work machine. The construction volume 43 is shown, for example, by the volume of earth worked by each work machine in one day.

[0027] The simulation result of the construction plan may include the period and cost required for construction. For example, the simulation unit 16 calculates the period required for construction based on the construction volume 43, the construction capacity of each work machine, and the operation rate 42. The simulation unit 16 calculates the cost required for construction based on the usage fee and fuel cost of the work machine, and the period required for construction.

[0028] In step S104, the power calculation unit 17 calculates the total amount of power required each day during the construction period. For example, as shown in FIG. 7, the work machine M1 includes a battery B1. The work machine M1 is driven by the power of the battery B1. The other work machines are also driven by the power of their batteries, like the work machine M1. The above-mentioned work machine data includes the power consumption of each of the multiple work machines assigned to each work area. The power consumption indicates the power consumption per unit time of the work machine. Alternatively, the power consumption may indicate the power consumption per unit work volume of the work machine. The power calculation unit 17 calculates the total amount of power required by the multiple work machines at the construction site 100 based on the construction volume 43 data and the work machine data.

[0029] In step S105, the power supply determination unit 18 determines the optimal power supply method and power supply timing for charging the multiple work machines. The power supply determination unit 18 determines the optimal power supply method and power supply timing from multiple different types of power supply methods for charging the multiple work machines based on the total amount of required power.

[0030] The multiple power supply methods include power supply methods using a "temporary power source", a "portable storage battery", a "portable generator", and "battery replacement". As shown in FIG. 7, the power supply method using a "temporary power source" involves installing a temporary power source 51 at the construction site 100 and charging multiple work machines with the temporary power source 51. The temporary power source 51 is connected to the power grid 6 and includes a transformer facility. The temporary power source 51 is connected to the work machine M1 via a charger 52.

[0031] 8, the power supply method using a "portable storage battery" involves transporting a charged portable storage battery 53 to a construction site 100 and charging a plurality of work machines using the portable storage battery 53. The portable storage battery 53 is transported to the construction site 100 after being charged, for example, at a charging station equipped with charging equipment away from the construction site 100.

[0032] As shown in Fig. 9, the power supply method using the "portable generator" involves transporting a portable generator 54 to a construction site 100 and using the portable generator 54 to charge a plurality of work machines. The portable generator 54 may be mounted on a vehicle 55. Alternatively, the portable generator 54 may be removed from the vehicle 55 and installed at the construction site 100. Similarly, the "portable storage battery 53" may be mounted on the vehicle 55, or may be removed from the vehicle 55 and installed at the construction site 100.

[0033] The power supply method by "battery exchange" is to transport a charged battery B2 to the construction site 100 and exchange it for a used battery B1 of the work machine M1, as shown in Fig. 10. The charged battery B2 is transported to the construction site 100 after being charged, for example, at a charging station equipped with charging equipment away from the construction site 100.

[0034] The power supply determination unit 18 calculates the cost of each of the multiple power supply methods for the total amount of power required. For example, the cost of the power supply method using a "temporary power source" is calculated based on the installation cost and usage fee of the temporary power source 51, and the electricity fee for the total amount of power required. The cost of the power supply method using a "portable storage battery" is calculated based on the transportation cost of the portable storage battery 53, the usage fee, and the electricity fee for the total amount of power required. The cost of the power supply method using a "portable generator" is calculated based on the transportation cost of the portable generator 54, the usage fee, and the electricity fee for the total amount of power required. The cost of the power supply method using a "battery replacement" is calculated based on the transportation cost of the replacement battery, the usage fee, and the electricity fee for the total amount of power required.

[0035] The power supply determination unit 18 determines the optimal power supply method based on the respective costs of a plurality of power supply methods. For example, the power supply determination unit 18 determines the power supply method with the lowest cost among the plurality of power supply methods as the optimal power supply method. The power supply determination unit 18 also determines the optimal timing of power supply to each electric work machine based on the daily required amount of power and electricity cost of the electric work machine.

[0036] The output control unit 19 outputs simulation data showing the results of a simulation of the construction plan. The output control unit 19 transmits the simulation data to the client computer 3. The simulation data includes the above-mentioned operation status data 40. The output device 5 displays an operation status screen showing the operation status data 40. The simulation data includes an optimal power supply method. The output device 5 displays a power supply proposal screen showing the optimal power supply method and the timing of power supply. The power supply proposal screen includes, for example, the power supply date, the machine to be powered (ID or model number), and the power supply method. The power supply proposal may include the required amount of power and the cost. This power supply proposal screen makes it easy to recognize when and which power supply equipment should be arranged for which electric work machine, and how much it will cost.

[0037] In the simulation system 1 according to the present embodiment described above, an optimal power supply method is determined based on the total amount of power required by a plurality of work machines at the construction site 100. As a result, it is possible to determine an appropriate power supply method according to the construction site 100. For example, installation of the temporary power source 51 may take a long time due to the need to apply to the power company that manages the power grid 6. However, according to the simulation system 1 according to the present embodiment, it is possible to determine in advance whether or not the temporary power source 51 needs to be installed. As a result, it becomes easy to arrange for the installation of the temporary power source 51 before the start of construction work. In addition, by determining the optimal timing for power supply to each electric work machine, it is possible to easily determine the timing for arranging the power supply equipment.

[0038] Although one embodiment of the present invention has been described above, the present invention is not limited to the above embodiment, and various modifications are possible without departing from the gist of the invention.

[0039] The above-described processing by the server computer 2 may be executed in the client computer 3. The above-described processing by the server computer 2 may be distributed and executed by a plurality of computers. The power supply method is not limited to that in the above embodiment and may be changed. [Industrial Applicability]

[0040] According to the present invention, a construction plan simulation method and a simulation system are used to determine an appropriate power supply method according to a construction site. [Explanation of symbols]

[0041] 14: First data acquisition section 15: Second data acquisition section 17: Power calculation section 18: Power supply determination unit 51: Temporary power source 53: Portable storage battery 54: Portable generator B1, B2: Battery M1-M3: Electric working machine

Claims

1. A method for simulating a construction plan using a plurality of electric work machines at a construction site, comprising: Acquiring construction volume data indicating a construction volume at the construction site; acquiring work machine data including an electric power consumption of each of the plurality of electric work machines; Calculating a total amount of power required by the plurality of electric work machines at the construction site based on the construction volume data and the work machine data; determining a power supply method from a plurality of different types of power supply methods for charging the plurality of electric working machines based on the total amount of required power; A method for providing the above.

2. the plurality of power supply methods include installing a temporary power source connected to a power grid at the construction site and charging the plurality of electric work machines using the temporary power source. The method of claim 1.

3. the plurality of power supply methods include transporting a charged portable storage battery to the construction site and charging the plurality of electric work machines with the portable storage battery. The method of claim 1.

4. The plurality of power supply methods include transporting a portable generator to the construction site and charging the plurality of electric work machines by the portable generator. The method of claim 1.

5. The plurality of electric working machines include a removable battery, The plurality of power supply methods includes replacement of the battery. The method of claim 1.

6. Calculating a cost of each of the plurality of power supply methods with respect to the total amount of required power; determining the power supply method based on a cost of each of the plurality of power supply methods; The method of claim 1.

7. and determining a timing for supplying power to each of the plurality of electric work machines based on the required power amount and the power cost of each of the plurality of electric work machines. The method of claim 1.

8. A simulation system for a construction plan using a plurality of electric work machines at a construction site, A first data acquisition unit that acquires construction amount data indicating a construction amount at the construction site; a second data acquisition unit that acquires work machine data including an electricity consumption rate of each of the plurality of electric work machines; a power calculation unit that calculates a total amount of power required by the plurality of electric work machines at the construction site based on the construction volume data and the work machine data; a power supply determination unit that determines a power supply method from a plurality of different types of power supply methods for charging the plurality of electric working machines based on the total required power amount; A simulation system comprising:

9. the plurality of power supply methods include installing a temporary power source connected to a power grid at the construction site and charging the plurality of electric work machines using the temporary power source. The simulation system according to claim 8.

10. the plurality of power supply methods include transporting a charged portable storage battery to the construction site and charging the plurality of electric work machines with the portable storage battery. The simulation system according to claim 8.

11. The plurality of power supply methods include transporting a portable generator to the construction site and charging the plurality of electric work machines by the portable generator. The simulation system according to claim 8.

12. The plurality of electric working machines include a removable battery, The plurality of power supply methods includes replacement of the battery. The simulation system according to claim 8.

13. The power supply determination unit is Calculating a cost of each of the plurality of power supply methods with respect to the total amount of required power; determining the power supply method based on a cost of each of the plurality of power supply methods; The simulation system according to claim 8.

14. the power supply determination unit determines a timing of power supply to each of the plurality of electric work machines based on the required power amount and the electricity cost of each of the plurality of electric work machines. The simulation system according to claim 8.

Citation Information

Patent Citations

  • Power supply system for construction machine

    JP2016084633A